ROSEMARY M. COLLYER, United States District Judge.
Plaintiff, sub-subcontractor Window Specialists, Inc., brought suit for breach of contract against Forney Enterprises, Inc., alleging that Window Specialists was wrongfully terminated and it is owed monies for labor and materials. Forney Enterprises countersued for breach of contract and indemnification, contending that the work done by Window Specialists was substandard. Plaintiff now moves for partial summary judgment. As explained below, the motion will be granted in part.
The contract at issue here arose from a U.S. Army project to improve property at Fort McNair in Washington, D.C. General contractor, IIU Consulting Institute, Inc. (IIU), entered into a contract with the Army for the McNair improvements, and Hanover Insurance executed a performance bond on the contract. See Compl. [Dkt. 1], Ex. 1 (Performance Bond and Army/IIU Contract).
Id.; see also Opp'n [Dkt. 43], Ex. 1 (Ukoh Aff.)
Forney claims that the majority of the issues in the Cure Notice had to do with WSI's poor workmanship. See Opp'n at 4. WSI hotly contests this, alleging that the deficiencies were all within IIU's scope of work because IIU did not properly supervise, prepare the window and door openings, or perform the trim work after installation. Mot. for Partial Summ. J. [Dkt. 41-1] at 2-4. Under the Forney/WSI contract, WSI's scope of work excluded demolition and interior trim. See Forney/WSI Contract.
The window deficiencies were not corrected, and on June 29, 2011, IIU sent a notice of termination to Forney. Compl., Ex. 9 (Notice of Termination). On September 20, 2011, Forney formally terminated WSI. According to IIU, all window installation done by WSI was demolished, and all windows were reordered and reinstalled. Ukoh Aff. ¶ 20. IIU also asserts that none of the doors purchased by WSI could be used, and all of the doors were reordered. Id. ¶ 21. Because IIU claimed that WSI's work was deficient, it did not pay WSI's second, third, and fourth payment applications, totaling $936,967.00.
WSI disputes that its work was in any way deficient and seeks payment on its contract with Forney. On September 7, 2011, WSI filed a Complaint against Forney, Hanover, IIU, and John McHugh, Secretary of the Army, alleging:
See Compl. ¶¶ 35-93.
Subsequently, WSI voluntarily dismissed Secretary McHugh and general contractor IIU. See Notice of Dismissal [Dkt. 8]. WSI also voluntarily dismissed Count IV, which sought an injunction to permit WSI to continue working on the project. Id. WSI also sought an injunction to prevent Forney from terminating WSI. See Compl., Count V. However, Forney terminated WSI on September 20, 2011, and WSI has waived its claim for injunction by not prosecuting it. In addition, the Court granted Forney's motion to dismiss Count II for failure to state a claim. See Order [Dkt. 27]. Thus, the Complaint remains pending against only two parties on two separate counts: against Forney on Count I for breach of contract and against Hanover on Count III for performance of the payment bond.
Forney filed a two-count Counterclaim, alleging breach of contract and indemnification. See Countercl. [Dkt. 23]. IIU informed Forney that it held Forney responsible for damages allegedly caused by WSI, including the cost to reprocure, repair, and complete WSI's work on the project. Ukoh Aff. ¶ 25. IIU settled its claims against Forney without a lawsuit. IIU agreed, in a written settlement agreement,
WSI seeks partial summary judgment against Forney on the following grounds: (1) Count II of Forney's Counterclaim, seeking indemnification, should be dismissed as unripe; (2) Count I of Forney's Counterclaim, for breach of contract, should be dismissed because Forney's damages were caused by IIU and not by WSI; (3) because Forney does not have standing to sue for damages suffered by IIU, Forney's damages should be limited to lost profits; and (4) WSI is entitled to judgment in the amount of $61,342.36 for payment made by the Army to IIU for materials supplied by WSI.
Under Rule 56 of the Federal Rules of Civil Procedure, summary judgment shall be granted "if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a); accord Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Moreover, summary judgment is properly granted against a party who "after adequate time for discovery and upon motion ... fails to make a showing sufficient to establish the existence of an element essential to that party's case, and on which that party will bear the burden of proof at trial." Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).
In ruling on a motion for summary judgment, the court must draw all justifiable inferences in the nonmoving party's favor and accept the nonmoving party's evidence as true. Anderson, 477 U.S. at 255, 106 S.Ct. 2505. A nonmoving party, however, must establish more than "the mere existence of a scintilla of evidence" in support of its position. Id. at 252, 106 S.Ct. 2505. In addition, the nonmoving party may not rely solely on allegations or conclusory statements. Greene v. Dalton, 164 F.3d 671, 675 (D.C.Cir.1999). Rather, the nonmoving party must present specific facts that would enable a reasonable jury to find in its favor. Id. at 675. If the evidence "is merely colorable, or is not significantly probative, summary judgment may be granted." Anderson, 477 U.S. at 249-50, 106 S.Ct. 2505 (citations omitted).
Count II of the Counterclaim, which seeks indemnification, has not yet accrued and is not yet ripe for decision. Under the U.S. Constitution, federal courts are limited to deciding "actual, ongoing controversies." Honig v. Doe, 484 U.S. 305, 317, 108 S.Ct. 592, 98 L.Ed.2d 686 (1988). To show that a claim is ripe, a litigant must demonstrate (1) the fitness of the issues for judicial decision, and (2) the hardship to the parties caused by withholding court consideration. Nat'l Treasury Employees Union v. Chertoff, 452 F.3d 839, 854 (D.C.Cir.2006) (citing Abbott Labs. v. Gardner, 387 U.S. 136, 149, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967)). A claim "is not ripe for adjudication if it rests upon `contingent future events that may not occur as anticipated, or indeed may not occur at all.'" Texas v. United States, 523 U.S. 296, 300, 118 S.Ct. 1257, 140 L.Ed.2d 406 (1998) (quoting Thomas v. Union Carbide
Federal courts have routinely found that "indemnity claims are unripe until the alleged indemnitee's liability has been fixed by a judgment or settlement." Pardee v. Consumer Portfolio Servs., Inc., 344 F.Supp.2d 823, 836 (D.R.I.2004). Thus, an indemnity claim "does not accrue until the party seeking indemnification is held liable and makes a payment." Casanova v. Marathon Corp., 256 F.R.D. 11, 14 (D.D.C.2009); see also 42 C.J.S. Indemnity § 54 (2005) ("Generally, ... an indemnitee is not entitled to recover under the agreement until he has made an actual payment or has otherwise suffered an actual loss.")
Forney contends that its right to indemnity in fact has accrued because it reached a settlement with IIU. An examination of the agreement, however, reveals that it did not actually fix liability and did not cause Forney to suffer any actual loss. The agreement, titled "Liquidating Settlement Agreement," provided:
Settlement Agreement ¶ 2; see also Ukoh Aff. ¶ 26 (IIU agreed to "limit its recovery against FEI to those amounts FEI recovers from WSI in this litigation, less Forney's lost profits.").
The Settlement Agreement is a chimera, a ploy to give the illusion that IIU and Forney have reached a fixed settlement. However titled, the terms of the agreement reveal that the IIU's claim against Forney has not been liquidated at all, as it does not set any particular sum that Forney is required to pay IIU. The agreement cannot be said to have "fixed" Forney's liability, see Pardee, 344 F.Supp.2d at 836, to have caused Forney to suffer any "actual loss," see 42 C.J.S. Indemnity § 54, or to have caused Forney to make payment to IIU, see Casanova, 256 F.R.D. at 14.
Because the liability of Forney, as indemnitee, has not been fixed by judgment or settlement, Forney's claim for indemnification against WSI is not ripe. Accordingly, Count II of the Counterclaim (indemnification) will be dismissed as unripe.
WSI also seeks summary judgment on Counterclaim Count I, breach of contract, asserting that Forney alleges damages caused by IIU, and not by WSI, and thus WSI cannot be held liable. The essential elements of a contract are "competent parties, lawful subject matter, legal consideration, mutuality of assent and mutuality of obligation." Henke v. U.S. Dep't of Commerce, 83 F.3d 1445, 1450 (D.C.Cir. 1996) (citations omitted). To state a claim for breach of contract, a party must allege that a contract existed, that he performed his contractual obligations, that the other party breached the contract, and that he
WSI alleges that Forney lost profits due to IIU's termination of the IIU/Forney contract, and not due to any action by WSI. WSI's allegation is disputed. The parties agree that: the Army identified deficiencies on the project, including problems with windows and doors; when the deficiencies were not corrected, IIU terminated Forney; and Forney terminated WSI and thus WSI did not complete its work on the project. Having said that, whether the identified deficiencies were due to WSI's poor workmanship, poor workmanship by others in preparing the window and door openings and installing the trim, or both, is a matter of dispute. Further, the amount of lost profits, if any, suffered by Forney is in dispute. Summary judgment will be denied on this ground.
WSI also seeks to limit Forney's damages to lost profits because Forney has not alleged that it has suffered any actual loss, other than lost profits. Forney insists that to survive summary judgment, it does not need to prove its damages but only needs to demonstrate that damages exist and are not speculative. See Cormier v. D.C. Water & Sewer Auth., 959 A.2d 658, 667-68 (D.C.2008). Forney contends that its damages exist and are not speculative, and that they include the costs of curing WSI's allegedly defective work on the project. IIU informed Forney that it "held" Forney responsible for the cost to reprocure, repair, and complete WSI's work on the project, see Ukoh Aff. ¶ 25, and IIU settled its claims against Forney by agreeing to limit its recovery against Forney to "those amounts Forney recovers from WSI in this litigation, less Forney's lost profits," see id. ¶ 26; Settlement Agreement.
While couched in less precise language, WSI's objection to Forney's counterclaim for damages is that Forney lacks standing to assert a loss that has been suffered by IIU. To have standing under Article III of the U.S. Constitution, a plaintiff must establish: "(1) it has suffered an `injury in fact' that is (a) concrete and particularized and (b) actual or imminent, not conjectural or hypothetical; (2) the injury is fairly traceable to the challenged action of the defendant; and (3) it is likely, as opposed to merely speculative, that the injury will be redressed by a favorable decision." Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., 528 U.S. 167, 180-81, 120 S.Ct. 693, 145 L.Ed.2d 610 (2000) (citing Lujan v. Defenders of Wildlife, 504 U.S. 555, 560-61, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992)). "The focus is on the qualifications and status of the party seeking to bring his complaint before a federal court and not on the issues he wishes to have resolved." McKinney v. U.S. Dep't of Treasury, 799 F.2d 1544, 1549 (Fed.Cir.1986) (citing Simon v. E. Ky. Welfare Rights Org., 426 U.S. 26, 28, 96 S.Ct. 1917, 48 L.Ed.2d 450 (1976)).
Forney's allegation that IIU "held" it responsible for the cost to correct and complete the windows and doors on the project is evidenced by a "settlement
WSI also claims that it is entitled to judgment against Forney in the amount of $61,342.36. The Army paid IIU $371,364.11 for the purpose of paying suppliers. IIU used these funds to pay two of WSI's suppliers a total of $310,021.75 as follows: it paid Malta Windows & Doors $279,938.75 and it paid Diamond Doors $30,083.00. WSI claims, without authority, that Forney should be adjudged liable for the remainder of this fund, i.e., $61,342.36. Forney was a stranger to the transaction between the Army and IIU and between IIU and the suppliers, Malta and Diamond. WSI has not pointed to undisputed facts that would lead the Court to conclude that Forney is liable on summary judgment for this amount.
For the reasons set forth above, the motion for partial summary judgment [Dkt. 41] filed by WSI will be granted in part and denied in part. Count II of the Counterclaim [Dkt. 23], seeking indemnification, will be dismissed. Count I of the Counterclaim, seeking damages for breach of contract, will be limited to lost profits. Genuine issues of material fact exist as to the remainder. A memorializing Order accompanies this Opinion.