CONTI, Chief Judge.
The instant action arises out of the contamination of real property caused by the use of hazardous substances and waste in connection with the operation of a railcar manufacturing facility. Pending before the court are cross-motions for summary judgment filed by the parties pursuant to Federal Rule of Civil Procedure 56. (ECF Nos. 143 & 151.) For the reasons that follow, each of those motions will be granted in part and denied in part.
In 1910, Greenville Metal Products Company ("GMPC") purchased the North Plant, which is located in Mercer County, Pennsylvania. (ECF No. 224 ¶¶ 1-2.) The North Plant consists of thirty-four acres found within the Borough of Greenville. (ECF No. 223 ¶ 1.) GMPC started to operate the North Plant as a facility to manufacture railcars. (ECF No. 222 ¶ 1.) In 1914, GMPC became known as the Greenville Steel Car Company ("Greenville"). (Id. ¶ 2.) It was formally incorporated in Pennsylvania on December 31, 1924. (ECF No. 146-5 at 1.) In August 1937, Pittsburgh Forgings Company ("PFC") purchased all of Greenville's stock. (ECF No. 222 ¶ 3.) Ampco-Pittsburgh Corporation ("Ampco"), a Pennsylvania corporation based in Pittsburgh, acquired PFC's stock in August 1979 and became Greenville's parent corporation. (ECF No. 224 ¶ 20.)
Trinity Industries, Inc. ("Trinity"), is a Delaware corporation maintaining its principal place of business in Dallas, Texas. (ECF No. 1 ¶ 1.) Trinity Industries Railcar Corporation ("TIRC") and Waldorf Properties, Inc. ("Waldorf"), are wholly-owned subsidiaries of Trinity. (ECF No. 223 ¶ 3.) Greenville and Trinity executed a purchase and sale agreement on December 9, 1986. (ECF No. 146-4.) Pursuant to the terms of the agreement, Trinity acquired
After the acquisition, Trinity manufactured railcars at the North Plant. (ECF No. 222 ¶ 15.) These manufacturing activities continued until 2000, when Trinity's operations at the North Plant ceased. (ECF No. 223 ¶¶ 6-7.) In February 2004, Trinity sold the North Plant to Waldorf. (ECF No. 1 ¶ 22.) Waldorf continues to own the North Plant. (ECF No. 223 ¶ 2.) Although Greenlease continues to exist as a corporate entity, it constitutes only a shell holding company that does not engage in business or commercial activities. (ECF No. 222 ¶ 14.) Greenlease has no employees. (Id.)
In June 2004, the Environmental Crimes Section of the Pennsylvania Office of Attorney General's Bureau of Criminal Investigations commenced an investigation into waste disposal activities that had occurred at the North Plant. (ECF No. 146-7 at 2.) The purpose of the investigation, which resulted from a referral made by Mercer County District Attorney James P. Epstein,
(ECF No. 146-7 at 2; ECF No. 146-8 at 1.) As a part of the investigation, Special Agent William F. Brown ("Brown") interviewed several former Trinity employees. (ECF No. 146-7 at 3-8; ECF No. 146-8 at 1-2.) Some of the individuals interviewed in connection with the investigation had also been employees of Greenville prior to Trinity's acquisition of the North Plant. (Id.)
On March 24, 2006, an investigative grand jury recommended that criminal proceedings be instituted against Trinity. (ECF No. 146-7.) One week later, Brown filed an eleven-count criminal complaint against Trinity for alleged violations of the SWMA. (ECF No. 146-9.) Trinity was charged with three second-degree felonies and eight third-degree misdemeanors. (Id. at 2-5.) Pursuant to the terms of a plea agreement executed on October 31, 2006, Trinity pleaded nolo contendere to five of the misdemeanor charges. (ECF No. 146-10.)
The SWMA established the Solid Waste Abatement Fund ("SWAF"), which is administered for the "abatement or elimination of present or potential hazards to human health or to the environment from the improper treatment, transportation, storage, processing, or disposal of solid wastes," and for the enforcement of the applicable statutory provisions. 35 PA. STAT. § 6018.701. On December 21, 2006,
On December 21, 2006, Trinity and the DEP executed a consent order and agreement pursuant to the Hazardous Sites Cleanup Act ("HSCA"), 35 PA. STAT. § 6020.101 et seq., the Land Recycling and Environmental Remediation Standards Act ("LRERSA"), 35 PA. STAT. § 6026.101 et seq., and the Administrative Code, 71 PA. STAT. § 510-17.
Trinity and TIRC commenced this action against Greenlease and Ampco (collectively, "defendants") on October 24, 2008, seeking redress under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 ("CERCLA"), 42 U.S.C. § 9601 et seq., the Resource Conservation and Recovery Act of 1976 ("RCRA"), 42 U.S.C. § 6901 et seq., and the HSCA. (ECF No. 1 ¶¶ 32-92.) In addition to the statutory claims, Trinity and TIRC (collectively "plaintiffs") brought common-law claims grounded in theories of contribution and negligence per se. (Id. ¶¶ 93-100.) The complaint contained requests for declaratory and monetary relief. (Id. ¶¶ 32-100.) Defendants answered plaintiffs' complaint on December 19, 2008, and asserted counterclaims for contribution and indemnity under the CERCLA and the common law of Pennsylvania. (ECF No. 9 at 18-19, ¶¶ 1-8.)
On September 14, 2009, defendants moved for a judgment on the pleadings pursuant to Federal Rule of Civil Procedure 12(c). (ECF No. 28.) That motion was denied in a memorandum opinion and order dated January 29, 2010, 2010 WL 419420. (ECF No. 40.) Plaintiffs filed a motion for partial summary judgment on October 14, 2011. (ECF No. 96.) That same day, Greenlease and Ampco filed separate motions for summary judgment. (ECF Nos. 88 & 92.)
While the motions for summary judgment filed by the parties in this case were still pending, parallel claims asserted by plaintiffs in a separate action involving the South Plant, a related property, against Chicago Bridge & Iron Company ("Chicago Bridge") were dismissed. Trinity Industries v. Chicago Bridge & Iron Co., 867 F.Supp.2d 754
On August 20, 2013, the court of appeals issued its decision and reinstated some of plaintiffs' claims against Chicago Bridge. Trinity Indus., Inc. v. Chicago Bridge & Iron Co., 735 F.3d 131 (3d Cir.2013). The order staying the proceedings in this case was lifted shortly thereafter. Trinity and TIRC filed a new motion for partial summary judgment on October 30, 2013. (ECF No. 151.) That same day, Greenlease and Ampco filed separate motions for summary judgment. (ECF Nos. 143 & 147.) In a memorandum opinion and order dated May 2, 2014, 2014 WL 1766083, the court granted Ampco's motion for summary judgment and denied the plaintiffs' motion for partial summary judgment with respect to the claims asserted against Ampco. (ECF Nos. 235 & 236.) Ampco is no longer a defendant in this action. (ECF No. 236.) The cross-motions for summary judgment concerning the claims brought against Greenlease are still before the court and will be resolved in this memorandum opinion.
Summary judgment may only be granted where the moving party shows that there is no genuine dispute as to any material fact, and that a judgment as a matter of law is warranted. FED. R. CIV. P. 56(a). Pursuant to Federal Rule of Civil Procedure 56, the court must enter summary judgment against a party who fails to make a showing sufficient to establish an element essential to that party's case, and on which that party will bear the burden of proof at trial. Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). In evaluating the evidence, the court must interpret the facts in the light most favorable to the nonmoving party, drawing all reasonable inferences in that party's favor. Watson v. Abington Twp., 478 F.3d 144, 147 (3d Cir. 2007). The burden is initially on the moving party to demonstrate that the evidence contained in the record does not create a genuine issue of material fact. Conoshenti v. Pub. Serv. Elec. & Gas Co., 364 F.3d 135, 140 (3d Cir.2004). A dispute is "genuine" if the evidence is such that a reasonable trier of fact could render a finding in favor of the nonmoving party. McGreevy v. Stroup, 413 F.3d 359, 363 (3d Cir.2005). Where the nonmoving party will bear the burden of proof at trial, the moving party may meet its burden by showing that the admissible evidence contained in the record would be insufficient to carry the nonmoving party's burden of proof. Celotex Corp., 477 U.S. at 322, 106 S.Ct. 2548. Once the moving party satisfies its burden, the burden shifts to the nonmoving party, who must go beyond that party's pleadings and designate specific facts by the use of affidavits, depositions, admissions or answers to interrogatories showing that there is a genuine issue of material fact for trial. Id. at 324, 106 S.Ct. 2548. The nonmoving party cannot defeat a well-supported motion for summary judgment by simply reasserting unsupported factual allegations contained in that party's pleadings. Williams v. Borough of West Chester, 891 F.2d 458, 460 (3d Cir.1989).
The court has subject-matter jurisdiction over the federal claims asserted in this case pursuant to 28 U.S.C. § 1331, 42 U.S.C. § 6971(a) and 42 U.S.C. § 9613(b). Supplemental jurisdiction over the state claims is predicated on 28 U.S.C. § 1367(a). Since there is complete diversity of citizenship between the parties and the amount in controversy exceeds $75,000.00, 28 U.S.C. § 1332(a)(1) supplies an alternative basis for the exercise of the court's subject-matter jurisdiction. Venue is proper under 28 U.S.C. § 1391(b), 42 U.S.C. § 6972(a) and 42 U.S.C. § 9613(b).
In the opinion issued on May 2, 2014, the court concluded that plaintiffs could not hold Ampco directly or derivatively liable under the standards articulated by the United States Supreme Court in United States v. Bestfoods, 524 U.S. 51, 118 S.Ct. 1876, 141 L.Ed.2d 43 (1998). (ECF No. 235 at 10-27.) Plaintiffs' inability to establish that Ampco had violated the applicable statutory provisions necessitated the dismissal of the contribution and negligence per se claims asserted against Ampco. (Id. at 27-29.) The court entered an order dismissing Ampco as a defendant in this action. (ECF No. 236.) The unresolved issues in this case concern only the dispute between plaintiffs and Greenlease.
In 1980 Congress enacted the CERCLA. Pub.L. No. 96-510; 94 Stat. 2767 (1980). The Supreme Court has described the CERCLA as "a comprehensive statute that grants the President broad power to command government agencies and private parties to clean up hazardous waste sites." Key Tronic Corp. v. United States, 511 U.S. 809, 814, 114 S.Ct. 1960, 128 L.Ed.2d 797 (1994). Section 106(a) of the CERCLA, which is codified at 42 U.S.C. § 9606(a), permits the Attorney General to commence an abatement action "when the President determines that there may be an imminent and substantial endangerment to the public health or welfare or the environment because of an actual or threatened release of a hazardous substance from a facility." Pub.L. No. 96-510, § 106(a); 94 Stat. 2767, 2780 (1980). A federal district court entertaining such an action may "grant such relief as the public interest and the equities of the case may require." 42 U.S.C. § 9606(a).
Section 107(a) of the CERCLA renders "four broad classes" of potentially responsible parties strictly liable for environmental contamination. Burlington Northern & Santa Fe Ry. Co. v. United States, 556 U.S. 599, 608-09, 129 S.Ct. 1870, 173 L.Ed.2d 812 (2009). That provision, which is codified at 42 U.S.C. § 9607(a), provides:
42 U.S.C. § 9607(a). Although the CERCLA creates a federal cause of action permitting the recovery of cleanup costs from culpable entities, it "does not provide a general cause of action for all harm caused by toxic contaminants." CTS Corp. v. Waldburger, ___ U.S. ___, 134 S.Ct. 2175, 2180, 2188, 189 L.Ed.2d 62 (2014). The CERCLA "does not provide a complete remedial framework" for those who have suffered "personal injur[ies] or property damage." Id.
The original version of the CERCLA contained no express provision permitting a private party to seek contribution from other potentially responsible parties for the costs of a cleanup. Key Tronic, 511 U.S. at 816, 114 S.Ct. 1960. Congress enacted the Superfund Amendments and Reauthorization Act of 1986 ("SARA"), Pub.L. No. 99-499; 100 Stat. 1613 (1986), which amended the CERCLA in order to authorize the commencement of contribution actions. Pub.L. No. 99-499, § 113; 100 Stat. 1613, 1647-1648 (1986). Section 113(f) of the CERCLA, which is codified at 42 U.S.C. § 9613(f), provides:
42 U.S.C. § 9613(f). The enactment of § 9613(f) was precipitated by litigation concerning the scope of § 9607(a). Beazer East, Inc. v. Koppers Indus., Inc., 525 F.3d 255, 259 (3d Cir.2008). The statutory amendment was designed to codify a right of contribution that some courts had previously found to be implicit in § 9607(a)'s remedial framework. Raytheon Aircraft Co. v. United States, 435 F.Supp.2d 1136, 1149-51 (D.Kan.2006).
In their complaint, plaintiffs assert claims under §§ 9607(a)(4)(B), 9613(f)(1) and 9613(f)(3)(B). (ECF No. 1 ¶¶ 33, 46-54.) Greenlease moves for summary judgment with respect to all those claims. (ECF No. 143 ¶¶ 3(a)-3(d).) Plaintiffs move for partial summary judgment only with respect to their claims under §§ 9607(a)(4)(B) and 9613(f)(3)(B). (ECF No. 151 at 1.) Each claim will be separately considered.
The plain language of § 9613(f)(1) provides that contribution from a liable or potentially liable party may be sought "during or following" a civil action commenced under § 9606 or § 9607. 42 U.S.C. § 9613(f)(1). In Cooper Industries, Inc. v. Aviall Services, Inc., 543 U.S. 157, 165-68, 125 S.Ct. 577, 160 L.Ed.2d 548 (2004), the Supreme Court construed that language to mean that the commencement of an underlying civil action was a statutory prerequisite to a claim for contribution under § 9613(f)(1). The Supreme Court described the sentence providing that
In United States v. Atlantic Research Corp., 551 U.S. 128, 138-39, 127 S.Ct. 2331, 168 L.Ed.2d 28 (2007), the Supreme Court recognized a distinction between a party's recovery of costs under § 9607(a) and a claim for contribution under § 9613(f). Elaborating on that distinction, the Supreme Court explained that "[w]hen a party pays to satisfy a settlement agreement or a court judgment, it does not incur its own costs of response." Atlantic Research Corp., 551 U.S. at 139, 127 S.Ct. 2331. The Supreme Court went on to observe that a party in such a situation would be "eligible to seek contribution" under § 9613(f) even though it could not "simultaneously seek to recover the same expenses" under § 9607(a).
In Trinity Industries, Inc. v. Chicago Bridge & Iron Co., 735 F.3d 131, 136-38 (3d Cir.2013), which involved the cleanup of the plaintiffs' South Plant, the United States Court of Appeals for the Third Circuit held that the consent order at issue in this case constituted "an administrative or judicially approved settlement" resolving plaintiffs' liability to Pennsylvania "for some or all of a response action."
The CERCLA requires the President to "establish procedures and standards for responding to releases of hazardous substances, pollutants, and contaminants...." 42 U.S.C. § 9605(a). The protocol established under the CERCLA, which was promulgated by the Environmental Protection Agency ("EPA"), constitutes one portion of a broader "national contingency plan."
Under § 9607(a), potentially responsible parties are strictly liable for costs falling within four different subsections. Burlington Northern, 556 U.S. at 608-09, 129 S.Ct. 1870. Removal or remedial costs incurred by the United States, a State or an Indian tribe may be recovered as long as they are "not inconsistent with the national contingency plan." 42 U.S.C. § 9607(a)(4)(A) (emphasis added). The "necessary costs of response" voluntarily "incurred by any other person" must be "consistent with the national contingency plan" in order to be recoverable. 42 U.S.C. § 9607(a)(4)(B) (emphasis added).
When Congress uses particular language in one provision but omits it from another provision of the same statute, courts generally presume that the language applies only within the context of the specific provision in which it appears. Barnhart v. Sigmon Coal Co., Inc., 534 U.S. 438, 452-53, 122 S.Ct. 941, 151 L.Ed.2d 908 (2002). Courts typically assume that Congress intends to establish different rules of law when it employs different language in two separate provisions. Sosa v. Alvarez-Machain, 542 U.S. 692, 711 n. 9, 124 S.Ct. 2739, 159 L.Ed.2d 718 (2004). These two principles of statutory construction contradict Greenlease's assertion that costs must always been incurred in a manner that is "consistent with the national contingency plan" in order to be recoverable under the CERCLA. (ECF No. 144 at 8-11; ECF No. 207 at 7; ECF No. 218 at 4-7.) The omission of that language from two subsections of § 9607(a) strongly suggests that certain costs are recoverable even in the absence of such consistency. 42 U.S.C. § 9607(a)(4)(C)-(D). The different phraseology used in § 9607(a)(4)(A) indicates that costs incurred by the United States, a State or an Indian tribe are recoverable even if they depart from established protocols, provided that they are "not inconsistent with the national contingency plan." 42 U.S.C. § 9607(a)(4)(A) (emphasis added). If Congress had intended to make a cleanup's consistency with the national contingency plan a prerequisite to cost recovery in every instance, it would have used the modifying language in more than one subsection of § 9607(a). Duncan v. Walker, 533 U.S. 167, 173-74, 121 S.Ct. 2120, 150 L.Ed.2d 251 (2001).
The CERCLA created sweeping remedies designed to force everyone who was potentially responsible for contamination to contribute to the costs of a cleanup. Bestfoods, 524 U.S. at 56 n. 1, 118 S.Ct. 1876. Under § 9607(a)(4)(B), a private party may recover costs voluntarily incurred during the course of a cleanup "without any establishment of liability to a third party." Atlantic Research Corp., 551 U.S. at 139, 127 S.Ct. 2331. In order to prevent private parties from incurring unnecessary costs and seeking reimbursement from other parties, Congress limited the statutory right of recovery to "necessary costs" incurred within the specific protocol prescribed by the national contingency plan. 42 U.S.C. § 9607(a)(4)(B). The national contingency plan operates "as a means of assuring that response actions [are] both cost-effective and environmentally sound." Artesian Water Co. v. Gov't of New Castle Cnty., 659 F.Supp. 1269, 1291 n. 42 (D.Del.1987). When a private party "resolve[s] its liability to the United States or a State for some or all of a response action or for some or all of the costs of such action in an administrative or judicially approved settlement," the terms of the settlement independently provide the strictures needed to prevent the party from unnecessarily increasing the costs of a cleanup. 42 U.S.C. § 9613(f)(3)(B).
As discussed earlier, a party must be sued under § 9606 or § 9607 in order to assert a claim for contribution under § 9613(f)(1). Cooper Indus., 543 U.S. at 165-68, 125 S.Ct. 577. A potentially responsible party sued under § 9607(a)(4)(B) may only be held liable for "necessary costs of response incurred by any other person consistent with the national contingency plan." 42 U.S.C. § 9607(a)(4)(B). When a party is sued
Plaintiffs were not sued under § 9607(a)(4)(B). (ECF No. 223 ¶ 26.) Their claims for contribution are based on their liability under the consent order. Atlantic Research Corp., 551 U.S. at 138 n. 5, 127 S.Ct. 2331. In Chicago Bridge, the court of appeals determined that the consent order constituted "an administrative or judicially approved settlement" resolving plaintiffs' liability to Pennsylvania "for some or all of a response action." Chicago Bridge, 735 F.3d at 136-38; 42 U.S.C. § 9613(f)(3)(B). Section 9613(f)(3)(B) makes the settlement itself, rather than any party's compliance with the national contingency plan, the applicable predicate for contribution. Cooper Indus., 543 U.S. at 163, 125 S.Ct. 577 (referring to the cause of action created by § 9613(f)(3)(B) as "a separate express right of contribution") (emphasis added). Since the contribution claims brought under § 9613(f)(3)(B) are not premised on an underlying action commenced against plaintiffs under § 9607(a)(4)(B), they remain viable regardless whether the terms of the consent order are consistent with the national contingency plan.
Although plaintiffs do not have to demonstrate that their actions were consistent with the national contingency plan in order to seek contribution under § 9613(f)(3)(B), they have done so in any event. The terms of the consent order were crafted in conformity with the HSCA and the LRERSA. (ECF No. 146-1 at 1, ¶ A.) The standards applicable under those statutes conform to the CERCLA's requirements. 35 PA. STAT. §§ 6020.504(a), 6026.106(a). In Chicago Bridge, which involved the consent order at issue in this case, the court of appeals specifically equated remediation under Pennsylvania law with remediation under the CERCLA. Chicago Bridge, 735 F.3d at 137. The consent order designated Joseph B. Gormley, Jr. ("Gormley"), of Golder Associates, Inc. ("Golder"), as the contractor responsible for performing, directing and supervising plaintiffs' work at the North and South Plants. (ECF No. 146-1 at 6, ¶ 4.) In an expert report submitted by Gormley on June 20, 2011, Golder stated that the work performed under the consent order had been consistent with the requirements of the national contingency plan. (ECF No. 216-1 at 19.) Greenlease points to nothing in the record which contradicts that statement.
Richard Barrett ("Barrett") testified on behalf of plaintiffs pursuant to Federal Rule of Civil Procedure 30(b)(6). (ECF No. 146-3.) During his deposition, Barrett stated that he was not familiar with the national contingency plan. (Id. at 18.) He responded in the negative when asked whether he was aware of efforts made by plaintiffs to ensure that Golder's employees were performing their work in accordance with the national contingency plan's requirements. (Id.) Greenlease characterizes
The argument advanced by Greenlease rests on the mistaken premise that a private party must consciously follow the prescribed protocol in order for its incurring of "necessary costs" to be "consistent with the national contingency plan." 42 U.S.C. § 9607(a)(4)(B). Under the EPA's regulations, a private party's "response action" is deemed to be "`consistent with the [national contingency plan]'" when it "is in substantial compliance with the applicable requirements ... and results in a CERCLA-quality cleanup." 40 C.F.R. § 300.700(c)(3)(i) (emphasis added). A "response action" carried out in compliance with an order or consent decree entered under the CERCLA is automatically considered to be consistent with the national contingency plan. 40 C.F.R. § 300.700(c)(ii). The court of appeals has found the standards governing the consent order at issue in this case to be "virtually identical" to the standards applicable under the CERCLA. Chicago Bridge, 735 F.3d at 137. In light of that determination, it is beyond dispute that actions taken pursuant to the consent order are in "substantial compliance" with the CERCLA's requirements. 40 C.F.R. § 300.700(c)(3)(i). Barrett's unawareness of those requirements has no bearing on whether plaintiffs actually incurred costs in a manner that was consistent with the national contingency plan. (ECF No. 146-3 at 18.)
Greenlease owned and operated an "onshore facility" within the meaning of the CERCLA. 42 U.S.C. § 9601(9), (18), (20). It is undisputed that Greenlease used and released products containing "hazardous substances." 42 U.S.C. § 9601(14); (ECF No. 224 ¶¶ 14-15.) The CERCLA renders potentially responsible parties strictly liable for the costs of a cleanup. United States v. Alcan Aluminum Corp., 964 F.2d 252, 259 (3d Cir. 1992). With respect to the contribution claims arising under § 9613(f)(3)(B), the court will deny the motion for summary judgment filed by Greenlease and grant the motion for partial summary judgment filed by plaintiffs. (ECF No. 1 ¶¶ 50-54; ECF No. 143 ¶ 3(c); ECF No. 151 at 1.) At this time, no opinion is expressed as to how the costs of remediation should be distributed among the parties. Litgo New Jersey, Inc. v. Comm'r of the New Jersey Dept. of Envt'l Prot., 725 F.3d 369, 383 (3d Cir.2013) (explaining that while the "CERCLA's strict liability regime may subject `innocent' private parties to liability," courts must "allocate response costs based on equitable factors").
The RCRA is a "comprehensive environmental statute" empowering the EPA to "regulate hazardous wastes" in accordance with "rigorous safeguards and waste management procedures." City of Chicago v. Envt'l Defense Fund, 511 U.S. 328, 331, 114 S.Ct. 1588, 128 L.Ed.2d 302 (1994). Section 7002(a)(1)(B) of the RCRA, which is codified at 42 U.S.C. § 6972(a)(1)(B), provides that
42 U.S.C. § 6972(a)(1)(B). A separate provision of § 6972(a) permits a federal district court
Plaintiffs' complaint includes claims under § 6972(a)(1)(B). (ECF No. 1 ¶¶ 55-69.) In the case involving the South Plant, plaintiffs asserted similar claims against Chicago Bridge. Summary judgment was entered in favor of Chicago Bridge with respect to those claims. Trinity Indus., Inc. v. Chicago Bridge & Iron Co., 867 F.Supp.2d 754, 763-64 (W.D.Pa.2012). Since Chicago Bridge was no longer conducting activities at the South Plant, a prohibitory injunction restraining it from continuing to contaminate the property was not an option. Id. Although the issuance of a mandatory injunction requiring Chicago Bridge to take remedial action was possible, it was not deemed to be "necessary" because the cleanup had already begun pursuant to the terms of the consent order. Id. at 764. Referring to a mandatory injunction as an "extraordinary remedy" that was to be "granted sparingly by the courts," the court of appeals affirmed the decision granting summary judgment in favor of Chicago Bridge with respect to plaintiffs' RCRA claims. Chicago Bridge, 735 F.3d at 138-40.
Unlike the relevant provisions of the CERCLA, § 6972(a)(1)(B) "was not intended to provide a remedy for past cleanup costs." Meghrig, 516 U.S. at 485, 116 S.Ct. 1251. Plaintiffs did not show that Greenlease's active participation in the ongoing cleanup effort is "necessary" within the meaning of § 6972(a). Chicago Bridge, 735 F.3d at 140. In a supplemental brief filed after the court of appeals' issuance of its decision in Chicago Bridge, plaintiffs informed the court that they were no longer pursuing injunctive relief under the RCRA. (ECF No. 229 at 2-3.) Accordingly, the court will deny plaintiffs' motion for partial summary judgment, and grant Greenlease's motion for summary judgment, with respect to the RCRA claims. (ECF No. 1 ¶¶ 55-69; ECF No. 143 ¶¶ 4(a)-4(b); ECF No. 151 at 1.)
In addition to their federal claims, plaintiffs bring HSCA claims against Greenlease under 35 PA. STAT. §§ 6020.701, 6020.702, 6020.705 and 6020.1101. (ECF No. 1 ¶¶ 70-92.) Section 6020.1101 declares "[a] release of a hazardous substance" to be a "public nuisance." 35 PA. STAT. § 6020.1101. That statutory provision renders "[a]ny person allowing such a release... liable for the response costs caused by the release." Id. A person's responsibility for such a release is controlled by section 6020.701(a), which provides:
35 PA. STAT. § 6020.701(a). A responsible person is subject to strict liability under section 6020.702(a), which provides:
35 PA. STAT. § 6020.702(a). In Agere Systems, the United States Court of Appeals for the Third Circuit found the "cost recovery" available under section 6020.702(a)(3) to be "virtually identical" to that available under § 9607(a)(4)(B) of the CERCLA. Agere Systems, 602 F.3d at 236.
Pursuant to 35 PA. STAT. § 6020.705, a responsible party sued for cost recovery may assert a claim for contribution under the following conditions:
35 PA. STAT. § 6020.705(a)-(c) (footnotes omitted).
Trinity acquired the North Plant from Greenville pursuant to a purchase and sale agreement executed on December 9, 1986. (ECF No. 146-4; ECF No. 223 ¶ 4.) The HSCA was signed into law on October 18, 1988. 1988 Pa. Laws 108. Greenlease moves for summary judgment on the ground that the HSCA does not retroactively apply. (ECF No. 143 ¶ 5;
The CERCLA imposes liability upon parties responsible for contamination occurring before its effective date. In the Matter of Penn Central Transp. Co., 944 F.2d 164, 166 n. 1 (3d Cir.1991). In most respects relevant to this case, the HSCA was modeled after the CERCLA. Gen. Elec. Envt'l Servs., Inc. v. Envirotech Corp., 763 F.Supp. 113, 115 n. 1 (M.D.Pa. 1991). The court of appeals has found the "cost recovery and contribution provisions" contained in the HSCA to be "virtually identical" to those contained in the CERCLA. Agere Systems, 602 F.3d at 236.
Greenlease attempts to distinguish the HSCA from the CERCLA by pointing out that several of the HSCA's provisions speak in the present tense even though the corresponding provisions of the CERCLA speak in the past tense. (ECF No. 144 at 16-19.) It is also worth noting that, under Pennsylvania law, "[n]o statute shall be construed to be retroactive unless clearly and manifestly so intended by the General Assembly." 1 PA. CONS.STAT. § 1926. Nonetheless, the HSCA expressly defines the term "[o]wner or operator" as "[a] person who owns or operates or has owned or operated a site, or otherwise controlled activities at a site." 35 PA. STAT. § 6020.103 (emphasis added). That definition controls the reach of the provision imposing liability upon "[t]he person who owns or operates the site...." 35 PA. STAT. § 6020.701(a)(1) (emphasis added). In Smith v. Weaver, 445 Pa.Super. 461, 665 A.2d 1215, 1221 (1995), the Pennsylvania Superior Court construed the applicable statutory language "to include, as responsible persons, those who ha[d] ... owned or operated a site" before the HSCA's effective date. A federal court presented with a question of state law generally should accord weight to decisions rendered by the intermediate appellate courts of the relevant State "unless it is convinced by other persuasive data that the highest court of the state would decide otherwise...." West v. American Tel. & Tel. Co., 311 U.S. 223, 237, 61 S.Ct. 179, 85 L.Ed. 139 (1940); Brown v. Tucci, 960 F.Supp.2d 544, 570 n. 8 (W.D.Pa.2013). Given the holding in Smith and because there is no other persuasive data indicating the Pennsylvania Supreme Court would render a different decision, plaintiffs' HSCA claims remain viable despite the fact that the HSCA did not become effective until after the execution of the purchase and sale agreement. Smith, 665 A.2d at 1221.
In an attempt to undermine the import of Smith, Greenlease calls the court's attention to Ingros v. BFG Electroplating & Manufacturing Co., 81 Pa. D. & C. 4th 481 (Pa.Ct.Comm.Pl.2006). (ECF No. 144 at 18-19.) In Ingros, the Court of Common Pleas of Jefferson County held that the HSCA did not retroactively apply. Ingros, 81 Pa. D. & C.4th at 494. That decision, however, made no reference to the superior court's earlier decision in Smith. Id. After supplemental jurisdiction over plaintiffs' HSCA claims against Chicago Bridge was declined in connection with the initial dismissal of the accompanying federal claims, plaintiffs refiled their HSCA claims in the Court of Common Pleas of Mercer County. (ECF No. 227-3 at 3-4.) In that action, the court of common pleas has already interpreted Smith to mean that the HSCA must be given retroactive effect. (Id. at 11-12.)
The undisputed facts of this case confirm that Greenlease "is responsible for a release or threatened release of a hazardous substance from a site." 35 PA. STAT. § 6020.702(a); (ECF No. 224 ¶¶ 14-15.) When construed in isolation, sections 6020.702(a) and 6020.1101 would appear to render Greenlease strictly liable for all resulting response costs. 35 PA. STAT. §§ 6020.702(a), 6020.1101. Nevertheless, the provisions of the HSCA are generally construed to be coterminous with the parallel provisions of the CERCLA. Chicago Bridge, 735 F.3d at 137; Agere Systems, 602 F.3d at 236. In Atlantic Research, the United States Supreme Court observed that a responsible party defending a claim under § 9607(a) "could blunt any inequitable distribution of costs" by filing a counterclaim under § 9613(f). Atlantic Research, 551 U.S. at 140, 127 S.Ct. 2331. As a settling party, however, Trinity cannot be held liable "for contribution regarding matters addressed in the settlement." 35 PA. STAT. § 6020.705(c)(2). The consent order broadly preserves Trinity's "protection from claims for contribution." (ECF No. 146-1 at 22, ¶ 39.) The "matters addressed in the settlement" include all response actions taken (and response costs incurred) at the North and South Plants. (Id.) Because Trinity is shielded from counterclaims for contribution, the reasoning employed in Agere Systems would appear to suggest that Trinity must pursue contribution claims under section 6020.705(c)(2) rather than seek to hold Greenlease jointly and severally liable under sections 6020.701, 6020.702 and 6020.1101.
Unlike Trinity, TIRC is not specifically named as a party to the consent order. (ECF No. 146-1 at 1). In Chicago Bridge, the court of appeals did not distinguish between Trinity and TIRC. Chicago Bridge, 735 F.3d at 133. Collectively referring to plaintiffs as "Trinity," the court of appeals treated them both as settling parties. Id. at 133, 136-38. The parties to this case identified no distinction between the status of Trinity and the status of TIRC. As far as the court can tell, TIRC would likewise enjoy statutory protection from counterclaims for contribution. 35 PA. STAT. § 6020.705(c)(2). If that is the case, TIRC cannot hold Greenlease jointly and severally liable under the remaining provisions of the HSCA. Agere Systems, 602 F.3d at 228-29.
Greenlease's motion for summary judgment, which is premised solely on a belief that the HSCA has no retroactive effect, does not distinguish between the different provisions of the HSCA relied upon by plaintiffs. (ECF No. 143 ¶ 5.) A
In addition to their statutory contribution claims under the CERCLA and the HSCA, plaintiffs assert common-law contribution claims against Greenlease. (ECF No. 1 ¶¶ 93-95.) Greenlease moves for summary judgment with respect to those claims. (ECF No. 143 ¶ 6.) The common-law contribution claims are not included within plaintiffs' motion for partial summary judgment. (ECF No. 151.)
Article VI of the United States Constitution declares "the Laws of the United States" to be "the supreme Law of the Land; ... any Thing in the Constitution or Laws of any state to the Contrary notwithstanding." U.S. CONST., ART. VI. "A fundamental principle of the Constitution is that Congress has the power to preempt state law." Crosby v. Nat'l Foreign Trade Council, 530 U.S. 363, 372, 120 S.Ct. 2288, 147 L.Ed.2d 352 (2000). Congress can preempt state law by explicitly declaring its intention to do so within the text of a federal statute. Shaw v. Delta Air Lines, Inc., 463 U.S. 85, 95-96, 103 S.Ct. 2890, 77 L.Ed.2d 490 (1983). Even in the absence of an explicit preemption provision, state law is preempted to the extent that it "regulates conduct in a field that Congress intended the Federal Government to occupy exclusively." English v. Gen. Elec. Co., 496 U.S. 72, 79, 110 S.Ct. 2270, 110 L.Ed.2d 65 (1990). Field preemption may be found where the federal regulatory scheme is "so pervasive as to make reasonable the inference that Congress left no room for the States to supplement it," or where "the federal interest is so dominant that the federal system will be assumed to preclude [the] enforcement of state laws on the same subject." Rice v. Santa Fe Elevator Corp., 331 U.S. 218, 230, 67 S.Ct. 1146, 91 L.Ed. 1447 (1947). When Congress does not intend for federal law to occupy a field exclusively, state law is nevertheless preempted "to the extent that it actually conflicts with federal law." California v. ARC Am. Corp., 490 U.S. 93, 100, 109 S.Ct. 1661, 104 L.Ed.2d 86 (1989). Conflict preemption may occur where concurrent compliance with federal and state law is impossible, or "where the state law stands as an obstacle to the accomplishment of the full purposes and objectives of Congress." Silkwood v. Kerr-McGee Corp., 464 U.S. 238, 248, 104 S.Ct. 615, 78 L.Ed.2d 443 (1984).
Greenlease argues that the CERCLA preempts common-law claims for contribution. (ECF No. 143 ¶ 6; ECF No. 144 at 20.) The CERCLA contains a provision clarifying that nothing contained therein "shall be construed or interpreted as preempting any State from imposing any additional liability or requirements with respect to the release of hazardous
The Pennsylvania Supreme Court has defined "negligence" as "the absence of ordinary care that a reasonably prudent person would exercise in the same or similar circumstances." Martin v. Evans, 551 Pa. 496, 711 A.2d 458, 461 (1998). Liability for negligence generally arises when there are facts establishing a "breach of a legally recognized duty or obligation of the defendant that is causally connected to actual damages suffered by the plaintiff." Scampone v. Highland Park Care Center, LLC, 618 Pa. 363, 57 A.3d 582, 596 (2012). Every cause of action for negligence "is premised on the existence of a duty owed by one party to another." Gibbs v. Ernst, 538 Pa. 193, 647 A.2d 882, 890 (1994). The "duty of care" owed by the defendant to the plaintiff is often rooted in "amorphous public policy considerations." Althaus v. Cohen, 562 Pa. 547, 756 A.2d 1166, 1169 (2000).
In certain instances, the relevant duty may be defined by "an applicable statute, ordinance or regulation designed to prevent a public harm." Cabiroy v. Scipione, 767 A.2d 1078, 1079 (Pa.Super.Ct.2001). A defendant's failure to comply with a legal prescription can sometimes establish as a matter of law that he or she has breached a duty of care owed to the plaintiff. Al's Cafe, Inc. v. Sanders Ins. Agency, 820 A.2d 745, 750 (Pa.Super.Ct.2003). Where a statutory violation amounts to such a breach, the defendant's conduct constitutes "negligence per se" under Pennsylvania law. Campo v. St. Luke's Hosp., 755 A.2d 20, 25 (Pa.Super.Ct.2000); Commonwealth of Pa., Dept. of Pub. Welfare v. Hickey, 136 Pa.Cmwlth. 223, 582 A.2d 734, 736 (1990). A plaintiff
Plaintiffs assert negligence per se claims against Greenlease in this case. (ECF No. 1 ¶¶ 96-100.) Those claims are premised on alleged violations of the CERCLA, the RCRA and the HSCA. (Id.) "A federal [statute or] regulation may establish the standard of care appropriate to the underlying tort of negligence per se under [Pennsylvania] law." Hassett v. Dafoe, 74 A.3d 202, 216 (Pa.Super.Ct.2013). Each of the three statutes will be considered for the purpose of determining whether plaintiffs' negligence per se claims are viable.
The HSCA declares it to be "unlawful" for a person to "[c]ause or allow a release of a hazardous substance," or to "[c]ause or allow [a] release of a contaminant in a manner that creates a public nuisance." 35 PA. STAT. § 6020.1108(1), (7). Plaintiffs' negligence per se claims appear to be predicated primarily on "violations" of those provisions. (ECF No. 1 ¶¶ 96-100.) As discussed earlier, however, the HSCA was not enacted until 1988. 1988 Pa. Laws 108. Greenlease's activities at the North Plant ceased on or before December 9, 1986. (ECF No. 146-4; ECF No. 223 ¶ 4.) The HSCA has retroactive effect to the extent that it renders previous owners and operators "responsible" for the costs of a cleanup. Smith, 665 A.2d at 1221. That effect does not mean that a pre-enactment "violation" of the HSCA can establish that such an owner or operator has been negligent per se. Negligence per se simply a recognizes that there are circumstances under which a plaintiff by certain means can establish the "duty" and "breach" elements necessary to recover under a theory of negligence. Fiorentino v. Cabot Oil & Gas Corp., 750 F.Supp.2d 506, 515 (M.D.Pa.2010). The statute creates the requisite "duty" owed to the plaintiff, and the defendant's violation of that statute constitutes the "breach" necessary to establish his or her negligence. J.E.J. v. Tri-County Big Brothers/Big Sisters, 692 A.2d 582, 585 (Pa.Super.Ct.1997); Alfred M. Lutheran Distrib., Inc. v. A.P. Weilersbacher, Inc., 437 Pa.Super. 391, 650 A.2d 83, 91 (1994). It is difficult to fathom how a person can breach a "duty" created by a statute that does not yet exist.
Even if the HSCA had been in effect at the time of Greenlease's conduct, it is not clear that the mere commission of an act declared to be "unlawful" thereunder could have established that Greenlease was negligent. Distinguishing negligence per se claims from those grounded in theories of strict liability, the superior court has held that an "excused violation" of a statutory provision does not constitute negligence per se under Pennsylvania law. Bumbarger v. Kaminsky, 311 Pa.Super. 177, 457 A.2d 552, 554-55 (1983). The doctrine of negligence per se does not impose liability without fault. McCloud v. McLaughlin, 837 A.2d 541, 544-45 (Pa.Super.Ct.2003). A plaintiff bringing a negligence per se claim must "establish that his [or her] complained of injuries were proximately caused by the statutory violations" allegedly committed by the defendant. Congini v. Portersville Valve Co., 504 Pa. 157, 470 A.2d 515, 518 n. 4 (1983).
The HSCA creates "a rebuttable presumption of law that a person who causes or allows the release of a hazardous substance shall be liable, without proof of fault, negligence, or causation, for all damages, contamination or pollution within 2,500 feet of the perimeter of the area
The negligence per se claims asserted in this case also appear to be premised on alleged violations of the CERCLA and the RCRA. (ECF No. 1 ¶ 97.) Under Pennsylvania law, negligence per se claims can arise only under statutory provisions exhibiting "an intention to protect specific groups from specific types of harm." Schemberg v. Smicherko, 85 A.3d 1071, 1075 (Pa.Super.Ct.2014). Plaintiffs maintain that the CERCLA and the RCRA "operate to protect persons who incur costs to respond to contamination attributable to others." (ECF No. 214 at 21.) That argument is problematic because the contamination at the North Plant is at least partially attributable to plaintiffs.
In order to recover under a theory of negligence per se, plaintiffs must
For the foregoing reasons, each of the pending motions for summary judgment will be granted in part and denied in part. Greenlease's motion for summary judgment (ECF No. 143) will be granted with respect to the claims arising under §§ 9607(a)(4)(B) and 9613(f)(1) of the CERCLA (ECF No. 1 ¶¶ 32-49), the RCRA claims (ECF No. 1 ¶¶ 55-69), the common-law contribution claims (ECF No. 1 ¶¶ 93-95), and the negligence per se claims (ECF No. 1 ¶¶ 96-100). Plaintiffs' motion for partial summary judgment (ECF No. 151) will be granted with respect to the statutory contribution claims arising under § 9613(f)(3)(B) of the CERCLA (ECF No. 1 ¶¶ 50-54) and section 6020.705(c)(2) of the HSCA (ECF No. 1 ¶¶ 87-92). The motions will be denied in all other respects. Both motions will be denied without prejudice with respect to the claims brought under sections 6020.701, 6020.702 and 6020.1101 of the HSCA (ECF No. 1 ¶¶ 70-86). An appropriate order will be entered.