PALMER, J.
This appeal requires us to consider the viability and scope of the doctrine of nullum tempus occurrit regi (no time runs against the king),
The state challenges these rulings on appeal,
The following facts and procedural history are relevant to our resolution of this appeal. The state acquired the Hartford campus of the University of Connecticut School of Law in the 1980s as part of a program to enhance the quality of education at the school as well as the standing of the university as a state institution. After acquiring the campus, the state began plans for the construction of a library to be built on land located at the center of the campus. The new library was intended to be a focal point of the campus and of such high quality that it would last for 100 years or more. The state retained Gilbane, a construction management firm, to work with the architect during the later stages of design to ensure construction input into the design process.
The project was designed beginning in 1992, and construction commenced in 1994. The project was completed in 1996. The state began occupying the library in January, 1996. Soon thereafter, the state experienced problems with water intrusion into the library. The defendant contractors were notified of the water problems and frequently visited the library to ascertain the nature and extent of the problems. Over the years, the water intrusion proved to be continuing and progressive. Beginning in or about 2000, and continuing for several years thereafter, the state retained forensic engineers to investigate the full extent and likely causes of the problem. The forensic investigation uncovered numerous defects in the building including, but not limited to, (1) improper design and installation of the wall anchoring system, the flashing, the windows, and the roof parapets, (2) improper design and construction of the exterior cavity wall, (3) inadequate waterproofing of the structural steel and the outside face of the building's structural wall, (4) inadequate relieving angles to support the exterior stone facade, and (5) inadequate design of the heating, ventilation and air conditioning system. These defects required the state to complete corrective work costing more than $15 million. The state commenced this action in March, 2008, seeking reimbursement for those costs.
All of the defendants raised time based defenses to the state's claims via motions to strike or motions for summary judgment, nearly all of which relied on applicable statutes of limitation and repose. In addition, Gilbane asserted that the state's claims against it were barred by the repose provision of Gilbane's contract with the state, which provided that "[t]he services performed pursuant to [the] contract shall be considered professional work to which any statutory period of repose then otherwise applicable to professional design
The trial court disagreed with the state's contentions, concluding, first, that the doctrine of nullum tempus does not shield the state from operation of the repose provisions of §§ 52-577, 52-577a, 52-584 and 52-584a or the limitation period of § 52-576. The trial court expressly acknowledged that the doctrine of nullum tempus "was well entrenched in English common law"; State v. Lombardo Bros. Mason Contractors, Inc., 51 Conn.Sup. 265, 296, 980 A.2d 983 (2009); that the rule was "imparted to our American justice system as one of the incidents of sovereignty," with each of the colonies taking the prerogative
On appeal, the state renews its claims that it is immune from statutes of limitation and repose pursuant to the doctrine of nullum tempus and that the commissioner lacked authority to contractually waive that immunity because General Statutes (Rev. to 1993) § 4b-99 does not explicitly or by necessary implication authorize such a waiver. The state contends that the trial court, in reaching a contrary conclusion, ignored centuries old precedent recognizing and applying nullum tempus as the law of this state, as well as the fundamental principle that statutes limiting rights are not to be interpreted as applicable to the state in the absence of a clear expression of legislative intent to the contrary. See, e.g., State v. Goldfarb, 160 Conn. 320, 323, 278 A.2d 818 (1971); State v. Shelton, 47 Conn. 400, 404-405 (1879).
The defendants counter with a variety of arguments. Some defendants contend that the rule of nullum tempus never was adopted in Connecticut and that the state always has been subject to statutes of limitation and repose. Others contend that Connecticut adheres to a more limited rule of sovereign immunity with respect to statutory limitation periods, one that exempts the state from statutes of limitation but not from statutes of repose, which, they argue, apply to the state by necessary implication. The defendants further maintain that the expiration of the repose periods contained in §§ 52-577, 52-577a, 52-584 and 52-584a vested in them a right to be free from liability afforded by the due process clause of article first, § 10, of the Connecticut constitution. Several defendants also contend that General Statutes § 4-61(a),
We agree with the state that the trial court had no basis for rejecting the rule of nullum tempus, which this and other courts of this state expressly have recognized as part of this state's common law since the second half of the nineteenth century. Because the rule defeats all of the defendants' time based defenses, the trial court improperly granted the defendants' motions to strike and motions for summary judgment.
We first address the state's contention that the trial court incorrectly concluded that the rule of nullum tempus never has been recognized as part of the common law of this state. The trial court reached that determination on the ground that "no reported Connecticut case has ever used" the term "nullum tempus"; State v. Lombardo Bros. Mason Contractors, Inc., supra, 51 Conn.Supp. at 296, 980 A.2d 983; and because the rule is incompatible with the legislative policies underlying statutes of limitation and repose. See id., at 297-301, 980 A.2d 983. The state contends that the rule has long been a part of our common law, and, in fact, the doctrine is so fundamental and important a feature of the state's sovereignty that only the legislature can abrogate it. The state further maintains that, in rejecting the doctrine, the trial court ignored binding precedent of this court and substituted its policy judgment for that of the legislature. We agree with the state.
As early as 1879, this court recognized a general principle, traceable to English common law, pursuant to which a statutory provision limiting rights is not to be construed as applying to the state unless the statutory language expressly or by necessary implication provides otherwise. State v. Shelton, supra, 47 Conn. at 404-405. By its terms, this general principle applied to statutes restricting the time period within which an action may be
"Nullum tempus ... is typically viewed as a privilege imparted to the federal and state governments as incidents of ... sovereignty." (Internal quotation marks omitted.) State v. Lake Winnipesaukee Resort, LLC, 159 N.H. 42, 45, 977 A.2d 472 (2009); see also District of Columbia v. Owens-Corning Fiberglas Corp., 572 A.2d 394, 401 (D.C.1989) ("[l]ike immunity from suit, the sovereign exemption from the running of time originated as a royal privilege"), cert. denied, 498 U.S. 880, 111 S.Ct. 213, 112 L.Ed.2d 173 (1990). "[S]overeign immunity from liability and governmental immunity from statutes of limitation [share] a philosophical origin and have the similar effect of creating a preference for the sovereign over the ordinary citizen...." Shelbyville v. Shelbyville Restorium, Inc., 96 Ill.2d 457, 460, 71 Ill.Dec. 720, 451 N.E.2d 874 (1983). "The ... distinction between [the] two doctrines lies in the manner in which they are employed in litigation. Sovereign immunity is invoked as a shield by the sovereign defendant against suits from parties allegedly injured by its wrongful conduct or that of its agents.... Conversely, nullum tempus is invoked by the sovereign plaintiff ... as a sword to strike down the statute of limitation defense raised by the defendant whose conduct is alleged to have injured the sovereign in some manner." (Citation omitted.) Indiana v. Acquisitions & Mergers, Inc., 770 A.2d 364, 372 (Pa. Cmwlth.2001). Thus, nullum tempus and sovereign immunity may be viewed as opposite sides of the same coin.
As to the historical origins of the rule, it has been observed that "[t]he rule of nullum tempus ... has existed as an element of the English law from a very early period. It is discussed in Bracton,
"Although ... nullum tempus may have had its roots in the prerogative of the
Presumably because the rule of nullum tempus is both well established and clear-cut, there appears to have been little controversy over its application in this state, with the result that our courts have not often been called on to consider it. On those occasions when the rule has been the subject of litigation, however, this court, the Appellate Court and the Superior Court all have recognized the doctrine in concluding, without exception, that an action by the state, or a subdivision of the state, was not barred by an otherwise applicable statutory limitation period or by laches.
In light of the foregoing, we find no merit in the defendants' contention that the rule of nullum tempus never was adopted in Connecticut. On the contrary, a review of our case law dating back more than one century makes it crystal clear that the rule has been and continues to be a part of the common law of this state.
The defendants nevertheless advance two primary arguments in support of their claim that the trial court's rejection of nullum tempus should be upheld. First, they argue that the rule never has been adopted in this state because it never has been applied as a holding in any Connecticut appellate case. The defendants attempt to substantiate this argument by parsing several of the cases in which this court or the Appellate Court has stated that statutes of limitation do not apply to the state, asserting that, although nullum tempus may have informed the analysis in those cases, it was not essential to the holdings. This contention is meritless. Even if we were to presume, for the sake of argument, that no appellate decision of this state has been decided on the basis of nullum tempus — a presumption with which we disagree
We long have held that our authority over the common law does not extend to the doctrine of sovereign immunity in the same way or to the same extent that it extends to other common-law principles. This is so because the doctrine derives from the very sovereignty of the state. Although originally recognized by the English common law, sovereign immunity "has ... been modified and adapted to the American concept of constitutional government where the source of governmental power and authority ... rests in the people themselves who have adopted constitutions creating governments with defined and limited powers and courts to interpret these basic laws. The source of the sovereign power of the state is now the constitution which created it, and it is now recognized that, as ... Justice [Oliver Wendell Holmes, Jr.] wrote: `A sovereign is exempt from suit, not because of any formal conception or obsolete theory, but on the logical and practical ground that there can be no legal right as against the authority that makes the law on which the right depends.'" Horton v. Meskill, 172 Conn. 615, 623, 376 A.2d 359 (1977).
In light of the derivation of sovereign immunity as a prerogative of the state arising directly out of the state's sovereign power, "we have continually expressed our reluctance to abolish [the doctrine] by judicial fiat.... The question [of] whether the principles of governmental immunity from suit and liability can best serve this and succeeding generations has become, by force of the long and firm establishment of these principles as precedent, a matter for legislative, not judicial determination." (Internal quotation marks omitted.) Rogan v. Board of Trustees for the State Colleges, 178 Conn. 579, 582, 424 A.2d 274
Our conclusion in this regard is buttressed by the fact that the primary modern rationale for both doctrines is the same: the fiscal well-being of the state. As we have stated with respect to sovereign immunity, that doctrine "is supported by a strong policy reason; that is, to prevent the imposition of enormous fiscal burdens on states." Fetterman v. University of Connecticut, 192 Conn. 539, 551-52, 473 A.2d 1176 (1984); see also Pamela B. v. Ment, 244 Conn. 296, 328, 709 A.2d 1089 (1998) ("[s]overeign immunity rests on the principle and on the hazard that the subjection of the state and federal governments to private litigation might constitute a serious interference with the performance of their functions and with their control over their respective instrumentalities, funds and property" [internal quotation marks omitted]). The doctrine of nullum tempus rests on similar principles, namely, those related to protecting the public fisc by allowing the government to pursue wrongdoers in vindication of public rights and property without regard to the time limitations applicable to other parties. Accordingly, the decision whether to abrogate the doctrine of nullum tempus, like the decision whether to abrogate the doctrine of sovereign immunity, is one for the legislature, not this court, to make.
We next consider the defendants' contention that the repose periods contained in §§ 52-577, 52-577a, 52-584 and 52-584a apply to the state by necessary implication. The defendants concede, and we agree, that none of them applies to the state by their express terms. The defendants maintain, however, that the policies effectuated by such statutes, together with the language of the statutes, compel the conclusion that they were intended to apply to the state.
It is well settled that, "in order for statutory language to give rise to a necessary implication that the state has waived its sovereign immunity, [t]he probability... must be apparent, and not a mere matter of conjecture; but ... necessarily such that from the words employed an intention to the contrary cannot be supposed.... In other words, in order for a court to conclude that a statute waives sovereign immunity by force of necessary implication, it is not sufficient that the claimed waiver reasonably may be implied from the statutory language. It must, by logical necessity, be the only possible interpretation of the language. Therefore, although a conclusion that statutory language is ambiguous ordinarily allows a court, pursuant to [General Statutes] § 1-2z,
The only textual argument that the defendants offer in support of their claim that §§ 52-577, 52-577a, 52-584 and 52-584a apply to the state by necessary implication is that all of them use unequivocal language such as "no action ... shall be brought," "no such action" and "in no event," terms that, according to the defendants, are so "comprehensive" as to necessarily encompass all actions, including those brought by the state. This court has held, however, that statutory language generally purporting to affect rights and liabilities of all persons will not be deemed to apply to the state in the absence of an express statutory reference to the state. Rivers v. New Britain, supra, 288 Conn. at 14, 950 A.2d 1247; see State v. Kilburn, 81 Conn. 9, 11, 69 A. 1028 (1908); see also State v. Chapman, 176 Conn. 362, 365, 407 A.2d 987 (1978) ("[a] statute giving a right to costs in general terms will not be construed to include an award against the [s]tate"); State v. Shelton, supra, 47 Conn. at 405 ("[t]he most general words that can be devised, as any person or persons, bodies politic and corporate, affect not [the state] in the least, if they may tend to restrain or diminish any of [its] rights or interests" [internal quotation marks omitted]). We can perceive of no reason, and the defendants have offered none, why this reasoning should not apply with equal force to the statutory language of the repose provisions at issue in the present case.
Our determination that §§ 52-577, 52-577a, 52-584 and 52-584a do not apply to the state is reinforced by the principle of statutory interpretation that requires us to presume that the legislature is cognizant of our interpretation of a statute, and that its subsequent failure to enact corrective legislation is evidence of its agreement with that interpretation. See, e.g., White v. Burns, supra, 213 Conn. at 333, 567 A.2d 1195. "Time and again, we have characterized the failure of the legislature to take corrective action as manifesting the legislature's acquiescence in our construction of a statute.... Once an appropriate interval to permit legislative reconsideration has passed without corrective legislative action, the inference of legislative acquiescence places a significant jurisprudential limitation on our own authority to reconsider the merits of our earlier decision." (Internal quotation marks omitted.) Hummel v. Marten Transport, Ltd., 282 Conn. 477, 494-95, 923 A.2d 657 (2007); see also State v. Courchesne, supra, 296 Conn. at 743, 998 A.2d 1 (inference of legislative acquiescence may apply to published opinions of Superior Court).
Finally, the defendants contend that a necessary implication of waiver can be inferred from the policies underlying statutes of repose. In support of this assertion, the defendants rely on "decisions of courts in other jurisdictions that have held statutes of repose to be substantive [per se] because, in their view, unlike statutes of limitation, statutes of repose operate as a grant of immunity serving primarily to relieve potential defendants from anxiety over liability for acts committed long ago...." (Citations omitted; internal quotation marks omitted.) Baxter v. Sturm, Ruger & Co., 230 Conn. 335, 343, 644 A.2d 1297 (1994). Courts that adhere to this view have concluded that, because "statutes of repose reflect legislative decisions that as a matter of policy there should be a specific time beyond which a defendant should no longer be subjected to protracted liability ... [such] a statute ... is intended as a substantive definition of rights as distinguished from a procedural limitation on the remedy used to enforce rights." (Internal quotation marks omitted.) School Board v. United States Gypsum Co., 234 Va. 32, 37, 360 S.E.2d 325 (1987); see also Daidone v. Buterick Bulkheading, 191 N.J. 557, 564-65, 924 A.2d 1193 (2007) ("Unlike a statute of limitations, the [s]tatute of [r]epose does not bar a cause of action; its effect, rather, is to prevent what might otherwise be a cause of [action] from ever arising.... For that reason, injury occurring [after the expiration of the applicable repose period] forms no basis for recovery.... The starkness of its application is intended: The injured party literally has no cause of action. The harm that has been done is damnum absque injuria — a wrong for which the law affords no redress. The function of the statute [of repose] is thus rather to define substantive rights than to alter or modify a remedy." [Citations omitted; internal quotation marks omitted.]).
The defendants note, moreover, that at least two courts have concluded that statutes of repose apply to the state by necessary implication. See Shasta View Irrigation District v. Amoco Chemicals Corp., 329 Or. 151, 164, 986 P.2d 536 (1999) ("The public policy for exempting governments from statutes of limitations ... does not apply to statutes of ultimate repose. That is so ... because the expiration of ultimate repose periods extinguishes all claims irrespective of whether the injured plaintiff was negligent in failing to assert claims in a timely manner."); Commonwealth v. Owens-Corning Fiberglas Corp., 238 Va. 595, 598, 385 S.E.2d 865 (1989) (concluding that
As many of the defendants concede, however, this court never has recognized a substantive distinction between statutes of limitation and statutes of repose. Indeed, we explicitly have rejected that distinction. Baxter v. Sturm, Ruger & Co., supra, 230 Conn. at 345, 644 A.2d 1297 ("Connecticut law makes no distinction ... between statutes of limitation and statutes of repose"); see also id., at 344-45, 644 A.2d 1297 ("the fact that a statute of repose may bar a claim before the cause of action has accrued does not form a basis to distinguish it from a statute of limitation"). As we have explained, "[w]hether seen as a sanction imposed on plaintiffs who sleep on their rights or as a benefit conferred [on] defendants to reduce the risk and uncertainty of liability, statutes of limitation and statutes of repose serve the same public policy of avoiding the litigation of stale claims." Id., at 344, 644 A.2d 1297; see also Barrett v. Montesano, 269 Conn. 787, 795-96, 849 A.2d 839 (2004) (noting "the legislature's repeated apparent use of the phrase `statute of limitations' as also encompassing a statute of repose").
Thus, in this state, "the characterization of a statute of repose as procedural or as substantive is governed by the same test that applies to statutes of limitation." Baxter v. Sturm, Ruger & Co., supra, 230 Conn. at 342, 644 A.2d 1297. Under that test, "statutes of repose, like statutes of limitation, are neither substantive nor procedural per se.... In any given case, the characterization of the applicable statute of repose depends on the nature of the underlying right that forms the basis of the lawsuit. If the right existed at common law, then the statute of repose is properly characterized as procedural because it functions only as a qualification on the remedy to enforce the preexisting right. If, however, the right is newly created by the statute, then the statute of repose is properly characterized as substantive because the period of repose is so integral a part of the cause of action as to warrant saying that it qualifie[s] the right." (Internal quotation marks omitted.) Id., at 346-47, 644 A.2d 1297.
"[When] ... a specific time limitation is contained within a statute that creates a right of action that did not exist at common law, then the remedy exists only during the prescribed period and not thereafter.... In such cases, the time limitation is not to be treated as an ordinary statute of limitation ... but rather is a limitation on the liability itself, and not of the remedy alone.... [U]nder such circumstances, the time limitation is a substantive and jurisdictional prerequisite, which may be raised [by the court] at any time ... and may not be waived." (Citations omitted.) Ecker v. West Hartford, 205 Conn. 219, 232, 530 A.2d 1056 (1987); cf. Moore v. McNamara, 201 Conn. 16, 22, 513 A.2d 660 (1986) ("[when] a statute of [repose] is procedural, it is subject to waiver; unless specifically pleaded it is deemed waived and the remedy continues beyond the prescribed period").
In State v. Goldfarb, supra, 160 Conn. at 326-27, 278 A.2d 818, we applied these principles in concluding that the time limitation for filing a claim against a decedent's estate, as provided in General Statutes (Cum.Sup.1967) § 45-205,
In Goldfarb, we concluded that the state's claim against the decedent's estate was barred by General Statutes (Cum.Sup. 1967) § 45-205 because the limitation period contained in the statute, unlike that of an ordinary or typical statute of limitations, imposed a condition precedent to the enforcement of the right of action, the nonfulfillment of which extinguished the right of action. See id., at 325-27, 278 A.2d 818. In reaching that determination, we framed the issue presented as follows: "The single claim made in this appeal is that the statute does not bar the state from pursuing [its] claim ... even though the claim was not presented ... within ... three months.... The purport of the special defense is that the state's failure to present its claim within the time limited by the [statute] is a complete bar to the cause of action stated in the complaint. The state attacks the defense on the ground that it is not, without its consent, subject to the `[s]tatute of [l]imitations'.... It would avoid [General Statutes (Cum.Sup. 1967)] § 45-205, which [is] assert[ed] to be a statute of limitation[s], on the ground of sovereign immunity." Id., at 323, 278 A.2d 818.
In considering the state's claim, we set forth the following general principles. "It may be stated ... as a universal rule in the construction of statutes limiting rights, that they are not to be construed to embrace the government or sovereignty unless by express terms or necessary implication such appears to have been the clear intention of the legislature, and the rights of the government are not to be impaired by a statute unless its terms are clear and explicit, and admit of no other construction.... The [s]tate holds the immunities in this respect belonging by the English common law to the [k]ing." (Citations omitted; internal quotation marks omitted.) Id., at 323-24, 278 A.2d 818. Applying these principles, we then concluded: "It is settled law that [General
"The distinction between a nonclaim statute and a statute of limitation[s] is made clear in Robbins v. Coffing, 52 Conn. 118, 141 [ (1884) ], [in which] this court [stated], in construing the predecessor of... [General Statutes (Cum.Sup.1967)] § 45-210 relating to suits brought on disallowed claims, that the statute contains a special limitation — not to prevent the litigation of stale claims, but to facilitate the speedy settlement of estates. Each statute has its own sphere of operation and is independent of the other.
"The sphere of operation of the nonclaim statute is to expedite the orderly and exact settlement of estates. [General Statutes (Cum.Sup.1967) §] 45-205 empowers the [Probate Court] to order executors and administrators to cite the creditors of the deceased ... to bring in their claims against such estate within the time ordered. If any creditor fails to do so he is barred of his demand against the estate. The clear purpose is one for the general good, to avoid the indefinite postponement of the settlement of estates to the detriment of the rightful beneficiaries, a purpose to which government as well as any other creditor should be required to adhere.
"This court has recognized the principle that a subdivision of the state, acting within its delegated governmental capacity, is not impliedly bound by the ordinary statute of limitations.... With respect to the non-claim statute, however, this court has held that a demand by a subdivision of the state which came within the definition of a claim against an estate was governed by this statute and, when not presented within the time limited by the [Probate Court], was barred." (Citations omitted; internal quotation marks omitted.) State v. Goldfarb, supra, 160 Conn. at 325-26, 278 A.2d 818.
In contrast to the nonclaim statute in Goldfarb, none of the statutes of repose at issue in the present case creates a condition precedent to bringing an action.
The defendants also claim that the legislature waived nullum tempus by necessary implication through its enactment of § 4-61, "which waives the state's sovereign immunity with respect to certain claims arising under public works contracts...." Dept. of Transportation v. White Oak Corp., 287 Conn. 1, 2-3, 946 A.2d 1219 (2008). In support of this contention, the defendants rely primarily on Lacasse v. Burns, 214 Conn. 464, 572 A.2d 357 (1990), in which we held that the legislature, in waiving the state's sovereign immunity from suit under General Statutes § 13a-144, the highway defect statute, "intended that procedural statutes and rules of court [including the accidental failure of suit statute, General Statutes § 52-592]
The state counters that nothing in the text or legislative history of § 4-61 supports the defendants' assertion that the statute's limited waiver of defensive sovereign immunity was intended to encompass the offensive use of nullum tempus. The state maintains that nullum tempus and sovereign immunity from suit serve very different roles in litigation and that most sister state courts that have considered the issue have concluded that a waiver of one does not encompass a waiver of the other. We agree with the state.
"[T]his court has recognized the well established principle that statutes in derogation of sovereign immunity should be strictly construed.... [When] there is any doubt about their meaning or intent they are given the effect which makes the least rather than the most change in sovereign immunity." (Internal quotation marks omitted.) Envirotest Systems Corp. v. Commissioner of Motor Vehicles, supra, 293 Conn. at 388, 978 A.2d 49. "The scope of [an] exception [to sovereign immunity] is not to be extended, modified, repealed or enlarged in its scope by the mechanics of [statutory] construction"; (internal quotation marks omitted) Dept. of Transportation v. White Oak Corp., supra, 287 Conn. at 13, 946 A.2d 1219; but "must be confined strictly to the extent the statute provides." (Internal quotation marks omitted.) First Union National Bank v. Hi Ho Mall Shopping Ventures, Inc., 273 Conn. 287, 294, 869 A.2d 1193 (2005).
By its express terms, § 4-61 "grants the right to sue the state ... to contractors who have `entered into a contract with the state' and who have a dispute `under such contract.'" Federal Deposit Ins. Corp. v. Peabody, N.E., Inc., 239 Conn. 93, 104, 680 A.2d 1321 (1996). "[W]e repeatedly have observed ... [that] § 4-61 was intended to carve out a narrow and limited exception to sovereign immunity. [Id., at 103, 680 A.2d 1321] (legislative history of § 4-61 reflects the narrow and limited purpose for the exception to sovereign immunity contained in § 4-61[a], and indicates that impleaders ... were not contemplated); DeFonce Construction Corp. v. State, [198 Conn. 185, 189, 501 A.2d 745 (1985) ] ([t]he legislative history [of § 4-61] makes no mention of contracts involving nonstate facilities ... [and] [i]n the absence of evidence of legislative intent to waive its immunity ... we presume that the legislature meant to exclude such contracts from the operation of the
"[The legislative] history [of § 4-61 likewise] reflects the narrow and limited purpose for the exception to sovereign immunity contained in [the statute].... [Before] § 4-61(a) was enacted, [actions] against the state by contractors were not countenanced because of sovereign immunity. Individualized legislative authorization to sue was required to be sought by petition before an action could be brought against the state. The legislature enacted § 4-61 in 1957 because of the mounting prevalence of these petitions for permission to sue the state. 7 S. Proc., Pt. 3, 1957 Sess., p. 1636. The legislature wanted to reduce the number of petitions for permission to sue the state that it received involving [actions] over state construction contracts. 7 H.R. Proc., Pt. 4, 1957 Sess., p. 1937.... Another reason for allowing parties who had contracted with the state to sue the state directly without seeking legislative authorization was the hope that affording contractors the right to sue would reduce the costs of construction projects to the state by eliminating the cost of the lengthy legislative authorization process that was often built into state construction contracts. Conn. Joint Standing Committee Hearings, General Law, Pt. 2, 1957 Sess., p. 436, remarks of Representative Merrill S. Dreyfus." (Citation omitted; internal quotation marks omitted.) Federal Deposit Ins. Corp. v. Peabody, N.E., Inc., supra, 239 Conn. at 103-104, 680 A.2d 1321.
The defendants have identified nothing in the text or legislative history of § 4-61 to support their assertion that the statute's limited waiver of government immunity from suit was intended to abrogate the doctrine of nullum tempus. This is not surprising in view of the fact that the state's immunity from statutory limitation periods arises only when the state commences an action. Section 4-61 is concerned solely with actions against the state. It does not address actions by the state, much less does it purport to restrict the state's right to bring such an action. See Ohio Dept. of Transportation v. Sullivan, 38 Ohio St.3d 137, 140, 527 N.E.2d 798 (1988) ("[Statute waiving sovereign immunity from suit] governs only suits against the state. It has no application to suits initiated by the sovereign against its citizens in courts of general jurisdiction [and, therefore, cannot be construed as waiving nullum tempus]."). To read such a restriction into § 4-61, therefore, would violate the cardinal rule of statutory construction that the scope of an exception to sovereign immunity "must be confined strictly to the extent the statute provides." (Internal quotation marks omitted.) First Union National Bank v. Hi Ho Mall Shopping Ventures, Inc., supra, 273 Conn. at 294, 869 A.2d 1193. Because sovereign immunity from suit and sovereign immunity from statutory limitation periods serve very different purposes in litigation, it does not logically follow that a waiver of one requires a waiver of the other.
We are far from alone in this view. Most courts that have considered the question have concluded that the abrogation of sovereign immunity from suit does not mandate the abolition of the state's exemption from statutes of limitation. See, e.g., Shelbyville v. Shelbyville Restorium, Inc.,
The defendants nevertheless contend that Lacasse v. Burns, supra, 214 Conn. at 464, 572 A.2d 357, stands for the proposition that, "when the state subjects itself to the jurisdiction of the court by bringing an affirmative claim, it waives the prerogatives
What the defendants ignore, however, is the portion of Lacasse in which we made clear that our holding did not apply to procedural statutes or rules of court that deprive the state of immunity beyond the scope of the explicit waiver giving rise to the action. See id. (emphasizing that Lacasse does not involve whether the "state's monetary liability can be expanded beyond that provided by a statute permitting the state to be sued ... but, rather, whether the state, having consented to being sued, is subject to procedural statutes applicable to all other litigants"). Statutory limitation periods are not procedural in the sense contemplated by Lacasse because their application would deprive the state of immunity. Indeed, under the defendants' view, the state automatically would waive nullum tempus in the only context in which it ever applies, that is, when the state brings an action. Notably, the defendants do not explain how their interpretation of Lacasse is reconcilable with our long-standing precedent exempting the state from the operation of statutory limitation periods. We take the defendants' silence on this issue as tacit acknowledgment that it cannot be reconciled.
We next address the state's claim that the trial court incorrectly concluded that the commissioner contractually waived nullum tempus in the contract with Gilbane by agreeing to be bound by the seven year repose provision then applicable to architects, professional engineers and land surveyors. See General Statutes § 52-584a (a). The state contends that the provision, when read in the broader context of the entire contract, merely reflects the parties' intent that Gilbane shall have the benefit of that repose period for claims against it by third parties, not the state. The state further maintains that, even if the provision can be construed as applying to the state, it is unenforceable under Envirotest Systems Corp. v. Commissioner of Motor Vehicles, supra, 293 Conn. at 382, 978 A.2d 49, because the statute authorizing the commissioner to enter into contracts; see General Statute (Rev. to 1993) § 4b-99; does not expressly or by force of necessary implication authorize him to waive the state's immunity from the operation of § 52-584a. In Gilbane's view, Envirotest is distinguishable from the present case because it involved an unauthorized waiver of the state's sovereign
The contract between Gilbane and the state contains a provision, entitled "Period of Repose," which provides: "The services performed pursuant to this contract shall be considered professional work to which any statutory period of repose then otherwise applicable to professional design work under Connecticut law shall apply." The trial court determined that this provision refers to § 52-584a and constitutes a waiver of any immunity that the state otherwise had with respect to the operation of that repose period. The state maintains, contrary to the determination of the trial court, that the provision does not apply to the state but, rather, to third parties. The state identifies several interpretative considerations which, it claims, support that conclusion; in particular, the state notes that the provision follows a paragraph in the contract that discusses Gilbane's liability to third parties only, and that the provision contains no mention of § 52-584a, referring instead to some future statutory repose period "then otherwise applicable...." We need not resolve the parties' dispute concerning the proper construction of the contractual language at issue because, even if we assume, arguendo, that the commissioner entered into the contract with Gilbane intending to waive the repose period of § 52-584a, it is clear under Envirotest that the commissioner had no authority to do so, and, accordingly, the provision is not enforceable.
The facts of Envirotest, which involved a purported waiver of sovereign immunity, closely mirror those of the present case, and our legal analysis in Envirotest is no less applicable to the present case in light of the marked similarities between sovereign immunity and nullum tempus. In Envirotest, we were required to determine whether General Statutes § 14-164c (e),
Envirotest subsequently claimed that the commissioner of motor vehicles had breached the contract "by virtue of the ... failure [of the department of motor vehicles] to use its best efforts to enforce emissions testing compliance by creating and maintaining a registration suspension program, and that, as a consequence of that alleged failure, [Envirotest] ha[d] suffered approximately $9 million in damages. After attempting to resolve the dispute ... [Envirotest] demanded that the commissioner [of motor vehicles] issue a decision pursuant to § 12 of the contract. The commissioner [of motor vehicles] responded by letter, indicating that it was the state's position that § 12 did not apply to [Envirotest's] claims for monetary damages." Id., at 386, 978 A.2d 49. Envirotest then filed an application to proceed with arbitration, which the commissioner of motor vehicles moved to dismiss on the ground that Envirotest's action "was barred by the doctrine of sovereign immunity." Id. "The trial court denied the motion to dismiss, concluding that, by necessary implication, § 14-164c (e) vested the commissioner [of motor vehicles] with authority to waive sovereign immunity. In so concluding, the court relied on the fact that § 14-164c (e) authorizes the commissioner [of motor vehicles] to enter into `negotiated' agreements in a project of considerable magnitude." Id.
On appeal to this court, we framed the issue presented as one that required a determination of whether § 14-164c (e) expressly or by force of necessary implication authorized the commissioner of motor vehicles to agree to binding arbitration. See id., at 386, 388, 978 A.2d 49. In concluding that the statute did not confer such authority, we stated: "The plain language of the statute illustrates that the legislature's objectives in providing the commissioner [of motor vehicles] with authority to negotiate and enter into inspection agreements pursuant to § 14-164c (e) were to identify the areas of negotiation, to establish the general scope and limitations of any agreement, to delineate the types of
Our holding in Envirotest is consistent with a long line of cases recognizing that government officials cannot waive sovereign immunity, contractually or otherwise, in the absence of explicit legislation authorizing them to do so. See, e.g., Bacon Construction Co. v. Dept. of Public Works, 294 Conn. 695, 711 n. 14, 987 A.2d 348 (2010) ("[w]e are mindful that only the legislature, and not the attorney representing the state in a particular dispute, may waive the state's sovereign immunity"); Berger, Lehman Associates, Inc. v. State, supra, 178 Conn. at 357, 422 A.2d 268 ("The plaintiff has also suggested that the contractual provision for service of process on the secretary of the state as agent acts as a nonlegislative waiver of sovereign immunity. The provision is in no way an explicit waiver, and, even if it were, the executive is not the appropriate authority to waive the state's immunity. Legislative action is necessary for the state to consent to suit."); Lambert v. New Haven, 129 Conn. 647, 649, 30 A.2d 923 (1943) ("[c]ertainly none of [the] officers [of the city] would have power to waive the right of a municipality to any immunity from liability which the law gives it, in the absence of special authority given them by the city"); Hoyle v. Putnam, 46 Conn. 56, 62 (1878) ("The fact that the selectman happened to be ex-officio the agent of the town ... does not affect the case. As such agent he would doubtless have power to appear and prosecute or defend suits, and transact much of the formal and ordinary business of the town; but the statute making him agent was not intended to authorize him to waive the legal rights of the town in an important matter like this.").
Envirotest also accords with the universal principle that "only those with specific authority can bind the government contractually; even those persons may do so only to the extent that their authority permits. [Thus], a party who seeks to contract with the government bears the burden of making sure that the person who purportedly represents the government actually has that authority...." (Emphasis added.) Gardiner v. Virgin Islands Water & Power Authority, 145 F.3d 635, 644 (3d Cir.1998). As the United States Supreme Court stated long ago: "It is too late in the day to urge that the [g]overnment is just another private litigant ... for purposes of charging it with liability.... The [g]overnment may carry on its operations through conventional executive agencies or through corporate forms especially created for defined ends.... Whatever the form in which the [g]overnment functions [however], anyone entering into an arrangement with the [g]overnment takes the risk of having accurately ascertained that he who purports to act for the [g]overnment stays within the bounds of his authority. The scope of this authority may be explicitly defined by Congress or be limited by delegated legislation, properly exercised through the rule-making power. And this is so even though... the agent himself may have been unaware of the limitations [on] his authority." (Citation omitted.) Federal Crop Ins. Corp. v. Merrill, 332 U.S. 380, 383-84, 68 S.Ct. 1, 92 L.Ed. 10 (1947); cf. id., at 385, 68 S.Ct. 1 ("The oft-quoted observation ... that `[m]en must turn square corners when they deal with the [g]overnment,' does not reflect a callous outlook. It merely expresses the duty of all courts to observe the conditions defined by Congress for charging the public treasury." [Citation omitted.]).
Thus, in order for Gilbane to prevail on its contractual claim, it "must prove ... that there is a precise fit between the narrowly drawn reach of the relevant statute, [General Statutes (Rev. to 1993) § 4b-99], and the contractual language [on] which [it] depends." Berger, Lehman Associates, Inc. v. State, supra, 178 Conn. at 356, 122 A.2d 268, This it cannot do. Indeed, Gilbane concedes that General Statutes (Rev. to 1993) § 4b-99 does not expressly or by force of necessary implication delegate to the commissioner the authority to waive sovereign immunity. That statute simply provides a procedure for selecting construction management firms to assist the department of public works with its projects, and authorizes the commissioner "[to] negotiate a contract for ... services with the most qualified firm from among the list of firms submitted by [a] panel, at compensation which he determines in writing to be fair and reasonable to the state." General Statutes (Rev. to 1993) § 4b-99 (c). "None of the language in the statute alludes to liability, lawsuits or dispute resolution." Envirotest Systems Corp. v. Commissioner of Motor Vehicles, supra, 293 Conn. at 394, 978 A.2d 49. Accordingly, we conclude that the commissioner was not authorized by General Statutes (Rev. to 1993) § 4b-99 to waive nullum tempus in the contract with Gilbane.
Gilbane nevertheless argues that we should not extend the holding in Envirotest to unauthorized waivers of nullum tempus because the public policy underlying that doctrine is not as "compelling" as that which supports the enforcement of contractual repose provisions, namely, "fairness, contractual certainty and sound economic policy." Gilbane contends that, in fairness, the state should not be permitted
If we were writing on a clean slate, these arguments, which are no less applicable to sovereign immunity than they are to nullum tempus, might have some persuasive force. But whatever appeal the arguments might have, they are unavailing in light of our analysis and conclusion in Envirotest. As we have explained throughout this opinion, it is not for this court to decide whether nullum tempus is sound policy generally or whether the interests it serves are more important than those served by the enforcement of contractual repose provisions. That decision rests solely and exclusively in the hands of the legislature,
Finally, we consider Gilbane's contention that the trial court's decision to strike the state's tort claims against Gilbane can be upheld on the alternative ground that they are barred by the limitation of remedies provision in the parties' contract. We also reject this claim.
The state's complaint contains five causes of action against Gilbane: negligence; breach of contract; negligent misrepresentation; intentional misrepresentation; and breach of fiduciary duty. Gilbane claims that all of the claims sounding in tort are barred by the limitation of remedies provision in the parties' contract. That provision, entitled "Construction Manager's Liability as to the [Department of Public Works]; Covenant Not to Sue," provides: "In recognition of the [consideration previously identified in the contract], the [c]onstruction [m]anager shall be liable to the [department of public
"Such liability shall not exceed, in the cumulative aggregate, an amount equal to the proceeds paid under all the insurance [purchased by the construction manager in accordance with the terms of the contract] plus [200 percent] of the [c]onstruction [m]anager's fee under this contract, and to the maximum extent permitted by law. The [department of public works] releases the [c]onstruction [m]anager from, and agrees not to sue the [c]onstruction [m]anager for, any liability for such loss, damage or expense in excess thereof; provided, however, that the foregoing limitation, release and covenant not to sue shall not apply to the extent that any claim for loss, damage or expense is attributable to the willful misconduct, gross negligence (recognizing that gross negligence is substantially and appreciably higher in magnitude than ordinary negligence), fraud or active concealment of the [c]onstruction [m]anager. The remedies afforded the [department of public works] under this contract shall be the ... sole and exclusive remedies [of the department of public works] with respect to the [c]onstruction [m]anager for liability, loss, damage or expense, irrespective of the nature of the cause of action, arising out of or in connection with this contract."
On appeal, Gilbane asserts that the last sentence of the limitation of remedies provision, which provides that the remedies afforded to the department of public works shall be its sole and exclusive remedies, "makes clear the legal insufficiency of the state's tort claims against Gilbane, as the contract clearly confines any attempted recovery against Gilbane to contractual remedies." We cannot discern how this language supports Gilbane's contention. Although the last sentence provides that the contractual remedies afforded the state shall be the state's sole and exclusive remedies, it does not identify what those remedies are. The two paragraphs directly preceding the last sentence, however, make clear that the state's remedies include tort remedies. Specifically, the first paragraph provides that Gilbane is liable to the department of public works for damage, loss or expense caused by Gilbane's "negligent errors or omissions ... or [the] negligent errors or omissions ... of its consultants, agents or employees...." The second full paragraph further provides that the covenant not to sue Gilbane for loss, damage or expense in excess of the liability limits (insurance proceeds plus 200 percent of Gilbane's fee) "shall not apply to the extent that any claim for loss, damage or expense is attributable to the willful misconduct, gross negligence... fraud or active concealment of [Gilbane]." It is well settled that, "[when] the language of the contract is clear and unambiguous, the contract is to be given effect according to its terms. A court will not torture words to import ambiguity [when] the ordinary meaning leaves no room for ambiguity.... Similarly, any ambiguity in a contract must emanate from the language used in the contract rather than from one party's subjective perception of the terms." (Internal quotation marks omitted.) Connecticut Light & Power Co. v. Lighthouse Landings, Inc., 279 Conn. 90, 110. 900 A.2d 1242 (2006). Furthermore, when, as in the present case, the contract language is definitive, the determination of the parties' intent as expressed
The judgment is reversed and the case is remanded for further proceedings according to law.
In this opinion the other justices concurred.
"(b) Notwithstanding the provisions of subsection (a) of this section, in the case of such an injury to property or the person or such an injury causing wrongful death, which injury occurred during the seventh year after such substantial completion, an action in tort to recover damages for such an injury or wrongful death may be brought within one year after the date on which such injury occurred, irrespective of the date of death, but in no event may such an action be brought more than eight years after the substantial completion of construction of such an improvement...."
We note that the state filed two separate appeals, one from the trial court's judgment with respect to the granting of the defendants' motions to strike and motions for summary judgment (SC 18462), and a second from the judgment with respect to the dismissal of certain cross complaints and apportionment complaints (SC 18463). These appeals, which are identical in all material respects, were consolidated by the Appellate Court prior to our transfer of the appeals to this court. Because the first appeal was jurisdictionally proper, the second appeal is merely redundant. Earlington v. Anastasi, 293 Conn. 194, 196-97 n. 3, 976 A.2d 689 (2009).
"(b) The responses received shall be considered by the state construction services selection panel established under section 4b-56. The panel shall select from among those responding no fewer than three firms, which it determines in accordance with criteria established by the commissioner are most qualified to perform the required construction management services....
"(c) The commissioner shall negotiate a contract for such services with the most qualified firm from among the list of firms submitted by the panel, at compensation which he determines in writing to be fair and reasonable to the state. If the commissioner is unable to conclude a contract with any of the firms recommended by the panel, he shall, after issuing written findings of fact documenting the reasons for such inability, negotiate with those firms which he determines to be most qualified, at fair and reasonable compensation, to render the particular construction management services under consideration...."
We note that the defendants are correct that no prior case of this court or the Appellate Court makes express reference to the term "nullum tempus." As we explain more fully hereinafter, however, both courts have recognized and applied the rule, albeit without calling it nullum tempus. With respect to the trial court's assertion that the rule has not been adopted in this state because our appellate courts previously have not used the term "nullum tempus," that assertion is manifestly incorrect. It is wholly irrelevant that neither this court nor the Appellate Court has used the term, as both courts have adopted the principle of law on which the rule is based, and both courts have done so in terms identical to the terms of the rule itself. Consequently, there is no merit to the trial court's assertion that the rule of nullum tempus is not a part of the common law of this state merely because our courts have not used that particular term in recognizing the doctrine that the right of the state to bring an action is not subject to any time based defense unless the legislature clearly and unmistakably has expressed a contrary intent.
The cases on which the defendants rely, however, do not support their contention that nullum tempus was rejected by our founders, either because the issue was not directly addressed; see Drake v. Watson, supra, 4 Day (Conn.) at 41-42; Dickinson v. Kingsbury, supra, 2 Day (Conn.) at 11; or because the case involved a criminal statute of limitations. See State v. Enos, supra, 1 Kirby (Conn.) at 22. It is axiomatic that a criminal statute of limitations would have applied to the state, if not expressly, then by necessary implication, because only the state can prosecute crimes. Nor do we agree that the 1786 enactment, entitled "An Act for the Limitation of Prosecutions in [Several] Cases, [C]ivil and [C]riminal"; see Acts and Laws of the State of Connecticut in America (1786) pp. 127-28. supports a different view. The defendants appear to argue that, because the legislature codified the first criminal and civil statutes of limitation in a single statute, both limitation provisions, by necessary implication, must have applied to the state. Suffice it to say that this argument falls short of the exacting standard for finding an implied waiver of sovereign immunity. See, e.g., Envirotest Systems Corp. v. Commissioner of Motor Vehicles, 293 Conn. 382, 389-90, 978 A.2d 49 (2009) ("[I]n order for a court to conclude that a statute waives sovereign immunity by force of necessary implication, it is not sufficient that the claimed waiver reasonably may be implied from the statutory language. It must, by logical necessity, be the only possible interpretation of the language."). That the legislature chose to enact the first criminal and civil statutes of limitation together was as likely a matter of expediency as anything else. In short, although it is true that we "have never given to [the English common law] a slavish adherence"; State v. Muolo, 118 Conn. 373, 377, 172 A. 875 (1934); the defendants have failed to persuade us that our adherence to nullum tempus has ever waivered.
This statute is now codified as amended at General Statutes § 45a-395.
"While such statutes limit the time in which a claim may be filed or an action brought, they have nothing in common with and are not to be confused with general statutes of limitation. The former creates a right of action if commenced within the time prescribed by the statute, whereas the latter creates a defense to an action brought after the expiration of the time allowed by law for the bringing of such an action." (Internal quotation marks omitted.) Bell v. Schell, 101 P.3d 465, 473-74 (Wyo.2004).
"Citing State v. Goldfarb, supra, 160 Conn. [at] 323 [278 A.2d 818], the state argues ... that it is for the legislature, not the court, to waive the state's sovereign immunity. The court in Goldfarb, however, `recognized the principle that a subdivision of the state, acting within its delegated governmental capacity, is not impliedly bound by the ordinary statute of limitations.' ... Id. [at], 326 [278 A.2d 818]....
"Ordinary is defined in Black's Law Dictionary (4th Ed. 1951) as `regular; usual; normal; common; reasonable.' In this case, the state is attempting to extend the principle of nullum tempus far past the `ordinary' or usual statute of limitations. In fact, here, the `ordinary' statute of limitations expired in 2002, six years after the construction was completed.
"To allow the state to bring [an action] so far past the `ordinary' statute of limitations is not routine or usual.
"If the court adopts the state's argument that in the event there is no statute of limitations that specifically includes the state, the doctrine of nullum tempus allows the state to bring a claim for breach of contract after the statute of limitations has expired, and the question becomes when, if ever, will the state be prohibited from bringing a claim against a contractor for construction work on a state building? Will the state be able to bring a claim twenty-five years after the building was completed? Fifty years? One hundred years? ... [T]he state's position [is] that the claim could be brought at any time. This slippery slope is ... a major public policy concern. In the construction field, buildings do not last forever. If the state is not bound by any statutes of limitations, it will have an unlimited time period to commence [actions] against contractors and subcontractors.
"Therefore, the court concludes that under the circumstances of this action, the contract claims by the state are barred by the statute of limitations set [forth] in § 52-576." (Citations omitted; emphasis in original.) State v. Lombardo Bros. Mason Contractors, Inc., supra, 51 Conn.Supp. at 301-302, 980 A.2d 983.
The trial court's unprecedented explanation of the meaning of the term "ordinary" statute of limitations is wrong. As we noted previously, the term refers to the typical or usual statutory limitation period that operates not as a jurisdictional limitation on liability, but as a limitation on remedy only. The trial court's misunderstanding of the term caused it incorrectly to conclude that the state was required to comply with the limitation period of § 52-576. None of the defendants seeks to defend the trial court's analysis on this issue.
On the basis of this reasoning, the trial court concluded: "The state legislature ... possesses the authority to abrogate any governmental immunity by statute that the common law gives to the state and municipalities.... Excepting the state from adherence to statutes of repose as set forth in §§ 52-577, 52-577a, 52-584 and 52-584a would be an exception that could not have been intended by the legislature in its aim to alleviate the difficulties and implications of litigating stale claims. The purpose of the statutes of repose was to allow defendants at some point to become free from liability, absent some unclean or fraudulent conduct. The logical conclusion is that the legislature intended the state to abide by the statutes of repose." (Citation omitted; internal quotation marks omitted.) State v. Lombardo Bros. Mason Contractors, Inc., supra, 51 Conn.Supp. at 294-95, 980 A.2d 983. As we have explained, in this state, we adhere to the principle that a statute of repose applies to the state only if the legislature clearly so indicates. Because none of the repose provisions on which the defendants rely contains any evidence of such intent — let alone the clear expression of intent necessary to overcome the strong presumption against waiver — the trial court had no basis for concluding that the legislature abrogated the rule of nullum tempus when it enacted those provisions.