FEUERSTEIN, District Judge.
On September 12, 2014, plaintiff National Audubon Society, Inc. ("plaintiff') filed: (1) a complaint pursuant to the Administrative Procedure Act ("APA"), 5 U.S.C. §§ 701-706, against defendants United
Subsequently, defendants moved, inter alia, to dissolve the TRO pursuant to Rule 65(d)(4) of the Federal Rules of Civil Procedure and to extend the briefing schedule for the preliminary injunction motion. By order dated September 17, 2014, defendants' motion was granted to the extent that their time to serve and file opposition to plaintiff's preliminary injunction motion was extended to October 2, 2014 and plaintiffs time to serve and file any reply was extended to October 6, 2014. Thereafter, plaintiff moved pursuant to Rule 408 of the Federal Rules of Evidence to strike certain paragraphs and exhibits of the Declaration of F. Franklin Amanat, dated September 16, 2014, submitted by defendants in support of their motion to dissolve the TRO ("the Amanat declaration").
Also pending before the Court is the motion of Fire Island Lighthouse Preservation Society ("FILPS") for leave to file a brief amicus curiae in opposition to plaintiff's motion for a preliminary injunction.
For the reasons set forth herein, all of the above referenced motions are denied.
The Project area stretches from Robert Moses State Park in the west to Smith Point County Park ("the Park") in the east, for a total of nineteen (19) miles, on Fire Island, New York. (Biological Opinion ["Bio. Op."] at 10). The Project includes "dune and beach construction * * [and] beach fill tapers (lateral extensions of dune and beach fill)" on Fire Island. (Bio. Op. at 5). The stated purpose of the Project is "to address shoreline erosion on Fire Island that occurred as a result of Hurricane Sandy ["the storm"] and to provide a level of storm damage protection to mainland developments * * *." (Id. at 10). Specifically, "[t]he storm created three breaches and extensive overwash areas on the eastern end of Fire Island," (id. at 11), particularly in the Park. (Id.)
On or about December 9, 2013, the Army Corps transmitted to the FWS the plan layout designs for the Project. (Bio. Op. at 5).
On or about December 13, 2013, the FWS provided recommendations to the Army Corps "to avoid or minimize impacts to listed and proposed species and their habitats[,]" (Bio. Op. at 5)
On or about December 16, 2013, the Army Corps transmitted to the FWS a preliminary Draft Environmental Assessment ("Draft EA"), including two (2) alternatives, i.e., a "No Action Alternative" and a "Beach Fill Alternative," that did not include a biological assessment for piping plovers because it was "being revised based on the December 13, 2013[] meeting." (Bio. Op. at 5-6).
On or about December 18, 2013, the Army Corps convened a meeting with the FWS, National Park Service ("NPS"), New York State Department of Environmental Conservation ("NYDEC"), Suffolk County Department of Parks, Recreation and Conservation ("SCDPRC") and Suffolk County Department of Public Works ("SCDPW") "to discuss endangered species conservation measures and habitat restoration alternatives in the proposed [P]roject area." (Bio. Op. at 6). The Biological Opinion indicates that at that meeting, the Army Corps "slightly modifie[d] the dune alignment at [Lighthouse Beach] * * * to address the [FWS's] December 13, 2013[] comments[;] * * * propose[d] to lower tolerance limits for berm elevation to 0.5 ft from 1.0 ft[;] [and] propose[d] several options for vegetation maintenance throughout the [P]roject area[] and habitat restoration near the east end of [the Park] in an area known as Great Gun Beach." (Id.)
On or about December 19, 2013, the Army Corps provided the FWS "its final
On or about January 9, 2014, the FWS transmitted correspondence to the Army Corps, inter alia, concurring with the Army Corps that the modifications adopted by it "are an improvement over [its] earlier proposed plan and impact less habitat than the earlier proposal," (Chang Decl., Ex. 6), but "identifying additional alternatives the [Army] Corps should consider for the [Park] portion of the project area," (Bio. Op. at 6), to "further diminish the impacts to habitat and provide storm protection[,]" (Chang Decl., Ex. 6). Those additional alternatives include "construct[ion] of an enhanced berm" only, with "no solid dune," at the Park; an "experimental" "`staggered dune' approach at [the Park] that would consist of two lines of dunes with overlapping staggered openings[;]" not having a dune constructed through "at least one of the three overwash lobes[;]" and having "breaks in the dunes[.]" (Id.) The FWS indicated, inter alia, that "[a]lthough [it] appreciate[s] monitoring and adaptive management of vegetation in specific [Park] areas, preserving the[] ocean-to-bay overwash lobes is most likely to provide the most recovery benefits." (Id.)
On or about January 10, 2014, the Army Corps provided the FWS with "updated project plans for a portion of the [P]roject at [the Park] * * * advis[ing] that the constructed dunes must be straight lines, with as shallow transitions as possible, but they can be modified during the Plans & Specification period of project planning[] * * * [and] that the back slope of the dune design can be modified slightly * * * for a `smaller' overall foot print." (Bio. Op. at 6).
On or about January 24, 2014, the DOI, Office of Environmental Policy and Compliance ("OEPC") submitted written comments and suggestions on the Draft EA, including comments from the United States Geological Survey ("USGS"), the NPS and the FWS, to the Army Corps. (Bio. Op. at 6; Chang Decl., Ex. 7).
On or about February 4, 2014, inter alia, the FWS received the Army Corps's Biological Assessment ("BA") and request for initiation of formal consultation pursuant to section 7 of the ESA for, inter alia, the piping plover. (Bio. Op. at 7).
On or about February 7, 2014, the Army Corps informed the FWS: (1) "that no beach fill will be placed within 1000 meters (m) of known populations of piping plover * * * during the breeding season[,]" (Bio. Op. at 7); and (2) that it expects "the effects of the [Project] will provide storm damage protection for approximately five years and then erode over the next five years to a point where it would not provide storm damage protection." (Bio. Op. at 7).
On or about February 12, 2014, the FWS met with the Army Corps, DOI, NPS and USGS to discuss the Project, the Army Corps's ESA responsibilities and the schedules for the BA and Biological Opinion. (Bio. Op. at 7).
On or about February 14, 2014, the FWS transmitted written comments to the Army Corps on, inter alia, the Project design. (Bio. Op. at 7).
Between February 20-21, 2014, a meeting, attended by the FWS, Army Corps, NPS and USGS, was held to discuss, inter alia, "the proposed [P]roject in more detail, looking at [P]roject features that
On or about February 28, 2014, the Army Corps transmitted, inter alia, a revised BA to the FWS, (Bio. Op. at 8), modifying its original BA to increase habitat in the Great Gun Area at the Park to be "managed for piping plovers to mitigate effects of [the Project]" from almost sixteen (15.7) hectares to nearly thirty-four (34) hectares, (Bio. Op. at 141), and to implement an additional six (6) hectare dredge site restoration on the bay side of the Park, south of New Made Island, to be "designed and managed to provide nesting and foraging habitat for plovers," (id. at 142).
On or about March 3, 2014, the Army Corps transmitted to the FWS, inter alia, its determination that the Project "may affect, and would be likely to adversely affect the piping plover * * *." (Bio. Op. at 8).
On or about March 4, 2014, (1) biologists from the FWS and Army Corps discussed the Project "and several areas where clarification in the [P]roject description [was] needed[,]" (Bio. Op. at 8); (2) the Army Corps "follow[ed] up via electronic correspondence addressing such issues as local maintenance of the [P]roject, land use management that might occur in the [P]roject area after construction, and [its] commitment to continue to work with the [FWS] on issues related to predator management and pre-, concurrent, and post-construction monitoring in the [P]roject area[,]" (id.); and (3) the FWS transmitted to the Army Corps correspondence accepting the BA, thereby officially beginning the process of formal consultation under the ESA. (Id.)
On or about May 7, 2014, a meeting, attended by, inter alia, the Army Corps, the NPS, the FWS, the NYSDEC and Suffolk County, was held "to discuss the County's proposed changes to the [Army] Corps's proposed [P]roject description for the area in [the Park] and * * * the [FWS's] draft biological opinion[] * * * preliminar[ily] determin[ing] that the [P]roject, as proposed, was likely to jeopardize the continued existence of the piping plover * * *." (Bio. Op. at 9). The FWS explained that its preliminary determination was based upon "the status of the species, environmental baseline, effects of the action, and cumulative effects of the [P]roject, as well as the regulatory standard required when undertaking jeopardy analyses." (Id.)
On or about May 8, 2014, a meeting attended by the Army Corps, the NPS, the FWS, the NYSDEC and Suffolk County, was held "to solicit comments on the [FWS's] methodology in evaluating the effects of the [Project], including an assessment of the carrying capacity of storm-created habitats affected versus those not affected by the proposed [P]roject and the with—[P]roject scenario." (Bio. Op. at 9).
Between May 15-16, 2014, a meeting, attended by the Army Corps, the NPS, the FWS, the DOI, the NYSDEC and Suffolk County, was held "to finalize conservation measures to minimize impacts to the piping plover." (Bio. Op. at 9).
On May 23, 2014, the FWS delivered its final biological opinion ("the Biological Opinion") to the Army Corps. (Bio. Op. at 9).
The Biological Opinion is based upon information provided in the Army Corps's final revised BA (Bio. Op. at 4, 12), and numerous other sources, (see Bio. Op. at 184-210).
The Biological Opinion indicates that the Project "includes dune and/or beach construction for 19 mi[les] of the entire 30
Piping plovers that breed on the Atlantic Coast of the United States and Canada ("the Atlantic Coast piping plover"), such as those at issue here, are classified as threatened under the ESA and breed "on sandy, coastal beaches from Newfoundland to North Carolina." (Bio. Op. at 49, 53-54). "[W]ide, flat, sparsely-vegetated barrier beach habitats * * * [that] include abundant moist sediments associated with blowouts, washover areas, spits, unstabilized and recently closed inlets, ephemeral pools, and sparsely vegetated dunes" are important for the recovery of Atlantic Coast piping plovers. (Id. at 49, 54, 56). Although Atlantic Coast piping plovers "may also nest on areas where suitable dredge material has been deposited at a low slope and elevation, * * * many factors * * * affect their nesting density and success in th[o]se areas." (Id. at 54). The FWS determined that piping plover "[h]abitat became unsuitable when vegetative cover exceeded 33.5%, distance from the high tide line to toe of the dune was less than 9.5 meters, dune height exceeded 2.0 meters, and dune slope exceeded 20%[,]" (id. at 49), and that "piping plovers respond positively to the creation of high quality habitat * * *." (Id.)
Four (4) recovery units have been established for the Atlantic Coast piping plover in an approved recovery plan, i.e., the 1996 revised Atlantic Coast Recovery Plan: (1) Atlantic (Eastern) Canada; (2) New England; (3) New York-New Jersey; and (4) Southern (Delaware, Maryland, Virginia and North Carolina). (Bio. Op. at 59).
"The preliminary 2013 Atlantic Coast piping plover population estimate was 1,797 pairs, more than double the 1986 estimate of 790 pairs * * *[,]" (Bio. Op. 62), representing "a net 1989-2013 increase of 88%." (Id.) "Abundance in the New York-New Jersey recovery unit experienced a net increase of 24% between 1989 and 2013, but the population declined sharply from a peak of 586 pairs in 2007 to 397 pairs in 2013 (-32%) * * *." (Id. at 63). "During [that] period, several storms occurred as did beach stabilization and nourishment efforts, and human development increased * * *." (Id.) "Changes in the Long Island population account for most of the absolute growth in the recovery unit population through 2007 and most of the decrease that has occurred in the last six years." (Id.) "On Long Island, the south shore has been the greatest contributor to population changes (both positive and negative), supporting about 50% of the entire recovery unit population." (Id.) "Low abundance in New Jersey and recent steep decreases in abundance on Long Island (especially on the south shore) contribute to the recovery units [sic] demographic vulnerability." (Id.)
"[L]oss and degradation of habitat remains a very prominent threat to piping plovers in the New York-New Jersey recovery unit."
"A detailed review of threats to piping plovers and their habitat in their continental U.S. migration and wintering range * * * shows a continuing loss and degradation of habitat due to sand placement projects, inlet stabilization, sand mining, groins, seawalls and revetments, dredging of canal subdivisions, invasive vegetation, and wrack removal." (Bio. Op. at 51). "It is believed habitat loss and degradation via artificial coastal stabilization are limiting growth and expansion of the recovery unit population of Atlantic Coast piping plovers, especially in the New York-New Jersey and Southern recovery units[,] [as] [t]he rates of habitat loss are increasing coincident with more stabilization activities." (Bio. Op. at 52). "[C]ontinuing artificial shoreline stabilization perpetuates many low quality habitats * * * and [w]idespread artificial habitat stabilization also exacerbates conflicts with human beach recreation by constraining nests and chicks to narrow ocean-front habitats." (Id. at 51, 73). "This, in turn, increases the costs and effort required to manage threats to plovers from human and pet disturbance to the point where sustainability of th[o]se efforts may be compromised." (Id. at 73).
"While it is expected that carrying capacity will fluctuate locally, and perhaps even within a state over time, it is anticipated that long-term carrying capacity of the Atlantic Coast[] piping plover habitat * * * will be maintained if natural coastal habitat formation processes are not interrupted." (Bio. Op. at 50-51, 71). "The 1996 revised [R]ecovery [P]lan states that discouraging new structures or other developments, discouraging interference with natural inlet processes, and discouraging beach stabilization projects are `priority 1' actions (those that must be taken to prevent extinction or to prevent the species from declining irreversibly in the foreseeable future)." (Id. at 51, 83, 115-16). "Studies and reports completed since the recovery plan * * * reinforce the continued importance of protecting preferred piping plover breeding habitats and the natural coastal processes that form and maintain them." (Id.) "Scientific research conducted on Long Island explicitly recommended avoiding beach management practices (e.g., jetty construction, breach filling, dune building, beach nourishment) that typically inhibit natural renewal of ephemeral pools, bay tidal flats, and open vegetation * * * and allowing natural storm processes that create habitat to act unimpeded * * *." (Id.)
"The piping plover population in the action area (Fire Island) has supported as many as 54 pairs of piping plovers (in 2008)." (Bio. Op. at 110). "The most consistent and major breeding sites over the last 15 years are Democrat Point, Fire Island Wilderness, and [the Park]." (Id. at 113). Prior to Hurricane Sandy, Democrat Point was the only site that provided the preferred "bay to ocean overwash" habitat for piping plovers. (Id.) Although bay to ocean overwash habitats were formed at the other two (2) sites by Hurricane Sandy, that habitat "was only available to piping plovers at Democrat Point and Old Inlet due to partitioning of beach habitat undertaken by Suffolk County to delineate recreational ORV use areas and plover breeding habitats." (Id.) Prior to the formation of a partial overwash area at Lighthouse Beach, "all plover breeding habitat in [that] area[] was limited to the ocean beach south of an established dune line." (Id.)
Between 2009 and 2013, the total number of breeding pairs of piping plover declined by fifty percent (50%) and "productivity [chicks fledged per pair] for piping plovers on Fire Island and the surrounding Long Island area has been declining for the past 14 years * * *." (Bio. Op. at 113-14). "The 1996 Recovery Plan calls for a productivity level of 1.5 to create an increasing population and achieve recovery." (Id. at 114). "2013 productivity levels for Fire Island were close to 0.7, well below replacement." (Id.)
"Although the Fire Island piping plover population declined to 27 pairs in 2013, Hurricane Sandy created approximately 162 hectares of new overwash habitat on Fire Island including at least 84 hectares of new overwash habitat located within the
Furthermore, the FWS determined that "susceptibility of the [P]roject area to additional overwash during future storms * * * creates the likelihood of more habitat formation in the action area[,]" (id.); that "habitat availability will be the primary determinant of whether the breeding population is actually able to increase[,]" (id.); and that "[i]n light of the widespread development and continuing stabilization elsewhere in the recovery unit, [Fire Island] plays a pivotal role via provision of existing habitat and the potential for future habitat formation that are key to survival and recovery of the piping plover in the New York-New Jersey recovery unit" (Id. at 110-11).
The FWS determined that "[h]abitat limitation, loss, fragmentation, beach stabilization, avian and mammalian predators, recreation, and ORV use * * * are all factors negatively affecting the species [sic] environment, distribution, reproduction and abundance on Fire Island[,]" (Bio. Op. at 107-08, 115), and that "[t]he vast majority of the 30 miles of beaches on Fire Island have been heavily impacted by habitat loss due to development, as well as, beach stabilization and recreational activities for decades leading to the precarious conservation status of the species within the action area."
Moreover, the FWS determined that "[t]he stabilized beach system on Fire Island has limited piping plover to narrower
The FWS further determined that "[t]here are numerous potential sources of disturbance to plovers that may utilize the FIIS including, but not limited to, ORVs [off-road vehicles], aircraft, recreational fishing, kite-flying, bird-watching, surfing, dog-walking, fireworks events, and vehicle patrols undertaken by law enforcement agencies that operate within the FIIS[]," (Bio. Op. at 108, 118); that "breeding habitat on Democrat Point is limited due to establishment of recreational ORV areas[,]" (id. at 118); that "ORV tire tracks can cause deep ruts which are impassable to chicks * * *, causing them to become entrapped[,]" (id.); and that ORV "use can reduce the quality of available foraging habitat[,] * * * compact and reduce any existing foraging base * * * [and] * * * result in mortality of adults, nests, and chicks[,]" (id. at 119).
The Biological Opinion indicates that the NPS's decision "to postpone moving forward with a consultation and proposal to fill in [the breach at Old Inlet] caused by Hurricane Sandy * * * [in order] to maintain newly created habitat as beneficial habitat for piping plovers for a period longer than if the breach were closed immediately through human action[] * * * is believed to provide a net benefit to the environmental baseline for piping plovers over the life of th[e] [P]roject." (Bio. Op. at 111). Other "[b]eneficial actions include monitoring and protection programs implemented by the NPS FIIS, NYSOPRHP, and [SCDPRC]," (Bio. Op. at 115), including the delineation and protection of "[s]uitable habitats * * * with symbolic fencing and monitor[ing] by staff[,]" (id.), and the implementation of "[v]ehicle closures * * * around breeding areas when flightless chicks are present[,]" (id.).
The FWS determined that the Project "would perpetuate stabilization of beach habitats with likely negative consequences to the piping plover[,]" (Bio. Op. at 125), and "would affect all existing overwash areas and * * * impair the formation of new overwash habitats within the project area[,] * * * [which] are the preferred habitats of the piping plover * * *." (Id. at 12). "Consequently, the [] [P]roject would result in short- and long-term changes to plover nesting, foraging, and chick rearing habitats, ultimately affecting the species' numbers, distribution, and reproduction in the wild." (Id.) In addition, the FWS determined that the Project (1) "would directly and indirectly impact occupied piping plover breeding habitat across all of Fire Island[,]" (id. at 122); (2) "would indirectly affect habitats not within the project area, but adjacent to dune and beach construction activities due to longshore littoral drift," (id. at 12); and (3) "would result in both immediate and long
(Id. at 122-23, 125).
The FWS determined that other adverse effects of the Project "include interruption and prevention of formation and maintenance of optimal habitats * * *, longer term reduction in prey resources * * *, increased recreational activities, the creation of habitat conditions that may facilitate increase [sic] mortality due to predators, and allowance for ORV access through breeding areas * * *." (Id. at 123). In addition, the FWS found that proposed "[s]and fencing can affect dune topography and promote the formation of steep, uniform dunes * * * [and] may also affect the movement of mesopredators (such as raccoons, red fox and feral cats), provide denning habitat for fox, and serve as perch sites for avian predators." (Id. at 123, 138-39). Nonetheless, the FWS concluded that "[t]he degree to which increases in predator habitat result in mortality or disturbances to plovers and their chicks depends on the degree to which the protection measures are implemented." (Id. at 139).
The FWS further determined that "[r]ecreational activities that may potentially, adversely affect piping plovers include unleashed pets, fireworks, kite-flying, and increase in garbage and refuse * * *[,]" (id. at 123, 137), insofar as "[u]nleased pets, such as dogs and cats, can prey on piping plovers * * * [and] [k]ite-flying may disturb piping plovers as it is believed that the piping plovers perceive kites as avian predators[,]" (id.); and that "[i]ndirect effects of disturbance to piping plovers also occur by limiting breeding habitat to oceanside habitats that are simultaneously made more attractive for recreational activities by beach stabilization projects." (Id. at 138). Nonetheless, the FWS determined that "[o]verall, the degree to which increases in recreational activity result in mortality or disturbances to plovers and their chicks depends on the degree to which the protection measures are implemented." (Id.)
The FWS determined that "[a]ll current sub-populations of breeding plovers and occupied habitat on Fire Island, totaling about 26 pairs, would be impacted by the proposed [P]roject[,]" (Bio. Op. at 125), and indicated that "[b]ecause of the small number of breeding sites on Fire Island,
The FWS determined that although the Army Corps proposed that construction activities will not occur in the Park or at Lighthouse Beach during the piping plover season, i.e., from April 1st to September 1st, "[p]otential direct effects of [its] construction and dredging activities upon piping plovers during initial construction include * * *[:]
(Id. at 126). The FWS further determined that "[t]o the extent that the [Army] Corps adheres to the 1,000 m buffer in the FIIS Communities, [it] believes that the potential for impacts will be minimized, but will not be eliminated." (Id. at 127).
The FWS determined that preferred plover habitats at the Park and Lighthouse Beach "would be degraded and fragmented by the [] [P]roject." (Bio. Op. at 127). Specifically, the FWS found that about one hundred twenty-one (121) acres at the Park "would be fragmented by the dune and vegetation, along with the re-establishment of Burma Road * * *[,]" and that more than sixty (60.3) acres of preferred habitat at Lighthouse Beach would be fragmented and impacted by "the artificially constructed berm." (Id.) In addition, "[t]he dune and beach fill would raise both the berm and dune elevation of the barrier island further decreasing habitat heterogeneity." (Id.)
The FWS indicated its "concern[] that the [] [P]roject would disrupt complex natural processes that create bayside and bay to ocean intertidal foraging habitats, and
The FWS estimated that without the Project, the preferred habitats created by the storm "could support close to 60 nesting pairs of plovers if left in their post-storm condition[,]" (Bio. Op. at 129), "assum[ing] full connectivity of bay to ocean habitat," but indicated that that assumption "is uncertain given the existing Burma Road, which is currently degraded from pre-Hurricane Sandy conditions but in use." (Id. at 130). The FWS, thus, determined that the `without project' estimate that 60 pairs worth of nesting habitat is available is not the best interpretation of reality given that ocean to bay habitat is already truncated in some fashion by previous, recent anthropogenic habitat modification, e.g., sand fencing, vehicle use * * *[,]" (id. at 147), and that, "based upon the best available science and experience," (id. at 148), a more reasonable `without project' estimate [is] 51.25 for the entire project area[,]" (id. at 147).
The FWS estimated that the potential nest area "with Project" capacity would "support plover nesting ranges from 17 to nearly 40 pairs," (Bio. Op. at 130), and indicated that the reduction in the potential nest area capacity "would result mostly from the fragmentation and degradation of preferred habitats via construction of the artificial dune * * *[,]" (id. at 131). The FWS ultimately determinated that a reasonable estimate for potential nest area "with project" capacity "based on the best available science and experience" is 40.32 pairs. (Id. at 148).
The FWS determined that although "[b]each nourishment may provide nesting substrate for the species, * * * recent surveys undertaken at beach nourishment projects on Fire Island showed that th[o]se habitats supported low numbers of breeding pairs with limited to no reproductive output, and experienced high levels of recreational disturbance and degradation due to off-road vehicle use * * *." (Bio. Op. at 132). "Further, the density of piping plovers that are confined to ocean-side habitats is much lower, when preferred bayside foraging habitats are absent." (Id.) The FWS determined that "[c]onsequently, artificially created beaches without access to high quality bayside foraging areas, may lead to `population sinks' by recruiting individuals to the area each season, only to yield reproduction levels less than one chick per pair which is below the level necessary to achieve a stationary population level." (Id.) The FWS further determined that "[i]n the event that plovers colonize these beaches they will experience loss of habitat area annually, as the beach erodes back to a stabilized dune[,]" (Bio. Op. at 132), and that "[b]ecause piping plovers demonstrate breeding site fidelity to their breeding sites, they are likely to persist in attempting to breed in these areas, even if these habitats degrade and plover productivity declines in future years." (Id.) According to the FWS, "[i]n
In addition, the FWS determined that "[h]abitat loss and adverse alterations can also result from physical changes to artificially constructed dunes and beaches." (Bio. Op. at 133) "Natural forces, which work to redistribute the sand that is placed on the beaches during nourishment projects, may create a sharp discontinuity of slopes between the upper beach and the intertidal zone, inhibiting the movement of piping plovers, especially chicks, into intertidal foraging areas." (Id.) In addition, beach scraping "may reduce the size of the intertidal foraging area, inhibit adult and chick movement into the intertidal zone, and possibly delay the formation of an upper beach wrack line, an important foraging habitat for piping plovers and their chicks." (Id.)
The FWS determined that "[c]onstruction between mid-October and January * * * may result in reduced productivity, or possibly abandonment of piping plover nesting areas because of reduced prey resource availability * * *[,]" (Bio. Op. at 137), and that the Project "would be expected to impact prey resources for breeding adults and their chicks at least one breeding season." (Id.) Nonetheless, the FWS determined that "[e]xcept where curtailed by mechanical beach raking or delayed by scarping [sic], partial to complete physical recovery of the organic material that comprises the wrack line can be expected within one year following sand nourishment, depending on the timing of the construction activity." (Id.)
The FWS determined that "[p]rivate projects to stabilize beaches, increase recreation, or build ORV roads are expected to degrade or destroy beach habitats such that plover population expansion is curtailed[,]" (Bio. Op. at 139); that "Suffolk County is planning to restore further Burma Road in [the Park] which would result in adverse effects * * * [and,] along with unregulated recreational activities such as boat landing and unrestricted pedestrian access[,] will disturb adults and prevent chick[s] from accessing bay side foraging habitats," (id. at 140); that "Marge scale habitat fragmentation is expected to occur at [the Park] as the [SCDPRC] further establish [sic] Burma Road as an ORV route within overwash habitat and piping plover breeding areas[,] [which] will destroy and degrade about 2.0 mi[les] of plover habitat," (id.); and that "[a]s part of [that] action [the SCDPRC] will install sand fences and plant beach grass, further stabilizing the beaches, and adversely affecting plovers and their habitats." (Id.)
The FWS further determined that although the "NYSDEC would be expected to continue to be able to issue tidal wetland permits for ocean and bay side stabilization activities, such as bulkhead construction, dune stabilization through sand bags and geotubes, and breach scraping[,] * * * it is uncertain the extent to which [that] action is expected to continue into the future * * *." (Bio. Op. at 140).
Additionally, the FWS determined that "[t]he NYSOPRHP will likely continue to stabilize their beaches using material from dredging projects or upland sources[,]" (Bio. Op. at 140), and that those activities falling outside of the Army Corps's regulatory jurisdiction, e.g., breach scraping, dune construction, the installation of sand
The Biological Opinion indicates that "[f]or a period of ten years after project completion, the [Army] Corps has proposed to implement a number of conservation measures to avoid or minimize adverse effects of the dune and beach construction to the piping plover * * *." (Bio. Op. at 16).
With respect to Lighthouse Beach, the proposed conservation measures include modifying "the dune and beach design template" (a) to provide for "a `straight' dune alignment," (id. at 17)
With respect to the Park, the Army Corp "indicated that it is not feasible to eliminate the proposed dune and beach or vary their heights * * * without compromising coastal storm risk reduction or severely curtailing management activities, operations, and recreational use within th[e] [P]ark." (Bio. Op. at 18).
Additional conservation measures proposed by the Army Corps include: (a) modifying "the extent of length of each fill taper on federal lands on Fire Island to 300 ft.[,]" (Bio. Op. at 16-17); (b) removing vegetation in the area known as Great Gun Beach and managing the habitat "from an approximately 82 [acre] area to provide habitat for endangered species * * *[,]" (id. at 19), "as an experimental approach to mimic early successional habitat[,]" (id. at 20); (c) "monitor[ing] and adaptively manag[ing] vegetation at 30-40% cover on the bayside * * * via mechanical, manual, or chemical means dependent on conditions and regulations of [SCDPRC] and the NYSDEC," (id. at 19); (d) planting beach grass on the dunes at a density of eighteen (18) inches on center within the FIIS communities; (e) coordinating with the FWS "in the preparation of a predator plan (mammalian) for pre-season and inseason predator monitoring program for all project areas, * * * includ[ing] measures needed to protect piping plovers, nests, and chicks," (id. at 20), to be implemented for ten (10) years; (f) clearing vegetation and modifying topography of an additional 6 ha [hectares] (15.8 ac [acres]) of bay side habitat south of New Made Island, as an experimental approach to mimic nesting and foraging plover habitat[,]" (id.); (g) contacting the FWS "upon initiation and completion of construction activities[,] * * * conduct[ing] pre-construction
The FWS determined that the Project "would, through each estimate, reduce the overall nesting area for future piping plovers[,] * * * [which they] need * * * to recover, * * * [but] that plover productivity on Fire Island, and the surrounding Long Island areas, is failing and is not on a path to recovering the species * * *, probably due to a mix of management-related elements, such as predator and vegetation management." (Bio. Op. at 141). The FWS recognized the "many competing uses for Fire Island, e.g., recreation, storm protection, plover habitat" and the "need to operate in the current context of th[o]se competing uses." (Id.) Accordingly, the FWS determined that "[a]chieving recovery for the plover is dependent on cooperation from State, County and Federal partners, and other local landowners, and possibly on the creation of new habitat alternatives, such as engineered habitat," (Id.), since "[i]t may be as real and detrimental an outcome for the plover if the [FWS] were to not work cooperatively with State, County and Federal partners, and other local landowners, thereby not fully engaging their ability to promote recovery, than if significant plover habitat quantity and quality was degraded." (Id.)
The FWS further determined that "[r]estored and managed habitat for plovers may be essential for the long-term recovery of plovers in the NY and NJ recovery unit, and the[] engineered and created areas and subsequent monitoring [proposed as conservation measures in the Project] will provide essential information to help [it] learn how best to restore [plover] habitats." (Bio. Op. at 142). Accordingly, in order to "improve the quality and productivity of the available habitat," the various agencies, including the FWS and the Army Corps, agreed: (1) to implement (a) a coordinated inlet-to-inlet monitoring program, led by the NPS, "to add consistency to the monitoring and reporting of plover reproductive activities," (Bio. Op. at 142), (b) a coordinated ten (10)-year inlet-to-inlet mammalian predator management program, funded through the Army Corps, (id.), and (c) a coordinated stewardship/visitor management program to attempt "to
The Biological Opinion indicates that "[t]he central question associated with [the FWS's] jeopardy analysis is whether the effects of the [Army] Corps [sic] [Project], together with cumulative effects, are likely to preclude or impair the capacity of the New York-New Jersey recovery unit from providing both the survival and recovery function assigned to it." (Bio. Op. at 145). "In other words, are the effects of the [Army] Corps [sic] [Project], together with cumulative effects, likely to preclude or impair the capability of th[e] [New York-New Jersey] recovery unit to support a minimum breeding population of 575 pairs of piping plovers that produce, on average, 1.5 fledged young per nesting pair?" (Id.) The FWS determined that the Project "will have an effect on the amount of nesting habitat available, even with the restoration acreage offered in the amended BA," (Id. at 148), but that its estimates regarding nesting density with and without the Project "do not quantitatively include the multiple expected benefits from the agreed to management actions[,]" (id.), which "will serve to improve the recovery outlook for the plovers." (Id. at 149). Although set forth in the "Incidental Take Statement" section of the Biological Opinion, the FWS determined that the "level of anticipated take is not likely to result in jeopardy to the species or destruction or adverse modification of critical habitat." (Bio. Op. at 150).
The FWS determined that "the [P]roject as described in the BA (amended, May[] 21, 2014) will take up to 11 pairs of piping plover, through the modification of habitat[,] * * * equal[ing] to roughly 1 pair each year of the project[,]"
The FWS further determined that the following "reasonable and prudent measures are necessary and appropriate to minimize impacts of incidental take of piping plovers," (id.): (1) the development and implementation (a) "of a coordinated mammalian predator management strategy across all major landowners, inlet to inlet, on Fire Island to reduce the threat predators pose to piping plovers for the 10 year expected life of the project[,]" (id.), and (b) "of a coordinated piping plover monitoring program, inlet to inlet, on Fire Island, to assess the current and future status of plovers on Fire Island[,]"
The Incidental Take Statement sets forth the "nondiscretionary" terms and conditions implementing the reasonable and prudent measures with which the Army Corps must comply "[i]n order to be exempt from the prohibitions of Section 9 of the [ESA][,]" (Bio. Op. at 151-52), and indicates that "[t]he reasonable and prudent measures, with their implementing terms and conditions, are designed to minimize the impact of incidental take that might otherwise result from the proposed action[,]" (id. at 152). The Incidental Take Statement further provides that "[i]f, during the course of the [Project], th[e] level of incidental take [of no more than 11 pair of piping plover] is exceeded, such incidental take represents new information requiring reinitiation of consultation and review of the reasonable and prudent measures provided[,] [and] [the Army Corps] must immediately provide an explanation of the causes of the taking and review with the [FWS] the need for possible modification of the reasonable and prudent measures." (Id. at 152-53). Moreover, "[i]n instances where the amount or extent of incidental take is exceeded, any operations causing such take must cease pending reinitiation." (Id. at 153).
The EA indicates that the stated purpose of the Project is "to reinforce the existing dune and berm system along [Fire Island]," (EA at 10), because "[r]ecent storm events, most notably Hurricane Sandy in 2012, have reduced sand volumes of beaches and dunes in the project area, leaving communities on the coastal barrier and along the bay shores north of Fire Island vulnerable to potential future storm surges." (Id.)
The EA evaluates two (2) alternatives: (1) the "No Action Alternative" and (2) a "Beach Fill Alternative," i.e., the Project, (EA at 14), with the latter being "the recommended alternative and [] the environmentally preferred plan because it reduces storm damages in a manner that mimics the natural protective features of the barrier island * * *." (Id.)
The EA indicates that although the Army Corps and federal government would take no action to reduce storm damages in the study area under the "No Action Alternative," local governments and non-governmental groups, e.g., homeowner associations, "could take actions to protect themselves by undertaking their own construction projects to build up the beach and dune profiles." (EA at 14, 61). Some of the elements that the Army Corps found "likely to occur within the No Action Alternative" include, inter alia,"[p]eriodic beach fills and beach scraping * * * by local governments and home owner associations
The Project is comprised of three (3) design templates: (1) the "berm only" template, proposed for areas on Fire Island "where eroded berm conditions have been observed, but where existing dune elevation and width are sufficient to reduce the risk of overwashing and breaching," (EA at 15), i.e., Robert Moses State Park, western Smith Point County Park and the TWA Memorial beach; (2) the "small" template, including berms and vegetated dunes at specified elevations, widths and foreshore slopes, "intended to reduce the risk of breaching" and "proposed for areas with limited oceanfront structures, including [the Park]," (id.)
The EA indicates:
(EA at 16). In addition, the EA identifies certain conservation measures and or project design adjustments undertaken by the Army Corps, including:
(EA at 21-22).
The Army Corps evaluated the environmental impacts, i.e., the effects upon the human environment; socioeconomics; transportation; recreation; cultural resources; physical environment, including water quality, geology/geomorphology and borrow areas; and natural resources, under both the No Action Alternative and the Project. (EA at 61-100).
Generally, the Army Corps concluded:
(EA at 61). The Army Corps also found that under the No Action Alternative "storms analogous to historic trends, consisting of frequent minor to moderate events, are likely to result in moderate adverse impacts to" land use and communities, social and economic interests, transportation, and recreation, and that those impacts "would be expected to be short to long term, depending on storm frequency and severity." (Id. at 61-63).
In addition, the Army Corps concluded, inter alia, that under the No Action Alternative "[a] single catastrophic storm event outside of the wilderness area, is likely to result in severe adverse impacts to transportation, including potential loss of roadways,
With respect to the effects upon the physical environment, the Army Corps concluded, inter alia:
(EA at 65-66).
With respect to the effects upon natural resources, and specifically, endangered or threatened species, the Army Corps concluded, inter alia, that the No Action Alternative "will continue the current level of protection that is afforded for rare and endangered species occupying the project area." (EA at 68, 73). With respect to migratory wildlife, the Army Corps concluded that the "No-Action Alternative is expected to have little beneficial to no impact on [the rare migratory bird species that may utilize the Project area referenced in another section of the EA, including the piping plover]." (Id. at 58, 68).
In addition, the Army Corps concluded that "[u]nder the No-Action alternative, there would be continuing shoreline erosion and a strong possibility of a breach or overwash occurring during a tropical or extra-tropical storm." (EA at 68). According to the Army Corps:
(EA at 68-69).
With respect to the specific effects of the No Action Alternative upon the piping plover, the Army Corps concluded:
(EA at 73, 92).
The EA indicates, in relevant part, that with the Project:
(EA at 75-76).
The Army Corps determined that with the Project, "storms analogous to historic trends, consisting of frequent minor to moderate events, are likely to result in minor adverse impacts to" land use and communities, social and economic interests, transportation, and recreation, and that those impacts "would be expected to be short term, depending on storm frequency and severity." (Id. at 76-77). In addition, the Army Corps determined that "[a] single catastrophic storm event is likely to result in minor to moderate adverse impacts to transportation. While some flooding and minor road damages could occur, there would be no loss of transportation systems. These impacts would be expected to be short term and there would be no loss of essential transportation, including for emergency services." (EA at 76).
With respect to impacts upon the physical environment, the Army Corps determined that the Project:
(EA at 79). In addition, the Army Corps determined that "[i]mpacts to the physical characteristics of the borrow area would be expected to be adverse, minor to moderate and short term." (Id. at 80).
With respect to the impacts of the Project upon natural resources, the Army Corps concluded:
(EA at 84-91). Specifically with respect to the piping plover, the Army Corps concluded, in relevant part:
(EA at 92-94).
The Army Corps concluded that
(EA at 101, 108).
With respect to the No Action Alternative, the Army Corps determined that "[b]ecause of the low percentage of disturbance and the recolonization potential, no cumulative impacts from [ongoing Federal and State civil projects occurring within close proximity to the Project] is expected" under the No Action Alternative. (EA at 101).
With respect to the cumulative impacts of the Project, the Army Corps concluded:
(EA at 102). In addition, the Project was modified to include, inter alia, the following conservation measures in order "[t]o minimize adverse impacts on the listed species," (EA at 102), by increasing protection and improving productivity:
(EA at 102-03). In the EA, the Army Corps indicated its belief that "the aforementioned modifications to the [P]roject will protect the available bayside, maintain habitats that might otherwise deteriorate over time, * * * create new habitat from areas currently unsuitable[,] * * * provide for more suitable habitat over time and potentially increase overall plover productivity of the area and advance the recovery of the species." (EA at 103).
In addition to the aforementioned Project modifications, the Army Corps agreed, inter alia, to the following conservation measures: to conduct surveys during the spring and summer, and prior to construction activities, to identify nesting plover in the Project area and document all known locations of piping plover for ten (10) years; to plant dunes at low densities; to contact the FWS upon initiation and completion of construction activities and to hold pre-construction meetings with all project staff to provide all information on resource protection and terms of the Project; to provide all Project personnel and construction staff with information regarding the conditions, including all conservation measures, of the Project; to refrain from all construction activities between April 1 and September 1, unless breeding piping plovers are not observed in an area, or are not within one thousand (1000) meters of an area by July 15; and to undertake only low impact construction activities, such as beach surveying, during the piping plover breeding season, utilizing a three hundred (300)-feet buffer zone. (EA at 104). In addition, the Army Corps agreed: (1) to implement, in coordination with the FIIS, Suffolk County and the FWS, a monitoring program for ten (10) years to be undertaken by a designated biologist who will be educated about the species and required to attend a piping plover management course organized by the FWS, the NYSDEC and The Nature Conservancy and who will "recommend and implement changes in the location and configuration of symbolic fencing and warning signs and gauge the effectiveness of management actions[,]" (EA at 104); (2) to place symbolic fencing and warning signs around suitable habitat within the Project area prior to piping plover breeding season and in coordination with the land manager(s) and the FWS's biologists; (3) to prohibit all pedestrian and ORV access into, or through, the breeding areas; (4) to conduct productivity and population surveys and record such information each year; and (5) to coordinate with the FWS in the preparation of (a) a de-vegetation plan within the three (3) primary overwash areas in the Park for ten (10) years and (b) "a predator plan (mammalian) for pre-season and in-season predator monitoring program for all project areas * * * for ten years of activity[,]" (EA at 104-07).
The Army Corps determined that since "the mitigative measures * * * will lessen temporary impacts," (EA at 108) and the Project "is designed to minimize adverse environmental impacts, the cumulative impacts to occur on the south shore of Long
(EA at 108).
On July 3, 2014, the Army Corps issued a FONSI determining, inter alia, that the Project "does not constitute a major Federal action significantly affecting the quality of the human environment" and, therefore, does not require the preparation of a detailed EIS. (FONSI, ¶ 4). That determination was based upon, inter alia, the following factors:
(FONSI, ¶ 4). The Army Corps found that the Project "would result in no significant adverse environmental impacts and is the alternative that represents sound engineering practices and meets environmental standards." (Id., ¶ 5).
On September 12, 2014, plaintiff filed: (1) a complaint pursuant to the APA against defendants challenging (a) the Biological Opinion issued by the FWS under Section 7(a)(2) of the ESA and (b) the EA and FONSI issued by the Army Corps under NEPA; and (2) an application pursuant to Rule 65 of the Federal Rules of Civil Procedure seeking a TRO and preliminary injunction enjoining defendants "from undertaking, either directly or indirectly, or causing or allowing [their] contractors * * * to undertake, the destruction or modification of upland areas, beaches, intertidal areas, tidal flats, ephemeral pools, and shorelines at [the Park] and [the Beach] * * *, including the construction of dunes, berms or roads, the operation of motorized equipment, and any other activity that alters or may have the effect of altering, either temporarily or permanently, the physical condition of the aforementioned areas [pending a ruling on the motion for a preliminary injunction and during the pendency of this action, respectively]." (OTSC at 2-3). The complaint seeks declaratory and injunctive relief and asserts the following eight (8) causes of action: (1) that the FWS's Biological Opinion is arbitrary and capricious, an abuse of discretion and not in accordance with law because (a) it "contains no explicit determination setting forth the Secretary's opinion whether the [] Project is likely to jeopardize the Atlantic Coast
By Order dated September 12, 2014, inter alia: (1) defendants were ordered to show cause, by filing a memorandum in response to the plaintiff's application and any supporting evidence on or before September 18, 2014, why a preliminary injunction should not be issued; and (2) plaintiff's application for a TRO was granted upon its posting of an undertaking in the amount of ten thousand dollars ($10,000.00) pursuant to Rule 65(c) of the Federal Rules of Civil Procedure. Plaintiff posted the requisite undertaking on September 15, 2014.
On September 16, 2014, defendants filed a motion seeking, inter alia: (1) to dissolve the TRO pursuant to Rule 65(dX4) of the Federal Rules of Civil Procedure; and (2) to extend their time to oppose the motion for a preliminary injunction for two (2) weeks, i.e., until Thursday, October 2, 2014, and plaintiff's time to reply thereto until Monday, October 6, 2014. By order dated September 17, 2014, inter alia, the branch of defendants' motion seeking extensions
On September 18, 2014, plaintiff filed a cross motion seeking to strike certain paragraphs and exhibits of the Amanat declaration pursuant to Rule 408 of the Federal Rules of Evidence.
At 6:53 p.m. on October 1, 2014, defendants filed a motion ("defendants' October motion") seeking, inter alia: (1) to have this Court deem the TRO expired on September 26, 2014 by operation of law pursuant to Rule 65(b)(2) of the Federal Rules of Civil Procedure, or, in the alternative, to dissolve the TRO pursuant to Rule 65(b)(4) of the Federal Rules of Civil Procedure; and (2) an additional three (3)-week extension of time, i.e., until Friday, October 24, 2014, to oppose plaintiff's motion for a preliminary injunction. By order dated October 6, 2014, inter alia, defendants' October motion was denied in its entirety.
Also pending before the Court is FILPS's motion for leave to file a brief amicus opposition to plaintiff's motion for a preliminary injunction.
"In general, district courts may grant a preliminary injunction where a plaintiff demonstrates `irreparable harm' and meets one of two related standards: either (a) a likelihood of success on the merits, or (b) sufficiently serious questions going to the merits of its claims to make them fair ground for litigation, plus a balance of the hardships tipping decidedly in [its] favor * * *." Otoe-Missouria Tribe of Indians v. New York State Dep't of Fin. Servs., 769 F.3d 105 (2d Cir.2014) (quotations and citation omitted); see also Central Rabbinical Congress of United States & Canada v. New York City Dep't of Health & Mental Hygiene, 763 F.3d 183, 192 (2d Cir.2014) (accord). However, "[a] plaintiff cannot rely on the `fair-ground-for litigation' alternative to challenge governmental action taken in the public interest pursuant to a statutory or regulatory scheme[] * * * [because] governmental policies implemented through legislation or regulations developed through presumptively reasoned democratic processes are entitled to a higher degree of deference and should not be enjoined lightly." Otoe-Missouria Tribe, 769 F.3d 105 (quotations and citation omitted); see also Central Rabbinical, 763 F.3d at 192. That exception to the "two-track rule" for granting a preliminary injunction applies even if the party "seeking to enjoin governmental action taken in the public interest pursuant to a statutory or regulatory scheme * * * [also] seeks to vindicate a * * * public interest." Otoe-Missouria Tribe, 769 F.3d 105 (quotations and citation omitted). Accordingly,
"The party seeking a preliminary injunction must also demonstrate that the public's interest weighs in favor of granting an injunction." Central Rabbinical, 763 F.3d at 192; see also Winter v. Natural Res. Def. Council, 555 U.S. 7, 24, 129 S.Ct. 365, 172 L.Ed.2d 249 (2008) ("In exercising their sound discretion, courts of equity should pay particular regard for the public consequences in employing the extraordinary remedy of injunction." (quotations and citation omitted)). Injunctive relief is "an extraordinary remedy that may only be awarded upon a clear showing that the plaintiff is entitled to such relief[,]" Winter, 555 U.S. at 22, 129 S.Ct. 365, and is "never awarded as of right." Id. at 24, 129 S.Ct. 365.
The APA provides, in relevant part, that "[a] person suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof." 5 U.S.C. § 702. "Agency action made reviewable by statute and final agency action for which there is no other adequate remedy in a court are subject to judicial review." 5 U.S.C. § 704.
"Pursuant to the APA, courts review contested agency action to determine if it is `arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.'" Brodsky v. U.S. Nuclear Regulatory Comm'n, 704 F.3d 113, 119 (2d Cir.2013) (quoting 5 U.S.C. § 706(2)(A)); see also Karpova v. Snow, 497 F.3d 262, 267 (2d Cir.2007)). "Under this deferential standard of review, [courts] cannot substitute [their] judgment for that of the agency." Natural Res. Def. Council v. Fed. Aviation Admin., 564 F.3d 549, 555 (2d Cir.2009); see also Fed. Commc'ns Comm'n v. Fox Television Stations, Inc., 556 U.S. 502, 513, 129 S.Ct. 1800, 173 L.Ed.2d 738 (2009) (holding that under the "narrow" arbitrary and capricious standard of review, "a court is not to substitute its judgment for that of the agency * * *." (quotations and citation omitted).
Nonetheless, "[a]lthough highly deferential, this standard does not equate to no review." Brodsky, 704 F.3d at 119. "Notably, the APA contemplates that, in deciding a challenge to agency action, a court will review the administrative record to ensure that the agency examined the relevant data and articulated a satisfactory explanation for its action." Brodsky, 704 F.3d at 119 (quotations and citation omitted); see also Marsh v. Oregon Natural Res. Council. 490 U.S. 360, 378, 109 S.Ct. 1851, 104 L.Ed.2d 377 (1989) (holding that courts must "ensure that agency decisions are founded on a reasoned evaluation of the relevant factors." (quotations omitted)); Karpova, 497 F.3d at 268 ("[S]o long as the agency examines the relevant data and has set out a satisfactory explanation[,] including a rational connection between the facts found and the choice made, a reviewing court will uphold the agency
"[W]hile a court can uphold a decision of less than ideal clarity if the agency's path may reasonably be discerned, it may not itself supply a reasoned basis for the agency's action than the agency itself has not given." Brodsky, 704 F.3d at 119 (quotations and citation omitted). "An agency's decision is accorded a presumption of regularity," Coal. on W. Valley Nuclear Wastes v. Bodman, 625 F.Supp.2d 109, 116 (W.D.N.Y.2007), aff'd sub nom Coal. on W. Valley Nuclear Wastes v. Chu, 592 F.3d 306 (2d Cir.2009) (quotations and citation omitted), "and the party challenging the decision has the burden of proof." Id.; see also Natural Res. Def. Council, Inc. v. U.S. Army Corps of Eng'rs, 457 F.Supp.2d 198, 220 (S.D.N.Y. 2006) (accord); Boatmen v. Gutierrez, 429 F.Supp.2d 543, 548 (E.D.N.Y.2006) ("Plaintiff's bear the burden of showing, by citation to evidence in the administrative record, that an agency's actions are arbitrary and capricious.")
The only issues presented in this case are whether the findings and conclusions of (1) the FWS in its Biological Opinion and (2) the Army Corps in its EA and FONSI are arbitrary and capricious under the APA. Since resolution of plaintiff's claims involves primarily issues of fact, and "analysis of the relevant documents requires a high level of technical expertise," Marsh, 490 U.S. at 377, 109 S.Ct. 1851 (quotations and citations omitted), "defer[ence] to the informed discretion of the responsible federal agencies" is required. Id.
Section 7(a) of the ESA provides, in relevant part:
16 U.S.C. § 1536(a)(2).
The FWS is responsible for administering the ESA with respect to all endangered and threatened wildlife and plant species designated in 50 C.F.R. § 17.11 and 17.12, respectively, see 50 C.F.R. § 402.01, including the piping plover. See 50 C.F.R. § 17.11(h). During formal consultation, the FWS must:
50 C.F.R. § 402.14(g).
Section 7(b) of the ESA provides, in relevant part:
16 U.S.C. § 1536(b)(3)(A).
50 C.F.R. § 402.14(h).
Plaintiff contends that the FWS's Biological Opinion is arbitrary and capricious because: (1) it failed to determine whether the Project will jeopardize the continued existence of the piping plover and any "no jeopardy" conclusion that can be inferred from the Biological Opinion "is not rationally related to the biological facts cited [therein] [,]" (Plf. Mem. at 32); (2) "it relied on vague and uncertain conservation measures to justify its purported no-jeopardy determination[,]" (id. at 36); and (3) the Incidental Take Statement failed to "use the best scientific and commercial data available," (Plf. Mem. at 40 (quoting 16 U.S.C. § 1536(a)(2))), and to consider that the Army Corps's "planned habitat restoration measures have no proven success and indeed have been found unlikely to succeed[,]" (id.).
The two hundred seventeen (217)-page Biological Opinion thoroughly considered
Moreover, the fact that the final Biological Opinion differs from the FWS's draft opinion, which concluded "that the effects of the proposed action, taken together with the status of the species, the environmental baseline, cumulative effects, are likely to appreciably reduce the likelihood of both the survival and recovery of piping plover in the wild by reducing its reproduction, abundance, and distribution[,]" (Draft Bio. Op. at 142), does not warrant a finding that the final Biological Opinion is arbitrary and capricious. "[T]he FWS was entitled to, and did, in fact, change its mind," Southwest Ctr. For Biological Diversity v. U.S. Bureau of Reclamation, 143 F.3d 515, 523 (9th Cir.1998), following discussions with the Army Corps, and state and local agencies regarding "ways to increase the quantity and productivity of the available habitat." (Bio. Op. at 141). The FWS considered all relevant factors and reasonably found, inter alia, that there is a "need to operate in the current context of [all] competing uses," (id.), and that the "nondiscretionary" conservation measures set forth in its final Biological Opinion, which were absent and/or different from the draft Biological Opinion, were sufficient to avoid jeopardy to the piping plover.
Since, inter alia, there is a rational connection between the facts found and the "no jeopardy" determination made by the FWS in the Biological Opinion, and plaintiff has not demonstrated that the FWS relied upon any improper factor, failed to consider an important aspect of the problem, or offered an explanation contrary to the evidence before it, or that the "no jeopardy" determination is so implausible that it cannot be ascribed to a difference in opinion, it has not demonstrated a likelihood of success on the merits of its APA claim alleging that the FWS's jeopardy analysis in its Biological Opinion was arbitrary and capricious.
The FWS properly relied upon mitigation or conservation measures in issuing its no jeopardy determination in the Biological Opinion. See, e.g. Native Fish Soc'y v. Nat'l Marine Fisheries Servs., 992 F.Supp.2d 1095, 1113 (D.Or.2014). Such "[m]itigation measures must be reasonably specific, certain to occur, and capable of implementation; they must be subject to deadlines or otherwise enforceable obligations; and most important, they must address the threats to the species in a way that satisfies the jeopardy and adverse modification standards." Natural Res. Def. Council v. Rodgers, 381 F.Supp.2d 1212, 1241 (E.D.Calif.2005); see also Native
Contrary to plaintiff's contention, the conservation measures set forth in the Biological Opinion are sufficiently specific and certain, particularly when considered together with the nondiscretionary terms and conditions set forth in the Incidental Take Statement, (Bio. Op. at 151-52), insofar as, inter alia, they are identifiable, capable of implementation, subject to deadlines and other enforceable obligations, and address the threats to the piping plovers resulting from the modification of their preferred habitat by ensuring the creation of suitable replacement habitat. That some of the proposed measures may be experimental does not warrant a finding that the FWS's reliance upon them is arbitrary and capricious since, inter alia, there is at least a rational reason to expect them to work as intended; "there is no requirement for the FWS to ensure the overall success of the plan[,]" In re Operation of Missouri River Sys. Litig., 421 F.3d at 635; and the Army Corps is required to closely monitor the performance of the measures and the effects of the Project upon the piping plovers and, if the level of incidental take is exceeded, to "immediately provide an explanation of the causes of the taking and review with the [FWS] the need for possible modification of the reasonable and prudent measures," (Bio. Op. at 152-53), and to cease "any operations causing such take," (id. at 53), pending reinitiation of consultation. See, e.g. In re Operation of Missouri River Sys. Litig., 421 F.3d at 635.
Moreover, the fact that some of the measures may require interagency cooperation does not render them uncertain, particularly since, inter alia, all of the agencies were represented at the meetings wherein those measures were proposed and agreed upon; the Army Corps is required to fund the measures and to ensure that the three (3) overwash areas and the restored area are managed in accordance with the measures; the interagency team must be formed prior to the initiation of any construction; and the monitoring and predator management plans must be drafted before the completion of the first phase of construction. (Bio. Op. at 151-52). And again, if the level of incidental take is exceeded during the course of the Project due to the failure of a third party to cooperate or otherwise, the Army Corps must "immediately provide an explanation of the causes of the taking and review with the [FWS] the need for possible modification of the reasonable and prudent measures," (Bio. Op. at 152-53), and cease "any operations causing such take," (id. at 53), pending reinitiation of consultation.
Accordingly, plaintiff has not satisfied its burden of demonstrating a likelihood of success on the merits of its APA claim
The ESA provides, in relevant part:
16 U.S.C. § 1536(b)(4)
Plaintiff contends that the FWS's Incidental Take Statement is arbitrary and capricious because it failed to "use the best scientific and commercial data available," (Plf. Mem. at 40 (quoting 16 U.S.C. § 1536(a)(2))), and to consider that the Army Corps's "planned habitat restoration measures have no proven success and indeed have been found unlikely to succeed[,]" (id.). However, plaintiff has not proffered any scientific or commercial data presented to or before the FWS that contradicts the data upon which the FWS relied and was ignored by the FWS in its Biological Opinion. Moreover, a review of the administrative record reveals that there is ample data supporting the proposed conservation measures and, as noted above, that those measures are reasonably specific, certain to occur, and capable of implementation; are subject to deadlines or otherwise enforceable obligations; and sufficiently address the threats to the species in a way that satisfies the jeopardy and adverse modification standards, particularly in light of the extensive monitoring programs to which the Project will be subject and the provision for reinitiation of consultation and cessation of operations in the event the level of incidental take is exceeded. Accordingly, plaintiff has not satisfied its burden of demonstrating a likelihood of success on the merits of its APA claim alleging that the FWS's Incidental Take Statement is arbitrary and capricious.
"NEPA directs agencies contemplating `major [f]ederal actions significantly affecting the quality of the human environment' to prepare an Environmental Impact
"[N]o EIS is required where the major federal action is not `significant' within the meaning of NEPA." Town of Orangetown v. Gorsuch, 718 F.2d 29, 34 (2d Cir.1983); see also 40 C.F.R. § 1501.4(b) ("In determining whether to prepare an [EIS] the Federal agency shall * * * prepare an [EA] * * *."); City of New York v. Slater, 145 F.3d 568, 571 (2d Cir.1998) ("Before deciding to prepare a full-blown EIS * * * an agency may conduct an [EA] * * * in order to determine whether an EIS is necessary. Where the action in question is not `significant,' no EIS is required."); Friends of Ompompanoosuc v. Fed. Energy Regulatory Comm'n, 968 F.2d 1549, 1556 (2d Cir.1992) ("If an agency prepares an EA and determines that a project will have no significant impact on the human environment, a costly and time consuming EIS need not be prepared.") An EA is defined in the regulations promulgated under NEPA as:
40 C.F.R. § 1508.9(a); see also Nat'l Audubon Soc'y v. Hoffman, 132 F.3d 7, 12 (2d Cir.1997) ("An EA is a concise document that briefly discusses the relevant issues and either reaches a conclusion that preparation of an EIS is necessary or concludes with a finding of no significant impact, in which case preparation of an EIS is unnecessary." (quotations, brackets and citation omitted)); Coal. for Responsible Growth and Res. Conservation v. U.S. Fed. Energy Regulatory Cornm'n, 485 Fed.Appx. 472, 474 (2d Cir.2012) (summary order) ("If an agency is uncertain as to whether the action requires an EIS, it must prepare an [EA] that briefly provides sufficient evidence and analysis for determining whether to prepare an EIS." (quotations, alterations and citations omitted)). The regulations further provide that an EA "[s]hall include brief discussions of the need for the proposal, of alternatives as required by section 102(2)(E) [of NEPA], of the environmental impacts of the proposed action and alternatives, and a listing of agencies and persons consulted." 40 C.F.R. § 1508.9(b).
"NEPA imposes only procedural requirements to ensure that the agency, in reaching its decision, will have available, and will carefully consider, detailed information concerning significant environmental impacts[,]" Winter, 555 U.S. at 23, 129 S.Ct. 365 (quotations, brackets and citation omitted), and "does not mandate particular results." Id.; see also Marsh, 490 U.S. at 371, 109 S.Ct. 1851 ("NEPA does not work by mandating that agencies achieve particular substantive environmental results. Rather, NEPA promotes its sweeping commitment to `prevent or eliminate damage to the environment and biosphere' by focusing Government and public attention on the environmental effects of proposed agency action." (quoting 42 U.S.C. § 4321)); SPARC, 352 F.3d at 557 ("NEPA is a procedural statute that mandates a process rather than a particular result.") "In other words, NEPA does not command an agency to favor any particular course of action but rather requires the agency to withhold its decision to proceed with an action until it has taken a `hard look' at the environmental consequences." SPARC, 352 F.3d at 557 (quoting Sierra Club v. U.S. Army Corps of Eng'rs, 701 F.2d 1011, 1029 (2d Cir. 1983)). "Significantly, `[i]f the adverse environmental effects of the proposed action are adequately identified and evaluated, the agency is not constrained by NEPA from deciding that other values outweigh the environmental costs.'" Fed. Aviation Admin., 564 F.3d at 556 (brackets in original) (quoting Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989)); see also Baltimore Gas, 462 U.S. at 97, 103 S.Ct. 2246 ("Congress in enacting NEPA * * * did not require agencies to elevate environmental concerns over other appropriate considerations. * * * Rather, it requires only that the agency take a `hard look' at the environmental consequences before taking a major action." (citation omitted)). "The only role for a court is to insure that the agency has taken a `hard look' at environmental consequences; it cannot interject itself within the area of discretion of the executive as to the choice of the action to be taken." SPARC, 352 F.3d at 557 (quotations and citations omitted); see also Baltimore Gas, 462 U.S. at 97-98, 103 S.Ct. 2246 ("The role of the courts is simply to ensure that the agency has adequately considered and disclosed
Plaintiff contends that the Army Corps's EA violates NEPA because it failed: (1) to consider relevant factors in its analysis of the Project's potential impacts on piping plovers; (2) to adequately evaluate all reasonable alternatives and to explain why it rejected alternatives proposed by other federal agencies; and (3) to adequately evaluate cumulative impacts. (Plf. Mem. at 43).
Plaintiff challenges, inter alia, the Army Corps's determination that the Project's impacts are "insignificant" on the basis that the EA "contains numerous unsupported and inaccurate assertions about the Project's impacts on the piping plover that are inconsistent with the findings in the Biological Opinion and the scientific evidence and comments provided to the [Army] Corps by FWS." (Plf. Mem. at 44).
Plaintiff has not satisfied its burden of showing a likelihood of success on the merits on its APA claim that the Army Corps's EA is arbitrary and capricious. The one hundred twenty-three (123)-page EA thoroughly identifies and evaluates all relevant factors including, inter alia, the environmental impacts, both adverse and beneficial, of the Project upon the piping plover species and habitat, and cites to numerous authorities in support of its findings. (See EA at 114-23). Since the Army Corps considered all environmental consequences of the Project and convincingly documented its determination that the Project would have "no significant adverse environmental impacts * * *," (FONSI, ¶ 5), plaintiff has not established a likelihood of success on the merits of its APA claim against the Army Corps alleging that its EA failed to adequately consider all relevant factors.
Under NEPA, "an agency must `[r]igorously explore and objectively evaluate all reasonable alternatives, and for alternatives which were eliminated from detailed study, briefly discuss the reasons for their having been eliminated.'" Fed. Aviation Admin., 564 F.3d at 556 (brackets in original) (quoting 40 C.F.R. § 1502.14(a)); see also Natural Res. Def. Council v. U.S. Dep't of Agric., 613 F.3d 76, 85 (2d Cir. 2010). "[U]nder NEPA the range of alternatives that must be discussed is a matter within an agency's discretion," Friends of Ompompanoosuc, 968 F.2d at 1558, and "the range of alternatives an agency must consider is narrower when * * * the agency has found that a project will not have a significant environmental impact." Id.; see also Brodsky v. U.S. Nuclear Regulatory Comm'n, 507 Fed.Appx. 48, 53 (2d Cir.2013) (summary opinion).
Plaintiff contends that the Army Corps "failed to consider reasonable alternatives and to identify reasons for dismissing th[o]se alternatives," (Plf. Mem. at 46), and "also failed to rigorously and objectively evaluate * * * the No Action Alternative and the [] Project Alternative * * *." (Id.) Specifically, plaintiff identified several alternatives proposed by the FWS in its January 9, 2014 letter that were not included in the EA, (id. at 47-48), i.e., "construct[ing] an enhanced berm" instead of a "solid dune," constructing a
Contrary to plaintiff's contention, the Army Corps clearly considered the proposed alternatives modifying the dune designs and "briefly discussed" its reasons for rejecting those alternatives in the EA by finding, inter alia, that within the Park, "it is not feasible to eliminate the proposed dune system or vary its height without compromising coastal storm risk management or severely curtailing county park management, operations and use." (EA at 103).
Moreover, the EA adequately explores and objectively evaluates the two (2) reasonable alternatives, i.e., the No Action Alternative and the Project, in terms of, inter alia, their environmental risks and benefits and "was not required to say more." Brodsky, 507 Fed.Appx. at 53. Accordingly, plaintiff has not established a likelihood of success on the merits of its APA claim against the Army Corps alleging that its consideration of alternatives in the EA is arbitrary and capricious.
Under NEPA, "the agency `shall consider. . . 3 types of impacts': direct, indirect, and cumulative." Fed. Aviation Admin., 564 F.3d at 558 (ellipsis in original) (quoting 40 C.F.R. § 1508.25(c)). The regulations define "cumulative impact" as "the impact on the environment which results from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions regardless of what agency (Federal or non-Federal) or person undertakes such other actions." 40 C.F.R. § 1508.7.
Plaintiff contends that the EA "fails to take a `hard look' at cumulative impacts because it (1) fails to identify and analyze the impacts of several past, present, and reasonably foreseeable future actions in the proximity of the [] [P]roject and (2) fails to adequately consider the cumulative impacts of the seven projects it does identify." (Plf. Mem. at 50).
Review of the administrative record reveals that the Army Corps adequately analyzed the cumulative impacts of all past, present and reasonably foreseeable future actions on existing conditions in the vicinity of the Project in full compliance
Moreover, contrary to plaintiff's contention, the EA considers, inter alia, the cumulative effects of local "[p]eriodic beach fills," (Plf. Mem. at 51) (brackets in original). (See EA at 101 ("Suffolk County periodically dredges local channels for maintenance purposes. * * * The dredging takes place mostly in the bays and not on the open Atlantic Ocean coast. The dredged materials are used as beach fill whenever the materials are suitable, and the placement is cost effective.")
In addition, plaintiff has not demonstrated that the Army Corps's cumulative effects analysis is inadequate. To the contrary, the Army Corps furnished sufficient information on, and analysis of, the cumulative effects of the past, present and reasonably foreseeable future actions within the vicinity of the Project by, inter alia, disclosing other sufficiently imminent or inevitable planned or proposed beach stabilization actions in proximity to the Project area and discussing and analyzing their combined environmental impacts with the Project.
Since plaintiff has not demonstrated that the Army Corps failed to consider the cumulative effects of any past, present of "reasonably foreseeable," i.e., imminent or inevitable, future actions occurring in the vicinity of the Project, or that the Army Corps' consideration of the cumulative effects of the actions identified in the EA is inadequate, it has not established a likelihood of success on the merits of its APA claim against the Army Corps alleging that the EA's cumulative impact analysis was arbitrary and capricious.
"If, pursuant to the EA, the agency concludes that no EIS is required, it must provide its reasons in a FONSI." Brodsky, 704 F.3d at 120; see also 40 C.F.R. § 1501.4(e) ("In determining
40 C.F.R. § 1508.13. "The agency shall make the [FONSI] available to the affected public as specified in § 1506.6." 40 C.F.R. § 1501.4(e)(1). "The decision not to prepare an EIS is left to the informed discretion of the agency proposing the action or project." Slater, 145 F.3d at 571 (quotations and citation omitted); see also Hoffman, 132 F.3d at 14 ("[W]hether a particular agency action will have a `significant' effect on the environment is a substantive question left to the informed discretion of the agency proposing the action."); Gorsuch, 718 F.2d at 34 ("The issue of whether a particular agency's action will have a `significant' effect on the environment is a substantive issue which has traditionally been left to the informed discretion of the agency proposing the action or project.")
In Hoffman, the Second Circuit held that:
132 F.3d at 14; see also Friends of Ompompanoosuc, 968 F.2d at 1556 ("Once an agency has made a decision subject to NEPA's procedural requirements, the only role for a court is to ensure that the agency has considered the environmental consequences. * * * Accordingly, a reviewing court must ensure that [the federal agency] has taken a `hard look' at the environmental consequences and assess whether the agency has convincingly documented its determination of no significant impact." (quotations, alterations and citations omitted)). "The court's "inquiry must be `searching and careful,' although the ultimate scope of judicial review is narrow." Hoffman, 132 F.3d at 14 (quoting Marsh, 490 U.S. at 378, 109 S.Ct. 1851). "The judiciary must not inject itself into an area where the choice of action to be taken is one confided by Congress to the executive branch." Id. Plaintiff bears the burden of showing that the Project will significantly affect the physical environment and, thus, that the Army Corps's decision to issue an EA and FONSI was arbitrary and capricious. See County of Seneca v. Cheney, 12 F.3d 8, 12 (2d Cir. 1993).
"Significantly as used in NEPA requires considerations of both context and intensity[.]" 40 C.F.R. § 1508.27; see also County of Seneca, 12 F.3d at 12 ("Under NEPA, an EIS or EA is not required unless the contemplated action will affect the environment `in a significant manner or to a significant extent,' with significance defined in terms of both context and intensity.") "[T]he significance of an action
Intensity "refers to the severity of impact." 40 C.F.R. § 1508.27(b). NEPA regulations provide that the following ten (10) factors "should be considered in evaluating intensity:
40 C.F.R. § 1508.27(b).
"Affecting" is defined in NEPA's implementing regulations to mean "will or may have an effect on." 40 C.F.R. § 1508.3
Plaintiff contends that the FONSI is arbitrary and capricious because four (4) of the ten (10) intensity factors "weigh in favor of a finding that the [] [P]roject will have a significant impact on the environment," (Plf. Mem. at 53), thus, requiring an EIS. Specifically, plaintiff contends that an EIS is required because: (1) that the Project will adversely affect the piping plover, see 40 C.F.R. § 1508.27(b)(9); (2) several impacts of the Project are uncertain or unknown, see id. § 1508.27(b)(5); (3) the Project is likely to "establish a precedent for future actions with significant effects," id. § 1508.27(b)(6); and (4) "it is `reasonable to anticipate a cumulatively significant impact on the environment' from the [] [P]roject and other similar beach engineering projects in the area," (Plf. Mem. at 55) (quoting 40 C.F.R. § 1508.27(b)(7)).
An action is not necessarily "significant," thus requiring an EIS, whenever one (1) of the ten (10) intensity factors are met. To the contrary, "[w]hile the ten [intensity] factors may show that the [agency] could have prepared an [EIS], they do not show that the [agency] acted
The Army Corps completed a thorough EA of the Project, considered all of the environmental effects mentioned in the intensity factors, and reasonably described the environmental impacts it finds to be "not significant" and NEPA "requires no more." Klein, 753 F.3d at 585; see also Coliseum Square, 465 F.3d at 240 (holding that as long as the agency has addressed and reasonably evaluated each intensity factor, it has complied with NEPA).
Moreover, as set forth above, the Army Corps's analysis of cumulative impacts in the EA is adequate and, thus, plaintiff cannot demonstrate that that intensity factor, 40 C.F.R. § 1508.27(7), requires an EIS. Moreover, since the EA was developed "to address the particular circumstances and problems encountered in and around [Fire Island]," Town of Cave Creek, Ariz. v. Fed. Aviation Admin., 325 F.3d 320, 332 (D.C.Cir.2003), it creates no binding precedent. See, e.g. Barnes v. U.S. Dep't of Transp., 655 F.3d 1124, 1140 (9th Cir.2011) ("EAS are usually highly specific to the project and locale, thus creating no binding precedent.'"): Town of Cave Creek, 325 F.3d at 332 (finding that approval of the project created no binding precedent, as it was developed "to address the particular circumstances and problems encountered in and around [the Project area].")
Furthermore, the "regulations do not anticipate the need for an EIS anytime there is some uncertainty, but only if the effects of the project are `highly' uncertain." In Defense of Animals, Dreamcatcher Wild Horse and Burro Sanctuary v. U.S. Dep't of Interior, 751 F.3d 1054, 1070 (9th Cir.2014). Plaintiff does not allege, much less demonstrate, that the effects of the Project are "highly uncertain," only that "several impacts" and the cumulative impacts of several other projects in the area are "uncertain." (Plf. Mem. at 53). Under the circumstances of this case, the uncertainty of some of the Project's effects, alone, is insufficient to require an EIS. See, e.g. Greater Yellowstone Coal. v. Flowers, 359 F.3d 1257, 1276 (10th Cir. 2004) (finding that where the uncertainty of the effects of the project were due to the unpredictability of, inter alia, the species, as opposed to a "lack of thoroughness in investigating potential impacts," "further assessment of impacts in an EIS before the project's implementation is unlikely to be productive").
In addition, "NEPA regulations direct the agency to consider the degree of adverse effect on a species, not the impact on individuals of that species." Environmental Prot. Info. Ctr. v. U.S. Forest Serv., 451 F.3d 1005, 1010-11 (9th Cir. 2006). Therefore, although the Project may effect individual pairs of piping plover, estimated by the FWS to be approximately one (1) pair per year of the Project, it was not arbitrary and capricious for the Army Corps to find that the Project will not cause a significant adverse effect on the species, particularly in light of the nondiscretionary conservation measures provided in the EA.
Since the mitigation measures in the EA are nondiscretionary and include, inter alia, a program to monitor and ensure their effectiveness, they are supported by substantial evidence.
For the foregoing reasons, plaintiff's motion for a preliminary injunction pursuant to Rule 65 of the Federal Rules of Civil Procedure is denied; defendants' motion pursuant to Rule 65(b)(4) to dissolve the TRO is denied and plaintiff's cross motion to strike certain paragraphs and exhibits of the Amanat declaration are denied as moot; and FILPS's motion for leave to file a brief amicus curiae is denied.
SO ORDERED.
"Destruction or adverse modification means a direct or indirect alteration that appreciably diminishes the value of critical habitat for both the survival and recovery of a listed species. Such alterations include, but are not limited to, alterations adversely modifying any of those physical or biological features that were the basis for determining the habitat to be critical." Id.
"Listed species means any species of fish, wildlife, or plant which has been determined to be endangered or threatened under section 4 of the [ESA] * * * [and] are found in 50 CFR 17.11-17.12." Id.
"Critical habitat refers to an area designated as critical habitat listed in 50 CFR parts 17 or 226." Id. No critical habitat has been designated in the Project area.