Summary: Case: 11-40305 Document: 00511779443 Page: 1 Date Filed: 03/06/2012 IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit FILED March 6, 2012 No. 11-40305 Lyle W. Cayce Clerk TOM WORTHEN, Plaintiff - Appellee v. FIDELITY NATIONAL PROPERTY AND CASUALTY INSURANCE COMPANY, Defendant - Appellant Appeal from the United States District Court for the Southern District of Texas USDC No. 3:09-CV-236 Before KING, WIENER, and HAYNES, Circuit Judges. PER CU
More
     Case: 11-40305     Document: 00511779443         Page: 1     Date Filed: 03/06/2012




            IN THE UNITED STATES COURT OF APPEALS
                     FOR THE FIFTH CIRCUIT  United States Court of Appeals
                                                     Fifth Circuit

                                                                            FILED
                                                                           March 6, 2012

                                       No. 11-40305                        Lyle W. Cayce
                                                                                Clerk

TOM WORTHEN,

                                                  Plaintiff - Appellee
v.

FIDELITY NATIONAL PROPERTY AND CASUALTY INSURANCE
COMPANY,

                                                  Defendant - Appellant



                   Appeal from the United States District Court
                        for the Southern District of Texas
                              USDC No. 3:09-CV-236


Before KING, WIENER, and HAYNES, Circuit Judges.
PER CURIAM:*
        Appellant Fidelity National Property and Casualty Insurance Company
(“Fidelity”) appeals the district court’s ruling in favor of Appellee Tom Worthen
(“Worthen”) that he timely renewed his Standard Flood Insurance Policy (the
“SFIP”). Because the district court committed error by concluding that Worthen
timely paid his renewal premium as a matter of law, we REVERSE and
RENDER.


        *
         Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
R. 47.5.4.
   Case: 11-40305   Document: 00511779443     Page: 2   Date Filed: 03/06/2012



                                 No. 11-40305

                               BACKGROUND
      On August 10, 2007, Worthen obtained an SFIP for a residential property.
Fidelity wrote Worthen’s flood insurance policy. Coverage was provided under
the National Flood Insurance Program (the “NFIP”), a federal program
established by the National Flood Insurance Act of 1968, as amended, 42 U.S.C.
§ 4001 et seq. (the “NFIA”), and regulated by the Federal Emergency
Management Agency (“FEMA”).
      Under Worthen’s policy, his coverage period began at 12:01 a.m. on August
10, 2007 and expired at 12:01 a.m. on August 10, 2008. Fidelity sent a Renewal
Notice dated June 17, 2008 and a Renewal Reminder Notice dated July 26, 2008,
advising Worthen that his current SFIP would expire at 12:01 a.m. on August
10, 2008. The Notices also stated that if Worthen wanted to ensure continued
coverage, he needed “to make [his] payment on or before the expiration date of
[his] current policy.” Fidelity then sent Worthen an Expiration Notice dated
August 10, 2008, informing him that because Fidelity had not received his
renewal premium, Worthen’s coverage had expired on “8/10/08 at 12:01 a.m.
standard time.” However, the Expiration Notice also stated that if Fidelity
received the “premium payment within 30 days of the expiration date indicated
above [8/10/08], [Worthen’s] policy should be renewed with no lapse in coverage.”
Worthen does not dispute that he received each of the aforementioned Notices.
      On the morning of September 9, 2008, while Texas residents awaited
Hurricane Ike’s impending arrival, Worthen called his insurance agent
regarding the renewal of his SFIP. Some time between 8:37 a.m. and 9:22 a.m.,
Worthen paid the renewal premium. Then, at 9:22 a.m., Worthen’s insurance
agent forwarded Worthen a document entitled Endorsement Payment
Transmittal that stated that the transaction date was “09/09/2008” and that the
Effective Date of his renewed SFIP was “08/10/2008.”



                                       2
   Case: 11-40305        Document: 00511779443        Page: 3    Date Filed: 03/06/2012



                                       No. 11-40305

       Four days later, on September 13, 2008, Hurricane Ike caused significant
damage to Worthen’s property. Shortly thereafter, Worthen filed a claim for
flood damages, but Fidelity denied his claim on the grounds that there was no
policy in effect to provide coverage. According to Fidelity, Worthen’s SFIP
renewal premium had not been paid within the 30-day grace period, thereby
triggering FEMA’s mandatory 30-day waiting period from the date of payment
before coverage could be reinstated. Thus, Fidelity maintained that Worthen’s
policy was not effective until October 9, 2008, leaving him without coverage
when Hurricane Ike damaged his property.
       Subsequently, Worthen filed suit in state court against Fidelity and his
insurance agent, Galveston Insurance Associates,1 alleging breach of contract
and various state-law-based extra-contractual and tort claims. Fidelity removed
the action to federal court, and pursuant to Federal Rule of Civil Procedure
12(b)(6) or, in the alternative, 12(c), filed a motion to dismiss Worthen’s state-
law-based extra-contractual and tort claims on the grounds that these claims
were barred and preempted by federal law.2 At the same time, Fidelity also filed
a motion for summary judgment arguing that Fidelity had properly denied
Worthen’s claim for federal benefits under his SFIP because Worthen’s renewal
payment was untimely since it was made after 12:01 a.m. on September 9, 2008.
       The district court granted Fidelity’s motion to dismiss.                Worthen v.
Galveston Ins. Assocs., No. G-09-236, 
2010 WL 3816044
, at *3 (S.D. Tex. Sept.
14, 2010). In its Amended Memorandum and Order, the district court concluded
that “there is no common law claim for insurance coverage that [Worthen] can


       1
           Worthen later settled with Galveston Insurance Associates.
       2
        Fidelity’s motion to dismiss excluded Worthen’s breach of contract claim for payments
under the SFIP policy. Fidelity moved for summary judgment on that claim. Although
Worthen never moved for summary judgment, the district court granted judgment to Worthen,
apparently on the facts set forth in Fidelity’s motion, Worthen’s response, and a stipulation
as to damages if the policy were in effect.

                                              3
   Case: 11-40305    Document: 00511779443       Page: 4   Date Filed: 03/06/2012



                                  No. 11-40305

make that is not preempted under the facts of this case.” 
Id. at *2-3.
However,
the district court also therein addressed the issue of the timeliness of Worthen’s
renewal premium payment. 
Id. at *1,
*3. In that regard, the district court held
that because Worthen made his renewal payment on September 9, 2008, he
qualified for continuation of his SFIP without a lapse in coverage. 
Id. at *3
(“Fidelity issued its ‘Endorsement Payment Transmitt[al]’ on September 9,
indicating receipt of [Worthen’s] payment of $600. That was the 30th day and
a premium payment made on the 30th day is timely.”). Having so held, the
district court further concluded that Worthen had “no procurement claim(s) since
he had coverage,” so that his “asserted procurement claims are, therefore,
preempted.” 
Id. (citation omitted).
      Based on its determination that Worthen’s renewal premium payment had
been timely, the district court denied Fidelity’s motion for summary judgment
and entered Final Judgment in favor of Worthen in the amount of $25,972.15 on
his claim for federal benefits under his SFIP.
      Fidelity timely appealed. Worthen did not cross-appeal.
                                 DISCUSSION
      Given the above undisputed facts, the question of whether Worthen’s
renewal premium payment was timely is a question of law that this court
reviews de novo. E.g., Pierce v. Underwood, 
487 U.S. 552
, 558 (1988); Atlas
Pallet, Inc. v. Gallagher, 
725 F.2d 131
, 134-35 (1st Cir. 1984) (“Generally, where
the facts upon which liability is claimed or denied under an insurance policy are
undisputed and the existence or amount of liability depends solely upon a
construction of the policy, the question presented is one of law for the court to
decide.” (citations omitted)).
      1.    Timeliness of Worthen’s Renewal Premium Payment
      Since the instant case involves an SFIP, this court applies federal law to
the issue, not the statutory or decisional law of any particular state, although

                                        4
   Case: 11-40305    Document: 00511779443      Page: 5   Date Filed: 03/06/2012



                                  No. 11-40305

general principles of state insurance law may be useful in determining federal
law. E.g., Borden v. Allstate Ins. Co., 
589 F.3d 168
, 172 (5th Cir. 2009); Linder
& Assocs., Inc. v. Aetna Cas. & Sur. Co., 
166 F.3d 547
, 550 (3d Cir. 1999) (“It is
well settled that federal common law governs the interpretation of the SFIP at
issue here.” (citations omitted)); Sodowski v. Nat’l Flood Ins. Program, 
834 F.2d 653
, 655 (7th Cir. 1987) (“Federal common law controls the interpretation of
insurance policies issued pursuant to the National Flood Insurance Program
(NFIP).” (citations omitted)).    For example, where appropriate, we have
interpreted policies by using general principles of state insurance law, including
but not limited to the following: (1) if the language of a policy is clear and
unambiguous, it is accorded its natural meaning; (2) if the meaning of a policy
provision is susceptible to different constructions, the one most favorable to the
insured prevails; (3) insurance contracts are to be reasonably construed in
accordance with the objective and intent of the parties; (4) in determining the
most reasonable construction of contested provisions, the court may draw from
the provisions, the policy as a whole, and the apparent objectives of the parties
in entering the contract; and (5) in the end, if the meaning of the policy terms
remains unclear, the policy is generally construed in the insured’s favor to
promote the policy’s objective of providing coverage.        See Hanover Bldg.
Materials, Inc. v. Guiffrida, 
748 F.2d 1011
, 1013 (5th Cir. 1984) (internal
citations and quotations omitted).
      In addition, since SFIPs are issued pursuant to the FEMA-administered
NFIP, see 42 U.S.C. § 4011(a), Worthen’s SFIP is also governed by FEMA’s flood
insurance regulations and the NFIA. E.g., Campo v. Allstate Ins. Co., 
562 F.3d 751
, 754 (5th Cir. 2009); Hanover Bldg. 
Materials, 748 F.2d at 1011-12
; 44 C.F.R.
Pt. 61, App. A(1), Art. IX (“This policy and all disputes arising from the handling
of any claim under the policy are governed exclusively by the flood insurance
regulations issued by FEMA, the [NFIA], and Federal common law.”). Moreover,

                                        5
   Case: 11-40305       Document: 00511779443          Page: 6    Date Filed: 03/06/2012



                                       No. 11-40305

FEMA’s interpretation of its own regulations is given “‘controlling weight unless
it is plainly erroneous or inconsistent with the regulation.’” Stinson v. United
States, 
508 U.S. 36
, 45 (1993) (quoting Bowles v. Seminole Rock & Sand Co., 
325 U.S. 410
, 414 (1945)).
       Furthermore, “provisions of an insurance policy issued pursuant to a
federal program [are] strictly construed and enforced.” Gowland v. Aetna, 
143 F.3d 951
, 954 (5th Cir. 1998) (footnote omitted); see also 44 C.F.R. § 61.13. In
addition, the insured is charged with constructive knowledge of the policy
provisions and of the NFIP program “regardless of actual knowledge of what is
in the [r]egulations or of the hardship resulting from innocent ignorance.” Fed.
Crop. Ins. Corp. v. Merrill, 
332 U.S. 380
, 385 (1947).
       Here, the relevant and contested provision in Worthen’s SFIP, which is
codified in the federal regulations, is the policy renewal provision:
       1.     This policy will expire at 12:01 a.m. on the last day of the
              policy term.
       2.     We must receive the payment of the appropriate renewal
              premium within 30 days of the expiration date.3

44 C.F.R. Pt. 61, App. A(1), Art. VII(H)(1)-(2). Worthen contends that this
provision is ambiguous because there is no suggestion of the specific date and
time that serves as the renewal premium payment deadline. In addition,
Worthen argues that FEMA’s own NFIP Flood Insurance Manual (the “Manual”)
exacerbates the ambiguity by the use of the term “after” in the Policy Renewals
section:
       III.   PREMIUM PAYMENT DUE




       3
         Although the SFIP does not explicitly label this as a “grace period,” for the purposes
of this case, it is undisputed that this 30-day period acts as such to retroactively permit
expired policies to be re-activated without any lapse in coverage. See 
Campo, 562 F.3d at 752
n.1.

                                              6
   Case: 11-40305   Document: 00511779443     Page: 7    Date Filed: 03/06/2012



                                 No. 11-40305

      To ensure that the policy is renewed without a lapse in coverage, the
      premium must be received by the NFIP within 30 days after the
      expiration date.
FEMA, National Flood Insurance Program Flood Insurance Manual (May 2008),
http://www.fema.gov/pdf/nfip/manual200805/12ren.pdf. According to Worthen,
the use of the word “after” suggests that the date that a policy expires is not
counted so that the insured has 30 days after and not inclusive of the actual
expiration date. Furthermore, Worthen argues that in the same Policy Renewals
section, it provides that the insured should “[u]se the renewal date plus 29 days
to determine if the renewal premium was received within 30 days.” According
to Worthen, the phrase “renewal date” in this calculation method is susceptible
to multiple, conflicting meanings when considered in light of the other parts of
the Manual’s Policy Renewals section.
      However, reading further in the Manual demonstrates the fallacy of
Worthen’s arguments:
      V.    RENEWAL EFFECTIVE DATE DETERMINATION
            If the Final Notice and the premium payment are received by
      the insurer within 30 days following the expiration, the policy will
      be issued under the same policy number as the previous term, with
      no lapse in coverage. For example, if the policy expires on May 1,
      the Final Notice and premium payment must be received on or
      before May 30.

Id. Applying the
Manual’s calculation method—“[u]se the renewal date plus 29
days to determine if the renewal premium was received within 30 days”—May
1st is the renewal date and May 30th is the 29th day after May 1st.
      Here, it is undisputed that without a renewal premium payment,
Worthen’s SFIP expired at 12:01 a.m. on August 10, 2008. Thus, applying the
Manual’s example and counting method to Worthen’s scenario, Worthen’s
renewal premium must have been received on or before the 29th day after
August 10, 2008—in other words, Worthen’s payment must have been received

                                        7
   Case: 11-40305    Document: 00511779443      Page: 8    Date Filed: 03/06/2012



                                  No. 11-40305

by September 8, 2008. Accordingly, Worthen’s renewal premium payment after
12:01 a.m. on September 9, 2008 was outside the 30-day grace period and was
untimely. Consequently, there was a lapse in coverage when Hurricane Ike
damaged Worthen’s property.
      The example provided by FEMA’s Manual resolves any potential
ambiguity. We conclude that the district court’s determination that Worthen’s
renewal premium was timely was error, and we must REVERSE the grant of
judgment to Worthen on his claim under the SFIP.
      2.    Unavailability of Remand
      Worthen requests that in the event we reverse, we remand rather than
render so that he may pursue litigation in the district court of his state-law-
based claims he calls “procurement claims.” He argues that the district court’s
dismissal of these claims was based upon its (now concluded to be erroneous)
conclusion that his renewal premium payment was timely so that he had
coverage. Worthen further argues that “absent the lower court’s finding of SFIP
coverage, the state-law claims would have certainly survived.”
      Worthen’s request exceeds our jurisdiction because of his failure to cross-
appeal. This court’s scope of review is limited to the issues that were timely
appealed. See FED. R. APP. P. 3-4; Greenlaw v. United States, 
554 U.S. 237
, 244-
45 (2008) (“[A]n appellate court may not alter a judgment to benefit a
nonappealing party. . . . [I]t takes a cross-appeal to justify a remedy in favor of
an appellee.” (citation omitted)); Torres v. Oakland Scavenger Co., 
487 U.S. 312
,
316-17 (1988) (“[A]lthough a court may construe the Rules liberally in
determining whether they have been complied with, it may not waive the
jurisdictional requirements of Rules 3 and 4, even for ‘good cause shown’ under
Rule 2, if it finds that they have not been met.” (footnote omitted)). Except in
limited circumstances not applicable here, failure to file a timely notice of appeal
deprives the appellate court of jurisdiction. Amazing Spaces, Inc. v. Metro Mini

                                         8
   Case: 11-40305       Document: 00511779443           Page: 9     Date Filed: 03/06/2012



                                        No. 11-40305

Storage, 
608 F.3d 225
, 250 (5th Cir. 2010) (“‘[T]his circuit follows the general
rule that, in the absence of a cross-appeal, an appellate court has no jurisdiction
to modify a judgment so as to enlarge the rights of the appellee or diminish the
rights of the appellant.’” (quoting Borrego Springs Bank v. Skuna River Lumber
(In re Skuna River Lumber, LLC), 
564 F.3d 353
, 356 (5th Cir. 2009))).
       Worthen’s request that this court remand the case to the district court for
litigation of the dismissed claims in the event of reversal is a request that the
appellate court enlarge his rights and/or diminish Fidelity’s rights.4 See Morley
Constr. Co. v. Md. Cas. Co., 
300 U.S. 185
, 191-92 (1937) (“‘Where each party
appeals[,] each may assign error, but where only one party appeals the other is
bound by the decree in the court below, and he cannot assign error in the
appellate court, nor can he be heard if the proceedings in the appeal are correct,
except in support of the decree from which the appeal of the other party is
taken.’” (quotation omitted)). Accordingly, we lack jurisdiction to grant Worthen
a remand on his state-law-based claims.5

       4
          Citing Klamath Strategic Investment Fund v. United States, 
568 F.3d 537
(5th Cir.
2009) and Ashley v. Boehringer Ingelheim Pharmaceuticals (In re Des Litigation), 
7 F.3d 20
(2d Cir. 1993), Worthen argues that since he was not aggrieved by the lower court’s decision,
he did not have standing to appeal it. However, in making this argument, Worthen appears
to conflate two distinct concepts. Specifically,“[a]s a general matter, a party who is not
aggrieved by a judgment does not have standing to appeal it.” Klamath 
Strategic, 568 F.3d at 546
(citing Ward v. Santa Fe Indep. Sch. Dist., 
393 F.3d 599
, 603 (5th Cir. 2004)). However,
this well-established rule is separate and apart from the “longstanding” cross-appeal rule.
Greenlaw, 554 U.S. at 244-45
. If Worthen sought only to uphold the district court’s judgment
under the policy by making arguments that the district court rejected, he would not need to
cross-appeal. However, he is now seeking to overturn the district court’s dismissal of his state-
law-based claims, a ruling adverse to him and by which he is “aggrieved,” even though he
would have been satisfied with the overall outcome were we to leave it undisturbed. By
requesting remand for that purpose, Worthen seeks to have this court alter the district court’s
judgment to enlarge his rights and/or diminish Fidelity’s. Thus, Worthen’s request is a
quintessential request that requires a cross-appeal: “If you leave the district court’s ruling as
is, I am happy, but if you reverse the judgment on the policy, then reverse the dismissal of my
state-law claims.”
       5
        We note that these claims appear to be based on nothing more than speculation and
conjecture. Worthen contends that he was misled by the issuance of renewal papers on

                                               9
  Case: 11-40305       Document: 00511779443          Page: 10      Date Filed: 03/06/2012



                                       No. 11-40305

       Therefore, we REVERSE the judgment of the district court in favor of
Worthen and RENDER judgment that he take nothing against Fidelity.
       REVERSED and RENDERED.




September 9 showing no lapse in coverage. He points to no evidence that, with Hurricane Ike
bearing down on the coast, he could have obtained other coverage that day or in the ensuing
few days before the hurricane hit. See, e.g., Warrantech Corp. v. Steadfast Ins. Co., 
210 S.W.3d 760
, 766 (Tex. App.—Fort Worth 2006, pet. denied) (“Insurance is designed to protect against
unknown, fortuitous risks, and fortuity is a requirement of all policies of insurance. An
insured cannot insure against something that has already begun and which is known to have
begun.” (citations omitted)).