DynCorp International LLC, ASBCA No. 61274 (2018)

Court: Armed Services Board of Contract Appeals Number: ASBCA No. 61274 Visitors: 1
Judges: Sweet
Filed: Mar. 20, 2018
Latest Update: Mar. 03, 2020
Summary: , Erin L. Felix, Esq.The motion for partial summary judgment is denied.I certify that the foregoing is a true copy of the Opinion and Decision of the, Armed Services Board of Contract Appeals in ASBCA No. 61274, Appeal of, DynCorp International LLC, rendered in conformance with the Board's Charter.
               ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of --                                  )
                                              )
DynCorp International LLC                     )      ASBCA No. 61274
                                              )
Under Contract No. FA8617-12-C-6208           )

APPEARANCES FOR THE APPELLANT:                       Gregory S. Jacobs, Esq.
                                                     Erin L. Felix, Esq.
                                                      Polsinelli PC
                                                      Washington, DC

APPEARANCES FOR THE GOVERNMENT:                      Jeffrey P. Hildebrant, Esq.
                                                      Air Force Deputy Chief Trial Attorney
                                                     Jason R. Smith, Esq.
                                                     Lt Col Byron Shibata, USAF
                                                      Trial Attorneys

         OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE
      GOVERNMENT'S MOTION FOR PARTIAL SUMMARY JUDGMENT

        Appellant DynCorp International LLC (DI) appeals the deemed denial of its
request for an equitable adjustment. The government has moved for partial summary
judgment, arguing that our decision in DynCorp International, LLC, ASBCA No. 59244,
 17-1 BCA 1 36,653 (DynCorp I) issued under the above-captioned contract precludes
the re-litigation of some issues in this appeal under the doctrine of collateral estoppel.
Familiarity with the facts of DynCorp I is presumed. The motion is denied.

       STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

       1. The T-6A/B is an aircraft used by the United States Air Force (USAF) and
the United States Navy for pilot training. It is stationed at multiple sites around the
United States. (Compl. 14)

       2. On 27 December 2010, the USAF issued Solicitation No. FA8617-l l-R-6208 (6208
RFP) for the new Joint Primary Aircraft Training System (JPATS) T-6A/B
Contractor Operated and Maintained Base Supply (COMBS) (R4, tab 199-200). The 6208
RFP contained numerous contract line item numbers (CLINs), including the 3XXX
CLINs. The 3XXX CLINs were for all maintenance, repairs, overhauls and
replenishments/replacements of the T-6A/B at various sites. The 6208 RFP indicated that
the government would pay on a fixed-rate cost per flight hour (CPFH) basis for a variable
number of flight hours. (Id. at 55-81) CPFH pricing differed among the various sites due
to several factors, including the number of aircraft, total projected flight hours, and aircraft
age (compl., 10).

        3. According to DI, offerors required historical information regarding the
consumption of aircraft parts and components at each site in order to propose
site-specific CPFH prices (app. opp'n, ex. 1,, 4). As a result, the USAF provided
historical consumption data in the bidder's library (R4, tabs 2-45). DI alleges that the
information in the bidder's library was inaccurate for the first quarter of 2010 because
parts for the T-6B from the Whiting Field site were incorrectly coded as being issued
from the Pensacola site (compl., 26; app. opp'n, ex. 1,, 6).

        4. DI submitted a proposal. It alleges that, due to the error in the bidder's
library, its proposed pricing for the Whiting Field site was lower than it would have
been had the USAF provided the correct data (app. opp'n, ex. 1,, 7).

      5. The USAF awarded Contract No. FA8617-12-C-6208 (COMBS contract) to
DI based upon the 6208 RFP (R4, tab 73).

        6. After performance began, DI alleges it discovered the error in the bidder's
library (compl., 26-34; app. opp'n, ex. 1,, 6).

       7. DI filed a claim on 12 May 2015. The contracting officer did not issue a
decision on that claim, such that it is deemed denied. This appeal followed. (Comp I. at I)

        8. The complaint alleges in the factual background section that "DI was forced
to rely solely on the veracity and completeness of the consumption data provided by
the USAF" (compl., 22). The factual background section also quotes Di's proposal
as stating that "[p]ricing of CLINs 3X00-3XIO assumes the data provided is both
complete and correct" (id., 25) (emphasis in original).

       9. The complaint then alleges two counts (compl. at 1-2).

        I 0. As Count I, the complaint alleges that there was a constructive change
entitling DI to an equitable adjustment "due to the USAF's providing inaccurate
consumption data" (comp I. at 1-2). In support of Count I, the complaint alleges that
"DI did as directed and developed its CPFH pricing in the only logical manner-with
reliance on the accuracy and completeness of the data provided" (id., 48). Count I
continues that, "[ u ]tilizing the faulty data, DI applied the consumption data for B-model
aircraft to Pensacola, causing Di's CPFH for Whiting to be lower than it would have
been had the proper consumption data been applied" (id., 49). Count I concludes that
"[t]he USAF's provision of faulty data constitutes a constructive change to the
Contract" (id. , 50).

       11. As Count II, the complaint seeks reformation based upon a mutual mistake
"regarding the accuracy of the consumption data" (compl. at 2). Count II alleges that


                                             2
"DI expressly informed the Government of DI's belief that the consumption data
provided in the Bidder's Library, upon which DI based its CPFH pricing, was both
complete and accurate" (id.~ 53). Count II continues that, "had DI been aware of the
mistakes in these data, it could have requested corrected data and adjusted its CPFH
proposal accordingly" (id.~ 55). Count II also alleges that "[n]either the RFP nor the
Contract put the risk of a mistake in the consumption data in the Bidder's Library on
DI. Notably, the USAF did not use any language to disclaim responsibility for the
completeness or accuracy of the data in the Bidder's Library." (Id.~ 56) Count II
concludes that "[t]he Contract price should be reformed to reflect what DI would have
proposed if the Bidder's Library data had been accurate" (id.~ 57).

                                        DECISION

        The government seeks partial summary judgment on the issue regarding DI's
alleged mistake and reliance on the completeness of the usage/consumption data in the
bidder's library. Based on the language of Di's complaint, the government contends
that issue can be interpreted as including the completeness issue, which DynCorp I
precluded under collateral estoppel. (Gov't mot. at 7) DI replies in opposition to the
government's motion that the matter upon which estoppel is sought is irrelevant to the
instant appeal, and that DI is making different arguments in this case (app. opp'n at 1).

I. The Standards for Summary Judgment

        Summary judgment will be granted if a moving party has shown that there are no
genuine issues of material fact, and it is entitled to judgment as a matter of law. Celotex
Corp. v. Catrett, 
477 U.S. 317
, 322 (1986). A non-movant seeking to defeat summary
judgment by suggesting conflicting facts must set forth specific facts showing that there
is a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242,248 (1986).
Thus, if the non-moving party carries the burden of proof at trial for elements of its case
and fails to provide such proof, the moving party is entitled to summary judgment.
Dairyland Power Coop. v. United States, 
16 F.3d 1197
, 1202 (Fed. Cir. 1994). In
deciding summary judgment motions, we do not resolve controversies, weigh evidence,
or make credibility determinations. Liberty 
Lobby, 477 U.S. at 255
. Moreover, we
draw all reasonable inferences in favor of the non-movant. 
Id. II. Collateral
Estoppel

        Collateral estoppel does not apply in this appeal. In order to establish that
collateral estoppel precludes the relitigation of an issue already decided in another
case, a proponent must show that: ( 1) the issue is identical to one decided in the prior
proceeding; (2) the issue was actually litigated; (3) resolution of the issue was essential
to the final judgment in the prior proceedings; and (4) the party defending against
preclusion had a full and fair opportunity to litigate the issue in the prior proceeding.
Laguna Hermosa Corp. v. United States, 
671 F.3d 1284
, 1288 (Fed. Cir. 2012).


                                             3
       The issue here is not identical to the one decided in DynCorp I-another appeal
arising out of the COMBS contract. In DynCorp I, we held that "DI had actual
knowledge that the [consumption] data was incomplete and that DI made a business
decision to submit a proposal despite the risk.'' 17-1 BCA, 36,653 at 178,498
(emphasis added). While the complaint in this appeal makes passing reference to the
consumption data's completeness, the data's completeness is not a significant issue in
this appeal (SOF ,, 8-10). Rather, reading the complaint as a whole reveals that the
operative issue for both the constructive change and mutual mistake claims is the
data's alleged inaccuracy-which the government concedes is distinct from the issue
of the data's completeness (id.; gov't mot. at 6-7).*

        We see no reason to strain to read a claim about the data's completeness into
this appeal, only to preclude such a straw-man claim under collateral estoppel. That is
particularly true given Di's binding disavowal of any such claim. As DI states in its
opposition to the summary judgment motion, "arguments regarding the completeness
of government-provided data ... are not at issue in the present Appeal" (app. opp'n at 1).
Because the data's completeness is not an issue in this appeal, the issue in this appeal
is not identical to the issue of the data's completeness that we decided in DynCorp I.
As such, the government has failed to meet the first prong of the Laguna Hermosa
case. Therefore, collateral estoppel does not apply in this appeal.

                                      CONCLUSION

         The motion for partial summary judgment is denied.

         Dated: 20 March 2018



                                                    JAMES R. SWEET
                                                    Administrative Judge
                                                    Armed Services Board
                                                    of Contract Appeals


(Signatures continued)



*   The government does not seek to preclude litigation on the issue of whether the data
         was inaccurate, which it concedes is an issue in this appeal. However, the
         government contends that, based on the language of the complaint, the issue of
         mistake and reliance on the accuracy of the data can be interpreted as including
         the completeness issue. (Gov't mot. at 6-7)

                                             4
 I concur                                         I concur



 RICHARD SHACKLEFORD                              OWEN C. WILSON
 Administrative Judge                             Administrative Judge
 Acting Chairman                                  Vice Chairman
 Armed Services Board                             Armed Services Board
 of Contract Appeals                              of Contract Appeals


     I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 61274, Appeal of
DynCorp International LLC, rendered in conformance with the Board's Charter.

      Dated:



                                                 JEFFREY D. GARDIN
                                                 Recorder, Armed Services
                                                 Board of Contract Appeals




                                           5
