ROBERT C. CHAMBERS, District Judge.
Pending before the Court are Plaintiff Fifth Third Bank's ("Fifth Third") Motion for Summary Judgment (Doc. 53) and Defendants Victor A. McClure and McClure Properties, Inc.'s ("Defendants") Omnibus Motion in Limine (Doc. 69). For the following reasons, Plaintiff's motion is
This case, filed on March 27, 2008, and as amended on May 2, 2008, concerns a commitment letter entered into by the parties, on November 5, 2004, and a series of commercial loans made by the Plaintiff Fifth Third to Defendant McClure Properties, following the November 2004 agreement. The loans at issue were executed and delivered on June 6, 2005, and May 26, 2006, for the sums of $1,500,000 and $2,240,000, respectively. Each loan was issued to McClure Properties with Defendant Victor McClure serving as personal guarantor. The loans were issued for the express purpose of providing McClure Properties with the capital to construct and open a gas station and convenience store at 1434-36 3rd Avenue, in Huntington ("the Huntington Project"). The real property located at 1434-36 3rd Avenue was owned by McClure Properties and served as collateral for the loans. Additionally, according to the 2004 commitment letter, a second property owned by McClure Properties was to serve as the
Fifth Third's Amended Complaint seeks action on the non-revolving draw note executed on May 26, 2006, for $2,240,000 plus interest, and on the personal guaranty provided by Mr. McClure on that same date. In the complaint, Fifth Third requests a finding of default against Defendant McClure Properties on the May 2006 note in the principal sum of $1,134,795.69, plus accrued but unpaid interest in the amount of $34,825.13 through January 11, 2008 and continuing thereafter at the rate of $240.36 per day; late fees of $2,670.85; and all other late fees, fines, expenses and advances that accrue on the note on and after January 11, 2008. Additionally, Plaintiff requests a judgment against Defendant McClure individually in the principal sum of $1,134,795.69, plus accrued but unpaid interest in the amount of $34,825.13 through January 11, 2008 and continuing thereafter at the rate of $240.36 per day; late fees of $2,670.85; and all other late fees, fines, expenses and advances that accrue on the note on and after January 11, 2008.
The McClure Defendants answered Plaintiff's Amended Complaint on August 1, 2008, providing a general denial of all allegations against them and raising a series of counterclaims against Fifth Third. In their answer, the McClure Defendants admit: (1) that Exhibit A to the Plaintiff's complaint is a true and accurate copy of the May 2006 note, and (2) that Exhibit B is a true and accurate copy of Mr. McClure's guaranty of the same. See Defs.' Answer (Doc. 12), at ¶¶ 5 & 6. Nonetheless, the McClure Defendants deny liability for their default on the May 2006 note on the basis of their counterclaims. These counterclaims include claims against Fifth Third for: (1) breach of the terms of the November 5, 2004 commitment letter; (2) breach of fiduciary duty and/or of an implied duty to act in good faith; (3) fraud; (4) intentional misrepresentation; (5) negligent misrepresentation; and (6) negligence.
On February 23, 2010, Fifth Third moved for summary judgment on all issues and claims. Essentially, Fifth Third argues that this is a simple breach of contract action to enforce the May 2006 promissory note and the loan agreement guaranty. Additionally, Fifth Third claims that it is entitled to all cost and expenses incurred in enforcement, including attorney fees, pursuant to section 11.03 of the loan agreement. The McClure Defendants oppose summary judgment on the
Rule 56(c) of the Federal Rules of Civil Procedure provides that summary judgment is proper if "the pleadings, the discovery and disclosure of materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law." Fed.R.Civ.P. 56(c). The availability of summary judgment therefore turns on whether a proper jury question exists in a pending case. Adickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970).
When considering a motion for summary judgment, the Court will not "weigh the evidence and determine the truth of the matter[.]" Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Rather, the Court considers the facts in the light most favorable to the nonmoving party, Adickes, 398 U.S. at 159, 90 S.Ct. 1598, drawing any permissible inference from the underlying facts in a manner that supports the nonmovant. Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 587-88, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). The party opposing summary judgment "must do more than simply show that there is some metaphysical doubt as to material facts," however. Id. at 586, 106 S.Ct. 1348. It must offer some "concrete evidence from which a reasonable juror could return a verdict in his favor[.]" Anderson, 477 U.S. at 256, 106 S.Ct. 2505.
Neither the applicable law nor the general facts are in dispute. From 2004 to 2006, Plaintiff Fifth Third Bank and the McClure Defendants entered into a series of commercial contracts, which included the May 2006 promissory note for an interim construction loan and the related personal guaranty. In their answer, the McClure Defendants admit to the truth and accuracy of these 2006 contracts. Further, the McClure Defendants do not contest that they are in default of these agreements. As a result, this case is a simple contract enforcement action, and the question raised by Plaintiff's motion is whether the counterclaims asserted by Defendants establish a genuine issue of material fact regarding a legal defense sufficient to prevent summary judgment.
One claiming rights under a contract must be able to show that he has performed his duties thereunder. Hupp v. Sasser, 200 W.Va. 791, 490 S.E.2d 880, 889 (1997); see also Restatement (Second) of Contracts § 237 (1981).
The McClure Defendants argue that they cannot be held liable for their default on the May 2006 loan agreement or personal guaranty because Fifth Third breached first, by failing to fulfill its obligations under the November 2004 commitment letter.
The pertinent question with regard to the McClure Defendants' first counterclaim, therefore, is whether Fifth Third breached the 2004 agreement. The McClure Defendants claim that Fifth Third breached the 2004 contract because it failed to: (1) assure the Huntington Project's permanent financing was obtained through the SBA 504 Program, and (2) disburse the promised funds (the full $2,200,000) in a timely manner. The McClure Defendants contend that Fifth Third's breach occurred first and caused Mr. McClure's business to fail. As a result, the defendants argue that their default was the result of Fifth Third's breach and, as such, should be excused.
To resolve the issue, the Court looks to the terms of the 2004 contract. Once formed, a contract is construed according to the plain, ordinary meaning of the language used. See Syl. Pt. 9, Arnold v. Palmer, 224 W.Va. 495, 686 S.E.2d 725 (2009) ("A valid written instrument which expresses the intent of the parties in plain and unambiguous language is not subject to judicial construction or interpretation but will be applied and enforced according to such intent."); Rollyson v. Jordan, 205 W.Va. 368, 518 S.E.2d 372, 376 (1999) ("Where parties contract lawfully and their contract is free from ambiguity or doubt, their agreement furnishes the law which governs them.") (quoting 4B Michie's Jurisprudence Contracts § 40, at 56 (Repl. Vol. 1986)). The 2004 commitment letter is four pages long. The portion of the commitment letter that refers to SBA financing
According to the McClure Defendants, the commitment letter should be construed against its drafter, Fifth Third Bank, and read to establish an affirmative duty on the part of the bank to assure that McClure Properties obtains SBA 504 Program financing for its permanent loan. Specifically, the McClure Defendants claim that "[the] Commitment Letter guaranteed Mr. McClure a loan amount of up to $2,200,000.00 and that the SBA 504 program would be used for 35% of the loan." Defs.' Resp. in Opp'n (Doc. 57), at 3 (emphasis supplied); see also McClure Depo. (Doc. 57-2), Ex. B, at 101 (testifying that the bank breached the commitment letter because "they did not follow the 504 program"). In short, the defendants claim that the bank had an obligation to either apply for, or otherwise assist the McClure Defendants in obtaining, SBA financing for the Huntington Project. Defs.' Resp. in Opp'n (Doc. 57), at 7, 11-12.
To support this contention, the McClure Defendants point to the commitment letter and the deposition testimony of Victor McClure.
In West Virginia, contracts are construed according to the plain meaning of the language used. See, e.g., Blake v. State Farm Mut. Auto. Ins. Co., 224 W.Va. 317, 685 S.E.2d 895, 901 (2009). As a result, parol evidence is only allowed if a contract is ambiguous. Id. ("It is only when the document has been found to be ambiguous that the determination of intent through extrinsic evidence become[s] a question of fact."); see also Holiday Plaza, 285 S.E.2d at 133 ("Prior or contemporaneous statements may not be admitted to vary written contracts, but West Virginia has always permitted parol evidence to explain uncertain, incomplete or ambiguous contract terms."). "The question as to whether a contract is ambiguous is a question of law to be determined by the court." Syl. Pt. 4, Blake, 685 S.E.2d 895. Thus, "[t]he mere fact that parties do not agree to the construction of a contract does not render it ambiguous." Id.
In determining whether Fifth Third agreed to obtain or otherwise assist McClure Properties in obtaining SBA financing, the 2004 commitment letter is not ambiguous. See Syl. Pt. 1, Shamblin v. Nationwide Mut. Ins. Co., 175 W.Va. 337, 332 S.E.2d 639 (1985) (holding a contract is only ambiguous if it is reasonably susceptible to two different meanings or reasonable minds might disagree as to its meaning). When they intended to establish affirmative duties, the parties to the 2004 commitment letter did so explicitly. For example, in the
The Court reaches a similar conclusion with respect to the timing of disbursements. Defendants claim that "Fifth Third Bank committed itself to lending Mr. McClure money in a timely fashion, to insure that his convenient store would open on time." Defs.' Resp. in Opp'n (Doc. 57), at 1. Defendants further claim that Fifth Third breached this duty and that such breach, ultimately, resulted in the McClure Defendants' default. Accordingly, Defendants claim they are not liable for their default because the bank breached first.
Again, the Court looks to the terms of the 2004 contract to resolve the matter. The 2004 commitment letter contains no time line for disbursement and no disbursement schedule is attached. Therefore, the contract does not explicitly answer the question of what constitutes a "timely" disbursement. In the absence of a concrete time schedule, the Court reviews the agreement as a whole to determine timeliness.
The 2004 commitment letter specified that Fifth Third agreed "to provide funding for the construction of a new gas station and convenience store." 2004 Commitment Letter (Doc. 53-3), Ex. C. The Court therefore implies a duty on the part of the bank, which would be triggered once the construction loan was established, to disburse the $2,200,000 it agreed to loan in 2004 in a reasonable manner consistent with industry standards for construction loans. As a result, the question presented by Defendants' untimeliness defense is whether Fifth Third's disbursement of the $2,240,000 it loaned McClure Properties, between November 2004 and September 2006, complied with these industry standards.
At first glance, the issue is a closer call than the question presented by the SBA 504 Program. The McClure Defendants present the deposition testimony of Victor McClure, see McClure Depo. (Doc. 57-2), Ex. B; the business plan for the Huntington Project produced by Quantitative Market Research, Business Plan (Doc. 57-1), Ex. A; and the expert report of Laura Savory Miller, Miller Report (Doc. 57-3), Ex. D, to support their contention of untimeliness. Victor McClure attests that Fifth Third unreasonably delayed disbursement. McClure Depo. (Doc. 57-2), Ex. B, at 102. He attests that the delay occurred in contravention of his expectations entering into the 2004 contract and of the contract itself. Id. Nonetheless, for the reasons stated above and below, the Court will not use Mr. McClure's testimony to add terms regarding timeliness to the 2004 contract.
The 2004 commitment letter is just that; a commitment to enter into a $2,200,000 loan to fund the construction of a new gas station and convenience store. See 2004 Commitment Letter (Doc. 53-3), Ex. C. Although the commitment letter sets out some of the terms of the agreed upon future loan (a 9-month term, a prime plus 1% interest rate, and a value of up to $2,200,000), it is not the loan contract. Id. ("Fifth Third Bank, Ohio Valley is pleased to submit this commitment to provide funding ... Please note that the actual loan documents will include other terms and conditions not outlined herein.") (emphasis supplied). As ruled, the commitment letter is a valid and enforceable contract.
To the contrary, the 2004 letter plainly indicates that, in November 2004, the parties agreed to enter into a loan, as specified, contingent on a series of disclosures and other conditions. See id. ("Prior to, or at the closing of the Loan, Obligors shall have provided to Lender such documents and information as Lender or its counsel may require in connection with the Loan, Obligors, Guarantors and/or Properties (all such documents and information to be in form and substance satisfactory to Lender), including but not limited to ..."). The parties then entered into the construction loans for the Huntington Project in June 2005 and May 2006. Clearly, the 2004 contract is not the only legal contract entered into by the parties. It therefore contains only a portion of the parties' mutual obligations; and a time line for disbursement is not one of them.
Thus, the Court finds that the 2004 contract, at a maximum, establishes an implied duty on the part of Fifth Third to disburse funds, once loaned, in a reasonable manner consistent with industry standards for construction loans. The Court further finds Victor McClure's deposition insufficient to establish a triable fact concerning whether such standards failed to be met.
Next, the Court looks to the expert report. The Miller Report concludes that McClure Properties suffered damages of $91,624 as a result of Fifth Third's delay in disbursement. Miller Report (Doc. 57-3), Ex. D. This conclusion is based upon Ms. Miller's finding that, "[u]nder the terms of the Commitment Letter, funds would have been disbursed as follows: $401,250 in November 2004 ... Equal monthly disbursements of $229,843.75 from December 2004 through July 2005." Id. Ms. Miller titles this finding an "assumption of projected disbursement" and explicitly states that her conclusions are based upon the "facts and/or assumptions" contained in her report. Id.
The Court is unpersuaded. Ms. Miller seeks to provide an expert opinion of the terms and effects of the 2004 contract. However, a plain reading of the agreement does not support Ms. Miller's assumption that Fifth Third agreed to distribute the $2,200,000 loan committed to in "[e]qual monthly disbursements of $229,843.75 from December 2004 through July 2005." As noted, the contract contains no time line for disbursement and no disbursement schedule is attached, or otherwise referred to. Therefore, although the 2004 agreement provides that the loan, once established, will be for a term of 9 months, the 2004 letter does not provide when this 9-month term will begin. Accordingly, there is no support in the record for Ms. Miller's assumption that the 9-month term was set to begin in November or December 2004. To the contrary, a close reading of the 2004 contract shows that the parties did not expect to enter into the construction loan until a series of disclosures were conducted and additional terms agreed to.
Finally, a review of the business plan produced by Quantitative Market Research leads the Court to the same conclusion—that the McClure Defendants have failed to establish a triable issue with regard to timeliness. See Business Plan (Doc. 57-1), Ex. A. The business plan, which it appears was made available to Fifth Third at the time of the commitment letter, contains no specific time lines for the construction or opening of the gas station and convenience store. Id. The plan contains charts outlining the projected sales and profits for the first 10 years the gas station and convenience store; however, these years are referred to generically (as "Year 1" to "Year 10") and no specific dates are included. Without more, this June 22, 2004, document does not establish a genuine issue of fact with regard to timeliness because the business plan does not contain any expectation, or other information, regarding the timing of the McClure Defendants' construction loan or the grand opening of the business. Thus, the business plan provides no support for Defendants' argument that the loan should have been fully disbursed by June 2005.
In contrast, when reviewed carefully, the business plan supports the bank's argument that the loan was disbursed, and the store opened, in a commercially reasonable manner. Specifically, in the section of the plan entitled "Time," Quantitative Market Research explains: "Bringing a Gas/C-Store facility to completion is a time consuming process. We find the time span from initial proposal to grand opening date is extending.
In sum, without concrete or contractual evidence that Fifth Third entered into a specific disbursement schedule for McClure Properties' construction loan, or that the bank breached industry standards for such disbursal, the Court finds the Defendants' untimeliness defense unconvincing. The Court further finds that the McClure Defendants have not established a genuine issue of fact to support their claim that Fifth Third breached the SBA 504 Program provision of 2004 commitment letter. Accordingly, these counter-claims do not present a defense to summary judgment. See, e.g., Anderson, 477 U.S. at 256, 106 S.Ct. 2505.
Plaintiff seeks summary judgment on the McClure Defendants' claim that the
As noted, Fifth Third, McClure Properties, and Victor McClure are all sophisticated commercial entities, or individuals. Thus, the 2004, 2005, and 2006 contracts between the parties constitute arms length business transactions. A fiduciary duty is a "duty to act for someone else's benefit, while subordinating one's personal interest to that of the other person. It is the highest standard of duty implied by law." Lucas v. Fairbanks Capital Corp., 217 W.Va. 479, 618 S.E.2d 488, 493 (2005) (quoting Elmore v. State Farm Mut. Auto. Ins. Co., 202 W.Va. 430, 504 S.E.2d 893, 898 (1998)). Like most commercial transactions, a debtor-creditor relationship is not characterized by a fiduciary relationship or duty. State ex rel. Ins. Comm'r of State of W.V. v. Blue Cross & Blue Shield of W.V., 219 W.Va. 541, 638 S.E.2d 144, 156 n. 37 (2006) ("A debt is a contractual obligation of one person to pay a fixed sum of money to another. The difference between a trust and a debt ... lies chiefly in the fact that the beneficiary of a trust has a beneficial interest in the trust property and the creditor has merely a personal claim against his debtor. A debt is not a trust and involves no fiduciary relationship or duty.") (ellipses in original); see also Elmore, 504 S.E.2d at 898 (finding the relationship between an insurer and a third-party claimant is adversarial and not characterized by a fiduciary duty). This would be sufficient to rebut the McClure Defendants' claims. However, section 11.02(c) of the May 2006 loan contract between Fifth Third and McClure Properties also disclaims the existence of a fiduciary relationship or duty. It specifically provides:
Accordingly, the claim for breach of fiduciary duty fails as a matter of law and is not a defense to summary judgment.
The same is true for the McClure Defendants' counterclaim for breach of good faith and honorable dealing. Referring to the 2004 contract, Defendants argue that Fifth Third "refused to fulfill its obligations under the agreement in bad faith and willfully and expressly breached the terms of the contract." Defs.' Answer (Doc. 12), at ¶ 43. Defendants seek punitive damages associated with such breach. Id. at ¶ 45.
In West Virginia, there is a covenant of good faith and fair dealing implied in every contract. Hoffmaster v. Guiffrida, 630 F.Supp. 1289, 1290 (S.D.W.Va. 1986) (citing Restatement (Second) of Contracts § 205 (1981)). Further, under West Virginia law, "good faith" is defined as "honesty in fact and the observance of reasonable commercial standards of fair dealing." W.V.Code § 46-1-201(20). The McClure Defendants expressly claim a breach of good faith based on Fifth Third's alleged breach of the 2004 commitment letter. Therefore, the claim effectively reasserts those breach of contract claims addressed above (that the bank breached the 2004 contract by failing to secure SBA financing for the permanent loan and fund the construction loan in a timely manner) recast as tort. The Court found these claims untenable as contract claims and reaches the same conclusion here.
Again, Defendants' fraud, intentional misrepresentation, negligent misrepresentation, and negligence claims arise out of Fifth Third's alleged breach of the 2004 contract. With regard to the fraud and intentional misrepresentation claims, the McClure Defendants allege that "[o]n or about November 5, 2004 [Fifth Third] specifically represented to [Defendants] that it would loan $2,200,000 for the project ... [and] that once construction was complete... permanent financing would be provided which included participation in the SBA 504 Program which was subject to a fixed rate of interest." Defs.' Answer (Doc. 12), at ¶ 48. Defendants claim "[i]n fact, [Fifth Third] had intended to provide only $1,500,000 of financing that was subject to a fluctuating variable rate of interest ... [and the] representations were made by [Fifth Third] with the intent to deceive and defraud [Defendants] and to induce him to enter the [2004] contract, and to forgo other opportunities, for the financing of the project." Id. at ¶¶ 49 & 50. Defendants then claim that "[t]he purpose of the fraud was for Fifth Third Bank to obtain Mr. McClure's substantial holdings in real property." Defs.' Resp. in Opp'n (Doc. 57), at 14.
There is no evidence in the record to support Defendants' contentions. To the contrary, the Court again agrees with Plaintiff that the fraud, intentional misrepresentation, negligent misrepresentation and negligence claims are, effectively, breach of contract claims. As discussed supra, Fifth Third did not breach the 2004 contract. As a result, these counterclaims do not provide grounds to avoid summary judgment.
Fraud includes intentional misrepresentation and the elements required to prove each tort overlap. See Syl. Pt. 6, Folio v. City of Clarksburg, 221 W.Va. 397, 655 S.E.2d 143 (2007); id. at 150.
"Where one person induces another to enter into a contract by false representations which he is in a situation to know, and which it is his duty to know, are untrue ... [i]t is not indispensable to a recovery that the defendant actually knew them to be false." Id. at 150. Defendants' fraud claims rely upon alleged false representations "regarding the use of the 504 program" made by Patrick Hickman and other Fifth Third representatives. Further, Defendants contend that they reasonably relied upon these representations "because Fifth Third Bank memorialized them in a Commitment Letter." Defs.' Resp. in Opp'n (Doc. 57), at 13. In other words, Defendants concede that their fraud claim is a breach of contract claim.
"Fraud cannot be predicated on a promise not performed. To make it available there must be a false assertion in regard to some existing matter by which a party is induced to party with his money or property." Syl. Pt. 3, Croston v. Emax Oil Co., 195 W.Va. 86, 464 S.E.2d 728 (1995) (emphasis in original). The Court has already found that Fifth Third did not violate the terms of the 2004 agreement. Consequently, Defendants' fraud claims fail.
Here, the Court again finds that the McClure Defendants' negligence claims are actually breach of contract claims recast as tort. Defendants contend "Mr. McClure has alleged a prima facie case of negligence as Fifth Third Bank breached its duty to fund the loan in a reasonable manner." Defs.' Resp. in Opp'n (Doc. 57), at 15. In other words, Defendants' negligence claim reasserts the claim that Fifth Third unreasonably delayed the disbursement of funds discussed supra. This is a contract claim. Further, because the 2004 contract did not establish any explicit duties with respect to timeliness, there is no breach sufficient to withstand summary judgment.
The McClure Defendants argue the May 26, 2006 contract is void due to economic duress.
There are no facts in the record to justify a finding of economic duress. To the contrary, the facts show that the May 2006 loan agreement is a valid contract, entered into by sophisticated business entities, for valuable consideration, and with mutual assent. Accordingly, it should be enforced. See Ways, 589 S.E.2d 36 at Syl. Pt. 9.
Section 11.03 of the May 2006 contract provides:
The language of the provision is unambiguous. As a result, the Court finds the McClure Defendants must reimburse Fifth Third for its reasonable costs and expenses,
For the foregoing reasons, Plaintiff's motion for summary judgment is
The Court