Energy Matter Conversion Corporation, ASBCA No. 61583 (2018)

Court: Armed Services Board of Contract Appeals Number: ASBCA No. 61583 Visitors: 46
Judges: Sweet
Filed: Dec. 18, 2018
Latest Update: Mar. 03, 2020
Summary: APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq. Nevertheless, the contracting, officer (CO) waived the penalties for including expressly unallowable costs in, EMC2's 2010/2011 FICRPs pursuant to FAR 42.709-5(c).underbiling is not an enumerated basis for a penalty waiver.
,,".                  ARMED SERVICES BOARD OF CONTRACT APPEALS

'-'    Appeal of --                                  )
                                                     )
       Energy Matter Conversion Corporation          )      ASBCA No. 61583
                                                     )
       Under Contract No. N68936-09-C-0125           )

       APPEARANCE FOR THE APPELLANT:                        Dr. Jaeyoung Park
                                                             President

       APPEARANCES FOR THE GOVERNMENT:                      Arthur M. Taylor, Esq.
                                                             DCMA Chief Trial Attorney
                                                            Stephen M. Wilson, Esq.
                                                             Defense Contract Management Agency
                                                             Carson, CA

                   OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE
                   GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

              The government has moved for summary judgment. It argues that it is entitled
()     to judgment as a matter of law on the claims of pro se appellant Energy Matter
       Conversion Corporation (EMC2) that the government improperly imposed a penalty
       because EMC2 included expressly unallowable legal costs in its cost proposals, and
       EMC2 is not entitled to a waiver of that penalty. EMC2 argues that the legal costs are
       not expressly unallowable, and that it is entitled to a waiver. Forthe reasons discussed
       below, the motion is granted.

              STATEMENT OF FACTS {SOF) FOR PURPOSES OF THE MOTION

              1. Beginning in 2006, the U.S. Department of Justice (DOJ) investigated
       EMC2 for potential mischarges, in violation of the False Claims Act, 31 U.S.C.
       §§ 3729-3733 related to a different contract than the one subject to this appeal (app.
       supp. R4, tab 12). The DOJ sought $556,745.83 (app. supp. R4, tab 13 at 9).

               2. On September 11, 2009, the Department of the Navy (Navy) awarded
       Contract No. N68936-09-C-0125 (0125 contract) to EMC2. The 0125 contract was a
       cost-plus-fixed-fee contract. (R4, tab 1) The 0125 contract included Federal
       Acquisition Regulation (FAR) clause 52 .216-7, ALLOW ABLE COST AND PAYMENT
       (DEC 2002), which incorporated FAR Part 31, Contract Cost Principles and Procedures (id.
       at 22). The 0125 contract also included FAR clause 52.242-3, PENALTIES FOR
       UN ALLOW ABLE COSTS (MAY 2001) (id. at 21 ).
(j
               3. On December 10, 2012, the Navy Acquisition Integrity Office (AIO) issued a
        show cause letter regarding questionable costs EMC2 charged to the Navy in fiscal year
        (FY) 2000 through FY 2005 related to different contracts than the one subject to this
        appeal (app. supp. R4, tab 1 at 1-2). 1 Among the questionable costs was the salary of
        Cortine McGowen. According to the show cause letter, Ms. McGowen told investigators
        that she worked as a housekeeper at the residence of EM C2 's prior owners, instead of at
        EMC2's offices. (Id. at 4) The show cause letter expressly stated that "[t]his evidence of
        cost mischarging indicates a serious lack of business integrity that may warrant the
        debarment ofEMC[2] from Government contracting pursuant to FAR 9.4" (id. at 2).

               4. By letter dated January 7, 2013, EMC2 disputed the assertion that the costs
        for Ms. McGowen's salary were not allowable (app. supp. R4, tab 2 at 2).

               5. In 2013, EMC2 resolved the DOJ and AIO investigations (collectively,
        investigations) by refunding the Navy $249,850.90. The compromise did not expressly
        provide that the costs incurred in connection with the investigations were allowable.
        (Compl. ,i 3(c); app. supp. R4, tabs 14-15)

               6. EMC2 submitted Final Indirect Cost Rate Proposals (FICRPs) for FY 2010
        and 2011 related to the 0125 contract (2010/2011 FICRPs). The 2010/2011 FICRPs
        are not in the Rule 4 file. EMC2 alleges that the 2010/2011 FICRPs included as
0   '   allowable costs legal costs EMC2 incurred in connection with the investigations (legal
        costs). (Compl. ,i l(c))

              7. On June 30, 2016, EMC2 submitted FICRPs for FY 2012 and FY 2013
        (2012/2013 FICRPs). The 2012/2013 FICRPs included as allowable costs over
        $10,000 oflegal costs. (R4, tab 4 at 94, 108-09, 116)

                 8. The Defense Contract Audit Agency (DCAA) audited the 2010/2011
        FICRPs (2010/2011 audit), allegedly between January 10, 2017 and January 24, 2017.
        The final audit report for the 2010/2011 audit is not in the Rule 4 file. (Compl.
        ,i l(a)-(b)) However, there is evidence that the DCAA concluded that EMC2 should
        be penalized for including expressly unallowable costs. Nevertheless, the contracting
        officer (CO) waived the penalties for including expressly unallowable costs in
        EMC2's 2010/2011 FICRPs pursuant to FAR 42.709-5(c). (App. supp. R4, tab 10)

        9.    On January 10, 2017, DCAA commenced an audit of the 2012/2013
        FICRPs (2012/2013 audit) (app. supp. R4, tab 5). The 2012/2013 audit resulted in an
        August 17, 2017 audit report (2012/2013 audit report). The 2012/2013 audit report

        1
            The AIO originally sent the show cause letter on November 5, 2012, but the letter
                did not reach EMC2 due to a change of address. The AIO then sent the letter to

C               the new address on December 10, 2012. (App. supp. R4, tab 1 at 1-2)
                                                   2
    £\   questioned the allowability of the legal costs under FAR 31.205-4 7 (b )( 4 ). EMC2 did


I""      not withdraw the 2012/2013 FICRPs prior to the DCAA audit. (R4, tab 4)

                 10. On January 9, 2018, the CO issued a final decision (COFD), assessing a

I        penalty in the amount of$53,614, including interest, due to the inclusion of the legal
         costs in the 2012/2013 FICRPs. The COFD also rejected EMC2's request for a waiver of

I        the penalty for the 2012/2013 FICRPs. (R4, tab 5)

                11. This appeal followed.
                                                                                                       t
                                                DECISION

         I.     The Standards for Summary Judgment

                 Summary judgment will be granted if a moving party has shown that there are no
         genuine issues of material fact, and it is entitled to judgment as a matter of law. Celotex
         Corp. v. Catrett, 477 U.S. 317,322 (1986). A non-movant seeking to defeat summary
         judgment by suggesting conflicting facts must set forth specific facts showing that there
         is a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242,248 (1986).
         In deciding summary judgment motions, we do not resolve controversies, weigh
         evidence, or make credibility determinations. Liberty 
Lobby, 477 U.S. at 255
.
         Moreover, we draw all reasonable inferences in favor of the non-movant. 
Id. II. Penalty
                 The government is entitled to judgment as a matter of law on EMC2' s claim
         that the government improperly imposed the penalty because there is no genuine issue
         of material fact but that the legal costs were expressly unallowable. "If the head of the
         agency determines that a cost submitted by a contractor in its proposal for settlement is
         expressly unallowable under a cost principle ... , the head of the agency shall assess a
         penalty." 10 U.S.C. § 2324(b); see also FAR 42.709-3. An expressly unallowable
         cost is "a particular item or type of cost which, under the express provisions of an
         applicable law, regulation, or contract, is specifically named and stated to be
         unallowable." FAR 31.001. It is the government's burden to show that it was
         unreasonable under all of the circumstances for a person in the contractor's position to
         conclude that the cost was allowable. Luna Innovations, Inc., ASBCA No. 60086,
          18-1 BCA iJ 36,919 at 179,871; Gen. Dynamics Corp., ASBCA No. 49372, 02-2 BCA
         ,i 31,888 at 157,570, rev 'din part on other grounds, Rumsfield v. Gen. Dynamics
         Corp., 
365 F.3d 1380
(Fed. Cir. 2004).

               The express provisions of the FAR specifically state that costs incurred in
         connection with any proceedings-including investigations-brought by the
         government for a violation of the law that result in disposition by compromise are

                                                     3
,,\
\.I
      unallowable if"the proceedings could have led to debarment." FAR 31.205-47(a)-(b). 2
      Here, EMC2 incurred the legal costs in connection with the DOJ and AIO
      investigations for a violation of the law (SOF ,i,i 1, 3, 6-7). Moreover, EMC2 disposed
      of the investigations by compromise when it refunded the Navy $249,850.90 in 2013
      (SOF ,i 5). Further, the investigations could have resulted in debarment, as the Navy
      informed EMC2 in the December 10, 2012 letter (SOF ,i 3; FAR 9.406-2). Because
      there is no genuine issue of material fact suggesting that it was reasonable under all of
      the circumstances for a person in EMC2' s position to conclude that the legal costs were
      allowable, there is no genuine issue of material fact but that the legal costs were
      expressly unallowable.

             EMC2 appears to question whether the investigations would have resulted in
      debarment by arguing that its January 7, 2013 letter establishes that Ms. McGowen's
      statements were not truthful, so EMC2 would have prevailed on the merits in the
      proceeding brought by the government (app. resp. at 2). However, after sending the
      January 7, 2013 letter, EMC2 paid the Navy $249,850.90 to dispose of the
      investigations (SOF ,i 5). That fact calls into question the strength of EMC2's
      argument that the January 7, 2013 letter establishes that it would have prevailed on the
      merits. In any event, under FAR 31.205-47(b), the government merely must show that
      the investigations "could have led to debarment"; not that it would have done so.

()          In sum, because there is no genuine issue of material fact but that the legal costs
      were expressly unallowable, the government is entitled to judgment as a matter of law
      on EMC2's claim that the government improperly imposed a penalty.

      III.    Penalty Waiver

             The government also is entitled to judgment as a matter of law on EMC2's
      claim that it was entitled to a penalty waiver because there is no genuine issue of
      material fact suggesting that EMC2 had adequate policies, training, controls, and
      review systems, and that it inadvertently incorporated the legal costs into the
      2012/2013 FICRPs. A CO must waive a penalty when:

                     The contractor demonstrates, to the cognizant contracting
                     officer's satisfaction, that...[i]t has established policies and
                     personnel training and an internal control and review
                     system that provide assurance that unallowable costs

      2
          EMC2 does not-and could not-argue that the exceptions in FAR 31.205-4 7( c )(1)
             for when a compromise expressly provides that legal costs are allowable, or the
             contractor incurred certain costs in connection with proceedings brought by a
             third party, or a state, local, or foreign government apply here (app. resp.;
C            SOF 111, 3, 5).
                                                    4
I
'




l()                        subject to penalties are precluded from being included in
                           the contractor's final indirect cost rate proposal...and [t]he
                           unallowable costs subject to the penalty were inadvertently
                           incorporated into the proposal, i.e., their inclusion resulted
                           from an unintentional error, notwithstanding the exercise
                           of due care.

            FAR 42.709-5(c). 3

                  Here, EMC2 argues that the government failed to inform EMC2 that the
            government was disallowing the legal costs in EMC2's 2010/2011 FICRPs until after
            EMC2 submitted its 2012/2013 FICRPs (app. resp. at 1). However, as we have
            recognized:

                           The broad purpose of the penalty provisions ... was "to
                           ensure that contractors, rather than the Government bear
                           the burden of assuring that contractor submissions for
                           reimbursement of costs on government contracts do not
                           include unallowable costs." (H.R. Conf. Rep.
                           No. 102-966, 728, reprinted in 1992 U.S.C.C.A.N. 1769,
                           1819 ... )[.]
    ()                            Congress was concerned with ending what
                           Congressman Bill Nichols, Chairman of the Investigations
                           Subcommittee, and an author of the penalty provision,
                           referred to as a "cat-and-mouse game," namely, "a game in
                           which the cost of an item is submitted regardless of
                           whether it's allowable, and the burden is placed on the
                           Government auditors to identify and disallow the item."
                           Review ofAllowable Costs in Overhead Submission[s] of
                           defense Contractors: Joint Hearings before the Seapower
                           and Strategic and Critical Materials Subcommittee and the




            3
                EMC2 does not-and could not-argue that the other exceptions in FAR 42. 709-5
                   for when the contractor withdraws the proposal before the government formally
                   initiates an audit, or the amount of the unallowable costs was $10,000 or less
    r···.          apply here (app. resp.; SOF ,r,r 7, 9).
    V                                                    5
0                  Investigations Subcommittee of the House Comm. on
                   Armed Services, 99th Cong. 52, 60 ( 1985)[.]

     Gen. Dynamics, 02-2 BCA ,r 31,888 at 157,568. Thus, EMC2 cannot avoid the
     penalty by placing the burden of identifying and disallowing the legal costs on the
     government.

             EMC2 also asserts that it updated its accounting policies on January 26, 2017
     (app. resp. at 2). However, EMC2 points to no evidence to support that assertion (id.).
     Even if it had, that would not be a basis for a penalty waiver. In order for the penalty
     waiver to apply, a contractor must have policies established at the time it submitted its
     erroneous FICRP. FAR 42.709-5. Thus, even ifEMC2, as it has alleged, updated its
     policies on January 26, 2017 this was after its submission of the 2012/2013 FICRPs on
     June 30, 2016 and it cannot avail itself of the penalty waiver (SOF ,r 7). Indeed, by
     asserting that it did not update its policies to address the error until January 26, 2017,
     EMC2 effectively concedes that it did not have adequate policies in place at the time it
     submitted the 2012/2013 FICRPs on June 30, 2016 (app. resp. at 2).

           Further, EMC2 asserts that it underbilled the government (app. resp. at 2).
     However, EMC2 points to no evidence supporting that assertion (id.). Even if it had,
     underbiling is not an enumerated basis for a penalty waiver. FAR 42.709-5.
()           Next, EMC2 points to the fact that the CO waived the penalty for its inclusion
     of the legal costs in its 2010/2011 FICRPs (app. resp. at 2). However, a CO's decision
     is not binding in any subsequent proceeding. Weststar Engineering, Inc., ASBCA
     No. 52484, 02-1 BCA ,r 31,759 at 156,853 n.2. Therefore, the CO's decision to waive
     the penalty for the 2010/2011 FICRP is not binding on his decision regarding whether
     to waive the penalty for the 2012/2013 FICRPs.

               Finally, EMC2 argues that it should only pay 55 percent of the penalty to reflect
     an apportionment of the legal costs attributable to its "success[]" in the investigations
     (i.e., the amount by which settlement reduced EMC2's potential liability) (compl.
     ,r 3( d); app. resp. at 2). However, FAR 42. 709-5 does not authorize such
     apportionment. Indeed, the United States Court of Appeals for the Federal Circuit has
     rejected apportionment under similar circumstances-namely in determining when
     legal costs are unallowable. Gen. 
Dynamics, 365 F.3d at 1385
. Therefore, the
     government is entitled to judgment as a matter oflaw on EMC2's penalty waiver claim
     because there is no genuine issue of material fact suggesting that EMC2 had adequate
     policies, training, controls, and review systems, and that it inadvertently incorporated
     the legal costs into the 2012/2013 FICRPs.




                                                 6
                                              CONCLUSION

                   For the reason set forth above, the government's motion for summary judgment
           is granted. This appeal is denied.

                 Dated: December 18, 2018




                                                            Administrative Judge
                                                            Armed Services Board
                                                            of Contract Appeals


           I concur                                         I concur



                                                            J. REID PROUTY
,,.,",,i   Administrative Judge                             Administrative Judge
                                                            Vice Chairman
'-'        Acting Chairman
           Armed Services Board                             Armed Services Board
           of Contract Appeals                              of Contract Appeals


                 I certify that the foregoing is a true copy of the Opinion and Decision of the
           Armed Services Board of Contract Appeals in ASBCA No. 61583, Appeal of Energy
           Matter Conversion Corporation, rendered in conformance with the Board's Charter.

                 Dated:



                                                           JEFFREY D. GARDIN
                                                           Recorder, Armed Services
                                                           Board of Contract Appeals




                                                     7
