Filed: Apr. 12, 2019
Latest Update: Mar. 03, 2020
Summary: United States Court of Appeals For the Eighth Circuit _ No. 18-1455 _ United States of America for the use of Wesco Distribution, Inc. lllllllllllllllllllllPlaintiff v. Liberty Mutual Insurance Company Defendant - Appellee International Fidelity Insurance Company lllllllllllllllllllDefendant - Appellant _ Appeal from United States District Court for the Southern District of Iowa - Des Moines _ Submitted: December 11, 2018 Filed: April 12, 2019 _ Before LOKEN, MELLOY, and ERICKSON, Circuit Judges
Summary: United States Court of Appeals For the Eighth Circuit _ No. 18-1455 _ United States of America for the use of Wesco Distribution, Inc. lllllllllllllllllllllPlaintiff v. Liberty Mutual Insurance Company Defendant - Appellee International Fidelity Insurance Company lllllllllllllllllllDefendant - Appellant _ Appeal from United States District Court for the Southern District of Iowa - Des Moines _ Submitted: December 11, 2018 Filed: April 12, 2019 _ Before LOKEN, MELLOY, and ERICKSON, Circuit Judges...
More
United States Court of Appeals
For the Eighth Circuit
___________________________
No. 18-1455
___________________________
United States of America for the use of Wesco Distribution, Inc.
lllllllllllllllllllllPlaintiff
v.
Liberty Mutual Insurance Company
Defendant - Appellee
International Fidelity Insurance Company
lllllllllllllllllllDefendant - Appellant
____________
Appeal from United States District Court
for the Southern District of Iowa - Des Moines
____________
Submitted: December 11, 2018
Filed: April 12, 2019
____________
Before LOKEN, MELLOY, and ERICKSON, Circuit Judges.
____________
LOKEN, Circuit Judge.
This appeal is part of a complex dispute over costs that resulted from contractor
defaults in completing a federal government construction project. After partial
summary judgment rulings and a bench trial, the district court1 entered judgment
against a subcontractor’s surety, International Fidelity Insurance Co. (“Fidelity”), and
in favor of the general contractor’s surety, Liberty Mutual Insurance Co. (“Liberty”),
for the full amount of Fidelity’s performance bond. Fidelity appeals. We affirm.
I. Background.
In March 2012, Greenleaf Construction Co. (“Greenleaf”) entered into a Prime
Contract with the United States to build an Army Reserve Center in Des Moines,
Iowa. As required by the Miller Act, 40 U.S.C. § 3131(b), Greenleaf obtained a
performance bond and a payment bond from Liberty naming Greenleaf as principal
and the United States as obligee. “A performance bond protects the owner, or
obligee, ensuring project completion if the general contractor defaults. A payment
bond ensures that laborers and material suppliers will be paid if the general contractor
defaults.” Pa. Nat’l Mut. Cas. Ins. Co. v. City of Pine Bluff,
354 F.3d 945, 949 n.2
(8th Cir. 2004) (citations omitted). In April, Greenleaf entered into a Subcontract in
which International Electric, Inc. (“Electric”), agreed to perform defined electrical
and communications work on the project for $1,020,000. The Subcontract required
Electric to furnish performance and payment bonds in the amounts of $1,020,000 (the
bonds’ “penal sum”). Electric obtained the bonds from Fidelity, naming Electric as
principal and Greenleaf as obligee. The performance bond obligated Fidelity to
“promptly remedy” a default by Electric on the Subcontract or “arrange for the
performance of [Electric’s] obligation under the subcontract.”
In January 2014, Greenleaf, Liberty, and the United States entered into a
Takeover Agreement in which Greenleaf and the government “agreed to an
immediate consensual termination and default” of the Prime Contract. Liberty agreed
1
The Honorable Rebecca Goodgame Ebinger, United States District Judge for
the Southern District of Iowa.
-2-
to “complete the Contract in accordance with its terms” and “reaffirm[ed] the validity
of [Liberty’s] Bonds to secure the obligations of its completion.” The Takeover
Agreement provided that Liberty “becomes entitled to all rights, titles, and interests
of Greenleaf in and to the [Prime] Contract.” The government agreed to accept
Vertex Companies, LLC (“Vertex”), as Liberty’s “completion contractor.” The
government also agreed to work with Liberty “to agree on a schedule establishing a
new construction completion date,” which had been October 12, 2013.
On February 7, Liberty and Electric entered into a Subcontract Ratification
Agreement in which Liberty agreed to pay Electric $244,134 for work previously
performed under the Subcontract but not paid by Greenleaf. Electric agreed to
“perform the balance of the work for [the unpaid balance of the $1,020,000
Subcontract amount, $347,612] in accordance with the terms and conditions of the
Subcontract, as modified by this Agreement.” Fidelity was not asked to -- and did not
-- bond the Ratification Agreement.
A dispute soon arose between Electric and Vertex as completing general
contractor, and Electric never returned to the project. Liberty terminated Electric for
its default in April 2014 and notified Fidelity. Fidelity refused to complete Electric’s
obligations under the Subcontract. Liberty hired an electrical subcontractor, ABC
Electric, to complete work under the Subcontract. ABC Electric concluded that much
of the work Electric had performed needed to be redone and ultimately charged
Liberty $1,657,745 to complete electrical and communications work on the project.
This lawsuit began in August 2014 when the federal government sued
Greenleaf, Electric, Liberty, and Fidelity on behalf of an unpaid supplier. That claim
has been resolved. Liberty filed a cross-claim against Fidelity and Electric for breach
-3-
of the Subcontract and breach of Fidelity’s performance and payment bonds.2 Ruling
on cross-motions for summary judgment, the district court granted Liberty partial
summary judgment, ruling that Liberty may assert claims against Fidelity’s
performance bond, the bond was not discharged by replacement or material alteration,
and Fidelity’s obligations “were triggered by the satisfaction of the bond’s conditions
precedent.” After a bench trial on Liberty’s claims against the performance and
payment bonds, the court entered judgment against Fidelity for $1,020,000, the full
amount of its performance bond. Fidelity has not appealed the $104,231 judgment
entered in favor of Liberty on its claims against Fidelity’s payment bond.
Fidelity argues it is not liable to Liberty on the performance bond because (1)
Liberty was not Greenleaf’s “successor” entitled to assert a claim on the bond; (2) the
Ratification Agreement discharged Fidelity’s performance bond because it was either
an entirely new agreement or materially altered Electric’s Subcontract, and Fidelity
did not bond the Ratification Agreement; and (3) Liberty’s claim did not meet
conditions precedent to the performance bond’s coverage.
II. The Successor Issue.
In holding that Liberty may assert a claim against Fidelity’s performance bond,
the district court first ruled that, by satisfying Greenleaf’s obligations under the Prime
Contract and the Subcontract, Liberty became subrogated to Greenleaf’s rights
through equitable subrogation. The court noted it is well-established “that a surety
who pays the debt of another is entitled to all the rights of the person he paid to
enforce his right to be reimbursed,” Pearlman v. Reliance Ins. Co.,
371 U.S. 132, 136-
37 (1962), and the Supreme Court of Iowa expansively views the rights of a subrogee
who “steps into the shoes” of another, Iowa Dep’t of Human Servs. v. Unisys Corp.,
2
Electric subsequently filed for bankruptcy protection. The bankruptcy court
lifted the automatic stay to permit Liberty’s claim against Fidelity to proceed.
-4-
637 N.W.2d 142, 156 (Iowa 2001). Without challenging this general principle,
Fidelity argues that Liberty as subrogee acquired no right to assert a claim against the
performance bond because the bond provides, “No right of action shall accrue on this
bond to or for the use of any . . . corporation other than [Greenleaf] or the heirs,
executors, administrators or successors of [Greenleaf].” Citing corporate law
decisions, Fidelity argues that Liberty was not Greenleaf’s “successor” under the
bond “because it never assumed generally Greenleaf’s liabilities.” Like the district
court, we disagree.
The Supreme Court of Iowa has stated that “[t]he exact meaning of the word
‘successor’ as applied to a contract must depend largely on the kind and character of
the contract, its purposes and circumstances, and the context.” Sun Valley Iowa Lake
Ass’n v. Anderson,
551 N.W.2d 621, 640 (Iowa 1996) (quotation omitted). Applying
this standard in the context of surety bonds, the district court agreed with decisions
from other jurisdictions concluding that a surety who has performed the contract
obligations of its principal “qualifies as a ‘successor.’” See Argonaut Ins. Co. v.
Commercial Std. Ins. Co.,
380 So. 2d 1066, 1067-68 (Fla. App. 1980), followed in
Menorah Nursing Home, Inc. v. Zukov,
548 N.Y.S.2d 702, 705-06 (App. Div. 1989).
Though Fidelity urges us to adopt a narrower definition of successor that is
more in tune with corporate law, we agree with the district court’s interpretation of
the word as used in Fidelity’s performance bond. Moreover, there is an additional
reason to adopt this interpretation. The performance bond Liberty issued to ensure
general contractor Greenleaf’s performance to the United States was a bond legally
mandated by the Miller Act. See generally Restatement (Third) of Suretyship &
Guaranty § 71 (1996). Federal Acquisition Regulations expressly encourage
government contracting officers to enter into a takeover agreement with a surety such
as Liberty who is willing to perform its defaulting principal’s obligations as
government contractor. See 48 C.F.R. § 49.404.
-5-
When a general contractor’s surety takes over completion of a federal
government construction project and “steps in the shoes” of its principal, the purposes
of the Miller Act and the FAR regulations to protect the government are served if the
surety is subrogated to the principal’s contract rights vis-a-vis a subcontractor such
as Electric and, if the subcontractor defaults, its surety. Fidelity, in the business of
issuing performance and payment bonds, necessarily understands this reality. Thus,
when Fidelity has issued a performance bond for a subcontractor on a federal project,
and its principal has defaulted, we reject its contention that the ambiguous word
“successor” in the performance bond did not include as obligee a surety operating
under a Takeover Agreement with the federal government.
III. Bond Discharge Issues.
Exalting form over substance and ignoring modern suretyship authorities,
Fidelity next argues that its obligations under the performance bond were discharged
“because the Ratification Agreement either replaced or materially altered” the
Subcontract that Fidelity bonded. Fidelity first argues that “[t]he bonded Subcontract
ended -- at the latest -- in January 2014 upon the execution of the Takeover
Agreement.” Fidelity cites no Subcontract provision or legal authority supporting
this contention, instead asserting that “the notion that the Subcontract continued
despite Greenleaf leaving the job is nonsensical.” Of course, this ignores the legal
and contractual consequences of Liberty as surety stepping in the shoes of its
principal to complete the Prime Contract. Nothing in Greenleaf’s Subcontract with
Electric provided that the contract terminates if Greenleaf ceases to be general
contractor. Indeed, the Subcontract expressly prohibited Electric, but not Greenleaf,
from assigning or transferring its interest without consent. In the February 2014
Ratification Agreement, Electric and Liberty expressly “ratif[ied] and confirm[ed]
that the Subcontract is in effect, and that [Electric] shall perform and complete the
Subcontract in accordance with the terms and provisions thereof at the direction of
[Liberty] and for the same consideration.” Thus, the Subcontract never “ended.”
-6-
Turning to a more difficult issue, Fidelity argues that the Ratification
Agreement discharged Fidelity’s bond because it was a “material alteration” of the
bonded Subcontract. Fidelity first urges us to adopt the “general rule” that any
contract change discharges the surety, even if to its benefit. See Holland v. Story
Cty.,
192 N.W. 402, 403 (Iowa 1923). The district court instead adopted the more
modern rule that, to be discharged, the surety must show that an alteration enlarged
or added to the obligations or otherwise prejudiced the performance of the surety’s
bonded principal. See Knapp v. Knapp,
99 N.W.2d 396, 402 (Iowa 1959); Throp v.
Chaloupka,
208 N.W. 299, 300 (Iowa 1926). The evolution of this rule reflected a
recognition that the older strict rule “was problematic when applied to secondary
obligors, such as surety companies, who were in the business of entering into
secondary obligations” and received a windfall if their obligations were discharged
for an alteration that caused no harm. Restatement Suretyship § 37, cmt. a. Agreeing
with this trend, the Restatement adopted, for most contract modifications, the rule that
a surety “is discharged from any unperformed duties . . . if the modification . . .
imposes risks on the [surety] fundamentally different from those imposed . . . prior
to modification.” § 41(b)(i). The Restatement rule and the rule the district court
derived from Knapp are essentially the same. We conclude the Supreme Court of
Iowa would apply an equivalent rule governing discharge of a surety in this
construction contract situation. Fidelity cites no contrary authority.
Applying this standard to the Ratification Agreement, the district court
concluded that none of the alterations alleged by Fidelity “materially altered
[Electric’s] actual obligations under the Subcontract.” We agree. The Ratification
Agreement expressly left the Subcontractor’s performance obligations, time to
complete its work, and compensation unchanged. Fidelity primarily argues that
changing the general contractor and bond obligee from Greenleaf to Liberty was
material and prejudicial because “the chief financial officers of Electric and Greenleaf
were close personal friends” but Electric had no such relationship with Vertex. We
reject this argument because it would automatically discharge a subcontractor surety’s
-7-
performance bond whenever the general contractor’s surety operating under a
Takeover Agreement becomes a successor bond obligee.
Fidelity further argues that the Ratification Agreement was a material alteration
because, as a result of changing the bond obligee, Fidelity “has been ordered to pay
hundreds of thousands of dollars to redo work that the named obligee, Greenleaf,
previously accepted” to complete a Subcontract that was valued at $347,612 in the
Ratification Agreement. But the alleged causation is unfounded. As the district court
observed, “these increased costs occurred after the parties signed the Ratification
Agreement. The Ratification Agreement did not amend the Subcontract to increase
Electric’s obligation -- and thus increase the total cost of Electric’s work.” Moreover,
Electric was terminated before it performed additional work under the Ratification
Agreement. True, the increased costs to complete performance of the Subcontract
were incurred after Electric was terminated. But they resulted from defective work
Electric performed before Liberty replaced Greenleaf under the Takeover Agreement.
Thus, had there been no Ratification Agreement, Liberty as Greenleaf’s successor
would have had virtually the same claim against Fidelity’s performance bond.
We agree with the district court that the many Subcontract changes in the
Ratification Agreement cited by Fidelity did not as a matter of law, singly or in
combination, so materially alter Electric’s obligations under the Subcontract that
Fidelity’s performance bond was discharged. This ruling did not foreclose possible
defenses to Liberty’s claim against the bond based on facts surrounding Liberty’s
takeover and completion of Electric’s performance under the Subcontract as modified
by the Ratification Agreement. Cf. Restatement Suretyship § 41(b)(ii). These
defenses were thoroughly litigated in the bench trial. For example, in response to
Fidelity’s contention that Liberty failed to mitigate its damages as successor obligee,
the court found that Liberty acted reasonably in replacing Greenleaf with Vertex as
completion contractor and took appropriate measures to avoid escalating costs during
the transition. Fidelity has not appealed these bench trial findings.
-8-
IV. Condition Precedent Issues.
The performance bond provided that Fidelity’s remedy obligations are
triggered “[w]henever [Electric] shall be, and be declared by [Greenleaf] to be in
default under the subcontract, [Greenleaf] having performed [Greenleaf’s] obligations
thereunder . . . .” Fidelity argues that Liberty’s claim against the performance bond
must be rejected because it failed to meet these two conditions precedent.
First, Fidelity argues that, at the time Liberty terminated Electric for its default
under the Subcontract, “Greenleaf could not have been performing under the
Subcontract because Greenleaf defaulted on the Project three months earlier.”
Second, Fidelity argues that “Greenleaf never declared Electric in default under the
Subcontract.” We agree with the district court that these contentions are without
merit because they are inconsistent with Liberty’s right as successor obligee. First,
Fidelity does not claim that Liberty had failed to perform the obligee’s obligations
under the Subcontract when the bond claim was made. At that time, Greenleaf’s
Subcontract performance was irrelevant. Second, it is undisputed that Electric was
in default when the claim was made (Fidelity as surety later filed a claim in Electric’s
bankruptcy proceeding). We reject as frivolous the contention that the notice of
default to Electric was ineffective because it was sent by Vertex rather than Liberty.
For the foregoing reasons, the judgment of the district court is affirmed.
______________________________
-9-