WILLIAM M. SKRETNY, Chief Judge.
In this action, Plaintiff L.W. Matteson, Inc. ("Matteson") brings suit against Defendant Sevenson Environmental Services, Inc. ("Sevenson") claiming that Defendant breached its contract with Plaintiff by failing to pay the agreed upon amount following Plaintiff's completion of dredging services on Defendant's behalf. Defendant counterclaims alleging Plaintiff negligently misrepresented its ability to perform the contract. Defendant also makes a cross-motion for sanctions claiming that Plaintiff destroyed evidence critical to its defense. Presently before this Court is Plaintiff's Motion for Summary Judgment on its breach of contract and prompt payment claims.
Plaintiff Matteson is an Iowa corporation with its principal place of business in Burlington, Iowa. (Complaint ("Comp."), Docket No. 1, ¶ 1.) Matteson is in the business of dredging materials from waterways and major bodies of water throughout the United States, in the role of general contractor, subcontractor, and lessor. (Plaintiff L.W. Matteson's Reply to Defendant's Response to the Statement of Material Facts in Support of Matteson's Motion for Summary Judgment ("Statement"), Docket No. 54, ¶ 1.) Defendant Sevenson is a New York corporation with its principal place of business in Niagara Falls, New York. Sevenson is in the business of environmental remediation projects and acts as a general contractor. (Id. at ¶ 2; Comp. ¶ 2.)
The TVA is a corporate agency and instrumentality of the United States engaged in electrical power generation. (Statement ¶ 4.) The TVA had been storing fly ash waste in a storage cell adjacent to the Emory River. (Id. ¶¶ 5, 6.) This storage cell failed on December 22, 2008, releasing fly ash into the Emory River, prompting the TVA to issue a Request for Proposal for dredging the Emory River of fly ash. (Id. ¶ 7, 9.)
Sevenson submitted a proposal which included the use of two dredging vessels, as well as a third vessel as needed, to meet the TVA's specifications that an average minimum of 9,000 cubic yards be dredged per day, for a total of 1.5 million cubic yards over the course of the project. (Id. ¶¶ 10, 11, 12.) Sevenson and the TVA entered into a contract on July 15, 2009 for dredging operations in the Emory River, with an effective date of July 1, 2009. (Id. ¶ 16.)
Prior to entering the contract with the TVA, Sevenson executed a Purchase Order ("PO") with Matteson, in which Matteson agreed to provide a dredging vessel, equipment, and personnel, and perform dredging work as directed by Sevenson at a per hour unit price. (Id. ¶¶ 20, 23.) The PO provided that Matteson would provide good and merchantable equipment, and would repair and replace equipment that Sevenson found faulty or defective. (Id. ¶ 23.) The PO also included a series of rental rates that set a payment schedule
Sevenson retained the right to terminate the contract for any reason and did so on February 1, 2010 after dredging operations were completed. (Id. ¶ 35.) Matteson calculated that the total hours of operation under the 100%, 70%, and 40% pay categories added up to a final cost of $5,173,273.50. (Id. ¶ 44.) This included 1,709.96 hours at 100% pay time, 776.01 hours at 70% pay time, and 85.42 hours at 40% pay time. (Id.) Sevenson reevaluated Matteson's calculations and paid Matteson only $2,931,587.11. (Id. ¶¶ 44, 47.) Matteson brings this action to recover the difference, plus interest. (Comp. ¶ 53.) Sevenson counterclaims alleging that Matteson misrepresented its ability to dredge 1.5 million cubic yards of fly ash at an average daily rate of 12,000-20,000 in situ cubic yards. (Answer with Counterclaim, Docket No. 8, ¶ 15.) Sevenson also claims Matteson was responsible for the destruction of evidence crucial to Sevenson's defense. (Memorandum of Law in Opposition to Plaintiff's Motion for Summary Judgment and in Support of Defendant's Cross-Motion for Sanctions ("Def.'s Opp'n"), Docket No. 52, 14.)
Plaintiff commenced this action on March 2, 2010 by filing a complaint in the United States District Court for the Western District of New York. On April 5, 2010, Sevenson filed an Answer and Counterclaim. Matteson responded with its Reply on April 26, 2010 and this Court referred non-dispositive pre-trial matters to the Honorable H. Kenneth Schroeder, Jr., United States Magistrate Judge. After a series of amended case management orders, discovery was set to close by June 1, 2011. Immediately prior to the close of discovery, Sevenson moved Judge Schroeder to grant an extension of time to complete discovery, as well as a motion to amend/correct its Answer to include a re-calculation of damages and clarification of its negligent misrepresentation counterclaim. The motions were fully briefed. Before Judge Schroeder could issue a decision resolving Sevenson's motions, Matteson filed its Motion for Summary Judgment. This Court stayed Judge Schroeder's amended case management order of March 4, 2011 pending resolution of Plaintiff's motion. Sevenson filed its Opposition to Matteson's motion on August 12, 2011, including a Cross-Motion for Sanctions. Matteson filed a reply to Sevenson's Opposition on September 2, 2011, and a Response to Sevenson's cross-motion on September 6, 2011. Sevenson filed an Affidavit in reply on September 16, 2011. Most recently, on October 27,
Rule 56 of the Federal Rules of Civil Procedure provides that summary judgment is warranted where the "pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law." Fed.R.Civ.P. 56(c). A "genuine issue" exists "if the evidence is such that a reasonable jury could return a verdict for the non-moving party." Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). A fact is "material" if it "might affect the outcome of the suit under governing law." Id.
In deciding a motion for summary judgment, the evidence and the inferences drawn from the evidence must be "viewed in the light most favorable to the party opposing the motion." Addickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S.Ct. 1598, 1609, 26 L.Ed.2d 142 (1970). "Only when reasonable minds could not differ as to the import of evidence is summary judgment proper." Bryant v. Maffucci, 923 F.2d 979, 982 (2d Cir.1991). The function of the court is not "to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial." Anderson, 477 U.S. at 249, 106 S.Ct. 2505.
Matteson's dispositive motion raises three primary issues: (1) whether Sevenson breached its contract with Matteson; (2) whether Sevenson's affirmative defenses preclude summary judgment in Matteson's favor; and (3) whether Matteson is entitled to summary judgment on Sevenson's counterclaim. These issues are discussed below.
Matteson argues that it is entitled to summary judgment because the PO requires payment according to the number of hours Matteson's equipment is used. Matteson asserts that on top of the $2,931,587.11 Sevenson previously paid, Matteson is entitled to an additional $3,926,760.92, plus prejudgment interest, for its work. Sevenson disputes the accuracy of Matteson's calculations and alleges that Matteson improperly charged a 100% payment rate anytime the dredge pumps were running, instead of reducing the payment rate whenever the dredge pumps were only pumping water.
Under New York law, a plaintiff alleging a breach of contract must establish (1) the existence of a contract; (2) performance of the contract by one party; (3) breach by the other party; and (4) resulting damages. Rexnord Holdings, Inc. v. Bidermann, 21 F.3d 522, 525 (2d Cir.1994).
The parties' agreement, detailed in the PO, calls for a 100% payment rate of $2,100 for every hour the dredge pumps were active and pumping material. (Statement ¶ 24.) "Material" is defined as anything over the density of water. (Def.'s Opp'n 4.) Because the density of water is 1.0 grams per cubic centimeter, anything over that number would constitute material. (Id.) Fly ash, the specific material Matteson was dredging for, ranged from 1.0001 to 1.4 grams per cubic centimeter. (Id.) The parties agree that whenever the dredges were pumping water, or 1.0 grams per cubic centimeter, and not material, that a reduced payment rate would be applied. (Plaintiff L.W. Matteson, Inc.'s Reply to Defendant's Opposition to Plaintiff's Motion for Summary Judgment ("Pl.'s Reply"), Docket No. 53, 3-4.)
The parties dispute how the number of 100% payment rate hours should be determined. Matteson argues that the hours should be measured according to the dredge logs. Sevenson argues that the dredge logs are inaccurate, and that the proper record is determined by a computer software program installed on Matteson's dredge vessel called Win-OPS. (Def.'s Opp'n 7.)
The dredge logs were kept by Matteson's dredge operators, or levermen, who operated the dredge pumps and recorded when those pumps were started and stopped, as well as the density of the material being pumped. (Pl.'s Ex. 20.) In addition, Sevenson had personnel on Matteson's vessel full-time to observe the effluent being discharged by the dredging operation. (Pl.'s Ex. 19.) The logs were submitted to Sevenson's Project Manager, Joseph Burke, who allegedly compared Matteson's pay applications with Sevenson's own records and resolved any discrepancies. (Plaintiff L.W. Matteson, Inc.'s Memorandum in Support of Motion for Summary Judgment, Docket No. 40, 3-4.) Using these records, Sevenson created a spreadsheet, identifying the number of hours dredged by Matteson. (Statement ¶ 28.) Further, Matteson contends that charging on the basis of the dredge logs constitutes the industry standard. (Pl.'s Reply 3.)
Sevenson disputes the accuracy of the dredge logs on a number of grounds.
However, Sevenson's argument ignores that the dredge logs do, in fact, show when
The affidavits Sevenson submits do little to counter this fact. For example, Sevenson argues that Burke's affidavit demonstrates that neither he nor anyone else kept track of when Matteson was pumping material. Yet Burke's deposition shows that he did go over Matteson's numbers, including downtime and standby time, and that he conferred with Mahlon Vance Mangum, Matteson's project superintendent, to ensure that the numbers were in agreement.
(Pl.'s Ex. 12.)
Sevenson also selectively quotes from the deposition of L.W. Matteson, Jr., Matteson's vice-president. Sevenson quotes the witness as saying that "[i]f the pump is turning, that's paytime, one hundred percent pay time," as evidence that Matteson only kept track of when the pump was on and off. (Def.'s Opp'n 5.) Sevenson neglects to include the following sentence, which states "[w]hen the clutch is out and you are moving anchors or cleaning debris, it's at a lesser rate." (Def.'s Ex. 9.) Sevenson continues to cherry-pick later parts of the deposition, quoting "[i]f there is water coming out of the end of the pipe, the clutch is engaged.... [i]f there's not, the clutch wouldn't be engaged.... [t]hat's the normal situation, yes." (Def.'s Ex. 9.) But Sevenson ignores the intervening testimony that rental agreements would typically also involve the parties agreeing on a daily basis what the run time was, including that in this contract Sevenson had individuals watching what was coming out of the pipe. (Def.'s Ex. 9.)
Sevenson has also submitted the affidavit of M.V. Mangum, who was Matteson's superintendent on the project, and responsible for preparing and submitting daily production reports to Sevenson. (Def.'s Ex. 6.) Sevenson argues that Mangum was never instructed to exclude from the levermen's logs or daily reports the time that only water was being pumped. Sevenson submits select pages from Mangum's deposition in support of this contention, but fails to include that testimony showing that Mangum would be contacted from the shoreline regarding what type of material the pump was releasing. (See Def.'s Ex. 14; Pl.'s Ex. 20.) Specifically, Mangum testified that:
(Pl.'s Ex. 20.) Mangum went on to testify that he "had reliable reports and the levermen there to hopefully tell [him] the truth." This was corroborated by Sevenson's President, Michael A. Elia, who testified that Sevenson's personnel observed Matteson's dredging operations. (Pl.'s Ex. 19.) Mangum's later affidavit testifies that Matteson failed to inform its levermen that the dredge logs should only include time spent pumping material. (Def.'s Ex. 6.) To the extent this affidavit conflicts with Mangum's earlier deposition testimony that the levermen were informed when only water was being pumped and that these reports were reliable, Mangum's affidavit is deemed inconsistent and will not be considered. Golden v. Merrill Lynch & Co., No. 06 Civ. 2970(RWS), 2007 WL 4299443, at *9 (S.D.N.Y. Dec. 6, 2007) ("Courts in this Circuit have rejected such attempts to rely on declarations that contradict the witness's prior deposition testimony and have granted summary judgment even where the purported new evidence would otherwise create a triable issue of fact." (citing Brown v. Henderson, 257 F.3d 246, 252 (2d Cir.2001)). This Court further notes that, as discussed above, the dredge logs did show when only water was being pumped.
Other affidavits submitted by Sevenson are no more availing. Richard Bradley, one of Matteson's engineers, now working for Sevenson, stated that levermen wrote in the dredge logs when the dredge pump was started and stopped, which "included the time that the dredge was pumping water in order to float lines and sink lines." (Def.'s Ex. 2.) But this corresponds exactly to what the dredge logs show, namely that the levermen would record, under the column labeled "Reasons," why payment at a reduced rate was appropriate, including during those times when they would float and sink lines.
Nevertheless, summary judgment cannot be granted in Matteson's favor because the record contains enough evidence to challenge the accuracy of the dredge logs. For example, Superintendent Mangum, during his deposition, described several problems with the nighttime levermen. "The nighttime people, they would write down stuff and I didn't ever know what half of it meant. I mean, I don't know whether they was [sic] just writing down stuff to be writing it down or what...." (Pl.'s Ex. 20.) Mangum further testified that the density meter was inoperable at times and that levermen would not always record gauge readings. (Id.) "They a whole lot of times just didn't fill it out. You know, whether it was working correctly or not, at times it was, at times it wasn't. I would have the levermen argue back and forth about it." (Id.) Other testimony confirms that the dredge reports were not entirely accurate. The affidavit of Timothy M. Donegan, a licensed engineer previously with Matteson, shows that Matteson's density gauge may not have been working properly. (Def.'s Ex. 5; Pl.'s Ex. 25.) This was corroborated by the affidavit of Timothy J. Harrington, a licensed engineer with a company called Hard Hat Services that was retained by Sevenson to analyze the dredge production of Matteson. (Def.'s Ex. 4.) Harrington's analysis revealed that the density meter would read 1.01 or 1.02 even when pumping only water. (Id.)
Further, although Matteson claims it proceeded in a manner consistent with the industry's standard, Matteson has not shown that the parties intended this standard to bind their agreement, especially since the PO stipulated that Matteson would act "in strict compliance" with the principal contract between the TVA and
The Court also notes that Sevenson has argued in favor of an alternative means of measuring Matteson's hours of operation. (Def.'s Opp'n 8.) WinOPS is a software program installed aboard dredging vessels, including Matteson's, that monitors the positioning of a dredge, as well as the density of material being pumped. (Pl.'s Ex. 25.) Data from that program reflects that between August 25, 2009 and September 1, 2009 there were significant discrepancies between the total hours WinOPS recorded the pumps processing material of a density in excess of 1.0 grams per cubic centimeter and the total hours that Matteson billed at 100%. (Def.'s Ex. 5.) Specifically, between August 25, 2009 and September 1, 2009, WinOPS recorded a density in excess of 1.0 for a total of 79.3 hours. (Id.) By contrast, Matteson billed Sevenson at a 100% payment rate for 114.25 hours. (Id.) Considering the total time the pump was operating, reveals that Matteson was only pumping material having a density greater than 1.0 for 53% of the time. (Id.) Unfortunately, for reasons discussed later, WinOPS data is available for only this eight day period.
Unsurprisingly, Matteson strongly contests the data's significance. Matteson argues that WinOPS is never used to calculate the amount of material dredged, or the number of hours a dredge was pumping, and reiterates that the industry standard is to abide by the dredge logs. (Pl.'s Ex. 25.) Of greater importance, is Matteson's assertion that WinOPS only records density data to a single decimal point. This means that a dredge pump could be processing material at a density of 1.0001, while WinOPS would record a density of 1.0, the density of water. (See Pl.'s Ex. 25.) WinOPS data in the record does indeed reflect that density is measured only to a single decimal. (See, e.g., Def.'s Ex. 5b.) Further, the density of fly ash in water ranges anywhere from 1.0001 to 1.3.
Accordingly, Matteson's Motion for Summary Judgment on its breach of contract claim will be denied.
Sevenson presents two affirmative defenses in its Answer. The first is that Matteson breached the contract by failing to provide a sufficient number of skilled employees and equipment in good working order. The second is that Matteson warranted that it would be able to excavate an average rate of 12,000 in situ cubic yards per day of fly ash. In its supporting memorandum, Matteson argues that neither of these defenses is sufficient to preclude summary judgment. Matteson points to the PO which does not contain any production requirements, and only specifies payment by hours of operation. Similarly, the PO does not specify staff levels. The PO also contains a merger clause stating that "[t]his agreement is the sole and entire agreement between the parties and supersedes all prior communications, proposals, offers and agreements, whether written or oral," which Matteson argues precludes Sevenson's affirmative defenses.
"Federal courts may deem a claim abandoned when a party moves for summary judgment on one ground and the party opposing summary judgment fails to address the argument in any way." Dunkin' Donuts Franchised Rests. LLC v. Tim & Tab Donuts, Inc., No. 07-CV-3662 (KAM)(MDG), 2009 WL 2997382, at *9 (E.D.N.Y. Sep. 15, 2009) (quoting Taylor v. City of New York, 269 F.Supp.2d 68, 75 (E.D.N.Y.2003)).
Upon review of Sevenson's responding memorandum, it is clear that Sevenson disputes Matteson's motion for summary judgment as to Sevenson's counterclaim, but makes no arguments responding to Matteson's arguments against its affirmative defenses. Specifically, Sevenson has no response to the fact that the PO does not contain minimum staffing or production levels, that the merger clause precludes warranty defenses, that the agreement already provided for pay exceptions for faulty equipment, and that Sevenson failed to exercise its right to terminate Matteson until the dredging operations were completed. Although there may be some factual cross-over between Sevenson's affirmative defenses and its counterclaim, Sevenson has chosen to address these, if at all, within the context of its counterclaim. "As a result of defendants' failure to oppose plaintiff's motion as to their defenses ... the court finds that the defendants abandoned their affirmative defenses.... [and] grants plaintiffs' motion for summary judgment as to the affirmative defenses...." Id. (citing Wecare Holdings, LLC v. Bedminster Int'l Ltd., 08-CV-6213, 2009 WL 604877, at *8, 2009 U.S. Dist. Lexis 20080, at *28 (W.D.N.Y. Mar. 9, 2009)).
In its Answer, Sevenson asserts a counterclaim for negligent misrepresentation.
"Under New York law, the elements for a negligent misrepresentation claim are that (1) the defendant had a duty, as a result of a special relationship, to give correct information; (2) the defendant made a false representation that he or she should have known was incorrect; (3) the information supplied in the representation was known by the defendant to be desired by the plaintiff for a serious purpose; (4) the plaintiff intended to rely and act upon it; and (5) the plaintiff reasonably relied on it to his or her detriment. In re Actrade Fin. Techs. Ltd., No. 02-16212(ALG), 2007 WL 433358, at *5 (Bankr.S.D.N.Y. Feb. 5, 2007) (quoting Hydro Investors, Inc. v. Trafalgar Power, 227 F.3d 8, 20 (2d Cir.2000)).
Matteson argues that Sevenson cannot establish reasonable reliance on Matteson's alleged misrepresentations. Even where there is a duty to disclose and a special relationship between the parties, it is not necessarily the case that one party reasonably relied on the misrepresentations or omissions of another. PPI Enters. (U.S.), Inc. v. Del Monte Foods Co., No. 99 Civ. 3794(BSJ), 2003 WL 22118977 (S.D.N.Y. Sep. 11, 2003). Here, there is conflicting testimony as to whether Sevenson relied on Matteson's representations regarding its ability to dredge 12,000 in situ cubic yards per day. Sevenson argues that Matteson quoted it this figure, and that Sevenson relied on this quote in making its June 15, 2009 bid, citing to excerpts of its president's deposition. (Def.'s Ex. 8.) However, that excerpt does not mention any date. Furthermore, Sevenson's reliance on a detailed cost summary by Matteson is misplaced because this was an internal document, that was never provided to Sevenson until discovery. (Def.'s Ex. 13.)
In any case, these testimonies are ultimately unavailing because the only actual quote Matteson made to Sevenson, from June 12, 2009, does not state any production requirements. Instead, it clearly states that "Pay hour quantities are estimated quantities." (Def.'s Ex. 15.) These estimates are backed up by the fact that the PO itself only lists estimated hours. Additionally, the PO contains a merger clause stating that the PO is the "sole and entire agreement between the parties and supersedes all prior communications, proposals, offers and agreements, whether written or oral." (Statement ¶ 31.) The PO also specifies that Matteson would be paid at a unit price, "regardless of whether the final quantities are more or less than the estimated quantities stated herein or in the Principal Contract." (Pl.'s Ex. 11.) These circumstances preclude Sevenson from establishing reasonable reliance because any representations would have been replaced by the parties' agreement which contained only an estimate of the hours, and did not bind Matteson to any particular production number. See Harsco Corp. v. Segui, 91 F.3d 337, 342-43 (2d Cir.1996) (affirming district court's holding that plaintiff failed to establish reasonable reliance where contract contained merger clause and disclaimed all representations not in the agreement).
Sevenson's claim that it reasonably relied on Matteson's assertions is further undermined because the record primarily references conversations regarding Matteson's production capabilities occurring after Sevenson had submitted its bid, and before execution of the PO. (Statement ¶ 38.) These meetings also reflect that Matteson was making no guarantees regarding its ability to process 12,000 cubic yards. (Pl.'s Ex. 13.)
Accordingly, this Court concludes that Sevenson could not have reasonably relied on any assertions Matteson allegedly made. Both parties are experienced business entities that knowingly entered into a contract that expressly provided that it was the sole agreement between them. (See Pl.'s Ex. 7.) That contract provided for an hour-based payment schedule. It did not contain a daily production average. Similarly, the only clear quote Matteson provided prior to Sevenson's bid submission also does not include a daily production average. Sevenson cannot now claim that a production schedule should be read into the parties' agreement. "[W]here, as here, an express provision in the written contract contradicts the claimed oral representations in a meaningful fashion .... the conflict between the provisions of the written contract and the oral representations negates the claim of reliance upon the latter." Bango v. Naughton, 184 A.D.2d 961, 584 N.Y.S.2d 942, 944, (N.Y.App.Div.1992). Matteson's Motion for Summary Judgment on Sevenson's counterclaim will be granted.
Sevenson asserts it is entitled to sanctions for Matteson's failure to retain WinOPS data. Sevenson argues that the parties' relationship provided Matteson with reasonable notice of the potential for litigation as early as September 2009, as evidenced by Sevenson's Notice of Potential Default/Termination to Matteson. (Def.'s Ex. 22.) Sevenson further argues that, knowing that litigation was reasonably foreseeable, Matteson failed to preserve the WinOPS data which allegedly included the only accurate record of Matteson's dredging operations. Matteson responds that it provided Sevenson with the WinOPS data throughout their relationship and that Sevenson expressed interest in this data only after Matteson filed its Motion for Summary Judgment.
A party seeking sanctions based on spoilation of evidence must establish that "(1) the party having control over the evidence had an obligation to preserve it at the time it was destroyed; (2) the records were destroyed with a culpable state of mind; and (3) the destroyed evidence was relevant to the party's claim or defense such that a reasonable trier of fact could find that it would support that claim or defense." Liberman v. FedEx Ground Package Sys., Inc., No. 09 CV 2423(RML), 2011 WL 145474, at *2 (E.D.N.Y. Jan. 18, 2011) (citing Zubulake v. UBS Warburg LLC, 229 F.R.D. 422, 430 (S.D.N.Y.2004)).
Of these, only the third element is clearly met. "[T]he party seeking an adverse inference must adduce sufficient evidence from which a reasonable trier of fact could infer that `the destroyed [or unavailable] evidence would have been of the nature alleged by the party affected by its destruction.'" Residential Funding Corp. v. DeGeorge Fin. Corp., 306 F.3d 99, 109 (2d Cir.2002) (quoting Kronisch, 150 F.3d at 127). Here the availability of several days' worth of WinOPS data is sufficient to show that the missing WinOPS data would likely have yielded similar information. However, in consideration of the remaining elements, this Court concludes that Sevenson's cross-claim should be denied.
A party seeking sanctions for destroyed evidence must establish that "the party having control over the evidence... had an obligation to preserve it at the time it was destroyed." Kronisch v. United States, 150 F.3d 112, 126 (2d Cir. 1998). The obligation typically arises when a party is put on notice that the evidence is relevant to litigation, which may be after or before suit is filed, depending on the circumstances. Liberman, 2011 WL 145474, at *3. Here, Sevenson alleges such an obligation attached as of August 25, 2009 and September 4, 2000 when Sevenson made Matteson aware that it was not satisfied with Matteson's performance. (Def.'s Exs. 18, 22.) However, although these letters express Sevenson's dissatisfaction, they do not contest the manner in which Matteson was tracking its hours of operation. The letters refer to holes in the hull of Matteson's vessel and Matteson's supply of spare parts, but does not reference the manner in which Matteson recorded the number of hours it pumped material, or the accuracy of that process. This does not create an obligation to save records from a software program that kept track of a dredging vessel's positioning.
Moreover, sanctions will not be imposed unless the party responsible had a sufficiently culpable state of mind. In re
Therefore, Sevenson's Cross-Motion will be denied.
For the reasons discussed above, Matteson's Motion for Summary Judgment is denied as to its breach of contract claim, and granted as to Defendant's First Affirmative Defense, Second Affirmative Defense, and Counterclaim. Sevenson's Cross-Motion for Sanctions is denied. Matteson's Motion for Status Conference and Suggestions in Support is denied as moot.
IT HEREBY IS ORDERED, that Plaintiff's Motion for Summary Judgment (Docket No. 30) is GRANTED in part and DENIED in part, in accordance with the Decision above.
FURTHER, that Defendant's Cross-Motion for Sanctions (Docket No. 52) is DENIED.
FURTHER, that Plaintiff's Motion for Status Conference and Suggestions in Support (Docket No. 69) is DENIED as moot.
FURTHER, that this matter is referred back to Judge H. Kenneth Schroeder, Jr. for resolution of Defendant's Motion to Extend Discovery and Amend/Correct Answer to Complaint (Docket No. 21).
SO ORDERED.
In opposition to this motion, Defendant filed a Response to Plaintiff's Statement of Material Fact, with Exhibits; and a Memorandum of Law. (Docket Nos. 44-52.)
In opposition to this motion, Plaintiff filed a Memorandum of Law, with attached Exhibits. (Docket No. 64.)