FABE, Chief Justice.
The Aleut Corporation terminated the employment of its chief executive officer, Troy Johnson. Johnson challenged the termination, and the matter was submitted to binding arbitration as required by the employment contract, which contained a broad arbitration clause providing that "[a]ny and all disputes ... arising out of, relating in any way to or in connection with this Agreement and/or Executive's employment with or termination of employment from the Company... shall be solely settled by an arbitration." At arbitration, the parties disputed whether The Aleut Corporation had violated the employment contract by terminating Johnson and whether Johnson's alleged breach of contract justified the termination. After determining that The Aleut Corporation had breached the employment contract, the arbitrator awarded damages to Johnson.
The Aleut Corporation petitioned the superior court to vacate the arbitrator's decision, claiming that the arbitrator had addressed an issue that was never submitted to arbitration and was thus not arbitrable. The superior court vacated the arbitration award, concluding that the arbitrator had exceeded his authority, and Johnson appeals. Because the
The Aleut Corporation is one of the 13 regional Native corporations established in 1972 under the Alaska Native Claims Settlement Act.
Paragraph 5 of the employment agreement established that Johnson's "Initial Term" as CEO would last three years, ending on March 31, 2010. Paragraph 5 also provided for a two-year "automatic extension" of Johnson's term, at The Aleut Corporation's option. To trigger this option term, Paragraph 5 required Johnson to provide a reminder notice to The Aleut Corporation's Board of its ability to cancel the option term. This notice was to be sent to the Board Chair at least 120 days before March 31, 2010. Upon receiving this reminder notice, The Aleut Corporation was to have the option to cancel the automatic extension of the term by written notice to Johnson at least 90 days before March 31, 2010. Paragraph 5 of the employment agreement provided:
(Emphasis in original.) The employment agreement also contained a broadly drafted arbitration clause: "Any and all disputes between Executive and the Company, however significant, arising out of, relating in any way to or in connection with this Agreement and/or Executive's employment with or termination of employment from the Company... shall be solely settled by an arbitration...."
Johnson testified that when he negotiated the employment agreement, he sought a longer initial term because he "wanted that security of a five-year contract" for his family. He further explained that "having been through the work of changing a company ... three years is a pretty short period of time." Johnson and The Aleut Corporation agreed that the purpose of the reminder notice provision was to ensure that the Board would not overlook the option term and inadvertently allow Johnson's contract to extend.
In July 2009, as the end of Johnson's initial three-year term approached, Johnson and The Aleut Corporation began negotiations for a new contract. On July 22, 2009, Johnson drafted a letter to Sharon Lind, the chair of The Aleut Corporation Board of Directors, providing the required notice of The Aleut Corporation's option to cancel the automatic extension of the term. Johnson created a fax cover sheet for the letter and attempted to fax the letter to Lind's office. But a subsequent review of electronic records from the fax machine at Lind's office indicated that Lind's machine never received Johnson's fax. Johnson also claimed that he later gave Lind a hard copy of the letter with a packet of other documents.
Under Paragraph 5, notice from Johnson would have triggered The Aleut Corporation's responsibility to notify Johnson before December 31, 2009 if the company decided to cancel the automatic extension. The Aleut Corporation did not provide notice to Johnson of its decision to cancel the automatic extension of his term by that date.
Throughout the contract renewal negotiations, Board Chair Lind sent inquiries to Daniel, The Aleut Corporation's attorney, regarding the employment agreement. Early in the negotiations, Lind asked Daniel a question about the automatic extension provision in Johnson's contract. Daniel confirmed that according to the provision, Johnson's contract would "automatically renew" for an additional two years "unless the board affirmatively cancels the extension at least 90 days before the current contract expires." (Emphasis in original.) Later, in February 2010, Daniel replied to an additional question from Lind, remarking that the "notice provisions" in the employment agreement were "mostly meaningless — the result of last minute changes that were made when we negotiated the contract." Meanwhile, the contract negotiations between The Aleut Corporation and Johnson continued into March 2010 without success.
On March 21, 2010, The Aleut Corporation's Board informed Johnson that it would allow Johnson's contract to expire at the end of the month. The following day, Johnson and a member of the Board discussed how Johnson might save his job. Johnson later testified that the Board member's comments led him to believe that he might retain his job if he fired Eric Waterman, The Aleut Corporation's director of operations. After the meeting, Johnson terminated Waterman and signed a severance and release agreement with him.
On March 30, 2010, Johnson's lawyer sent a letter to The Aleut Corporation declaring that The Aleut Corporation had improperly terminated Johnson's contract because Johnson had faxed the reminder notice to Lind and the Board had not timely cancelled the option. The next day, Johnson completed his last day of employment at The Aleut Corporation. On April 9, 2010, Johnson's attorney sent a second letter to The Aleut Corporation, proposing a settlement and advising that Johnson would proceed to arbitration if the parties could not agree on a settlement.
The arbitration clause of the employment agreement required that "[a]ny and all disputes... arising out of, relating in any way to or in connection" with the employment agreement "shall be solely settled by an arbitration" conducted in accordance with the American Arbitration Association rules. Accordingly, Johnson submitted a statement of claims to the American Arbitration Association on October 15, 2010.
Johnson's statement of claims argued that The Aleut Corporation had breached the employment agreement when it terminated his contract. Johnson explained that he had provided timely notice to the Board reminding it of its option to cancel the automatic extension and that the Board had failed to provide timely notice that it was cancelling the automatic extension. Johnson's statement of claims concluded with a request that "the arbitrator find the Company failed to timely exercise its option to terminate the automatic two-year extension of Mr. Johnson's Contract beyond March 31, 2010," and
The Aleut Corporation responded that Johnson had not in fact provided the required reminder notice and thus the employment agreement had expired on March 31, 2010. The Aleut Corporation also claimed, as an "[a]ffirmative [d]efense," that Johnson had breached the employment agreement by terminating Waterman and obligating The Aleut Corporation to a severance agreement without the proper authority.
The parties submitted a joint statement of uncontested facts to the arbitrator. That statement provided that "Paragraph 5 [of the employment agreement] required Johnson to notify the Chair of [The Aleut Corporation's] Board, Sharon Lind, of [The Aleut Corporation's] option to cancel the `Option Term' 120 days prior to March 31, 2010, or December 1, 2009." Their statement described the negotiations of Johnson's contract renewal, Johnson's letter to Lind, Daniel's statements concerning the option term, Johnson's firing of Waterman, and The Aleut Corporation's termination of Johnson's contract.
On April 12 and 13, 2011, Arbitrator Thomas P. Owens, Jr. conducted the arbitration hearing. The parties disputed whether Johnson's decision to fire Waterman constituted a breach of contract. Johnson argued that The Aleut Corporation's termination of the employment agreement "had no valid basis" and was a "breach of the Contract." He presented evidence that he had provided the requisite reminder notice to trigger the automatic extension of the term. The Aleut Corporation contended that the "issue in the case is whether or not Mr. Johnson's contract automatically extended" and that "at the end of this arbitration hearing there will be no evidence in this case ... that Ms. Lind received that required notice.... And that's the entire case."
The arbitrator heard testimony from Johnson, Board Chair Lind, Daniel, The Aleut Corporation's chief financial officer, and a member of the Board. The testimony covered a variety of topics, including the parties' intent surrounding the initial negotiation of the option term of the employment agreement, Johnson's decision to fire Waterman, Johnson's performance as CEO, the recent contract-renewal negotiations, and the termination of Johnson's contract. In particular, Johnson testified that Daniel had proposed the reminder notice language "so that the board, whoever was in the board at that time, would be aware that ... you can cancel this automatic two-year extension." Johnson also testified about his performance as CEO, his firing of Waterman, the 2009 contract negotiations, and his attempts to send the notice letter to Lind. Lind reported that she had never received Johnson's notice letter. The arbitrator also heard testimony from Daniel describing both the initial negotiations of the option term in Johnson's employment agreement and the contract renewal negotiations.
In June 2011 Arbitrator Owens issued his decision and award. He summarized Johnson's claim: "Claimant claims that Respondent prematurely ended his employment, in violation of the Contract, and that he is entitled to compensatory damages as a result of the breach." The arbitrator determined that to resolve the parties' dispute, he was required to answer three questions:
The arbitrator further explained that "[r]esolution of the issues in this case requires that the arbitrator interpret the Contract," and that in light of Alaska contract law jurisprudence, the primary goal was to "enforce the reasonable expectations of the parties."
The arbitrator made detailed findings about the parties' expectations. He found "Troy Johnson's testimony concerning the negotiation of ¶ 5 of the Contract to be credible and un-contradicted." He further found "that the reasonable expectations of the parties regarding the term" of the employment agreement were:
The arbitrator also found that the reminder notice clause was not inserted into the contract "to create an unrelated, arbitrary pre-requisite that could operate to negate the automatic extension, regardless of the state of [The Aleut Corporation's] knowledge about its rights." Rather, "the primary intent and expectation of the parties with regard to the term of the Contract was that the initial three-year term of the Contract would be automatically extended for two years, unless [The Aleut Corporation] notified Johnson by December 31, 2009, that it was cancelling the extension."
The arbitrator found that The Aleut Corporation was independently "well aware" of the existence of the option term during the summer and fall of 2009, as evidenced by Daniel's correspondence with Lind. The arbitrator found that although Lind had never received the fax of Johnson's letter, this issue was of "secondary" importance in light of the conclusion that Johnson's reminder notice was "not a pre-requisite, the non-occurrence of which would excuse [The Aleut Corporation] from the obligation to affirmatively notify Johnson of a cancellation in all circumstances, regardless of the state of its knowledge about its right to cancel." Accordingly, Johnson's failure to provide the reminder notice "did not extinguish [The Aleut Corporation's] obligation to timely notify Johnson of a decision to cancel the automatic extension." Therefore, the arbitrator determined that by terminating Johnson without providing timely notice, The Aleut Corporation had "breached the Contract." The arbitrator concluded that "[t]o find otherwise would exalt form over substance and betray the expectations of the parties to the Contract."
Finally, the arbitrator relied on the employment agreement's definition of "cause" for termination, finding that "the conduct of Johnson with regard to Waterman['s termination and severance package] did not constitute willful, reckless or grossly negligent misconduct that would justify termination of his employment for cause." Because the arbitrator decided that The Aleut Corporation had breached the contract while Johnson had not breached it, the arbitrator awarded damages to Johnson for lost salary and benefits.
Arguing that the arbitrator exceeded his authority, The Aleut Corporation petitioned the superior court to vacate the arbitration award. The superior court vacated the arbitrator's award, concluding that the arbitrator had exceeded his authority by deciding an issue that was not submitted to arbitration and that the award was therefore "procedurally unfair." The superior court reasoned that it was "not reasonably possible that the scope of the arbitration required the arbitrator to interpret the CEO Contract and determine if the Reminder Notice was a condition precedent to the automatic renewal." It further noted that "[t]his finding is emphatically supported by the fact that the arbitrator ruled on an issue in a manner contrary to concessions that both parties had made; namely, the CEO Contract would not renew unless Johnson provided the Reminder Notice." As a result, the superior court awarded partial attorney's fees and costs to The Aleut Corporation.
Johnson moved for reconsideration, but the superior court denied the motion. Johnson now appeals, arguing that the superior court erred when it vacated the arbitration award.
A superior court's decision reviewing an arbitration award is subject to de novo review.
"There are no statutory grounds for review of an arbitrator's determination as to the meaning of contract provisions which do not pertain to the issue of arbitrability."
Alaska's Revised Uniform Arbitration Act provides that "the court shall vacate an award made in the arbitration proceeding if... an arbitrator exceeded the arbitrator's powers."
We do not review an arbitrator's interpretation of a contract provision for ordinary error.
The scope of a demand for arbitration should not be subjected to the same strict standards of construction that would be applied in formal court proceedings.
Not only do we defer to the arbitrator's interpretation of the question presented, we "apply a presumption in favor of arbitrability," resolving all doubts in favor of arbitrability.
Here, the arbitrator found that the parties had presented a dispute consisting of three questions:
First, Johnson and The Aleut Corporation agreed in their employment contract to refer to an arbitrator "[a]ny and all disputes" regarding Johnson's employment contract and termination. The language and scope of the negotiated binding arbitration clause of the employment agreement was quite broad: "Any and all disputes ... arising out of, relating in any way to or in connection with this Agreement and/or Executive's employment with or termination of employment from the Company ... shall be solely settled by an arbitration...." Thus, as the arbitrator concluded, this dispute, which focused on whether the termination of Johnson constituted a breach of contract, fell squarely within the scope of the contract's arbitration clause.
Moreover, in submitting the dispute to arbitration, Johnson's claim was broadly framed: He contended that The Aleut Corporation had breached the employment agreement by failing to provide timely notice of its decision to terminate him. In his statement of claims, Johnson requested that "the arbitrator find the Company failed to timely exercise its option to terminate the automatic two-year extension of Mr. Johnson's Contract beyond March 31, 2010, [and] that the Company termination of Mr. Johnson's employment as CEO effective March 31, 2010, constituted a breach by the Company of the Contract." Johnson's claim was based on the "company's breach of the Contract." The arbitrator evidently understood Johnson's claim in this manner, as the arbitrator summarized the issue before him in similarly broad terms: whether "the termination of Claimant's employment by Respondent breach[ed] the Contract." And in order to determine whether a contract has been breached, it is predictably necessary to interpret the language and meaning of the contract that is alleged to have been breached. As the superior court recognized, "the parties do not appear to have explicitly limited the issues submitted to the arbitrator." Although Johnson acknowledged that he "was required to notify the Chair of the Board in writing 120 days before the initial term expired of the Company's option to cancel the automatic extension," the arbitrator ultimately had the authority to rely on his "interpretation of ... [the contract] provisions and his findings regarding ... contractual obligations" to determine whether the contract had been breached.
Finally, as Johnson correctly observes, the arbitration briefs and hearing "encompassed much more than the discussion [of] the notice provision." In light of the evidence presented, the arbitrator reasonably interpreted the dispute as whether The Aleut Corporation breached the employment agreement by terminating Johnson. Over the course of the two-day hearing, the arbitrator heard evidence not only on the narrow factual issue of Lind's receipt of Johnson's notice letter, but also on the initial negotiation of the employment agreement, the parties' intent surrounding the provision for automatic extension of the term, the recent negotiations, and Johnson's performance as CEO. And The Aleut Corporation explained that the motivation behind Paragraph 5 was a concern that the provision for terminating Johnson "could
"[A]n arbitrator's misconstruction of a contract is not open to judicial review, except on questions of arbitrability."
We answered that question in Ahtna, Inc. v. Ebasco Constructors, Inc., where we concluded that arbitrators do have the authority to resolve an arbitrable dispute on a basis that "differs from that which ... was initially argued by the claimant."
Relying on provisions of the agreement that had not been cited or relied on by the parties, the arbitrator concluded that Ebasco had breached a different provision of the joint venture agreement by failing to reimburse Ahtna directly for its expenses under the reimbursement clause of the joint venture agreement.
In Ahtna, we upheld the arbitrator's award, concluding that the arbitrator had "merely given a basis for the award which differs from that which, according to Ebasco, was initially argued by the claimant."
Similarly, the arbitrator's decision here relied on the arbitrator's interpretation of Paragraph 5 of the employment agreement and his findings regarding the parties' intent. Even though his rationale for determining that the employment agreement was breached differed from that asserted by Johnson, the arbitrator had the broad authority to interpret the provisions of the employment agreement in deciding whether it had been breached.
Because we reverse the superior court's decision to vacate the arbitration award, the award of attorney's fees and costs must be vacated.
The arbitrator resolved an arbitrable dispute, and we therefore REVERSE the superior court's order vacating the arbitration award. The case is REMANDED with direction to the superior court to confirm the arbitration award. The superior court's award of attorney's fees and costs is VACATED.
STOWERS, Justice, dissenting.
In Sea Star Stevedore Co. v. International Union of Operating Engineers, Local 302, we held that arbitrators "are given broad powers to fashion remedies on submitted issues. However, an arbitrator does not have the power to reach the merits of a grievance not submitted to him."
In the first paragraph of Johnson's statement of claims initiating arbitration, he stated the following: "Johnson was required to notify the Chair of the Board ... of the Company's option to cancel the automatic extension; if he failed to give this notice, then the automatic extension of the Contract would terminate at March 31, 2010, without the Company needing to exercise its option to cancel the automatic extension." Here it is clear that among the myriad issues Johnson might be submitting to the arbitrator, he was explicitly not submitting the issue of whether he was required to provide notice. Rather, at the outset, he conceded that such notice was required. Johnson reiterated this concession in the joint statement of uncontested facts that the parties submitted to the arbitrator prior to the arbitration hearing. There, both parties agreed that Johnson's employment agreement "required Johnson to notify the Chair of [The Aleut Corporation's] Board, Sharon Lind, of [The Aleut Corporation's] option to cancel the `Option Term.'" Again, it is clear that both parties agreed Johnson was required to provide notice. If both parties agree on a particular fact, there is no dispute between them as to that fact — and thus no issue for the arbitrator to decide.
Further, at the arbitration hearing Johnson said and did nothing to call into question his concession that he was required to provide notice. On the contrary, he repeatedly affirmed that he was required to provide notice. For example, in Johnson's cross-examination of Thomas Daniel, Johnson's attorney stated that The Aleut Corporation's "obligation to provide the notice to Mr. Johnson... was only triggered if Mr. Johnson provided a notice." Similarly, in Johnson's closing argument he stated that "[t]he only way [The Aleut Corporation] was ever obligated to provide notice that it intended to cancel Mr. Johnson's two-year automatic extension was if Mr. Johnson first provided his notice of [The Aleut Corporation's] obligation."
In short, Johnson consistently affirmed throughout the arbitration process that his employment agreement required him to provide notice in order to trigger the contract extension. The superior court was therefore correct when it concluded that "it is not reasonably possible that the scope of the arbitration required the arbitrator to interpret
In support of its decision today that the arbitrator did not exceed his powers, the court points to three sources of evidence: (1) the arbitration clause of the employment agreement; (2) Johnson's statement of claims; and (3) the evidence provided at the arbitration hearing. Each of these sources of evidence, however, fails to show that Johnson submitted the issue of whether he was required to provide notice.
First, it is true that Johnson's contract included a broad arbitration clause. It is also true that if Johnson had chosen to submit to arbitration the issue of whether he was required to provide notice, such issue would have been within the scope of the arbitration clause and within the arbitrator's authority to decide. But, regardless of the scope of the arbitration clause, the arbitrator is empowered to decide only those issues that are submitted to him.
Second, the court observes that Johnson's statement of claims was "broadly framed" and generally based on the "company's breach of the Contract." However, the next-to-last paragraph of Johnson's statement of claims summarized his claim in the following terms: "For the foregoing reasons, Mr. Johnson requests the arbitrator find [The Aleut Corporation] failed to timely exercise its option to terminate ... [and] that [the] termination ... constituted a breach by the [Corporation] of the Contract." Nowhere in the foregoing paragraphs of Johnson's statement of claims did he argue that he was not required to provide notice; rather, he clearly and explicitly stated that he was required to provide notice (and argued that he had, in fact, provided such notice).
Finally, the court cites the range of evidence presented at the arbitration hearing in support of the conclusion that the issue submitted to the arbitrator was broader than simply the question of whether Lind received Johnson's notice. But the evidence Johnson introduced during the hearing was introduced for the purpose of supporting his argument that he had, in fact, provided notice. As the superior court found, "Johnson never used the evidence he introduced to put the Reminder Notice provision's intent at issue."
In support of its decision today, the court also relies on our decision in Ahtna, Inc. v. Ebasco Constructors, Inc., in which we held that an arbitrator may resolve a contract dispute on grounds that are not submitted by the parties.
In sum, despite Alaska's strong public policy in favor of upholding arbitration decisions, I agree with the superior court that this case "presents the rare scenario where the arbitrator goes beyond the reasonably foreseeable scope of his authority such that the Court must vacate his award." This court has created a line of precedent that gives great — virtually unreviewable — deference to arbitrators' decisions, even where those decisions are factually and legally erroneous. Today's decision extends that deference to also permit an arbitrator to determine what the issue is to be decided, even where both parties agreed they intended the arbitration to resolve a different issue. I fear this court has abrogated its responsibility to review virtually any error in arbitration, and I cannot agree with this decision because I believe the court has a duty to ensure that — at the least — an arbitrator does not exceed the limits of his authority. I therefore respectfully dissent.