CHARLES S. COODY, Magistrate Judge.
Plaintiff Peach State Roofing, Inc. ("Peach State" or "PSR") filed this action on July 22, 2015, against defendants Kirlin Builders, LLC ("Kirlin")
The court has jurisdiction over these claims pursuant to its diversity jurisdiction and will apply Maryland law due to choice of law provisions in the contract documents. See 28 U.S.C. § 1332(a)(1). Pursuant to 28 U.S.C. § 636(c)(1) and M.D. Ala. LR 73.1, the parties consented to the United States Magistrate Judge conducting all proceedings in this case and ordering the entry of final judgment. A bench trial was held in December 2016, and the court now makes the following findings of fact and conclusions of law.
This is a tale of two contracts. The United States Army Corps of Engineers ("the Government") awarded Kirlin the Prime Contract to act as Prime Contractor on a roofing project at Lyster Army Health Clinic, Fort Rucker, Alabama. In conjunction with the Prime Contract
Furthermore, much of the difficulty in this case began with a lack of precision in the terms used in the contracts. The contracts are a labyrinth of attachments and references which would confound even lovers of the impossible constructions art of M.C Escher.
On January 27, 2014, the Government requested Kirlin and six other companies to offer proposals to replace and repair the roof at Lyster Army Health Clinic in Fort Rucker, Alabama. (Tr. Ex. 1).
On February 28, 2014, the Government amended its Scope of Work.
(Tr. Ex. 2 at 1).
Thus, the Scope of Work as amended required a minimum R-20 valued thermal insulation under a PVC membrane roof but did not explicitly require that the insulation be installed in two layers. The Scope of Work as amended also does not reference roofing construction standard Section 07 22 00.
Proposals for the contract were due to the Government by March 17, 2014. (Tr. Ex. 3). An extension was granted to allow proposals to be submitted by March 20, 2014. (Id. at 7).
On April 24, 2014, the Government offered the Prime Contract for the project to Kirlin at a price of $3,436,024.85. (Tr. Ex. 6). Kirlin accepted the Government's offer to contract as the prime contractor on the roofing project on May 6, 2014. The Prime Contract between the Government and Kirlin required Kirlin to replace the roof at Fort Rucker Lyster Army Health Clinic "in accordance with the attached scope of work dated 24 January 2014."
The Scope of Work as amended delineates the Task Order as "Roof Replacement" and describes the project as follows.
(Id. at 3).
In addition, under the Prime Contract, Kirlin was obligated to develop a site survey and report, and was responsible for preparing "design documents."
(Id. at 4) (emphasis added)
The Scope of Work as amended specifies the insulation required by the contract.
(Id. at 6).
The Prime Contract obligated Kirlin to provide to the Government the following work plan documents
The Scope of Work as amended was not the only document to which Kirlin was obligated to adhere. It was incumbent on Kirlin to understand its responsibilities under the Prime Contract and to ensure that its subcontractor, Peach State, provided a roofing system that met Kirlin's obligations under Prime Contract. Attachments 1 & 2, entitled PVC Roofing Spec, include sections related to Roof Insulation. (Id. at 10).
(Att. 2 at 10, Section 2.1.9; Att. 1 at 10, Section 2.1.9)
Attachment 2 requires the roof membrane manufacturer to accept the "insulation and other products and accessories to be provided by and warranted under the full system guarantee of the roof membrane manufacturer." (Id. at 10).
Pursuant to its Prime Contract with the Government, Kirlin was responsible for examining and verifying that the roof was installed in compliance with the Scope of Work as amended. See Id. at 12-14, Section 3.2, Section 3.3.2, Section 3.3.3.
(Id. at 12-13, Section 3.2) (emphasis added)
Section 07 22 00 is a government construction standard that sets forth the requirements for insulation on roofs and decking on government buildings.
(Tr. Ex. 11 at 72).
Finally, Kirlin also agreed to ensure that the PVC membrane was installed free from wrinkles and fishmouths.
In conjunction with its submission of a proposal to the Government, Kirlin solicited bids from roofing companies to perform the work that would be required for the roofing project at Fort Rucker if Kirlin received the Prime Contract. Prior to submitting its formal proposal, Peach State engaged in an email exchange with Kirlin discussing the specifications of the roofing project. (Tr. Ex. 5). On March 18, 2014, Kirlin asked Peach State to confirm that it understood "that [Kirlin] [is] obligated to the Government's Scope of Work and it's (sic) attachments." (Id.) Kirlin advised Peach State that specifications with the Scope of Work were "rarely included" so Peach State needed to "read those documents." (Id.) After a further series of emails, on March 27, 2014, Peach State submitted a proposal to Kirlin to act as the roofing subcontractor to replace and repair the roof at Fort Rucker. (Tr. Ex. 5 at 7). Peach State's proposal included the following
(Id.) (emphasis added).
Peach State proposed completing the work for $2,107,315.00 and included a performance bond costing $32,000.00. (Id.) Although the Subcontract is dated May 19, 2014, Kirlin awarded Peach State the Subcontract for the roofing replacement project on May 6, 2014.
(Id.)
The Subcontract between Peach State and Kirlin states that Peach State would "furnish and install new R-20 minimum polyiso insulation" (id. at 10) which conformed to the Government's Scope of Work as amended. The Scope of Work as amended references R-20 insulation but does not specify one or two layers of insulation.
In addition, Attachment A to the Subcontract defines "PSR Scope of Work."
(Id. at 10) (emphasis added)
Division 07 specifications refer to Government building construction standards that relate to Thermal and Moisture Protection and include much more than just roof and deck insulation. (Tr. Ex. 11 at 31; Def's Tr. Ex. 3 at 1-2). Included in Division 07 is Section 07 22 00 but it differs from Section 07 22 00 contained in Kirlin's Work Plans. For example, in Division 07, Section 07 22 00, "[r]oof insulation should be specified by thermal resistance (R value) necessary to obtain required overall thermal transmittance (U value) need to satisfy design criteria for particular type of facility." (Def's Tr. Ex. 3 at 12, Section 2.1.1). In addition, Division 07 discusses polyisocyanurate insulation which was to be installed on the roof. See Def's Tr. Ex. 11 at 15.
(Def's Tr. Ex. 3 at 26, Section 3.4.4.1) (footnote added)
This section does not specify two layers of insulation. Attachment A to Peach
State's Subcontract with Kirlin required Peach State to "[p]erform all Roofing work associated with the work plan documents, including, but not limited to,
Thus, to the extent that the Subcontract references insulation, it provides that Peach State will "[f]urnish and install new R-20 polyiso insulation" in accordance with Division 07 specifications that meets the 120 mph wind zone requirements for the building. (Id.)
Kirlin places great reliance on the Subcontract's "Flow Down" provision which obligated Peach State to Kirlin "in the same way [Kirlin] is [obligated] to the [Government.]"
Finally, the Subcontract contains the following provision.
(Id. at 11) (emphasis added).
And, Attachment A to the Subcontract further advised Peach State that "[n]o Additional Design Documents will be furnished," and "[t]here will be no change orders unless new areas and/or work are added by the customer." (Id. at 11). Attachment B lists the Contract Drawings and Specifications applicable to the project. The Contract Drawing that is listed is Task Order No. 0021 which is dated April 24, 2014 but that document is not included or attached.
(Id. at 29) (emphasis in the original)
The dispute clause upon which Kirlin relies in this case, FAR52.233-1, is not listed as one of the federal contract clauses that is incorporated in the Subcontract. (Id. at 28-29).
To fulfill its obligation to the Government under the Prime Contract, Kirlin was required to create a 35% Work Plan, a 65% Work Plan and a 100% Work Plan. The 35% Work Plan was dated July 2014 (Def's Ex. 11); the 65% Work Plan was dated 6 October 2014 (Def's Ex. 13); the 100% Work Plan — unrevised
The 35% Work Plan initially describes the roof replacement project as "a fully-adhered, single-ply 72-mil minimum PVC-membrane system with a 20-year No-Dollar Limit (NDL) warranty and
(Id. at 8; Def's Ex. 13 at 6).
In the 35% Work Plan, Kirlin stated that "[n]ew rigid insulation will be installed and inspected to conform to the
(Id. at 15) (emphasis added).
Through its Architect or Engineer, Kirlin had the responsibility and obligation to review submittals to ensure that the submittals complied with the Prime Contract.
(Id. at 38) (emphasis added).
The 35% Work Plan gives the Government Contracting Officer the authority to require Kirlin as the Prime Contractor to "resubmit any item found not to comply with the contract." (Id. at 43).
(Id).
The 35% Work Plan also includes the Section 07 22 00 Roof and Deck Insulation "to the extent referenced." (Id. at 69). The referenced specification relates to "thermal insulation above the roof deck with an R value of 20 and
(Id. at 72).
In only a single sentence on insulation application does Section 07 22 00 mention two layers of insulation. "
Two provisions of the 35% Work Plan relate to Kirlin's obligations to inspect and approve all work on the roof. Kirlin was required to "establish and maintain an inspection procedure to assure compliance of the installed roof insulation with the contract requirements. Any work found not to be in compliance with the contract shall be promptly removed and replaced or corrected in an approved manner." (Id. at 74). The 35% Work Plan also contemplated that during the roof replacement, Kirlin would verify that the PVC membrane and insulation were properly adhered, secured and free of "ridges, wrinkles, kinks, and fishmouths." (Id. at 93).
Finally, the 35% Work Plan specified that the roofing materials would be provided by Carlisle Manufacturing. The 35% Work Plan included Carlisle's Roof Product Data on its Roof Membrane and System. (Id. at 141). The 35% Work Plan referenced Carlisle Sure-Flex PVC 80-mil Membrane with Carlisle Insulation included. (Id. at 142-44). Carlisle's materials indicated that "[a]ll equipment will be installed in accordance with manufacturer's instructions and recommendations." (Id. at 152).
The 65% Work Plan included the Carlisle Product Information and again stated that the roof would be "installed in accordance with the manufacturer's installation instructions." (Def's Ex. 13 at 186). In response to the 65% Work Plan, the Government requested that Peach State provide "installer's certification from roof membrane manufacturer." (Id. at 193-95). Carlisle submitted the requested certification to Kirlin which stated that Peach State Roofing was "a Carlisle Authorized Applicator." (Id. at 197).
On March 4, 2015, Kirlin's 100% Work Plan was approved by the Government. All the Work Plans included Carlisle's Product Data and clearly contemplated that Peach State would install a Carlisle Sure-Flex PVC 80-mil Membrane Roofing system including insulation.
On July 11, 2014, Kirlin sent an email to Peach State and Hughes, the plumbing subcontractor, notifying them that "[t]he 35% Work Plan for the 778021 Fort Rucker Roof Replacement work project [was] online for review . . ." (Tr. Ex. 9). However, nobody at Peach State reviewed the 35% Work Plan because Peach State understood that the 35% Work Plan was a document between Kirlin and the Government. (Tr. Trans. at I-25-26, I-82).
For reasons that were not at all explained at trial, in November 2014, Kirlin and Peach State began an email discussion about the use of Carlisle products.
(Id. at 3).
Kirlin also confirmed the use of Carlisle products. "Proceed with Carlisle. Carlisle product data was approved within the 35% Work Plan that PSR was given an opportunity to review." (Id.)
Kelly then sought confirmation that Peach State was permitted to order "the Carlisle 3.5" polyisocyanurate R=20 and the Carlisle 72 mil or greater PVC." (Id.) Kirlin replied that it was Peach State's decision as to when it ordered the material but went on to say
(Id.)
Peach State also asked for the credentials to log in and view the 35% Work Plan which Kirlin provided. (Id. at 2). On November 14, 2014, Kirlin forwarded to Peach State the 65% Work Plan. (Id. at 1). Peach State's project manager James Grant did not review the 65% Work Plan because he was relying on Kirlin's representation that the Carlisle product had been approved in the 35% Work Plan. (Tr. Trans. at I-28-29). In other words, the email exchanges set out above related only to the use of Carlisle products and no other aspects of the Work Plans.
At some point,
(Tr. Ex. 11) (emphasis added)
In addition, the documentation contained a page describing Carlisle's HP-H Polyiso Insulation. (Id. at 13). To achieve the R-20 thermal value, the requisite thickness of the insulation is 3.50" and is circled in red. (Id.) Carlisle's product data plainly demonstrates that Peach State was proposing a single 3.5" layer insulation. (Id).
Peach State amended its submittal, and on February 18, 2015, BMH Engineering on behalf of Kirlin, stamped its approval on Peach State's submittal. (Tr. Ex. 12 at 3).
Submittal No. 778021 has been reviewed by BMH Engineering, LLC.
(Tr. Ex. 12 at 3) (emphasis added).
Specifically, the noted exceptions were the use of 80-mil PVC membrane
(Id. at 4) (emphasis added).
Carlisle's letter also reiterates that Peach State would install "a 3.5" thick Carlisle HP-H Polyisocyanurate Insulation mechanically fastened" and "adhered to the deck." (Id.) On February 18, 2015, Kirlin emailed to the Government Peach State's approved submission with exceptions noted. (Id. at 1). Consequently, based on the approval from BMH Engineering on behalf of Kirlin, Peach State was prepared to
(Tr. Trans. at I-37).
Peach State's proposal to Kirlin to secure the Subcontract and its' submittals for approval to Kirlin and BMH Engineering all contemplated a single layer of 3.5 inch insulation suitable to meet the 120 mph wind zone requirement. Kirlin approved Peach State's second submittal noting that it "conforms with exceptions noted." (Tr. Ex. 12). Unquestionably, Peach State's proposal, Subcontract and submittal are inconsistent with the Government's requirements and Kirlin's work plans. For example, Kirlin's work plans called for R-20 value insulation with "
Also, on February 18, 2015, Kirlin forwarded to Peach State by email roof drawings and government construction standards. Kirlin's email to Peach State in its entirety read: "Please see attached." (Tr. Ex. 14). Jim Grant, Peach State's project manager, testified that he received these documents from Kirlin because he had previously not received any "official roof drawings." (Tr. Trans. at I-41). However, when Grant looked at the documents to find the roofing drawings none were included in the attachment to the email. (Id. at I-42).
At trial, Kirlin suggested that this document was the 100% Work Plan. (Tr. Trans. at II-13-14). But as evidenced below by the court's colloquy with Attorney Patin, following his examination of a witness, the attachments to the email would not have notified any reasonable person that the attachments contained the 100% Work Plan.
(Tr. Trans. at II-13-16).
More importantly, Kirlin subsequently admitted into evidence the 100% Work Plan which plainly establishes that the attachment to the email was not that document. See Def's Tr. Ex. 18.
On March 24, 2015, Peach State began installing the roof in accordance with its' submittal approved by Kirlin and pursuant to the Subcontract. As described by Peach State, the work began around 5:00 p.m. once Kirlin's representative gave Peach State permission to start. (Tr. Trans. at I-84). Johnson or Jeff Rhodes ("Rhodes"), both Kirlin employees, approved Peach State's work each day before Peach State was permitted to leave the job site. (Id.) In addition, Kirlin completed daily quality control reports detailing Peach State's work, adding a notation if there was any issue with the work or Peach State's employees. (Tr. Ex. 18). These daily reports were shared with Peach State.
On day one, Kirlin noted a problem with how Peach State was installing fastening patterns. (Tr. Trans. at I-86; Tr. Ex. 18 at 5). Peach State promptly corrected the issue. (Id.) Kirlin also informed Peach State that the screw placement was not in conformance with Peach State's submittal. Kirlin gave Peach State's on-site roofing foreman the submittal package and told him "to correct the screw fastening pattern, and here's how you do that." (Tr. Trans. at I-88). On this day, the daily quality control report noted the exchange between Kirlin and Peach State.
(Tr. Ex. 18 at 1, 3, 5).
Peach State immediately corrected these errors as well. (Id.) After the errors were corrected, Johnson certified on the daily quality control report that "all materials and equipment used and work performed during this reporting period are in conformance with the contract plans and specifications, to the best of my knowledge, except as noted above." (Id. at 5).
Each day Johnson or Rhodes granted Peach State permission to start work. (Tr. Trans. at I-88). Peach State was dependent on Kirlin for authorization to access the roof. (Tr. Trans. at I-89). Each day Kirlin inspected Peach State's work on the roof and documented any issues. For example, on April 2, 2015, Peach State installed insulation and membrane on the roof. (Tr. Ex. 18 at 44). While overseeing Peach State's work, Kirlin noted that "the weather changed and a dense fog blew in. When that happened it impeded our progress of installing the roof membrane." (Id. at 46-47). The moisture caused by the weather required Peach State to replace the membrane the next day, which it did.
From the beginning of the roofing installation, the Government had issues with Peach State's workmanship. For example, on April 2, 2015, Kirlin emailed photographs of the roof installation to the Government illustrating that "Corrected Screw Pattern and Cricket," "Applying Adhesive to insulation and membrane," "Seaming Joints" and "Installed Membrane."
(Tr. Ex. 21). However, Kirlin did not inform Peach State about the government's concerns as set out in the email. Instead, through its daily inspections and quality control reports, Kirlin led Peach State to believe that any issues with its work were resolved.
Although Peach State did not receive a copy of the Government's email to Kirlin, on April 14, 2015, Peach State participated in a production meeting. (Tr. Trans. at I-98-99; Tr. Ex. 22). Peach State agreed to get an inspection report from Carlisle and forward it to Kirlin as well as provide information from Carlisle regarding the wrinkles and ¼ inch offsets. (Id. at I-99; Tr. Ex. 22 at 2). Kirlin affirmatively stated that it was conducting quality control inspections on a daily basis to "insure that construction operations are being conducted in accordance with the Work Plan requirements." (Tr. Ex. 22 at 3). Again, Kirlin's actions led Peach State to believe that the Government's issues with the roof were resolved by Peach State either by its work or by providing documentation from Carlisle.
On April 17, 2015, Peach State submitted to Kirlin the inspection report from Carlisle that was referenced at the April 14 production meeting. (Tr. Ex. 23). Carlisle's Technical Assistance Report addressed insulation fastening, installation of flashing material, use of T-Joint patches and use of expansion joints. (Tr. Ex. 23).
(Id. at 2.)
Carlisle also attached letters about the use of epoxy on insulation plates, and the use of PVC flashing on T-joint intersections. (Id. at 4-5).
After Peach State provided this information to Kirlin, Peach State treated the issues as closed because Kirlin did not request additional information or clarification from Peach State. (Tr. Trans. at I-101). Minutes from an April 30, 2015 production meeting with Kirlin and Peach State also noted that the issues were closed. (Tr. Ex. 28).
On April 27, 2015, Kirlin's project manager emailed to others at Kirlin photographs of the roof. (Tr. Ex. 24). There is no indication on the photographs or in the emails of any deficiencies with the roof. Kirlin then forwarded the photographs to the Government.
On April 30, 2015, the Government emailed Kirlin about concerns with the installation of the roofing membrane, specifically wrinkles and voids and inconsistencies with the ISO boards. (Tr. Ex. 30) (emphasis added).
(Id.) (emphasis added).
Kirlin did not share this email with Peach State even though on the same day, Kirlin emailed Peach State the weekly subcontractors' meeting minutes which indicated as old business an issue with Peach State's inspection and report. And once again, Kirlin failed to apprise Peach State of the Government's concerns with Peach State's work on the roof. For reasons that were not explained at trial, the meeting minutes also stated that "[a]ll known
On May 4, 2015, the Government sent Kirlin another email about the roofing membrane.
(Id.)(emphasis added)
Again, Kirlin did not send this email to Peach State. The only issue noted on Kirlin's May 4 Daily Quality Control Report was an incident with Peach State's drivers. "They were using an unapproved loading and unloading point." (Id. at 159). Kirlin took the corrective action of citing the drivers for safety violations, and then required all Peach State drivers to participate in a safety briefing. (Id.) On May 5, 2015, there was another safety issue that involved a Peach State employee "climbing down an extension ladder with a fire extinguisher." (Tr. Ex. 18 at 159, 165). Kirlin took the corrective action of instructing the employee to "not climb up and down a ladder with anything in his hand. Must maintain 3 points of contact with ladder." (Id.) On May 9, 2015, Kirlin found deficiencies "in the insulation installation on the concrete deck about the penthouse. PSR was directed to temporarily cover the area and replace insulation tomorrow." (Id. at 187). On May 10, 2015, the Daily Quality Control Report indicates that Peach State "[r]emoved and replaced 7,000 sq. ft. of Membrane and ISO Insulation on Phase 5." (Id. at 193). Thus, when there were quality control or safety issues, Kirlin documented the issues on the Daily Quality Control Report and included in the report the corrective action issued to Peach State to remedy the issue. When no issues were discovered during inspection, Kirlin recorded that information as "no QC deficiency (sic) were noted." (Id. at 193). Finally, Kirlin verified on each Daily Quality Control Report that the "report is complete and correct, and all materials and equipment used and work performed during this reporting period are in conformance with the contract plans and specifications, to the best of my knowledge, except as noted above." (Id. at 5, 12, 19, 26, 33, 40, 47, 54, 61, 68, 75, 82, 89, 96, 103, 110, 117, 123, 129, 135, 141, 147, 153, 159, 165, 171, 177, 183, 189, 195, 201, 207 and 212).
Thus, Kirlin was approving Peach State's work on a daily basis, and issuing corrective action instructions to Peach State and its employees when Kirlin discovered a quality control or safety issue. The quality control reports demonstrate that Peach State was responsive to and corrected any the deficiencies requested by Kirlin. The quality control reports also demonstrate that between April 2 and May 13, 2015, with Kirlin's approval, Peach State installed approximately 88,200 square feet of insulation and membrane.
On May 13, 2015, a cast iron pipe fell through the ceiling of the building, and Kirlin implemented a safety shutdown on the roof.
Finally, on May 9, 2015, prior to the safety shutdown, Kirlin emailed Peach State a list of quality control deficiencies with the installation of the roof, and requested Peach State to notify Kirlin "when corrections have been made" even though many of the problems had already been corrected. (Tr. Ex. 31). The Quality Control Deficiency Log as it related to Peach State's work
The final two issues required Peach State to "[p]rovide
On May 19, 2015, Kirlin forwarded to the Government Carlisle's Inspection report dated April 29, 2015. (Tr. Ex. 27). In that report, Carlisle addressed blistering and patches on the roof.
(Tr. Ex. 27 at 3-4)
On May 13, 2015, the date the roofing project shut down and prior to receiving Carlisle's April 29, 2015 Technical Assistance Report, Koczenasz, as Kirlin's senior project manager, met with the Government to discuss the safety shutdown. (Tr. Trans. Vo. II-111). At that time, the Government contracting officer voiced his concerns that "he didn't believe he was getting adequate responses" to his questions about the roof. (Id.) Consequently, Kirlin offered to bring in a roofing expert to "provide a report that hopefully would alleviate the government's concerns that everything was okay." (Id.) At trial Koczenasz's testified that Kirlin hired Mays "to see if we could get the roof going again." (Tr. Trans. at II-112). At this time, the work on the roof was stopped due to the safety shutdown, not due to any issue with Peach State's work. Kirlin subsequently hired Gary Mays of Mays Consulting & Evaluation Services to inspect the roof.
Without inspecting the roof and relying only on Kirlin's 100% Work Plan and Peach State's February 2015 submittal, Mays submitted a "Cursory Review and Comments to Construction Documents."
Notwithstanding that Kirlin had drafted the Subcontract and BMH's had approved Peach State's submittal, Mays' review of the documents appears to be the first time that Kirlin realized that Peach State's original proposal, the Subcontract and the submittal approved by BMH were inconsistent with Kirlin's Work Plans and the Prime Contract.
On June 1, 2015, Kirlin emailed to Peach State a copy of Mays' report.
(Id. at 5).
Kirlin then asked Peach State about whether Carlisle was responding to the requests for information related to the FM I-90 and FM I-120 wind lifts and the "insulation thickness of one board vs. two boards per Carlisle's system details, etc." (Id. at 4). Peach State responded as follows:
(Id. at 3-4).
Kirlin asked that Carlisle "state in the letters how we're meeting FM I-120 and that we are. Have them address the insulation and the rest of the items in the Mays letter." (Id. at 3). At this point, Peach State asked Kirlin about Mays' purpose in looking at the roof. "I thought the sole purpose of Mays being brought in was to address the "fully adhered." (Id. at 3). In this email exchange, Kirlin and Peach State acknowledge that there is a conflict in the wind uplift and wind zone specifications. (Id. at 2-3).
Apparently unbeknownst to Peach State, Koczenasz was forwarding Peach State's emails to Mays. (Def's Tr. Ex. 38 at 1). This is Mays' response on June 2, 2015. Based on review of the attached Carlisle Roof Wind Uplift Calculations data sheet,
(Def's Tr. Ex. 38) (emphasis added).
On June 5, 2015, Carlisle provided Peach State a letter stating that the roof as installed exceeds the requirements of ASCE 7-10 "Minimum Design Loads for Buildings and Other Structures." (Def's Tr. Ex. 34 at 2-3). Nonetheless, on June 8, 2015, after talking with Mays, Kirlin determined that the roof as installed did not meet its contract documents with respect to the wind uplift requirement and the insulation. (Id. at 1). According to Koczenasz, "[he] talked at length with our team and Mr. Mays this morning on what options we have to try to keep the roof and as previously stated, there is not a way to do that and meet our obligations." (Id.). At trial, Kirlin's counsel asserted that "the government insisted that [the insulation] should be in two layers." (Tr. Trans. at I-73). However, Kirlin introduced no evidence which supports that assertion, and, of course, counsel's statements are not evidence. The court finds that Kirlin unilaterally made the decision that the roof needed to be removed and reinstalled.
Representatives from Peach State, Kirlin, Mays and Carlisle met at the job site to discuss Mays' report. (Tr. Trans. at I-210). Once on the roof, Mays "stated that the roof did not comply with the requirements of the work plan. Peach State rebutted that the work plan wasn't part of [the] contract." (Id.) Peach State disagreed with Mays and took the position that it was bound by the Subcontract, not by the Work Plans. In his June 18, 2015 Project Site Visit Report, Mays memorialized his conclusion about the roof.
(Tr. Ex. 43 at 5; Def's Ex. 36 at 6) (emphasis added).
There is no indication in the record that Kirlin provided Peach State with Mays' conclusions about the roof.
On June 23, 2015, Peach State forwarded to Kirlin by email Carlisle's wind uplift calculations. (Tr. Ex. 44).
On June 26, 2015, Kirlin emailed the Government with an update on the roof repair. (Tr. Ex. 45).
(Id. at 1-2) (emphasis added).
On June 29, 2015, Peach State forwarded another letter from Carlisle to Kirlin in which Carlisle responded to concerns about the roof installation. (Tr. Ex. 46). In essence, Carlisle defended the installation with a single layer of insulation, and again offered to warrant the roof after installation was complete. (Id.) Carlisle also opined "that there is no reason to remove a perfectly good roof installation that meets International Building Code (IBC) and manufacturer's requirements who would be warranting the final installation." (Id.) Peach State maintained that the roof project was "always bid with one layer of insulation. It was contracted with one. It was submitted and approved with one." (Tr. Trans. at I-218).
Notwithstanding Peach State's comments, on June 30, 2015, Kirlin sent Peach State a letter in which it notified Peach State that because the roof installation did not meet the work plan and the Government's Scope of Work as amended, Kirlin directed Peach State to resume work on the roof by first removing all the work already completed.
(Id).
Kirlin represented to Peach State that the Government did not approve the work and the roof needed to be removed because it did not meet the work plan. Kirlin's representation about the government is not correct. There is no evidence before the court that, at this point, the Government had concluded that the roof needed to be removed. The Government had concerns about the membrane blistering and with the method of fastening. However, Kirlin made the decision to require the roof to be removed after it received Mays' report which highlighted how Kirlin had allowed Peach State to proceed with work which did not meet the requirements of the Prime contract or the work plans. Rather, based on Mays' suggestion to Kirlin that "the only feasible remediation" was to replace the entire roof, Kirlin informed the Government that it was going to remove and reinstall a new roof.
On July 1, 2015, Koczenasz emailed Peach State regarding Kirlin's June 30 demand letter.
(Def's Ex. 40 at 2).
After a series of email exchanges, Koczenasz reaffirmed that Peach State had until July 2, 2015 to respond to its June 30, 2015 letter. (Id.) Peach State disagreed with Kirlin that the roof needed to be replaced or that the roof as installed did not match the Subcontract or Peach State's submittal which was approved by BMH Engineering on Kirlin's behalf. (Tr. Trans. at I-218).
In response to Koczenasz's email, on July 1, 2015, acting through its attorney, Peach State responded to Kirlin's directive to remove the roof.
(Tr. Ex. 48).
In short, [Kirlin's] directive is without legal basis. [Kirlin] expressly approved Peach State's submittals and confirmed that the submittals "conforms (sic). . . to the Standards required by the Work Plan." Peach State's construction, in turn, fully conforms to the submittals. [Kirlin] witnessed, oversaw, and approved Peach State's construction daily. [Kirlin] has no legal basis to require Peach State to remove the roof and re-install it according to standards or plans that do not form the basis of the Contract or that are contrary to the submittals that [Kirlin] expressly approved. Peach State will not be liable for, nor will it absorb, any additional costs or damages as a result of [Kirlin's] unilateral decision to require Peach State to cease work or to materially change the submittals that [Kirlin] already approved.
Please be advised that Peach State views [Kirlin's] unilateral decisions and unlawful demands in this regard to be a breach, or an anticipatory breach, of the Contract. . . . Peach State does not want to engage in expensive and lengthy litigation or an unproductive letter writing campaign. Peach State is ready, willing, and able to complete the construction of the project in accordance with the submittals that [Kirlin] approved. Alternatively, Peach State is ready, willing, and able to remove the roof and install it in the new way that [Kirlin] demands, provided that Peach State is compensated for it.
(Tr. Ex. 48).
Inconsistent with its statements to Peach State that the roof must be replaced, on July 6, 2015, Kirlin wrote to the Government, explaining some of the difficulty with the roof installation. (Tr. Ex. 50; Def's Tr. Ex. 41). Kirlin claimed at trial that this letter demonstrates that it was trying to help Peach State by getting the Government to accept the roof. In the court's view upon consideration of the surrounding facts the language of the letter belies Kirlin's position.
(Id.) (footnote added).
Kirlin's letter makes no mention of the insulation issue and fails to mention that Kirlin approved all of Peach State's work. Kirlin did not provide Peach State with a copy of this letter, and apparently did not tell Peach State that Kirlin was seeking permission for work to resume on the roof. (Tr. Trans. at I-223-224).
On July 22, 2015, Peach State's attorney again wrote to Kirlin because Kirlin had not responded to Peach State's July 1, 2015 letter. (Tr. Ex. 49). Peach State accused Kirlin of attempting to "delay the Project, blame Peach State for the delay and eventually attempt to shift liability to Peach State for any purported damages resulting from the delay." (Id.; Tr. Trans. at I-222). Although Peach State characterizes this letter as an attempt to get direction, the letter was merely a reiteration of Peach State's position that the roof met the requirements of its approved submittal and the Government's Scope of Work as amended. See Tr. Trans. at I-222 & Tr. Ex. 49. Unbeknownst to Kirlin, on the same day, Peach State filed suit in this court accusing Kirlin of anticipatory breach of contract and breach of contact. (Doc. # 1).
On July 23, 2015, Kirlin responded to Peach State's letters of July 1 and July 22, 2015, informing Peach State that the Government had issues with the workmanship of the roof installation. (Tr. Ex. 52). Kirlin attached a July 21, 2015 letter from the Government in which the Government contended "does not meet the requirements of the Statement of Work
(Id.).
According to the Government, Kirlin was "made aware of these issues from the Contracting Officer's Representative on March 27, 2015, however, to date no progress in correcting these issues has been made by Kirlin." (Id.) Attached to the Government's letter are several undated photographs. (Id.) Notably, several of the issues raised by the Government had been addressed by Peach State and Kirlin on April 9, 2015, (Tr. Ex. 21) and Peach State believed the issued were resolved at that time. The Government, however, did not believe the issues were resolved, but Kirlin did not inform Peach State of the Government's dissatisfaction. Instead, Kirlin's quality control reports coupled with its requests for documentation reasonably led Peach State to believe that their work and responses were acceptable. The Government directed Kirlin to provide a corrective action plan within fifteen days. (Def's Tr. Ex. 42).
On July 28, 2015, representatives from Peach State, Kirlin, Carlisle and the Government participated in a teleconference to discuss the roof. The Government declined to accept the work as installed due to the eight specific deficiencies listed in its July 21,2015 letter to Kirlin. The Government reiterated that
(Tr. Ex. 53 at 2; Def's Tr. Ex. 45 at 2).
But the Government did not reject the roof based on a single layer of insulation or on the wind uplift and wind zone discrepancies. (Id.) Peach State reiterated its position that the work was acceptable, and that Kirlin had approved all the work. (Id.) Kirlin countered that Peach State is "the roofing expert[] and PSR has a responsibility to do their own quality control as well." (Id.) As the conference degenerated into arguments, the Government interrupted "to note that this call was a courtesy to clarify points of concern and that the points have been made and the work needs to get done." (Id. at 3). While Kirlin and Peach State argued about the adhesive and bubbles in the membrane, the Government did not request that the roof be removed and replaced. (Id.) The Government only wanted its noted deficiencies corrected in an acceptable manner.
Immediately following the conference call, Kirlin emailed Peach State a "Notice of Default" and a copy of the Government's July 21, 2015 letter and photographs. (Tr. Ex. 54). According to Kirlin, Peach State's failure to provide a Corrective Action Plan during the teleconference, coupled with its "defective work, and its failure to cure the same," constituted a default under Article 15 of the Subcontract. (Id. at 2). Kirlin demanded Peach State "cure its default" within 48 hours of receipt of the Notice. (Id.)
Peach State promptly responded to Kirlin's Notice of Default by first noting that its forty-eight hour notice to cure was inconsistent with its demand that Peach State provide a Corrective Action Plan by August 2, 2015. (Tr. Ex. 55). Peach State agreed to repair any "legitimate issues" with the roof but contended that Kirlin had failed to notify it of the issues in a timely manner. (Id.). Peach State denied that it was in default. Nonetheless, Peach State addressed each issue and requested permission to meet with Kirlin on site to identify and address each issue. (Id. at 2-3).
The next day, on July 31, 22015, Kirlin and Peach State met on the roof to identify the Government's problem areas. (Tr. Trans. at I-234-235) Kirlin was unable to specifically identify any areas with problems with wrinkling or fasteners. (Id. at I-235). But at the end of the meeting, Peach State agreed to create a corrective action plan.
While negotiating with Peach State to repair the roof, sometime during the last week in July, Kirlin met with representatives from TeamCraft Roofing to discuss TeamCraft removing the current roof and replacing it using two layers of insulation and a fully-adhered PVC membrane. (Tr. Ex. 63). It is undisputed that Peach State was unaware that Kirlin was seeking to replace it as the roofing subcontractor.
On August 4, 2015, Kirlin held a subcontractor production meeting, (Tr. Ex. 58), but Peach State did not participate in this meeting.
On August 6, 2015, Kirlin held another production meeting which also did not include Peach State. (Tr. Ex. 60) At that time, Kirlin indicated that during the July 28 teleconference, it was "determined that work would be replaced and done as per the work (sic). Kirlin Builders has sent a 48 hr notice to PSR to comply."
On August 11, 2015, Peach State requested permission to begin repairing the roof, but Kirlin denied permission allegedly because the Government had not yet responded to Peach State's corrective action plan. (Tr. Ex. 61 at 1). Peach State could not begin repairs until Kirlin granted permission, and at no time did Kirlin authorize Peach State to begin repairing the roof.
On August 12, 2015, Kirlin received a proposal from TeamCraft Roofing dated August 5, 2015, to replace the existing roof and replace it using two layers of insulation and a fully-adhered PVC membrane. (Tr. Ex. 63). TeamCraft Roofing expressed concern about the wind zones design, the use of water-based adhesives in cold weather, and the possibility of blistering. (Id. at 2). To Kirlin's undoubted dismay, TeamCraft Roofing's proposal exceeded Peach State's submittal by one million dollars.
On August 17, 2015, Kirlin sent Peach State an email questioning whether Peach State was "pulling off this project" because a forklift and container were missing from the worksite. (Tr. Ex. 64). Peach State responded that the forklift remained on site and the container was erroneously removed by the container company. Peach State reiterated that the items would be needed "once [Peach State] resume[d] work, and "[o]nce all the issues have been worked out, PSR will be back onsite to resume the roof replacement project." (Id.; see also Tr. Trans. I-246). Kirlin still did not notify Peach State that it was seeking a new roofing contractor, and Peach State would be replaced. Instead, the next day, Kirlin sought bids on a proposed scope of work to replace the roof which included section 07 22 00 in the scope of work, and specifically required two layers of insulation. (Tr. Ex. 75 at 1 & 3).
On August 31, 2015, Kirlin forwarded to Peach State the Government's response to the corrective action plan submitted by Kirlin to the Government on July 31, 2015. (Tr. Ex. 65). Kirlin directed Peach State to submit "a new CAP [corrective action plan] as directed by the Government no later than close of business September 8, 2015 so that Kirlin has time to review the same before submitting it to the Government." (Id.). The Government rejected every repair suggested by Peach State. (Id. at 2-8). "The Government has reviewed the Corrective Action Plan regarding the subject roof project, and finds that this plan is unacceptable as submitted as it does not adequately address the corrections of the deficiencies in the workmanship and requirements of this Lyster Army Health Clinic task order." (Id.)
Of primary concern to the Government was the fact that the roof as currently installed was leaking and the repairs suggested by Peach State did not ameliorate that problem. In rejecting the corrective action plan, the Government did not request or require that the roof be removed and replaced. (Id.) Moreover, while the Government suggested that one cause of the water leakage might be the lack of two layers of insulation, it did not demand that Peach State install two layers of insulation. (Id.) Peach State's new corrective action plan was due no later than September 8, 2017. (Id.; Tr. Trans. at I-248).
On September 8, 2015, Peach State responded to Kirlin's request for another corrective action plan. (Tr. Ex. 66). Peach State contended that it had "substantially complied with the contract during its installation of the roof," and was "entitled to be paid by Kirlin for the work performed up to this point." (Id.) Peach State did not submit a new corrective action plan but instead insisted that it was "ready, willing and able to submit a change order" to install "a roof different than the one agreed to and approved by Kirlin," provided that Kirlin paid in full what Peach State was owed and assured Peach State that it would be paid for any additional work. (Id.)
On September 14, 2015, upon receipt of Peach State's September 8 letter, Kirlin informed the Government that Peach State had declined to provide another corrective action plan in response to the Government's August 28 letter. (Tr. Ex. 67). Kirlin specifically asked the Government to "confirm direction to replace the roof in order to meet the scope of work." (Tr. Ex. 67). This request is interesting because up to this point, the Government had not directed Kirlin to remove the roof. Rather, the evidence shows that Kirlin unilaterally made the decision in June to replace the roof. On September 17, 2015, the Government directed Kirlin "to meet the specifications of the Statement of Work as awarded." (Tr. Ex. 68). Kirlin had ten days to submit a corrective action plan. (Id.) Kirlin was warned that if its plan was "determined to be unacceptable, Termination for Default proceedings may ensue." (Id.)
On September 18, 2015, Kirlin notified North American Specialty Insurance Company, Peach State's bonding company, of a potential default and claim pursuant to the performance bond.
(Tr. Ex. 69).
According to Kirlin, Peach State was also in default for failing to pay Roofers Mart, a supplier of roofing material. (Id.)
By this time, communications between Peach State and Kirlin had deteriorated to the point that the companies were communicating only through their lawyers. On September 23, 2015, Peach State's attorney notified Kirlin's attorney that Peach State had concerns about third-party roofing contractors having access to the roof. (Tr. Ex. 70).
(Id.)
On September 23, 2015, Kirlin held a production meeting without Peach State's presence or participation. (Tr. Ex. 71). At that time, Kirlin noted that Peach State's September 8 response was not a corrective action plan, and that Peach State had "not agreed to remove and replace the work in place, therefore, it [did] not conform to the expected Task Award." (Id. at 2). Kirlin further noted that it was "reviewing interested subcontractors proposals and will be awarding the project within a week in order to comply with the [Government's] Directive." (Id.)
On September 25, 2015, Kirlin submitted its corrective action plan to the Government in which it proposed "removing and replacing the existing roof to include roofing work performed under the task order to date." (Tr. Ex. 72). Kirlin also notified the Government that it would be replacing Peach State Roofing as the subcontractor. (Id.) Peach State did not receive a copy of this letter. (Id. at 2).
On October 2, 2015, the Government accepted Kirlin's September 25 corrective action plan. (Tr. Ex. 73). Peach State was not provided a copy of the Government's acceptance. (Id.)
On October 13, 2015, Kirlin held a production meeting without Peach State's presence or participation. (Tr. Ex. 74). Notes of the meeting indicate that Peach State "has been notified [of the Government's acceptance of Kirlin's corrective action plan] and
On October 23, 2015, Kirlin contacted Peach State by email and asked that Peach State ensure that the roof was secure and watertight due to impending rains. (Tr. Ex.76). In that email, Kirlin misrepresented the status of the roof replacement project. "Peach State has an obligation to maintain the Roof Replacement Project here at Ft. Rucker that
(Id. at 4) (emphasis added).
(Id. at 2).
While Peach State was communicating with Kirlin about the leaking roof, on October 27, 2015, Peach State discovered that Kirlin had sought bids on a new Scope of Work in August. (Tr. Ex.75). And, when Peach State reviewed Kirlin's August Scope of Work, it noted that it differed significantly from the Scope of Work as amended on which Peach State had bid the previous year. (Tr. Trans. at I-258-59). For example, Kirlin included in its August Scope of Work the pertinent sections of Section 07 22 00 that delineate two layers of insulation as well as the specific wind up lift requirements. (Tr. Ex. 75).
On October 29, 2015, Peach State sent a crew to repair leaks in five areas of the roof where Peach State had done work. (Tr. Trans. at I-259). At that time, Peach State determined that there was no leaking in areas where it had performed work. (Tr. Ex. 76 at 1)
(Id. at 1).
Kirlin issued a termination of default letter to Peach State on November 11, 2015.
(Tr. Ex. 79)
(Id. at 2).
Despite Kirlin's assertion that Peach State refused to cure its defaults, it is undisputed that Kirlin denied Peach State to access the roof from May 13, 2015 until October 29, 2015. Peach State was only permitted on the roof in October 2015 to fix areas that were allegedly leaking. The undisputed evidence shows that the roof was not leaking in any areas where Peach State had worked on the roof.
The central issue in this case is whether Peach State or Kirlin breached the Subcontract. The Subcontract contains a valid choice of law provision that requires this court to apply Maryland law to the issues before it.
JJK Group, Inc. v. VW Intern., Inc. 2015 WL 1459841 (D.Ct. Md. Mar. 27, 2015). It is within these parameters that the court addresses the parties' claims.
At trial, Peach State contended that Kirlin materially and wrongfully breached the Subcontract in the following ways:
Peach State further asserts that Kirlin breached the implied covenant of good faith and fair dealing required by Maryland law, and wrongfully terminated it when it decided to replace Peach State as the roofing contractor.
Peach State also contended at trial that Kirlin wrongfully terminated the Subcontract when it failed to provide adequate notice and opportunity to cure as required by the Subcontract. Peach State asserted that Kirlin's notice of default
As a result of Kirlin's breaches, Peach State contends that it is entitled to a damages award against Kirlin which would include payment of outstanding invoices, lost profits and costs, attorneys' fees, and all additional costs and expenses resulting from the removal of the on-site materials and the replacement cost of any materials caused by Kirlin as well as all other costs incurred by Peach State relating to the roofing project.
Kirlin denies that it breached the Subcontract in any manner. Instead, Kirlin asserts that Peach State breached the Subcontract in September 2015 when it refused to provide a corrective action plan or repair the roof in accordance with the directives of the Government. Kirlin contends that Peach State's refusal to proceed with removing and replacing the roof in September constituted a material breach of the subcontract that justified Peach State's termination from the project. Relying specifically on Peach State's letter of September 8, 2015, Kirlin contends that Peach State's demand for payment constituted an anticipatory repudiation by Peach State that justified Kirlin's termination of the Subcontract. Kirlin also argues that because Peach State was obligated under the Subcontract's flow down provision to Kirlin in the same manner in which Kirlin was obligated to the Government, Peach State can be liable for a breach of the Prime Contract.
In response to Kirlin's claim of breach of contract, Peach State denies that it anticipatorily breached the contract. Peach State contends that it repeatedly stressed that it was "ready, willing and able" to perform the work but that Kirlin refused permission. Finally, Peach State also contends that Kirlin waived any right to recover damages for work on the roof under the theory that Kirlin approved Peach State's submittal and accepted Peach State's work on a daily basis.
The Subcontract indeed does contain a flow down provision that obligated Peach State to Kirlin "in the same way [Kirlin] is [obligated] to the [Government]." However, the Subcontract also contains an important exception provision
E. Const. & Elec., Inc. v. Universe Techs., Inc., 2011 WL 53185, 4 (D.N.J. Jan. 6, 2011) (No. CIV.10-1238 RMK KMW).
There is no dispute that Peach State and Kirlin owed contractual duties to each other pursuant to the Subcontract, but the fundamental issue before the court is whether either party or both breached the Subcontract, and if so, when the breach occurred. Turning first to Peach State's claim that Kirlin breached the Subcontract, the court concludes that Kirlin materially breached the terms of the Subcontract when it hindered Peach State from completing work on the roof by withholding critical information and actively misleading Peach State. Kirlin's conduct towards Peach State violated its implied covenant to work in good faith with Peach State.
The parties do not dispute that the contract documents required Government acceptance of Peach State's work. (Tr. Trans. II-18). It is also undisputed that as early as March 27, 2015, the Government expressed concern to Kirlin about Peach State's work, but Kirlin did not timely notify Peach State of the Government's concerns with Peach State's workmanship. Because Kirlin was the Prime Contractor on the roofing project, the Government would deal exclusively with Kirlin. Peach State was prohibited by the Subcontract from communicating directly with the Government. Kirlin's quality control and project manager approved and continued to approve Peach State's work from March 24 until May 13, 2015, when work ceased through no fault of Peach State. Yet, during this time period Kirlin never advised Peach State about the Government's concerns or gave Peach State an opportunity to remediate any of the problems identified by the Government.
Kirlin was required to approve Peach State's work on a daily basis, and Peach State could not leave the job site until Kirlin inspected and signed off on the work. Kirlin attempts to dismiss the import of the daily quality control reports arguing that they were only for the benefit of the Government. However, it is undisputed that Kirlin gave the daily reports to Peach State. The Subcontract requires Peach State to "abide by the [Kirlin] . . . Site Specific Quality Control Plan," (Tr. Ex. 7 at 9), and the Daily Quality Control Reports clearly delineate that they are part of the Kirlin's Quality Control Plan. (Tr. Ex. 18). The daily quality control reports detail any issues Kirlin had with Peach State's work on the roof and include any corrective action Kirlin directed Peach State to take to remedy any perceived flaws in Peach State's work. Thus, contrary to Kirlin's assertion that Peach State had the ultimate responsibility because it was the roofing expert, Kirlin's quality control reports show that Kirlin had ultimate authority over Peach State's work. Moreover, every time Kirlin brought up an issue of workmanship to Peach State, Peach State immediately corrected the problem. Kirlin's quality control reports show that issues were deemed closed after Peach State implemented Kirlin's corrective action directive. See Tr. Ex. 28.
Although the Government complained to Kirlin on April 30 and May 4, 2015 about the roof installation, the Government's complaints were about wrinkles in the membrane and inconsistencies in the ISO boards. (Tr. Ex. 30). The Government did not complain about insulation. On May 9, 2015, Kirlin finally emailed Peach State about some deficiencies in the roof but none of the deficiencies related to the insulation. (Tr. Ex. 31). The court concludes that Peach State installed the roof in accordance with its Subcontract and its submittal as approved by BMH Engineering on Kirlin's behalf.
In passing, Kirlin asserts that Peach State breached the Subcontract when it failed to note any deviation in its initial submittal as it was required to do by the terms of the Subcontract. According to Kirlin, because Peach State did not note deviations on its submittal, it failed to comply with the Subcontract's requirements, and thus, Peach State is ultimately responsible for any inconsistencies between the Subcontract and other documents. Kirlin's position is not well taken. Kirlin concedes that Peach State's submittal was approved by BMH as Kirlin's engineer on the project and that it did not conform to Kirlin's work plans. (Doc. # 103 at 11). In fact, BMH approved Peach State's amended submittal with the notation that it "
To recap, Kirlin inspected Peach State's work on a daily basis and documented every quality control or safety issue it had with Peach State's work. Peach State corrected every deficiency as required by Kirlin. Kirlin certified each day that Peach State's work was in conformity with the contract plans and specifications and approved and signed off on Peach State's work from March 24, 2015 until the safety shut down in May, 2015. In late March and early April of 2015, the Government expressed concerns to Kirlin that the membrane application was not wrinkle free. Kirlin did not tell Peach State about these concerns. Until May 9, 2015, Kirlin, by its actions, represented to Peach State that its work was acceptable and conformed to the project's specifications and contract documents.
The Mays report highlighted the conflicts in the contractual documents related to insulation and wind lift requirements. It also demonstrates that Kirlin had failed in its responsibilities to insure that the work done by Peach State was in compliance with the Prime Contract, the Subcontract, the Government's Scope of Work as amended, and its own Work Plans. This failure, coupled with Kirlin's daily approval of Peach States' work on the roof and Kirlin's failure to timely inform Peach State about the Government's concerns, leads the court to conclude that Kirlin breached its duty of good faith through its improper administration of the contract. See e.g., Celeron Gathering Corp. v. United States, 34 Fed. Cl. 745 (1996) (Breach of good faith duty founded on an agency's award of contract permitting use of wells know local authorities would not permit that use.) Every contract under Maryland law embodies an implied covenant of good faith and fair dealing that requires the parties to "refrain from doing anything that will have the effect of frustrating the right of the other party to receive the fruits of the contract between them." Questar Builders, Inc. v. CB Flooring, LLC, 410 Md.241, 281, 978 A.2d 651, 675 (Ct. App. Md. 2009). Kirlin's actions did not comply with the covenant.
The actions taken by Kirlin after receipt of Mays' report constitute a further breach of the implied covenant of good faith and fair dealing. Kozcenasz, as Kirlin's representative, made the unilateral decision in June 2015 that the work on the roof could not be brought into conformity with to Kirlin's Work Plan and had to be removed so a new roof could be installed. Thereafter, Kirlin represented to Peach State that it would continue as the roofing subcontractor while representing to the Government that they would be replacing Peach State as the roofing contractor. For example, on June 29, 2015, Kirlin reported to the Government that it had the option of "using another company to complete the project." (Tr. Ex. 45). But Kirlin then represented to Peach State that the installed work was not approved by the Government because the work "does not meet the work plan, applicable codes, or the Government Scope of Work." (Tr. Ex. 47). This was a misrepresentation by Kirlin. While Kirlin knew that the Government was dissatisfied with the workmanship on the roof because of blistering and wrinkles, the Government had not rejected Peach State's work for the reasons stated.
"Maryland law generally implies a covenant "to act in good faith and deal fairly with the other party or parties to a contract." Manning v. Mercatanti, 898 F.Supp.2d 850, 859 (D.Md. 2012) (quoting Questar Builders, 410 Md. at 273, 978 A.2d at 670.) Even if the contract allows Kirlin some discretion, that discretion must also be exercised with good faith. Id.
Neal v. Monument Realty LLC, 2016 WL 1733193, *10 (Ct.Spec.App. Md. Apr.26, 2016) (No. 0266 SEPT. TERM 2014), cert. denied sub nom. Realty v. Neal, 450 Md. 126, 146 A.3d 474 (2016).
Once Kirlin made the decision that the "only feasible remediation is to replace the installed roof system," (Tr. Ex. 43), it took action to frustrate Peach State's ability to "receive the fruits of the contract." On June 26, 2015, Kirlin told the Government that it was willing to replace Peach State as the roofing contractor. (Tr. Ex. 45). In its June 30 letter to Peach State, Kirlin told Peach State that the Government refused to accept the work because it did not comply with the Work Plan. However, at that point in time, the Government had not refused to accept the work, nor had the Government directed to Kirlin to remove the roof. The Government was working with Kirlin to find an acceptable solution to its problems with the roof.
Kirlin led Peach State to believe the Government's concerns in March and April about the roof were resolved. However, on July 23, 2015, Kirlin reversed course and told Peach State about the Government issues with its workmanship. Kirlin's letter of July 28, 2015 reiterates that the alleged defects in the roof were only the eight issues identified by the Government. Up to this point, at no time did Kirlin or the Government express to Peach State concerns about the single layer of insulation or the wind uplift and wind zone requirements. And, since the middle of May, Kirlin had not allowed Peach State access to the roof to deal with the problems identified by the Government.
Despite its correspondence with Peach State during this period, Kirlin was actively communicating with other roofing companies, and seeking bids to replace Peach State. (Tr. Ex. 63). Kirlin was representing to the Government, and had been for at least a month, that Peach State was going to be replaced as the roofing contractor. In addition, the scope of work for which Kirlin was seeking bids differed from the Subcontract in material ways. In fact, the replacement scope or work corresponded to Kirlin's Work Plans and its Prime Contract with the Government; it did not reflect Peach State's Scope of Work as set forth in the Subcontract.
The court finds that, by the end of July at the latest, Kirlin did not deal with Peach State in good faith. While Kirlin was telling Peach State it needed to repair the eight (8) items as noted by the Government, Kirlin actually was planning to remove the roof and replace Peach State as the roofing contractor. (Tr. Ex. 60). Although Kirlin indicated that a decision had been made in the July 28 teleconference to replace the roof, in reality, that decision was made in early June. Moreover, Kirlin did not convey that information to Peach State in June or July. At the heart of this matter is Kirlin's realization that the Subcontract that it entered into with Peach State did not conform to Kirlin's Prime Contract with the Government. Coupled with the facts that Kirlin had misled Peach State about the Government's concerns with workmanship, and had approved Peach State's work, the court finds that Kirlin's actions violated its covenant of good faith thereby breaching the Subcontract. Once Peach State was ordered off the roof in May 2015 due to an unrelated safety issue, Kirlin refused Peach State permission to return to work, clearly frustrating Peach State's ability to complete the work. Kirlin's actions prevented Peach State from being able to enjoy the fruits of the Subcontract.
During the pendency of this case, Kirlin has taken the position that Peach State's failure to provide a Corrective Action Plan in September 2015 was sufficient to justify Kirlin's actions. The court disagrees. The court finds that Kirlin breached the Subcontract in June 2015 when it discovered that Peach State's submittal which was approved by Kirlin as "conforms with exceptions," did not actually conform to Kirlin's Prime Contract with the Government. Consequently, the court need not determine whether Peach State subsequently breached the Subcontract in September 2015.
In support of its claim that Peach State breached its contract by not installing two layers of insulation, Kirlin relies heavily on Section 07 22 00 and insists that the subcontract required two layers of insulation. Kirlin parses the documents too finely, and ignores the fact that Peach State's proposal, the Subcontract and Peach State's submittal all called for a single 3.5" layer of insulation. Moreover, Kirlin approved Peach State's proposal for installation of a single 3.5" layer of insulation
Kirlin further argues that because the Scope of Work as amended designates the project at Type 3 Work Plan/Design Project, Peach State should have known additional work plan documents would be provided and should have been followed. This argument is unpersuasive. Section 2.1.2 of the Scope of Work as amended provides as follows:
On the other hand, Task Order No. 21 indicates that the project was a Type K Work Repair and Renovation project. (Tr. Trans. at I-67-68; Tr. Ex. 6 at 2). Regardless of the designation, the work plan/design documents were Kirlin's responsibility that related directly to Kirlin's obligations to the Government. Kirlin drafted the Subcontract; if Kirlin wanted the work plan/design documents incorporated into the Subcontract, it could have included them. Kirlin points to language in the subcontract under "Description of Work" that it asserts put Peach State on notice that it was required to roof in accordance with the 35%, 65% and100% work plans. "All work will be conducted per work plan documents, Government scope of work and its attachments 1 & 2." (Tr. Ex. 7 at 10). The court concludes that Kirlin depends too heavily on the term "work plan documents."
Newell v. John Hopkins Univ., 215 Md.App. 217, 236, 79 A.3d 1009, 1020 (Ct. Spec. App. Md. 2013).
As the court has concluded, the language of the Subcontract governs, and the Subcontract plainly states in large, bold print that Kirlin will provide no other design documents to Peach State. (Tr. Ex. 7 at 11). The subcontract does not identify "work plans/design documents" as contract documents. (Id. at 2, ¶ 5-6). Peach State understood that the work plan documents consisted of the Government's Scope of Work as amended which included Task Order no. 21, and Attachments 1 & 2, and the Subcontract supports that understanding. (Tr. Trans. at I-195). The Prime Contract between the Government and Kirlin describe the work plans as "minimal design documentation required for [the Government] to monitor [Kirlin's] efforts with regard to schedules, costs, codes and standards. . . ." (Tr. Ex. 8 at 8). Even if the subcontract obligated Peach State to Kirlin in the same manner as Kirlin was obligated to the Government, the Prime Contract in no way notifies Peach State that the work plans supersede Peach State's proposal, the Subcontract and the submittal approved by Kirlin. The Subcontract specifically provides that it "shall govern any inconsistent provision of the Contract Documents." (Tr. Ex. 7 at 2, ¶ 8).
It was not until Kirlin realized that its Subcontract with Peach State did not conform to its Prime Contract with the Government did Kirlin raise the issue about the insulation. "Maryland law also recognizes that "the obligation to act in good faith and deal fairly prohibits a party from terminating its contract (or otherwise exercising its discretion) to `recapture' an opportunity that it lost upon entering the contract." CA Funds Group, Inc. v. Walker & Dunlop Investment Advisory Servs., LLC, 2016 WL 305360, *5 (N.D. Ill. 2016) (quoting Questar, 978 A.2d at 675). Given Kirlin's approval of Peach State's work, it cannot now argue that Peach State's installation of one layer of insulation was a breach of its Subcontract.
As earlier explained, on July 21, 2015, the Government wrote to Kirlin stating that the roofing work did not meet contractual requirements.
Choice Hotels Intern., Inc. v. Madison Three, Inc., 83 F.Supp.2d 602, 608 (D. Md. 2000). First, the court concludes that Peach State's September 8, 2015 letter does not constitute anticipatory repudiation. Although Peach State contends that its September 8, 2015 letter constituted a corrective action plan, it was not. (Tr. Trans. at I-252). Regardless of whether Peach State agreed with the Government about the quality of the work or the effectiveness of the corrective action plan already presented, when the Government rejected the August 28, 2015, plan, Peach State did not act properly when it simply did nothing after sending the September 8 letter and did not provide another corrective action plan. (Tr. Ex. 67).
Nonetheless, the court cannot conclude that Peach State's September 8 letter was "definite, specific, positive, and unconditional" "conduct inconsistent with an intent to be bound." Altmayer-Pizzorno v. L-Soft Intern., Inc. 302 F. App'x 148, 153 (4th Cir. 2008). "In order to constitute an anticipatory breach of contract, there must be a definite and unequivocal manifestation of intention on the part of the repudiator that he will not render the promised performance when the time fixed for it in the contract arrives." Harrell v. Sea Colony, Inc., 35 Md.App. 300, 306, 370 A.2d 119, 123 (Ct. Spec. App. Md.1977) (citing Corbin, Contracts, s 973). In its letter, Peach State stated that it was "ready, willing and able to submit a change order" to install "a roof different than the one agreed to and approved by Kirlin." Regardless of the myriad interpretations that might be placed on this statement, it cannot be construed as an unequivocal statement not to be bound.
More importantly, however, the court has already concluded that Kirlin breached the Subcontract long before Peach State's September 8, 2015, letter. Once Kirlin breached the contract, Peach State was no longer bound by it. Under Maryland Law, a material breach of the contract by Kirlin excused Peach State from further performance.
Accordingly, the court concludes that judgment is due to be entered in favor of Peach State on its breach of contract and wrongful termination claims, and against Kirlin.
In light of the court's conclusions regarding Peach State's breach of contract claims, the court turns to Kirlin's counterclaim against Peach State and NAS. Kirlin contends that Peach State was
(Doc. # 71 at 26-27). Kirlin further contends in its counterclaim against NAS that NAS "breached its performance bond agreement as a matter of law" when Peach State failed to perform and when NAS failed to cure Peach State's default. (Id. at 27).
As previously stated, Peach State was not obligated to install the roof in accordance with Kirlin's work plans/design documents. Thus, Peach State did not breach the Subcontract by installing a single layer of insulation. In addition, because the court concludes that Kirlin materially breached the Subcontract by interfering with and hindering Peach State's ability to work on the roof, Peach State was no longer bound by the terms of the Subcontract. Kirlin conveniently ignores the pertinent fact that it prohibited Peach State from completing the installation of the roof. Because the court concludes that Peach State did not materially breach the Subcontract, judgment is due to be entered in favor of Peach State and NAS and against Kirlin on Kirlin's counterclaim.
In these claims, Peach State contends that because Kirlin accepted Peach State's submittal and represented that it conformed to the work plan, Kirlin is now estopped from asserting that the submittal did not conform to the task order or work plan documents. Peach State styles these counts as promissory estoppel and quantum meruit.
The court concludes that Peach State's quasi-contractual claims of promissory estoppel and unjust enrichment fail as a matter of law. "The general rule is that no quasi-contractual claim can arise when a contract exists between the parties concerning the same subject mater on which the quasi-contractual claim rests." Cnty Comm'rs of Caroline Cty v. J. Roland Dashiell & Sons, Inc., 358 Md.83, 96, 747 A.2d 600, 607 (Ct. App. Md. 2000). See also Chevron U.S.A. Inc. v. Apex Oil Co., Inc., 113 F.Supp.3d 807, 822 (D. Md. 2015); FLF, Inc. v. World Publications, Inc., 999 F.Supp. 640, 642 (D. Md. 1998).
Although Peach State is not barred from pleading alternative theories, there is an express contract between Peach State and Kirlin which now governs. See Chevron U.S.A., 113 F.Supp.3d at 822. In light of the court's determination that Kirlin breached the Subcontract, Peach State cannot recover under these quasi-contract theories. See Klicos Painting Co., Inc. v. Saffo Contractors, Inc., 2017 WL 3976625, *5 (D. Md. Sept. 6, 2017) (Civ. Act. No. JFM-15-02505). Judgment in favor of Kirlin on these claims is due to be granted.
Peach State seeks a declaration from this Court that (1) Peach State is not obligated to pay any past, present, or future expenses or costs resulting from Kirlin's breaches and unilateral decision to halt construction on the Project and terminate Peach State, and (2) that Peach State is not responsible for any damages or delay arising out of Tecta America's work on the Project.
By asserting a claim for "Suppression, Deceit, Concealment of Material Facts," Peach State conflates "two similar, yet distinct, claims sounding in fraud." Bourgeois v. Live Nation Entertainment, Inc., 3 F.Supp.3d 423, 459 (D. Md. 2014).
Id. at 459. See also Green v. H & R Block, Inc., 355 Md.488, 525, 735 A.2d 1039, 1059 (Ct. App. 1999).
According to Peach State, in March 2015, Kirlin fraudulently concealed or deceived by non-disclosure the material fact that the Government had issues with Peach State's workmanship of the roof. Peach State contends that the Government's eight issues were material and Kirlin had a duty to disclose those issues when Kirlin first received notice of them in March. Instead, Kirlin permitted Peach State to install a significant portion of the roof without notifying Peach State about the Government's ongoing concerns.
Regardless of which fraud theory Peach State is attempting to travel under, the court concludes that Peach State has failed to present any evidence that Kirlin made any misrepresentations with the deliberate intent to deceive. "To create a cause of action, concealment must have been intentional and effective — the hiding of a material fact with the attained object of creating or continuing a false impression as to that fact. The affirmative suppression of the truth must have been with intent to deceive." Fegeas v. Sherrill, 218 Md. 472, 476-77, 147 A.2d 223, 225-26 (Ct. App. Md. 1958). According to Peach State, Kirlin's misrepresentations were designed to "induce Peach State to continue to install the roof." (Doc. # 71 at 17). Peach State worked on the roof from March 2015 until May 13, 2015 which a safety issue halted work on the roof. Thus, any misrepresentations occurred in March and April when the Government first notified Kirlin of its issues with the roof. Peach State has presented no evidence that during this time, Kirlin intentionally withheld information about the Government's concerns intentionally to deceive Peach State. As the court has noted, Kirlin's failure to properly administer the contracts demonstrated a lack of good faith as a matter of law, not fact. Consequently, the court concludes that judgment in favor of Kirlin on this claim is due to be granted.
Based on the court's findings of fact and conclusions of law, the court concludes that:
1. As stated in open court, judgment as a matter of law is GRANTED in favor of BMH Engineering and against Peach State and BHM Engineering is hereby DISMISSED as a defendant in this action.
2. Judgment will be entered in favor of Peach State and against Kirlin on Peach State's breach of contract and wrongful termination claims.
3. Judgment will be entered in favor of Peach State and NAS and against Kirlin on Kirlin's counterclaim, and the counterclaim will be dismissed with prejudice.
4. Judgment will be entered in favor of Kirlin and against Peach State on Peach State's claims of promissory estoppel, unjust enrichment, negligence, negligent misrepresentation, declaratory judgment, respondeat superior, and suppression, deceit, non-disclosure and concealment of material facts. These claims will be dismissed with prejudice.
The court will enter final judgment after the matter of damages is resolved. Accordingly, it is ORDERED as follows:
1. The defendant Kirlin's motion for summary judgment (doc. # 62) be and is hereby DENIED as moot.
2. That on or before