RANDOLPH J. HAINES, Bankruptcy Judge.
The issue here is whether various mechanics' lien claimants, who claim priority dating from the commencement of construction in November 2006, have priority over a construction deed of trust that was recorded in May of 2007. Among other defenses, the construction lender asserts the doctrine of equitable subrogation gives it priority back to that of a prior deed of trust because a portion of the construction lender's loan was used to pay off the prior debt.
The construction project at issue is the remodeling or refurbishment of an existing building commonly known as the Hotel Monroe. Its owner, Central and Monroe, LLC, first obtained a loan from First Commonwealth Mortgage Trust in the amount of $3.2 million, secured by a deed of trust recorded in May, 2002. In July, 2005, that loan was refinanced by an $8.5 million dollar loan provided by Mortgages Ltd., secured by a deed of trust recorded that same month. Almost $3 million of the proceeds of that loan were used to satisfy the First Commonwealth debt and obtain a release of the First Commonwealth deed of trust.
In December, 2006, the owner obtained a new loan from Choice Bank in the amount of $9.3 million. It was secured by a deed of trust recorded that same month. Approximately $7.3 million of the proceeds of the Choice loan were used to satisfy the debt to Mortgages Ltd. and obtain a release of its 2005 deed of trust.
By the time the Choice Bank deed of trust was recorded in December, 2006,
The Choice Bank debt was refinanced by another loan from Mortgages Ltd. in the amount of $75.6 million, in May, 2007. The deed of trust securing that debt was recorded on May 16, 2007. From the proceeds of this second Mortgages Ltd. loan, more than $8.9 million was used to satisfy the Choice Bank debt and obtain a release of its 2006 deed of trust.
More than six months later, the owner signed another contract with another general contractor, Summit Builders. It commenced work on January 1, 2008, and recorded its notice and claim of mechanics' and materialmen's lien in July, 2008.
Summit claims that although it had a separate contract with the owner, some of the work it contracted to do was on the same "project" that KGM had worked on, the demolition of the interior of the building to prepare for the substantial remodeling.
Mortgages Ltd. has moved for summary judgment against Summit Builders and all of its subcontractors on essentially three theories:
Mortgages Ltd. asserts that at a status conference on July 6, 2010, Summit's counsel announced in court that it would be dismissing its lien claim. It was not until a subsequent status conference on October 25 that Summit's counsel announced that Summit had changed its mind and would not be dismissing its lien claim. Mortgages Ltd. argues that the intended dismissal that was announced on the record should be enforced as a settlement agreement.
Mortgage's second basis for summary judgment is that Summit's lien is invalid because Summit failed to provide Mortgages Ltd. with a preliminary twenty-day lien notice as required by statute.
Finally, Mortgages asserts that because portions of the proceeds of its loan were used to pay off prior secured debts, Mortgages Ltd. is entitled to the priority of those prior deeds of trust under the doctrine equitable subrogation.
The court is not inclined to grant summary judgment on the theory that Summit's stated intent to dismiss its lien claim constituted a settlement agreement. It does not appear that it was so much of an agreement as merely a unilateral decision and announcement by Summit. Although a unilateral statement of position can be enforced either as a judicial estoppel or as quasi-judicial estoppel, those doctrines generally apply only if there has been some benefit obtained as a result of this statement, or some detrimental reliance by the court or other parties. Here no such showings have been made.
But Mortgages Ltd. might be entitled to summary judgment due to the failure of Summit to provide the preliminary 20-day notice required by A.R.S. § 33-992.01(B). There can be no dispute that Mortgages Ltd. qualified as a "construction lender" or a "reputed construction lender" as referred to in this statute. Summit had constructive notice at the time that it commenced work in January of 2008 that Mortgages Ltd. was such a construction lender because its deed of trust had been of record for more than seven months.
Summit's defense is that it substantially complied with the statute by providing a preliminary 20-day notice to the owner, and that Mortgages Ltd. was not prejudiced by the failure of notice because it had actual knowledge that the construction was going on. But while case law has upheld liens when there has been substantial compliance with the 20-day preliminary notice requirement even though the notice failed to include all of the statutorily required elements,
Summit has a better argument that Mortgages is statutorily estopped from asserting the preliminary 20-day notice defense because the owner failed to correct the failure of the notice to identify Mortgages Ltd. as its construction lender. Arizona law provides that the owner has ten days after receipt of a preliminary 20-day notice to identify its construction lender and to correct any misinformation contained in the notice.
Of course Mortgages Ltd. was not the owner at the time that the preliminary twenty-day notice was given to the owner. But Mortgages Ltd. is now the owner because it bought the property by a credit bid at its own trustee's sale.
The statute defines the "owner" to be "the person, or the person's successor in
Because Mortgages Ltd. is a successor in interest to an owner who failed to correct the misinformation contained in the preliminary 20-day notice that was served on the owner, Mortgages cannot assert the failure to serve the notice on the construction lender as a defense.
Probably the most accurate and authoritative statement of the doctrine of equitable subrogation as now recognized in Arizona is found in the 1965 Court of Appeals decision in Peterman-Donnelly:
There is no dispute here that Mortgages Ltd. agreed to advance money to discharge the owner's obligation to Choice Bank. Nor is there any dispute that in doing so, Mortgages was not acting as a volunteer. Most of the argument has focused on the nature of the express or implied agreement that Mortgages would be substituted in place of Choice Bank as to lien priority.
Arizona case law seems to hold conclusively that the subsequent lender's intent to obtain first lien priority is sufficient to satisfy the agreement requirement. In Lamb,
In the argument and in the memoranda the mechanics' lien claimants assert various arguments why it would not be equitable to recognize equitable subrogation here. Most of these arguments hinge on
The Lamb opinion similarly rejected the trial court's reliance on the argument that the bank had a "superior position" over the "truly innocent intervening lien holders." The decision did so by noting that the mechanics' lien holders were in no worse position then they had been when they undertook to perform work on property that was already subject to the prior deed of trust.
There is apparently no argument here, as there has been in connection with some other Mortgages Ltd. loans, that Mortgages should be denied an equitable remedy because it was the cause of the financial disaster for everyone, due to its failure to fully fund the loan it committed to make. But even if there were such an argument, it would similarly seem to be rejected by Lamb's indication that the requisite inequity must be based on some fact or circumstance that would make it inequitable to leave the lien claimants in a position junior to the prior deed of trust.
Finally, the original contractor, KGM, argues that it commenced work in November of 2006, prior to the December, 2006, recording of the Choice Bank deed of trust. KGM therefore argues that equitable subrogation of Mortgages to the Choice Bank deed of trust cannot render it superior to KGM's lien. Other lien holders also assert that same KGM priority by arguing that although it was done under a different contract,
No party has been able to cite a case applying equitable subrogation in this daisy-chain fashion. But such a two-step subrogation seems to be entirely consistent with the general principles and purposes of the doctrine. The effect of equitable subrogation is simply to substitute one lien holder to the lien-priority position
For the foregoing reasons, Mortgages Ltd. is entitled to partial summary judgment establishing a lien priority date of July 1, 2005, to the extent of the $7.3 million portion of the Choice Bank loan that was used to discharge the first Mortgages' deed of trust. Mortgages is also entitled to partial summary judgment establishing a lien priority date of May 16, 2007, to the extent of the $8.9 million loan proceeds that were used to discharge the Choice Bank deed of trust. Mortgages is entitled to these summary judgments as against KGM, Summit Builders and all of their subcontractors.