D.P. MARSHALL, Jr., District Judge.
1. We're finally at the core of this case — whether Windstream broke its contract with Hal-Tee when the parties wound down their business relationship. This Court's prior Orders give the details. No. 34 & 59. Hal-Tee is in the margins: it assigned its contractual rights to Amerifactors, who is the Plaintiff here; and Hal-Tee is in default on Windstream's third-party complaint. Windstream seeks summary judgment, while Amerifactors says disputed facts require a trial. The parties agree that their contract is unambiguous. The Court concurs. And viewing the record in the light most favorable to Amerifactors, the Court sees no genuinely disputed material facts. Hyman Freightways v. Carolina Freight Carriers Corp., 942 F.2d 500, 502 (8th Cir. 1991).
2. Windstream, it's agreed, terminated the parties' relationship in late April 2009 effective at the end of July. The parties' contract allowed for immediate termination for cause. No. 1-1 at ¶ 33(a). Windstream had cause because Hal-Tee wasn't installing communication lines and related equipment in a timely and efficient fashion. No. 97-1 at 25, 29, 33-35, 40; No. 97-2 at 4-9. So the ninety days was an accommodation. In early May, Windstream sent Hal-Tee a confirming letter about the ninety-day period for wrapping up the approximately fifty projects Hal-Tee had in hand. No. 75-2. The letter is quoted in the margin.
Around the time of the confirming letter, though, things changed again. It turned out that, notwithstanding promise of best efforts, Hal-Tee might not be able to complete all its projects by late July. Windstream pulled approximately forty projects — all those where Hal-Tee had not already started work. When the parties parted ways, Hal-Tee possessed several hundred thousand dollars of contract-related supplies that it had, as the contract required, bought from Windstream.
Hal-Tee's main point is that Windstream back tracked on the ninety days. That period, the contractor says, would have allowed it to use up the supplies, or most of them. Pulling most of the current projects, and then not buying the materials back, was a one-two punch that (Amerifactors argues) violated both the parties' oral contract about how to unwind their relationship and the parties' foundational agreement.
3. The meaning of the parties' unambiguous "Master Contractor Agreement for Network Services" presents questions of law. Artman v. Hoy, 370 Ark. 131, 136-37,257S.W.3d 864,869 (2007). The parties agreed that there could be no change in their agreement without a writing signed by both sides: "No modification or amendment of the terms of this Agreement other than as specifically provided herein, shall be effective except through a writing executed by both parties." No. 1-1 at ¶38(g). No such writing exists. Windstream's confirming letter wasn't signed by Hal-Tee. Locking in a ninety-day grace period would have been a substantial change in the parties' master agreement, which allowed immediate termination.
Windstream's primary argument-the no-oral-modification clause entitles it to judgment-fails. As counter-intuitive as it may seem on first thought, this kind of clause is unenforceable in this kind of case. Article 2 of the Uniform Commercial Code, which the clause echos, is inapplicable to this services agreement. ARK. CODE ANN.§ 4-2-101. The parties' agreement is not within the statute of frauds. ARK. CODE ANN.§ 4-59-101. The common law applies. And that law, in Arkansas and elsewhere, allows contracting parties such as Windstream and Hal-Tee to rescind or vary their obligations by making a new contract notwithstanding the terms of their existing one. National American Insurance Co. v. Hogan, 173 F.3d 1097, 1107 (8th Cir. 1999)(summarizing and applying the Arkansas cases); see generally, RICHARD LORD, 29 WILLISTON ON CONTRACTS § 73:22 (4th ed.); SARAH JENKINS, 13 CORBIN ON CONTRACTS § 71.2(2) (2003).
Beatty v. Guggenheim Exploration Co., 225 N.Y. 380,387-88,122 N.E. 378,381 (1919)(Cardozo, J., on the rule at common law, with quotations and citations omitted).
This is not the end of the analysis, though. Windstream' s decision in late April not to terminate the parties' relationship entirely at that point was a waiver: a voluntary and intentional relinquishment of a known right. Ellis v. Block, 212 Ark. 264, 267-68, 205 S.W.2d 708, 710 (1947); Lester v. Mount Vernon-Enola School District, 323 Ark. 728, 732, 917 S.W.2d 540, 542 (1996). This waiver was undoubtedly effective in law. Windstream confirmed it in writing — remember the May letter, which the parties' master agreement required. No. 1-1 at ¶ 38(c). What did Windstream waive? It's right in late April to terminate immediately and completely then.
Taking the record in the light most favorable to Amerifactors, Windstream did not waive its right to terminate for non-performance during the ninety-day period. Hal-Tee and Windstream's transition arrangement remained subject to the parties' master agreement. Windstream' s letter said so. Hal-Tee's president confirmed this on deposition:
No. 97-1 at 26-27. Under the master agreement, Windstream retained the right to pull the plug on some, or all, of the projects if and when Hal-Tee failed to perform. No. 1-1 at ¶ 33. The parties' agreed, moreover, that Windstream's forbearance on any contractual point would not waive the compass right to later assert the parties' agreement. "Waiver by Windstream of any default by [Hal-Tee] shall not be deemed a waiver of any other default." No. 1-1 at ¶ 38(c).
The result is the same if the parties' transition arrangement is evaluated in terms of consideration. Windstream got none. Hal-Tee neither gave nor promised any performance that it wasn't already bound to give. This is not a case where both sides got some new or different benefit. E.g.,]. C. Engleman, Inc. v. Briscoe, 172 Ark. 1088, 291 S.W. 795, 797 (broker's commission decreases, but he's now authorized to employ subagents). It's not a case where performance under the parties' original contract was disputed. E.g., Cox v. McLaughlin, 315 Ark. 338, 344-45, 867 S.W.2d 460, 462-63 (1993). This is, instead, the paradigm case of no consideration: Hal-Tee promised to do during the transition period only what it was already obligated to do, perform under the parties' master agreement. Windstream's promise to let Hal-Tee do so is not enforceable because it was unsupported by any consideration. Ibid; 3 WILLISTON ON CONTRACTS § 7:36.
The parties are experienced businesses. They tried to make the best of their parting with a transition period. Performance problems arose almost immediately. No. 97-1 at 8-9, 39-40; No. 97-2 at 7-9. Windstream disputes the ninety-day promise. Accepting for present purposes that it was made, as Hal-Tee's president testified and as Windstream's letter shows, this promise was not in a vacuum: the parties' master agreement was the air around the delayed termination. When Hal-Tee could not ensure completion of all its projects during the ninety days, Windstream moved on. No. 97-1 at 39. It retained the contractual right to do so. Just as Hal-Tee came in early and finished some of its predecessor's incomplete projects before the formal Hal-Tec/Windstream master contract was made, No. 97-1 at 7, other contractors stepped in to do Hal-Tees jobs when timely completion was in some doubt. Windstream is entitled to judgment on Hal-Tee's claim about the ninety-days.
4. Hal-Tee has no solid claim about unused wire and other supplies either. Reading all the material provisions of the parties' contract, No. 1-1 at ¶¶ 1, 10, 11, 33, 34, Windstream had the right, not the duty, to repurchase these materials. "May" can be a murky word. First United Bank v. Phase II, 347 Ark. 879,901, 69 S.W.3d 33,48 (2002). But here the parties used it to mean that Windstream could buy back the materials if it chose to do so. These are the parties' words.
The "shall" in paragraph 34(b) casts a shadow. As Hal-Tee argues, the word usually means a mandate. Marcum v. Wengert, 344 Ark. 153, 165, 40 S.W.3d 230, 238 (2001). This is not always so; shall can be murky too. Gutierrez de Martinez v. Lamagna, 515 U.S. 417, 432 n.9 (1995). In any event, this paragraph must be read with paragraphs 11 and 33(a) and, if possible, harmonized. Asbury Automotive Used Car Ctr., L.L.C. v. Brosh, 364 Ark. 386, 392, 220 S.W.3d 637, 642 (2005).
Paragraph 34(b) covers more than the pre-ordered materials and supplies; it includes uncompleted work contracts, records, plans, surveys — everything Windstream would need to take over a project midway through. It's thus the mandate for handling a mid-project termination. But this clause also says Windstream dictates any handoff "in the manner and at the time" it decides. No. 1-1 at ¶ 34(b). The discretion here conferred about materials and supplies echos the" may" in the specific provisions about those items. No. 1-1 at ¶¶ 11(d),33(a). Under the parties' agreement as a whole, Hal-Tee is stuck with the pre-ordered materials because Windstream didn't elect to repurchase them. Amerifactor' s claims about these materials, made in Hal-Tee's stead, fail as a matter of law.
Windstream' s renewed motion for summary judgment as supplemented, No. 75 & 97, granted. Windstream's motion to exclude evidence, No. 82, denied as moot.
So Ordered.
Windstream Supply, LLC hereby notifies you that it is terminating its Master Contractor Agreement (MCA) with Hal-Tee Construction, Inc., dated January 1, 2009 in accordance with section33(a). This termination will be effective on July 31, 2009. It is our expectation that Hal-Tee will perform under the terms of the MCA and provide for a smooth and orderly transition. The Windstream point of contact for the transition will be Mr. Ken Allison. Ken can be reached at 918-451-3436 or via email at
If you have any questions do not hesitate to contact me.