Elawyers Elawyers
Washington| Change

Horton Construction Co., Inc., ASBCA No. 61085 (2017)

Court: Armed Services Board of Contract Appeals Number: ASBCA No. 61085 Visitors: 33
Judges: Osterhout
Filed: Sep. 01, 2017
Latest Update: Mar. 03, 2020
Summary: APPEARANCE FOR THE APPELLANT: Gregory D. Coleman, Esq. In response, Horton, alleged that Mr. Chauncy Horton was not authorized to sign the final release of claims and, the VEQ clause should be read into the contract as a matter of law. We deny the, government's motion for summary judgment.
              ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of--                                   )
                                              )
Horton Construction Co., Inc.                 )      ASBCA No. 61085
                                              )
Under Contract No. W9124E-11-C-0021           )

APPEARANCE FOR THE APPELLANT:                        Gregory D. Coleman, Esq.
                                                      Johnson Hopewell Coleman, LLC
                                                      Decatur, GA

APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
                                                      Army Chief Trial Attorney
                                                     MAJ Bruce L. Mayeaux, JA
                                                      Trial Attorney

           OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT
       ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

       This is an appeal of a contracting officer's denial of a claim by Horton Construction
Co., Inc. (Horton or appellant), alleging that it is owed $274,599.00 because the contract
required, in part, crushing and removal of approximately 69,000 tons of concrete but the
actual amount was closer to 29,000 tons and, alternatively, $244,282.00 under the
"Variation in Estimated Quantity clause," which was not included in the contract (R4,
tab 27 at 25). In its complaint, Horton alleges that one of three clauses should have been
used to grant its relief: Federal Acquisition Regulation (FAR) 52.243-4, CHANGES
(JUN 2007); FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984); or FAR 52.211-18,
v ARIA TION IN ESTIMATED QUANTITY (VEQ clause). The government moves for summary
judgment arguing there is no genuine dispute that the request for equitable adjustment was
made after final payment with a final release of claims and the VEQ clause was not a part of
the contract and thus it is entitled to judgment as a matter of law. In response, Horton
alleged that Mr. Chauncy Horton was not authorized to sign the final release of claims and
the VEQ clause should be read into the contract as a matter of law. We deny the
government's motion for summary judgment.

       STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

       I. In September 2011, a contracting officer from the Directorate of Contracting,
Mission and Installation Contracting Command, Fort Polk, Louisiana, awarded Contract
No. W9124E-l l-C-0021, a firm-fixed-price contract in the amount of$1,943,148.51, to
Horton. The contract provided in the Rule 4 file is not signed by any Horton representatives.
(R4, tab 1) Additionally, Horton's final proposal provided in the Rule 4 file is not signed by
any Horton representatives (R4, tab 4 ).
       2. The work to be performed included crushing a concrete stockpile and work
associated with erosion control at Fort Polk, Louisiana (R4, tab 1 at 7).

       3. The following clauses were incorporated into the contract and state in
pertinent part:

              FAR 52.243-4, CHANGES (JUN 2007). "(f) No proposal by
              the Contractor for an equitable adjustment shall be allowed
              if asserted after final payment under this contract." (R4,
              tab 1 at 48)

              FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984).
              "( d) No request by the Contractor for an equitable
              adjustment to the contract for differing site conditions shall
              be allowed if made after final payment under the contract."
              (R4, tab 1 at 43)

              FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE
              CONSTRUCTION CONTRACTS (SEP 2002). "(h) Final
              payment. The Government shall pay the amount due the
              Contractor under this contract after- ... (3) Presentation of
              release of all claims against the Government arising by
              virtue of this contract, other than claims, in stated amounts,
              that the Contractor has specifically excepted from the
              operation of the release." (Id.)

       4. FAR 52.211-18, VARIATION IN ESTIMATED QUANTITY, was not included in
the contract (R4, tab 1).

      5. The contract called, in part, for crushing a "[ s]tock pile of approximately
69,000 Tons of concrete" (R4, tab 1 at 10).

      6. During performance of the contract, the actual amount of concrete that
Horton was required to crush amounted to approximately 28,997 tons of concrete
(compl. ~ 11 ).

        7. On 18 January 2012, the parties executed a no-cost bilateral modification to
revise the Statement of Work and other administrative changes, signed for appellant by
Mr. Chauncy Horton (R4, tab 6).

       8. On 27 January 2012, Mr. Chauncy Horton notified the government via electronic
mail that the concrete at the site was not 69,000 tons and requested a rate adjustment
without specifying the rate it wanted (R4, tab 8).



                                            2
       9. On 1 February 2012, the contracting officer responded via a letter, denying the
request to adjust the rate (R4, tab 9). The denial was based on the language
"approximately 69,000 Tons of concrete" and the possibility of more concrete being
added because the period of performance was still continuing (id. at 1).

       10. On 29 June 2012, the parties executed a no-cost bilateral modification to
extend the period of performance, signed for appellant by Mr. Chauncy Horton (R4,
tab 13).

       11. On 29 August 2012, the parties executed another no-cost bilateral modification
to extend the period of performance, signed for appellant by Mr. Chauncy Horton (R4,
tab 14).

        12. On 12 November 2012, Mr. Chauncy Horton signed FP Form 1186,
Certification of Final Payment, Contractors Release of Claims (final payment and final
release). This release of claims was witnessed by someone with the title "Estimator"
and someone with the title "Secretary." The secretary signature appears to be that of
Dominique Horton Washington.* (R4, tab 16)

       13. On 6 March 2014, the parties executed a bilateral modification to de-obligate
funds, signed for appellant by Mr. Chauncy Horton (R4, tab 18).

        14. Between 23 October 2014 and 17 July 2015, Mr. J. L. Horton, Sr., signed
several letters requesting an equitable adjustment due to the difference between the
estimated 69,000 tons of crushed concrete and the lower actual amount of crushed
concrete (R4, tabs 19-23). The second oftwo letters sent on 23 October 2014 included
a reference to Horton's subcontractor for the reduced amount of crushed concrete to an
arbitrator's award of"nearly $250,000" (R4, tab 20). On 5 October 2015, Horton
submitted an unsigned update including legal expenses in the amount of $551,091.94
(R4, tab 24).

       15. On 27 May 2016, attorneys for Horton submitted a certified claim for equitable
adjustment in the amount of $274,599.00 (R4, tab 27). Ms. Dominque Horton Washington,
Vice President, signed the certification (id. at 26).

       16. On 16 December 2016, the contracting officer denied the claim (R4, tab 28).

       17. By letter dated 8 March 2017 Horton filed a timely notice of appeal with the
Board, which was docketed as ASBCA No. 61085.


* Dominique Horton Washington is listed as Secretary on 12 November 2012, and on
      27 May 2016 in the certified claim nearly 4 years later, Ms. Washington's title is
      listed as Vice President (SOF iii! 12, 15).

                                          3
                                       DECISION

        The government contends, inter alia, it should be granted summary judgment
because the claim arose after several modifications, the final payment, and a final
release were executed (gov't mot. at 9). Horton argues that the individual who signed
the final payment and final release, Mr. Chauncy Horton, was not authorized to do so.
Thus, Horton concludes that because Mr. Chauncy Horton did not have the requisite
authority or the intent to release a claim, genuine issues of fact exist as to the
sufficiency of the government's fundamental position that the final release was properly
executed. (App. resp. at 7) The government counters that Mr. Chauncy Horton was a
business point of contact and had actual or apparent authority to bind appellant (gov't
reply at 2).

        We have carefully considered the Army's allegations and the underlying
modifications and release in question and conclude that there are genuine issues of
material fact that preclude summary judgment. It is well settled that summary judgment
is appropriate where the moving party establishes that there are no disputed material
facts, and the moving party is entitled to judgment as a matter of law. Riley & Ephriam
Constr. Co. v. United States, 
408 F.3d 1369
, 1371-72 (Fed. Cir. 2005); Mingus
Constructors, Inc. v. United States, 
812 F.2d 1387
, 1390 (Fed. Cir. 1987). However,
"all significant doubt over factual issues must be resolved in favor of the party opposing
summary judgment." 
Mingus, 812 F.2d at 1390
(citations omitted). A material fact is
one that affects the outcome of the case. Anderson v. Liberty Lobby, Inc., 
477 U.S. 242
,
247 (1986).

        The moving party, in this case the government, bears the burden of demonstrating
that there are no genuine issues of material fact. The Public Warehousing Co., ASBCA
No. 57510, 13 BCA ii 35,314 at 173,363 (citing Celotex Corp. v. Catrett, 
477 U.S. 317
,
323-24 (1986)). Summary judgment must be denied if the moving party fails to submit
sufficient evidence to meet its initial burden, even if the non-moving party fails to
oppose the proffered evidence. 
Id. (citing Adickes
v. S.H Kress & Co., 
398 U.S. 144
,
160 (1970)).

        Here, our review concludes that the Army failed to submit sufficient evidence to
meet its initial burden, specifically whether Mr. Chauncy Horton was authorized to sign
the final payment and final release for appellant. Because the government relies upon the
final payment and final release in its argument, the validity of the final payment and final
release is material to the government's motion. As noted in our findings, neither the
original contract nor the final Horton proposal are signed by any Horton representatives
and do not demonstrate which Horton personnel had the authority to enter into
agreements between Horton and the Army. While Mr. Chauncy Horton signed several
modifications which were signed prior to the final payment and final release paperwork,
all of these modifications were no-cost changes and do not demonstrate the extent to
which Mr. Chauncy Horton was authorized to enter agreements between Horton and the


                                            4
Army. Further, the affidavits provided by the government do not provide this missing
information. Because this missing information demonstrates a genuine issue of material
fact, we must deny the motion for summary judgment.

       Based on the decision above, we need not, at this time, decide if the VEQ clause
should be read into the contract as a matter of law or whether Chauncy Horton had
apparent authority.

                                   CONCLUSION

       The government's motion for summary judgment is denied.

       Dated: 1 September 2017



                                                  Adminis rative Judge
                                                  Armed Services Board
                                                  of Contract Appeals

 I concur                                         I concur




 RICHARD SHACKLEFORD                             OWEN C. WILSON
 Administrative Judge                            Administrative Judge
 Acting Chairman                                 Vice Chairman
 Armed Services Board                            Armed Services Board
 of Contract Appeals                             of Contract Appeals

       I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
Services Board of Contract Appeals in ASBCA No. 61085, Appeal of Horton Construction
Co., Inc., rendered in conformance with the Board's Charter.ยท

      Dated:



                                                 JEFFREY D. GARDIN
                                                 Recorder, Armed Services
                                                 Board of Contract Appeals




                                           5

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer