Elawyers Elawyers
Ohio| Change

Ford Lumber & Building Supply, Inc., ASBCA No. 61617, 61618, 61619 (2019)

Court: Armed Services Board of Contract Appeals Number: ASBCA No. 61617, 61618, 61619 Visitors: 3
Judges: D'Alessandris
Filed: Aug. 01, 2019
Latest Update: Mar. 03, 2020
Summary: Appeals of ), ), Ford Lumber & Building Supply, Inc. ) ASBCA Nos. Ford, has supported with declarations statements that the steam pipe insulation was falling off, of the steam lines and had been run-over by lawnmowers for years and that the pipes, were a health and safety hazard (app.
                     ARMED SERVICES BOARD OF CONTRACT APPEALS

     Appeals of --                                 )
                                                   )
     Ford Lumber & Building Supply, Inc.           )      ASBCA Nos. 61617, 61618, 61619
                                                   )
     Under Contract No. DACA27-1-96-9              )

     APPEARANCE FOR THE APPELLANT:                        Timothy D. Hoffman, Esq.
                                                           Dinsmore & Shohl LLP
                                                           Dayton, OH

     APPEARANCES FOR THE GOVERNMENT:                      Michael P. Goodman, Esq.
                                                           Engineer Chief Trial Attorney
                                                          Nicole E. Angst, Esq.
                                                           Engineer Trial Attorney
                                                           U.S. Army Engineer District, Louisville

           OPINION BY ADMINISTRATIVE JUDGED' ALESSANDRIS ON THE
        GOVERNMENT'S MOTION TO DISMISS AND FOR SUMMARY JUDGMENT

               Pending before the Board is the motion to dismiss filed by respondent the United
      States Army Corps of Engineers (Corps or government).· These appeals arise from a
      1996 Base Realignment and Closure (BRAC) Lease in Furtherance of Conveyance for
      land that was previously part of the Jefferson Proving Ground, in Jefferson County,
      Indiana. The government asserts that appeal 61617, for damages to a building and
      generator caused by a government contractor "in the late 1990s," is barred by the statute
      of limitations; that appeal 61618 requesting a reduction in the purchase price of property
      was not premised upon a valid claim because it did not state a sum certain; and that
      appeal 61619 seeking reimbursement of asbestos-related remediation costs and fines
      should be dismissed for failure to state a claim upon which relief can be granted (gov't
      mot. at 7-11). Because the government cited documents beyond the complaint in its
.,    motion, the Board notified the parties that it intended to treat the government's motion as
      a motion for summary judgment. The order specifically noted that the opposition to the
      motion to dismiss filed by appellant, Ford Lumber & Building Supply, Inc. (Ford), stated
      that it "could provide additional testimony" regarding the "real facts" of the appeal. The
      Board informed Ford that "it should provide such relevant evidence in the form of
      declarations in response to this order." (Bd. corr. Order Jhd. Jan. 8, 2019) For the
     .reasons described below, we grant the government's motion in part, and dismiss appeals
      61617 and 61618, but deny the government's motion with regard to appeal 61619.
STATEMENT OF FACTS (SOF) FOR PURPOSE OF THE GOVERNMENT'S MOTION

        On October 16, 1995, the Corps issued an invitation for bids for the sale of
approximately 3,400 acres of the Jefferson Proving Ground in Jefferson County, Indiana
(R4, tab 8 at GR4_79, 88). Mr. Dean Ford, president of appellant, was the successful
bidder (R4, tab 8). The parties entered into a Lease in Furtherance of Conveyance
(LIFOC) 1 on May 13, 1996 (id. at GR4_78). The initial term of the lease was 5 years, or
until delivery of the final deed, whichever was sooner (R4, tab 8 at GR4_ 63 ), but this
lease term was modified to 50 years by Supplemental Agreement No. 3 on November 25,
1997 (id. at GR4_167).

        The lease provided that the government would transfer the property to the awardee
once environmental clean-up made the property suitable for transfer (R4, tab 8 .
at GR4_62). The contract made clear that there was asbestos and lead paint in the
property to be transferred (R4, tab 8 at GR4_93). ("The facilities at Jefferson Proving
Ground contain asbestos. The asbestos contains materials that are believed to be
nonfriable. The family housing units were constructed prior to 1978 and lead-based paint
is present."). The contract additionally provided at i12.3.5 that it would issue a Finding
of Suitability for Transfer (FOST) that:

               [W]ill indicate that all remedial actions necessary to protect
               human health and the environment have been taken to the
               satisfaction of the concerned regulatory agencies with
               jurisdiction over the property, ·and will identify, to the extent
               such are required to protect human health and the
               environment, appropriate use restrictions to be included as
               covenants in the instruments of title conveyance.

(R4, tab 8 at GR4_84)

        The LIFOC indicated that additional environmental restrictions may apply:
                       '

               [A ]s soon as the Finding of Suitability to Transfer (FOST) is
               executed by the Army for the Leased Premises, or a portion
               of said Leased Premises, and said Leased Premises may be
               conveyed consistent with the requirements of the
               Comprehensive Environmental Response, Compensation and
               Liability Act (CERCLA), 42 United States Code (U.S.C.),
               Section 9620 (h), as amended, and other legal and policy

1A   LIFOC is commonly used by the government as a means of transferring property
        from itself to private entities while allowing for environmental remediation by the
        government prior to full conveyance of title.

                                               2
              requirements, the Secretary intends to convey to the
              Buyer/Lessee by one or more quitclaim deeds, for said
              property or portions of said property, subject to any necessary
              restrictions, reservations, conditions, and exceptions, and the
              Buyer/Lessee hereby agrees to accept such conveyance(s) as
              soon as the above-referenced conditions are met. ...

(R4, tab 8 at GR4_63) (emphasis added) The contract additionally provided that the
Army will effectuate conveyance of title to the property offered for sale herein, subject to
appropriate covenants, restrictions, and other reasonable and necessary limitations on use
of the property (id. at GR4_84).

       The LIFOC provided for indemnification by the lessee to the government and by
the government in favor of the lessee as follows:

              14. INDEMNITY

                     a. The United States shall not be responsible for
              damages to property or injuries to persons which may arise
              from or be incident to the exercise of the privileges herein
              granted, or for damages to the property of the Lessee, or for
              damages to the property or injuries to the person of the
             Lessee's officers, agents or employees or others who may be
              on the Leased Premises at their invitation or the invitation of
              any one of them, and the Lessee shall indemnify and hold the
              United States harmless from any and all such claims, not
            , including damages due to the fault or negligence of the
              United States or its contractors.

                      b. The Army shall hold harmless, defend, and
              indem.riify in full the Lessee and any successor, assignee,
              transferee, lender, or sublessee of the Lessee as provided for
              in, and subject to the conditions set out in, Section 330 of the
              Department of Defense Authorization Act of 1993, and to
              otherwise meet its obligations under the law. To the extent
              that these persons or entities contributed· to any such releases
              or threatened release, this indemnification shall not apply.
              The deed(s) of conveyance will include the covenants
              required by Section 120(h), 42 U.S.C., Section 9620(h).

                    c. The Lessee shall indemnify and hold harmless the
            · Government from any costs, expenses, liabilities, fines, or



                                              3
              penalties resulting from discharges, emissions, spills, storage,
              disposal, or any other action by the Lessee giving rise to
              Government liability, civil or criminal, or responsibility under
              Federal, state or local environmental laws.

(id. at GR4_ 68)

        The reference in paragraph b of the indemnification clause to Section 330
refers to Section 330 of the National Defense Authorization Act for Fiscal Year 1993,
Pub. L. 102-484, 106 Stat. at 2315, 2371, 10 U.S.C. § 2687 (note). This uncodified
provision provides, in relevant part, that:

              Except as provided in paragraph (3) and subject to subsection
              (b), the Secretary of Defense shall hold harmless, defend, and
              indemnify in full the persons and entities described in       _
              paragraph (2) from and against any suit, claim, demand or
              action, liability, judgment, cost or other fee arising out of any
              claim for personal injury or property damage (including
              death, illness, or loss of or damage to property or economic
              loss) that results from, or is in any manner predicated upon,
              the release or threatened release of any hazardous substance
              or pollutant or contaminant as a result of Department of
              Defense activities at any military installation (or portion
              thereof) that is closed pursuant to a base closure law.

106 Stat. at 2371. Paragraph 3 excludes from coverage "persons and entities" that
"contributed to any such release" (id. at 2372). Indemnification is not available, unless
the person or entity seeking indemnification "notifies the Department of Defense in
writing within two years after such claim accrues or begins action within six months after
the date of mailing, by certified or registered mail, of notice of final denial of the claim
by the Department of Defense" (id.).

        The reference in paragraph b of the indemnification clause to Section 120(h),
refers to the Comprehensive Environmental Response Compensation and Liability Act
(CERCLA, also known as Superfund) Section 120(h), 42 U.S.C. § 9620(h); requiring the
government to provide notice of the type and quantity of hazardous substances, a
description of remedial action taken and, relevant to this appeal, a covenant warranting
that all remedial action necessary to protect human health and the environment with
respect to hazardous substances remaining on the property has been taken prior to
transfer, and that any additional remedial action found to be necessary after the date of
transfer will be taken by the United States. 42 U.S.C. § 9620(h)(3)(A). However, the
covenant regarding remediation is not available to a "potentially responsible party," that



                                              4
is, a party that contributed to the contamination, with regard to that transferred property.
42 U.S.C. § 9620(h)(3)(B).

       Ford alleges in its claim, which we treat as its complaint, that in the late 1990s,
while removing fuel tanks, "contractors hired by the Army damaged a generator and
building located on the property" (R4, tab 3 at GR4_14). Ford additionally alleges that
"these claims have been discussed with Army representatives over phone and email over
the years" (id.). Ford's counsel asserts that "[t]he claim was actually made timely (years
ago) by the Appellant and the Respondent unilaterally informed the Appellant that it
would wait until the final deeds were executed to decide it" (app. resp. at 1), and that it
was "told repeatedly over the years that the proper time to submit a claim on the
generator and building damage was near the time frame when the final parcels would be
transferred" (app. opp'n at 12). Ford's counsel additionally speculated that it "is highly
probable that Army personnel who passed this information along to the Fords made
mistakes, since the 6-year statute of limitations on cfaims had just gone into effect the
year before" (id.).

        Additionally relevant to these appeals, the transferred property included portions
of over three miles of above-ground insulated steam lines. In the Jefferson Proving
Ground, South of the Firing Line; Final Asbestos Survey Summary Report: Volume IV
(Building 501 through Building 903), September 1993 report (Final Asbestos Report), the
Corps' contractor that drafted the report reported the presence of asbestos in the outside
overhead insulated steam lines. (R4, tab 7 at GR4_55) 2 On the record before us, there is
no evidence that this report was incorporated into the invitation for bids or the LIFOC. 3
The LIFOC does reference a "Draft Remedial Investigation for Jefferson Proving Ground
(July 1994)" that was to be attached as an exhibit to,the LIFOC (R4, tab 8 at GR4_73);
however, the exhibit is not contained in the Rule 4 file submitted by the government, or
in the version of the LIFOC submitted by appellant. The Final Asbestos Report was
referenced in the Finding of Suitability to Transfer Remaining Parcels, March 2010 (app.
supp. R4, tab A at Ford-53, 62, 67) and the Finding of Suitability to Transfer Remaining
Parcels 1-7, December 2014 (R4, tab 11 at GR4_211).

       In the fall of 2010, Jim Reed, a former employee of Ford, approached Ford for
permission to remove old steam pipes on the property, in exchange for the scrap metal
(app. supp. R4, ex. 2, Ford decl. 'if'if 7-8; R4, tab 5 at 1). Mr. Ford told Mr. Reed that he

2
  Ford designated its claim documents as its complaints in these appeals. While we cite
       to certain facts relevant to appeal no. 61619 submitted by the government that go
       beyond the claim documents, we still consider them in the light most favorable to
       Ford.
3
  We note that that invitation for bids contained in the Rule 4 file is missing exhibit D
       "Community Environmental ·Response Facilitation Act Report/ Draft Remedial
       Investigation" (R4, tab 8 at GR4_61).

                                               5
was not authorized to give permission and that Mr. Reed would need to obtain
permission from the Army (id. 17). Mr. Reed subsequently obtained permission from
Ken Knauf, Army site manager, who stated that the pipe contained plaster ofparis, so he~
had no objection. The work was additionally performed with the knowledge of
Paul Cloud, the Army's environmental coordinator (id at ex. A). According to Mr. Ford,
the "pipes had been deteriorating for years, and had even fallen on the ground in some
places" and constituted a health and safety hazard (id. 17). Mr. Reed additionally alleges
thafapproximately a quarter of the insulation was already on the ground, and that the
Army ~ould simply pick-up fallen pieces of insulation. Mr. Reed additionally stated that
fallen insulation was "mowed over" by department of corrections prisoners "for years"
(id. at ex. A). Mr. Lamb, who works in a building on the former Jefferson Proving
Ground additionally provided a declaration that the insulation was decaying and "was
falling off every time there was a storm" (id at ex. B).

       Ford was subsequently contacted by the Indiana Department of Environmental
Management(IDEM) regarding asbestos contamination from the steam pipes. Ford hired
an asbestos contractor to clean-up the contamination and incurred costs for the clean-up,
plus a fine from the IDEM, and attorney fees (id. 119-1 O; R4, tabs 5, 9).

        In December 2014, the government issued a FOST for the remaining parcels to be
transferred to Ford. The FOST included, in Enclosure 9, environmental restrictions and
restrictive covenants for the transfei;red property. The FOST provides that that deed will
prohibit residential use of parcels 1 through 4 and part of parcel 5, as well prohibiting the
use of groundwater on parcels 2 and 4 and part of parcel 5, and restrictions on
excavations for parcel 1. (R4, tab 11 at GR4_234)

       In a letter dated November 14, 2017, Ford asserted a certified claim in the amount
of $197,000 for the damaged generator and building, based on price quotes provided in
2009 and 2010, for the damage purportedly caused in the "late 1990's" (R4, tab 3). The
claim letter asserts that "[o]ver the 20-year duration of our Lease in Furtherance of
Conveyance, Army personnel have advised us to wait to submit claims until the final
parcels of [Jefferson Proving Ground] are near to the time of transfer" (id.). The
government did not issue a final decision on Ford's claim and Ford appeals from the
deemed denial of the claim. This' claim was docketed by the Board as ASBCA
No. 61617.

        In a second letter, with the same date, Ford asserted a claim regarding land use
restrictions placed on parcels 1 through 7 in the final FOST, including a restriction
against residential use for a portion of the property (R4, tab 4 at GR4_18). In the
document Ford alternatively requests that the government "please remove residential
restrictions" or provide "a ~orresponding reduction in the purchase price of the land" (id.
at GR4_19-20). Ford's letter does not request a specific reduction on the amount of the
purchase price for the land, rather it notes that purportedly similar building lots near the


                                              6
    property in question are assessed "at or above $20,000 per acre" (id. at GR4_19). Ford
    notes that 123 of 770 ac.res in question could be valued at $2,575,620 at the assessed
    values, before noting that the remaining acreage is "not as valuable" but that' the "interior
    woods certainly suffers from these restrictions as well." (Id. at GR4_19-20) Ford refers
    to lost rental income of $864,POO over the next 30 years for parcel 5 (id. at GR4_18).
    The claim does not address the reduction in value of parcels 2-4, 6, and 7. In a final
    decision dated February 13, 2018, the Corps contracting officer denied the claim on the
    basis that the claim failed to set forth a sum certain (R4, tab 1). On appeal to the Board,
    this claim was docketed as ASBCA No. 61618.

            In a third letter, again with the same date, Ford asserted a claim for expenses
    incurred in remediating asbestos from the above ground steam pipes. The claim asserts
    that the government authorized a contractor to remove steam pipes from the property,
    still owned by the government, in exchange for the scrap metal recovered. The letter also
    asserts that the government monitored the progress of the contractor; and that the
    dismantled steam pipes exposed material that was later determined to be asbestos. IDEM
J   notified Ford and the government of an environmental hazard and the government
    refused to acknowledge its involvement and Ford was forced to perform remediation
    activities on the property at a cost of $457,259, including a fine assessed by IDEM, and
    attorney fees (R4, tab 5 at GR4_21-22). In a final decision dated February 14, 2018 the
    contracting officer denied Ford's claim, finding that Ford had failed to request written
    permission from the government to make any alterations to the property and the lease
    expressly placed liability for cleanup of hazardous materials on Ford, and that Ford was
    to indemnify the government for any costs of environmental remediation (R4, tab 2
    at GR4_11). Ford appealed to the Board from the final decision and the appeal was
    docketed as ASBCA No. 61619.

                                            DECISION

    I.     Standard Of Review

          Ford bears the burden of proving the Board's subject matter jurisdiction by a
    preponderance of the evidence. Reynolds v. Army & Air Force Exchange Service,
    
846 F.2d 746
, 748 (Fed. Cir. 1988); United Healthcare Partners, Inc., ASBCA
    No. 58123, 13 BCA 1J 35,277 at 173,156.

           We will grant summary judgment only if there is no genuine issue as to any
    material fact, and the moving party is entitled to judgment as a matter of law. Celotex
    Corp. v. Catrett, 
477 U.S. 317
, 322 (1986). A material fact is one that may affect the
    outcome of the decision. Anderson v. Liberty Lobby, Inc., 
477 U.S. 242
, 248-49 (1986).
    The moving party bears the burden of establishing the absence of any genuine issue of
    material fact, and all significant doubt over factual issues must be resolved in favor of the
    party opposing summary judgment. Mingus Constructors, Inc. v. United States, 
812 F.2d 7
1387, 1390 (Fed. Cir. 1987). Once the moving party has met its burden of establishing
the absence of disputed material facts, then the non-moving party must set forth specific
facts, not conclusory statements or bare assertions, to defeat the motion. Pure Gold, Inc.
v. Syntex (US.A.), Inc., 
739 F.2d 624
, 626-27 (Fed. Cir. 1984).              .

II.      Appeal No. 61617 -Damage To Generator And Building

        The government moves to dismiss appeal number 61617 as untimely because it
was not brought within six years of accrual of the claim (gov't mot. at 7). Pursuant to
statute, a claim must be submitted within six years of accrual of the claim. 
41 U.S. C
.
§ 7103(a)(4)(A). · We interpret the term "accrual of the claim" based upon the definition
in the Federal Acquisition Regulation (FAR). See, Kellogg Brown & Root Services, Inc.
v. Murphy, 823 F.3d 622,626 (Fed. Cir. 2016). The FAR defines accrual of a contract
claim, in relevant part, as the "date when all events, that fix the alleged liability of either
the Government or the contractor and permit assertion of the claim, were known or
should have been known." FAR 33.201.

        Here, Ford alleges that the government damaged a generator and a building in "the
late 1990s" (R4, tab 3 at GR4_14). Ford's claim is dated November 14, 2017, or roughly
twenty years after the cause of action accrued. Thus, Ford's claim is time-barred, unless
it can establish that it submitted a valid claim at an earlier date, 4 or that it was under an
infirmity sufficient to toll the statute of limitations.

        Ford asserts that the "claim was actually made timely (years ago) by the Appellant
and the Respondent unilaterally informed the Appellant that it would wait until the final
deeds were executed to decide it" (app. resp. at 1). However, Ford cites to no record
evidence in support of this statement. While Mr. Ford submitted a declaration in
response to the Board's order informing the parties that it would treat the government's
motion as a motion for summary judgment, his declaration does not address this issue.
When a motion to dismiss denies or controverts allegations of jurisdiction, only
uncontroverted factual allegations are accepted as true for purposes of the motion, and
other facts underlying the jurisdictional allegations are subject to fact-finding.
Cedars-Sinai Medical Center v. Watkins, 
11 F.3d 1573
, 1583-84 (Fed. Cir. 1993);
Arbaugh v. Y&H Corp., 
546 U.S. 500
, 514 (2006). The facts supporting jurisdiction are
subject to fact-finding by the Board based on our review of the record. CCIE & Co.,
ASBCA Nos. 58355, 59008, 14-1 BCA 'if 35,700 at 174,816; Raytheon Missile Sys.,
ASBCA 58011, 13 BCA 'if 35,241 at 173,016. As the burden is on Ford to establish
jurisdiction, we find that Ford has not established that it submitted a claim prior to the
one submitted on November 17, 2017.

4
    Assuming the most generous possible interpretation of "the late 1990's" possible Ford's
        claim would have needed to be submitted on or before December 31, 2005 to be
        within the 6-year statute of limitations.

                                               8
       The Board has held that the CDA's six-year statute oflimitations "may be
equitably tolled when a litigant has (1) been pursuing his rights diligently, and (2) some
extraordinary circumstance 'stood in his way and prevented timely filing.'" Adamant
Group for Contracting and General Trading, ASBCA No. 60316, 16-1 BCA 1J 36,577
at 178,136, citing Menominee Indian Tribe of Wis. v. United States, 
136 S. Ct. 750
, 755
(2016). In addition, equitable tolling is available "where the complainarit has been
induced or tricked by his adversary's misconduct into allowing the filing deadline to
pass." Environmental Safety Consultants, 
97 Fed. Cl. 190
, 200-01 (2011), citing Irwin v.
Dep 't of Veterans Affairs, 
498 U.S. 89
, 96 (1990). As we noted in Raytheon Missile
Systems, in the absence of trickery, once a claim has accrued and the statute of limitations
begins to run, "subsequent communications between [the contractor] and the government
about the claim's merits and magnitude [do] nothing to toll it." Raytheon Missile Systems,
13 BCA 1J 35,241 at 173,018.

        Here, Ford's claim5 asserts that "[o]ver the 20-year duration of our Lease in
Furtherance of Conveyance, Army personnel have advised us to wait to submit claims
until the final parcels of [Jefferson Proving Ground] are near to the time of transfer" (R4,
tab 3 at GR4 14). Ford's counsel asserts, without any citation to record evidence, that
"[t]he claim was actually made timely (years ago) by the Appellant and the Respondent
unilaterally informed the Appellant that it would wait until the final deeds· were executed
to decide it" (app. resp. at 1). In response to the Board's order informing the parties that
it would treat the government's motion as one for summary judgment and stating that
Ford "should provide such relevant evidence in the form of declarations in response to
this order" Ford responded only with statements of counsel to the effect that the Fords
were "told repeatedly over the years that the proper time to submit a claim on the
generator and building was near the time frame when the final parcels would be
transferred" (app. opp'n at 12). Ford's declaration does not address this issue. Counsel
additionally speculated that it "is highly probable that Army personnel who passed this
information along to the Fords made mistakes, since the 6-year statute of limitations on
claims had just gone into effect the year before" (id.).

        Even assuming that the statements of counsel in opposition to the government's
motion were sworn statements, they would not be sufficient to support tolling of the
statute of limitations. At best, Ford makes a vague allegation that, in an unspecified
number of instances, at unspecified times over a 20-year period, unspecified "Army
personnel" informed him to wait until the time of transfer to assert his claim. Ford's
statements do not allege that these statements were made by a contracting officer or other
individual with authority to bind the government, nor does Ford explain why he did not
review the terms of the LIFOC, which specifies the procedure for asserting a claim (R4,
tab 8 at GR4_ 70-71 ). To establish equitable tolling, the party advocating tolling must
demonstrate that it has been pursuing its rights diligently. We find that Ford has not

5
    Absent more, an assertion included in a claim does not constitute evidence.

                                               9
satisfied this requirement. Additionally, the party advocating equitable tolling must
establish that some extraordinary circumstance prevented it from timely filing its claim.
Here, Ford does not allege any such extraordinary disability.

        To the extent Ford is alleging that the government provision of incorrect
information about filing its claim constitutes an extraordinary circumstance, we reject
that claim. The courts have found, in rare instances, that "trickery" can be a basis for
equitable tolling; however, here, Ford alleges error on the party of the government, rather
than trickery or an intent to deny Ford its right to present its claim (app. opp'n at 12). 6
Accordingly, we find that Ford has not established equitable tolling and grant the
government's motion to qismiss ASBCA No. 61617.

III.     ASBCA No. 61618 -Failure To State Sum Certain

        The government moves to dismiss ASBCA No. 61618 on the grounds that Ford
fails to assert a valid claim because its demand included no sum certain (gov't mot.
at 8-9). Pursuant to the CDA, a contractor may, "within 90 days from the date of receipt
ofa contracting officer's decision" under 41 U.S.C. § 103 "appeal the decision to an
agency board as provided in" section 7105. 41 U.S.C. § 7104(a). Our reviewing court,
the Federal Circuit, has held that CDAjurisdiction requires both a valid claim and a
contracting officer's final decision on that claim. M Maropakis Carpentry, Inc. v. United
States, 
609 F.3d 1323
, 1327 (Fed. Cir. 2010) (citing James M Ellett Constr. Co. v.
United States, 
93 F.3d 1537
, 1541-42 (Fed. Cir. 1996)). The FAR defines a claim as a
"written demand or written assertion by one of the contracting parties seeking, as a matter
of right, the payment of money in a sum certain.... " FAR 2.101. The Federal Circuit has
held that an additional jurisdictional requirement is that a claim be submitted in writing
and contain a "clear and unequivocal statement that gives the contracting officer adequate
notice of the basis and amount of the claim." Contract Cleaning Maintenance, Inc. v.
United States, 
811 F.2d 586
, 592 (Fed. Cir. 1987); 
Maropakis, 609 F.3d at 1327
. "The
statement of claim must provide a basis for meaningful dialogue between the parties
aimed toward settlement or negotiated resolution of the claim if possible, or for adequate
identification of the issues to facilitate litigation should that be necessary." Blake
Constr., Co., ASBCA No. 34480 et al., 88-2 BCA, 20,552 at 103,890; see also Holk
Development, Inc., ASBCA Nos. 40579, 40609, 90-3 BCA, 23,086 at 115,939.

       Here, Ford's letter purporting to be a claim requests alternatively that the
government "please remove residential restrictions" or provide "a corresponding
reduction in the purchase price of the land" (R4, tab 4 at GR4_19-20). Ford's letter does

6
    We note that the LIFOC initially had a five year term. If the damage alleged to have
        occurred in the late 1990s happened before the term of the LIFOC was extended to
        50 years, a government employee statement to wait until the end of the lease
        would not have raised a statute of limitations issue.

                                             10
not request a specific reduction on the amount of the purchase price for the land, rather it
notes that purportedly similar building lots near the property in question are assessed ''at
or above $20,000 per acre" (id. at GR4_19). Ford notes that at 123 of 770 acres in
question could be valued at $2,575,620 at the assessed values (id. at GR4_20).

        To the extent Ford seeks a Board award compelling the government to remove the
residential restrictions from the deed, such a request would constitute a valid claim;
however it would be a request for specific performance which we lack jurisdiction to
entertain. See, e.g., Versar, Inc., ASBCA No. 56857, 10-1BCA134,437 at 169,959.
The Board does possess jurisdiction to entertain a claim for a monetary adjustment to the
purchase price of the property. However, here, we find that Ford did not assert a valid
claim because it does not request a sum certain. While Ford's counsel represents that the
claim .could be treated as one for $2,575,620, such representations to the Board cannot
correct a deficient claim. Such a resolution would deprive the contracting officer of the
ability to review Ford's claim in the first instance. Even ifwe were inclined to treat the
$2,575,620 amount as a sum certain, Ford's claim implies that this amount represents
compensation for only aportion of the property. Ford's claim letter states that there are
deed restrictions in the final POST. (R4, tab 4 at GR4_18). Ford refers to lost rental
income of $864,000 over_ the next 3 0 years for parcel 5 (id.). Ford then "highlights the
effect on Parcel 1" in computing damages of $2,575,620 for 123 of770 c1,cres in parcel 1,
before noting that the remaining acreage is "not as valuable" but that the "interior woods
certainly suffers from these restrictions as well" (id. at GR4_19-20). The letter does not
address the reduction in value of parcels 2-4, 6, and 7. The CDA "requires that claims
for monetary relief must be quantified as to amount before the contracting officer is
obligated to issue a final decision." Liberty Painting Co., ASBCA No. 39562, 91-1 BCA
123,561 at 118,119. Thus, we hold that Ford's letter has not set forth a valid claim
because it does not assert a sum certain. We grant the government's motion to dismiss
ASBCA No. 61618.

IV.    ASBCA No. 61619 -Asbestos Remediation

        The government seeks summary judgment on this count, asserting that there is "no
obligation on the part of the government under the contract or under state or federal law
to indemnify the lessee for penalties resulting from violations of the law" (gov't mot.
at 10). The government notes that Ford was on notice of the existence of asbestos in the
steam pipes and that Ford failed to comply with the LIFOC by obtaining written
permission from the government for the work (id. at 11). Ford alleges that there is a
factual issue in dispute regarding the responsibility for asbestos abatement with regard
to the steam pipes and that this prevents the entry of summary judgment (app. opp'n
at 9-10). Ford further relies upon the holding of the Court of Federal Claims in
Richmond American Homes of Colorado, inc. v. United States, 
75 Fed. Cl. 376
(2007)
finding the government liable for asbestos remediation in the base alignment and closure
context pursuant to Section 330 of the National Defense Authorization Act for Fiscal


                                             11
Year 1993, Pub. L. 102-484, 106 Stat. at 2315, 2371, 10 U.S.C. § 2687 (note) (id.). The
government responds that any claim pursuant to Section 330 would be time-barred under
that provision's two-year statute oflimitations (gov't reply br. at 7-9).

        The BRAC process protects purchasers of former base property in two ways.
First, the base closure act requires conveyances of property to contain CERCLA section
120(h), 42 U.S.C. § 9620(h), requiring the government to provide notice of the type and
quantity of hazardous substances, a description of remedial action taken and, relevant to
this appeal, a covenant warranting that all remedial action necessary to protect human
health and the environment with respect to hazardous substances remaining on the
property has been taken prior to transfer, and that any additional remedial action found to
be necessary after the date of transfer will be taken by the United States. 42 U.S.C.
§ 9620(h)(3)(A). However, the covenant regarding remediation is not available to a
"potentially responsible party," that is, a party that contributed to the contamination, with
regard to that transferred property. 42 U.S.C. § 9620(h)(3)(B).

        The second protection provided in the transfer of BRAC properties is Section 330
of the NDAA. That provision provides that the Secretary of Defense will: "hold
harmless, defend, and indemnify" purchasers ofBRAC properties "from and against any
suit, claim, demand or action, liability, judgment, cost or other fee arising out of any
claim for personal injury or property damage" resulting from "the release or threatened
release of any hazardous substance" as a result ofDoD activities. 106 Stat. at 2371.
Paragraph 3 excludes from coverage "persons and entities" that "contributed to any such
release" (id. at 2372). Indemnification is not available, unless the person or entity
seeking indemnification "uotifies the Department of Defense in writing within two years
after such claim accrues or begins action within six months after the date of mailing, by
certified or registered mail, of notice of final denial of the claim by the Department of
Defense" (id.).

        We first turn to CERCLA § 120(h), which provides a covenant requiring the
government to remediate health and safety issues discovered after transfer. While the
government asserts that the existence of asbestos insulation on the above-ground steam
pipes was known and had been disclosed to Ford (R4, tab 7 at GR4_55), the record
before us is not sufficiently developed to support the entry of summary judgment in favor
of the government. The record before us does not establish that the Final Asbestos
Report was disclosed in the LIFOC, although it was disclosed in FOSTs that are part of
the record (R4, tab 11 at GR4_211; app. supp. R4, tab A at Ford-53, 62, 67). Moreover,
the Final Asbestos Report disclosed asbestos in the steam pipes, but did not address
fallen asbestos in the soil, at least in the portion of the report included in the record. Ford
has supported with declarations statements that the steam pipe insulation was falling off
of the steam lines and had been run-over by lawnmowers "for years" and that the pipes
were a health and safety hazard (app. supp. R4, ex.' 2, Ford. decl. ,r 7, exs. A, B). We
note that the LIFOC disclaims indemnity on behalf of the government "to the extent that


                                              12
the [transferee] contributed to any such release or threatened release" (R4, tab 8
at GR4_68; see also 42 U.S.C. § 9620(h)(3)(B)). However, the Court of Federal Claims
has found similar indemnity language to be ambiguous. See American Inter. Specialty
Lines Ins. Co. v. United States, No. 05-1020C, 
2008 WL 1990859
at *17 (Fed. Cl.
Jan. 3l,2008)(AISLIC).

        AISLIC involved claims for remediation costs for chlordane and organochlorine
pesticides (OCPs) applied by the Navy prior to BRAC transfer of property that was part
of the Naval Air Station Alameda. 
Id. at* 1.
The AISLIC court reasoned that the "release
or threatened release" could apply to the release of the OCPs prior to transfer or the
release caused by demolition of buildings (which had been sprayed with OCPs) after
transfer. 
Id. at* 17.
Similarly here, we find paragraph 14(b) of the LIFOC to be
ambiguous (R4, tab 8 at GR4_68). Ford's statements, read in the light most favorable to
the non-moving party, assert that the government was responsible for releases of asbestos
in the soil from asbestos falling off the steam lines over a period of years, and further was
responsible for authorizing Mr. Reed's removal of the overhead steam line. Thus,
pursuant to the facts presented we cannot find that the government bears no responsibility
for the remediation costs.

        Similarly, the LIFOC provides that Ford will indemnify and hold harmless the
government from claims for damages to the property, this indemnification does not
include "damages due to the fault or negligence of the United States or its contractors"
(R4, tab 8 at GR4_68). Thus, to the extent Mr. Reed alleges he was given permission by
the Army to remove the steam lines, we cannot find that Ford is exclusively responsible
for the asbestos remediation. Thus, on the record before us, which appears to be missing
several re_levant documents, we cannot find that the government is not responsible for any
of the release of asbestos.

        With regard to a claim for reimbursement pursuant to.Section 330 of the NDAA,
we similarly find that factual issues prevent entry of summary judgment. The
government did not address Section 330 in its motion to dismiss. After the Board
informed the parties that it would treat the motion as a motion for summary judgment,
Ford raised the Section 330 issue by citing Richmond American Homes (app. opp'n
at 8-10) which had held that Section 330 makes the government liable for environmental
remediation costs on BRAC properties. The government raised the section's two-year
statute of limitations as a defense in its supplemental reply.(gov't reply at 7-9).

         The Court of Appeals for the ·Federal Circuit has held that a claim for remediation
  costs pursuant to action by a state regulator states a claim for indemnification pursuant to
  Section 330. Indian Harbor Ins. Co. v. United States, 
704 F.3d 949
, 956 (Fed. Cir .
. 2013). Board precedent holds that we have jurisdiction, pursuant to the CDA, to
  entertain a claim pursuant to Section 330 based upon the indemnification provisions in a



                                              13
LIFOC. New London Development Corp., ASBCA No. 54535, 05-2 BCA 133,018
at 163,637.

        The government's motion treats Section 330's requirement for a claim as
requiring a CDA claim. However, the plain language of the statute, and case law, do not
support this interpretation. The language of Section 330 requires that the "person or
entity making a claim for indemnification ( 1) notif1y] the Department of Defense iri
writing within two years after such claim accrues." 106 Stat. at 2372. The language
"claim for indemnification" does not imply that a CDA claim is required. The
requirement is simply that the party "notifl:y]" the "Department of Defense" (id.). The
statute does not require that the notification contain the elements of a CDA claim (viz.
certification of claims over $100,000, a statement that the claim is made in good faith,
etc.) and, notably, the claim for indemnification is required to be made to the
"Department of Defense" and not the contracting officer. Moreover, we note that the
appeal period contained in section 330 is six-months (id.), and not the appeal period for a
CDA claim.                      .

        Additionally, we note that the Court of Federal Claims has asserted jurisdiction to
entertain Section 330 claims pursuant to its Tucker Act jurisdiction to entertain non-CDA
contracts with the government. See, e.g., Indian Harbor Ins. Co. v. United States, 100
Fed. Cl. 239,242 (2011), rev'd on other grounds 
704 F.3d 949
(Fed. Cir. 2013);
Richmond American 
Homes, 75 Fed. Cl. at 385
. While the Board has the power to
determine its jurisdiction sua sponte, here, where the government raised the statute of
limitations defense for the first time in its reply brief, 7 we believe further development of
the factual record is necessary before deciding the issue and deny the government's
motion.




7
    The parties have not addressed whether the statute of limitations in Section 330 is
         jurisdictional. See Sikorsky Aircraft Corp. v. UnitedStates, 
773 F.3d 1315
,
          1321-22 (Fed. Cir. 2014) (holding that the CDA's statute of limitations is not
         jurisdictional).                                        ·

                                               14
                                   CONCLUSION ,

     For the reasons stated above, we grant the government's motion to dismiss
ASBCA appeals number 61617 and 61618 but deny the government's motion for
summary judgment with regard to ASBCA number 61619.

      Dated: August 1, 2019




                                               DAVID D' ALESSANDRIS
                                               Administrative Judge
                                               Armed Services Board
                                               of Contract Appeals

                                               I concur




 OWEN C. WILSON                                J. REID PROUTY
 Administrative Judge                          Administrative Judge
 Acting Chairman                               Vice Chairman
 Armed Services Board                          Armed Services Board
 of Contract Appeals                           of Contract Appeals


      I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA Nos. 61617, 61618, 61619,
Appeals of Ford Lumber & Build Supply, Inc., rendered in conformance with the Bo~rd's
Charter.

      Dated:



                                               PAULLAK. GATES-LEWIS
                                               Recorder~ Armed Services
                                               Board of Contract Appeals




                                         15

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer