Judges: Shackleford
Filed: Sep. 30, 2020
Latest Update: Oct. 13, 2020
Summary: ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Sweet Star Logistic Service ) ASBCA No. 62082 ) Under Contract No. W91B4N-18-P-5056 ) APPEARANCE FOR THE APPELLANT: Ms. Sweeta Rahimi President APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney LTC Stephen M. Hernandez, JA Trial Attorney OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD ON THE GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION The government moves to dismiss this appeal for lack of subject matt
Summary: ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Sweet Star Logistic Service ) ASBCA No. 62082 ) Under Contract No. W91B4N-18-P-5056 ) APPEARANCE FOR THE APPELLANT: Ms. Sweeta Rahimi President APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney LTC Stephen M. Hernandez, JA Trial Attorney OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD ON THE GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION The government moves to dismiss this appeal for lack of subject matte..
More
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Sweet Star Logistic Service ) ASBCA No. 62082
)
Under Contract No. W91B4N-18-P-5056 )
APPEARANCE FOR THE APPELLANT: Ms. Sweeta Rahimi
President
APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq.
Army Chief Trial Attorney
LTC Stephen M. Hernandez, JA
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD ON THE
GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION
The government moves to dismiss this appeal for lack of subject matter
jurisdiction, alleging that appellant failed to submit a certified claim in accordance with
the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109. However, because we find
that appellant’s purported claim lacked a sum certain, we dismiss this appeal for lack of
jurisdiction.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. On September 4, 2018, the United States Army (government) awarded Contract
No. W91B4N-18-P-5056 (contract) to Sweet Star Logistic Service (Sweet Star or
appellant) for the delivery of information technology equipment and cable supplies at a
total contract price of 14,051,489.13 AFN ($203,644.77) (R4, tab 1 at 1, 3).
2. By email dated September 13, 2018, the government reiterated to Sweet Star
that in accordance with FedBid terms (see R4, tab 4), appellant was to be paid in local
Afghanistan currency (AFN) (R4, tab 12 at 1).
3. By email dated October 31, 2018, subsequent to delivery and inspection of the
contract items, the government notified appellant that some of the items were missing,
damaged, and non-conforming to the contract specifications (R4, tab 29 at 1).
4. By email dated December 7, 2018, the contracting officer (CO) informed
appellant it was not responsible for items that came up missing due to the fact a
government representative attested that all items were accounted for upon delivery (R4,
tab 58 at 1).
5. On December 10, 2018, the government issued a purported bilateral contract
modification, 1 changing the unit price of contract line item number 0001 (CLIN 0001).
CLIN 0001 was changed from 12,985,439.13 AFN ($188,194.77) to 5,795,103.69
($83,987.01) (a decrease of 7,190,335.44 AFN ($104,207.76)). The purpose of the
modification was to “deobligate the funding that represent[ed] the total for the items that
were returned to the customer.” (R4, tab 60 at 1)
6. By email dated January 11, 2019, the government notified appellant it had until
January 24, 2019 to collect all non-conforming contract items, as the government would
not be delivering said items to appellant. The government informed appellant that after
January 24, 2019, any non-conforming items that had not yet been collected would be
considered “abandoned,” leaving the government to dispose of the items in accordance
with agency procedures. (R4, tab 74 at 1)
7. At the conclusion of the January 24, 2019 deadline, appellant failed to collect
its non-conforming contract items (see R4, tab 80 at 1).
8. By email dated March 25, 2019, appellant submitted to the CO a request for
payment stating the following:
Hope you Doing well, [sic] I am Contacting you concerning
the Contract Number W91B4N18P5056 Lifted Materials, as
you know [sic] We have received about 45% Payment of the
subject Contract but our 55% Materials are with your
customer which they have not return [sic] the materials [sic]
Please computerize with us when you will going to pay for
the materials your customer keep it there [sic]
Please Finalize your decision concerning that materials if Gov
[sic] will not pay for it why they keep those materials we are
going to Apply for Appeal in Armed Service Board of Appeal
(ASBCA)
[T]his is our Final Notice to going for Appeal after that we
hope the [B]oard get the right Decision of this.
1 The contract modification was only signed by the government. The record before the
Board does not provide a December 10, 2018 contract modification signed by both
the government and appellant.
2
The request for payment did not include a sum certain, nor did the request contain
the claim certification set forth at 41 U.S.C. § 7103(b)(1). (R4, tab 90 at 1)
9. The government considered appellant’s March 25, 2019 email to be a claim for
the amount by which the contract was reduced, or $104,207.76. By email dated May 16,
2019, the government instructed appellant to certify its purported claim, as it exceeded
$100,000. (R4, tab 92) Notwithstanding the government’s assumption as to amount, we
are not persuaded that the claim included a sum certain.
10. By email dated May 18, 2019, the CO issued a final decision denying
appellant’s purported claim in part. The CO accepted 29,849.40 AFN ($432.60) of
appellant’s purported claim, and denied the remaining balance of 7,160,486.04
($103,775.16). (R4, tab 93 at 1, 3, 5)
11. By email dated May 23, 2019, appellant timely filed a notice of appeal to the
Board, which the Board docketed as ASBCA No. 62082.
DECISION
Appellant bears the burden of establishing the Board’s jurisdiction by a
preponderance of the evidence. Naseem Al-Oula Co., ASBCA No. 61321 et al., 20-1
BCA ¶ 37,490 at 182,148 (citation omitted). Under the CDA, the Board’s jurisdiction is
predicated upon a contractor’s submission of a claim to the CO for decision. See 41
U.S.C. § 7103(a)(1). The CDA does not define what a claim is; however, the Federal
Acquisition Regulation (FAR) defines a claim as “a written demand or written assertion
by one of the contracting parties seeking, as a matter of right, the payment of money in a
sum certain, the adjustment or interpretation of contract terms, or other relief arising
under or relating to the contract.” FAR 2.101. For any contractor claim that exceeds
$100,000, the contractor must certify that:
a) the claim is made in good faith;
b) the supporting data are accurate and complete to the best
of the contractor’s knowledge and belief;
c) the amount requested accurately reflects the contract
adjustment for which the contractor believes the Federal
Government is liable; and
3
d) the certifier is authorized to certify the claim on behalf of
the contractor.
41 U.S.C. § 7103(b)(1). A purported contractor claim in excess of $100,000 does not
become a claim under the CDA until it is certified as required by statute. FAR 2.101.
“[W]here there is no claim there can be no effective decision from which to appeal.”
Mawaraa AlBihar Co., ASBCA No. 58585, 13 BCA ¶ 35,426 at 173,783.
The government moves to dismiss this appeal, contending that the Board lacks
jurisdiction over appellant’s purported claim, which the government asserts exceeded
$100,000, and was not certified in accordance with the CDA (gov’t mot. at 1).
Appellant’s response focuses on the merits of the appeal, failing to address the
jurisdictional issues (app. resp.). We have found that appellant’s request for payment did
not include a claim certification (SOF ¶¶ 8-9). However, because we conclude that
appellant’s purported claim did not include a sum certain, and therefore, was not a valid
claim, we need not address the issue of a lack of a claim certification.
It is well settled, for the purposes of the Board’s jurisdiction, a contractor’s
monetary claim must be submitted to the CO in a sum certain. Equine Architectural
Products, Inc., ASBCA No. 59743, 15-1 BCA ¶ 36,004 at 175,873 (citation omitted).
This Board views a claim is set forth in a sum certain whenever the contractor has
submitted in writing to the CO ‘“a clear and unequivocal statement that gives the
contracting officer adequate notice of the basis and amount of the claim.”’ Precision
Standard, Inc., ASBCA No. 55865, 11-1 BCA ¶ 34,669 at 170,788 (quoting Contract
Cleaning Maintenance, Inc. v. United States,
811 F.2d 586, 592 (Fed. Cir. 1987)). In an
appeal where the gravamen of the claim is money, a contractor cannot avoid the
requirement for a sum certain. Eaton Contract Services, Inc., ASBCA No. 52888 et al.,
02-2 BCA ¶ 32,023 at 158,268 (citation omitted).
In appellant’s March 25, 2019 purported claim, it states it has received about
forty-five percent payment, but that fifty-five percent of its materials remain with the
government. There is no mentioning of a dollar amount requested anywhere in
appellant’s March 25, 2019 purported claim. (SOF ¶ 8) Similarly, in Equine, appellant
submitted a purported claim for the return of materials and equipment, failing to provide
a sum certain. See Equine, 15-1 BCA ¶ 36,004 at 175,872. Appellant failed to describe
its monetary claim “with such particularity as to enable the CO to easily compute a sum
certain.”
Id. at 175,873. The Board concluded it was without jurisdiction.
Here, appellant’s purported claim is ambiguous, unclear, and gives the CO
inadequate notice of the basis and amount of the claim. Without providing a sum certain
that is readily calculable by simple arithmetic, see PHI Applied Physical Sciences, Inc.,
ASBCA Nos. 56581, 58038, 13 BCA ¶ 35,308, there is no claim over which the Board
has jurisdiction. Jurisdiction is a matter over which the Board lacks discretion, as
4
jurisdiction is a concept that is absolute; it either exists or it does not exist. Eaton, 02-2
BCA ¶ 32,023 at 158,266 (citation omitted). Without a proper sum certain in appellant’s
request to the CO, we conclude that there is no claim. Accordingly, the Board is devoid
of jurisdiction. 2
CONCLUSION
For the reasons set forth above, this appeal is dismissed for lack of jurisdiction.
Dated: September 30, 2020
RICHARD SHACKLEFORD
Administrative Judge
Acting Chairman
Armed Services Board
of Contract Appeals
I concur I concur
OWEN C. WILSON MICHAEL T. PAUL
Administrative Judge Administrative Judge
Vice Chairman Armed Services Board
Armed Services Board of Contract Appeals
of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 62082, Appeal of Sweet Star
Logistic Service, rendered in conformance with the Board’s Charter.
Dated: September 30, 2020
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
2 Should appellant chooses to resubmit its claim it must make sure it is in a sum certain
and if it exceeds $100,000 it must be certified as set forth in this opinion.
5