Elawyers Elawyers
Ohio| Change

USA for Use & Benefit of OLS v. Southwind Construction Service, 12-6132 (2013)

Court: Court of Appeals for the Tenth Circuit Number: 12-6132 Visitors: 64
Filed: Feb. 07, 2013
Latest Update: Feb. 12, 2020
Summary: FILED United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit FOR THE TENTH CIRCUIT February 7, 2013 Elisabeth A. Shumaker Clerk of Court THE UNITED STATES OF AMERICA (FOR THE USE AND BENEFIT OF O.L.S., INC., d/b/a OZARK LASER AND SHORING), Plaintiff-Appellant, v. No. 12-6132 SOUTHWIND CONSTRUCTION (D.C. No. 5:11-CV-00195-R) SERVICES, LLC, an Oklahoma (W.D. Okla.) corporation; SOUTHWIND CONSTRUCTION COMPANY, INC., an Oklahoma corporation; FIDELITY & DEPOSIT COMPANY OF MARYLAN
More
                                                              FILED
                                                  United States Court of Appeals
                     UNITED STATES COURT OF APPEALS       Tenth Circuit

                            FOR THE TENTH CIRCUIT                       February 7, 2013

                                                                      Elisabeth A. Shumaker
                                                                          Clerk of Court
THE UNITED STATES OF AMERICA
(FOR THE USE AND BENEFIT OF
O.L.S., INC., d/b/a OZARK LASER
AND SHORING),

             Plaintiff-Appellant,

v.
                                                          No. 12-6132
SOUTHWIND CONSTRUCTION                             (D.C. No. 5:11-CV-00195-R)
SERVICES, LLC, an Oklahoma                                (W.D. Okla.)
corporation; SOUTHWIND
CONSTRUCTION COMPANY, INC.,
an Oklahoma corporation; FIDELITY &
DEPOSIT COMPANY OF
MARYLAND, a Maryland corporation,

             Defendants-Appellees.


                            ORDER AND JUDGMENT*


Before ANDERSON and BALDOCK, Circuit Judges, and BRORBY, Senior Circuit
Judge.




*
      After examining the briefs and appellate record, this panel has determined
unanimously to grant the parties’ request for a decision on the briefs without oral
argument. See Fed. R. App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore
ordered submitted without oral argument. This order and judgment is not binding
precedent, except under the doctrines of law of the case, res judicata, and collateral
estoppel. It may be cited, however, for its persuasive value consistent with
Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.
      O.L.S., Inc. (“Ozark”) was a third-tier subcontractor on a federal construction

project at Tinker Air Force Base in Oklahoma. When it did not get paid for the

equipment it leased to a second-tier subcontractor, Ozark brought an action on the

payment bond against the first-tier subcontractor, the prime contractor, and the surety

under the Miller Act, 40 U.S.C. §§ 3131, 3133.1 The district court dismissed the suit

for lack of jurisdiction, concluding that because Ozark was a third-tier subcontractor,

it was not protected by the bond and could not sue under the Miller Act. Ozark

appeals, arguing that the prime contractor and the first-tier subcontractor should be

treated as a single, unitary prime contractor, thereby eliminating a tier of the

contractual structure and making Ozark a second-tier subcontractor entitled to

protection under the bond.

      In 2005, Southwind Construction Company, Inc. (“Southwind”) received a

multi-year Indefinite Duration, Indefinite Quantity contract from the government

known as a SABER contract. Over the course of five years, the government issued

multiple delivery orders to Southwind for maintenance, repair, and construction

services at Tinker Air Force Base. At issue here is an order issued to Southwind in

September 2009 to perform a project known as “Repair RAC FirePond” (“RAC

Project”). In connection with this project, Southwind, as principal, and Fidelity &

Deposit Company of Maryland (“Fidelity”), as surety, executed a payment bond.


1
   As required by the Miller Act, the suit was brought in the name of the United
States for the benefit and use of Ozark. See 40 U.S.C. § 3133(b)(3)(A).


                                          -2-
      Southwind subcontracted the majority of the work on the RAC Project to

Southwind Construction Services, LLC (“Services”), which then subcontracted part

of that work to Johnson & Johnson Utility (“Johnson”). Johnson later entered into a

contract with Ozark to lease equipment. The RAC Project had significant

cost-overruns, and Johnson failed to pay Ozark $22,288.21. Ozark seeks to recover

that amount from Southwind’s payment bond.

      The Miller Act requires every contractor who is awarded a government

construction contract of $100,000 or more to furnish a payment bond “for the

protection of all persons supplying labor and material in carrying out the work

provided for in the contract for the use of each person.” 
Id. § 3131(b)(2). The
Act

defines a “contractor” as “a person awarded a contract . . . for the construction,

alteration, or repair of any public building or public work of the Federal

Government.” 
Id. § 3131(a), (b).
The Act further provides that a person who

provides labor or material to the contractor may bring an action on the payment bond,

id. § 3133(b)(1), as
can “[a] person having a direct contractual relationship with a

subcontractor but no contractual relationship, express or implied, with the contractor

furnishing the payment bond,” 
id. § 3133(b)(2). Although
the Miller Act defines the term “contractor,” it does not define the

term “subcontractor.” The Supreme Court has held that Congress intended to give

the term its “technical meaning, as established by usage in the building trades.”

Clifford F. MacEvoy Co. v. U.S. ex rel. Calvin Tomkins Co., 
322 U.S. 102
, 108-109


                                          -3-
(1944). Accordingly, a “subcontractor” is “one who performs for and takes from the

prime contractor a specific part of the labor or material requirements of the original

contract.” 
Id. at 109. “[A]
contract with the prime contractor is a prerequisite to

being a ‘subcontractor.’” J.W. Bateson Co. v. U.S. ex rel. Bd. of Trs. of Nat’l

Automatic Sprinkler Indus. Pension Fund, 
434 U.S. 586
, 590 (1978).

      Looking at the contractual scheme here, Southwind, as the company that had

the contract with the government and posted the payment bond, was the prime

contractor. Services, as a company who had a contract with Southwind to take from

Southwind a part of the labor or material requirements of Southwind’s contract with

the government, was a subcontractor (or first-tier subcontractor). And Johnson,

which had a direct contract with Services but no contract with Southwind, was a

sub-subcontractor (or second-tier subcontractor) entitled to make a claim against the

payment bond. See 40 U.S.C. § 3133(b)(2). Ozark, which had no contract with

either Southwind or Services, was a third-tier subcontractor and had no right to make

a claim against the bond. See 
Bateson, 434 U.S. at 591-92
.

      Ozark argues, however, that the court should look at the substance, rather than

the form, of the parties’ respective contractual relationships and recognize that

although Services was nominally a subcontractor, in reality, it was the de facto prime

contractor. Accordingly, Ozark argues, the court should treat Southwind and

Services as a unitary prime contractor and Johnson as a first-tier subcontractor, which

would make Ozark a second-tier subcontractor entitled to protection under the Miller


                                          -4-
Act. Ozark relies on this court’s decision in Glens Falls Insurance Co. v. Newton

Lumber & Manufacturing Co., 
388 F.2d 66
(10th Cir. 1967), as authority for

disregarding the parties’ formal contractual relationships.

      In Glens Falls, two third-tier subcontractors sought the protection of the prime

contractor’s payment bond by arguing that the nominal first-tier subcontractor,

Campbell, was a sham and that the nominal second-tier subcontractor, Whiteside,

was the true first-tier subcontractor. Following a bench trial, the district court found

that Campbell was a sham; that he permitted DMH, the prime contractor, to use his

name in the contract with Whiteside in order to protect DMH; that DMH did not

intend to impose any contractual obligation on Campbell despite its contract with

him; that the purpose of executing a contract between DMH and Campbell and then a

contract between Campbell and Whiteside was to insulate DMH from liability to

Whiteside’s materialmen by making Campbell appear to be the subcontractor; and

that Campbell’s true relationship with DMH was that of employee or agent. 
Id. at 69. On
appeal, this court concluded that the district court “properly regarded

substance, rather than form,” in concluding that Whiteside was the true first-tier

subcontractor, because “[o]therwise, the purpose of the remedial statute, to protect

suppliers of materials to the actual subcontractors of the prime contractor, could be

defeated by setting up by formal contract a straw man as a subcontractor between the

prime contractor and one who in substance and intent is the actual subcontractor.”




                                          -5-

Id. at 69-70. We
therefore affirmed the district court’s judgments against DMH and

its surety in favor of the plaintiffs who supplied materials to Whiteside.

      Ozark argues that we should take a similar “substance over form” approach

here. But there are several impediments to doing so. First, it is not clear that this

court’s focus on “substance and intent” to determine “the actual subcontractor,”

id. at 70, is
still proper after the Supreme Court’s decision in Bateson. The Court in

Bateson acknowledged that, in earlier cases, it had taken a functional approach to

determining who is a subcontractor for purposes of the Miller 
Act. 434 U.S. at 593-
94. But it explained that in those previous cases, notably, MacEvoy and F.D. Rich

Co. v. U.S. ex rel. Industrial Lumber Co., 
417 U.S. 116
(1974), the party in question

had a “direct contractual relationship with the prime contractor” and the question

before the Court was whether that party qualified as a “subcontractor” or was merely

a supplier. 
Bateson, 434 U.S. at 594
. By contrast, in Bateson, where the employees

of a second-tier subcontractor sought to make a claim on the bond, the Court said that

a functional approach was improper because “the traditional tools of statutory

construction provide a definitive answer to the question before us.” 
Id. at 594. The
Court held that “the word ‘subcontractor’ must be limited in meaning to

one who contracts with a prime contractor.” 
Id. And although the
second-tier

subcontractor did have a direct contractual relationship with the first-tier

subcontractor, the second-tier subcontractor’s employees did not and were therefore

not entitled to make a claim against the bond. 
Id. at 591-92. “Congress
. . . intended


                                          -6-
the scope of protection of a payment bond to extend no further than to sub-

subcontractors.” 
Id. at 591. The
Court was “not unmindful of [its] obligation to

construe the highly remedial Miller Act liberal[ly] . . . in order properly to effectuate

the Congressional intent to protect those whose labor and materials go into public

projects.” 
Id. at 594 (second
& third alterations in original) (internal quotation marks

omitted). But “such a salutary policy does not justify ignoring plain words of

limitation and imposing wholesale liability on payment bonds.” 
Id. (internal quotation marks
omitted). The Court recognized the “importance of certainty with

regard to bonding practices on Government construction projects.” 
Id. at 592. Following
Bateson, it is not clear that anyone who does not have a direct

contractual relationship with either the prime contractor or a first-tier subcontractor

could legitimately make a claim against the payment bond, regardless of the actual

functions carried out by the respective parties. See U.S. ex rel. K & M Corp. v.

A & M Gregos, Inc., 
607 F.2d 44
, 47 (3d Cir. 1979) (“We agree that Bateson rules

out a holding that the court may look to the functions carried out by contracting

parties, rather than to the position they occupy in the contractual structure, to identify

the first-tier subcontractor.”). But even if it may still be possible after Bateson to

establish that a nominal first-tier subcontractor was merely a sham or alter ego of the

prime contractor so that the second-tier subcontractor’s contract with the nominal

first-tier subcontractor could be said, in reality, to have been with the prime

contractor, such a theory would not benefit Ozark.


                                           -7-
      First and foremost, Ozark does not seek to show that Services was a sham

subcontractor, so that Johnson’s subcontract should be deemed to have been directly

with Southwind. Ozark concedes that Services actually performed for and took from

Southwind a specific part of the labor or material requirements of Southwind’s

contract with the government. See 
MacEvoy, 322 U.S. at 109
(defining who is a

“subcontractor”). In fact, Ozark’s complaint is that Services took on and performed

too many of Southwind’s obligations and thus functioned more like a prime

contractor than a subcontractor. But the Miller Act quite clearly defines the prime

contractor as the person who is awarded the contract with the government and who

posts the surety bond. 40 U.S.C. § 3131 (a), (b). And Ozark does not dispute that

Southwind is the only party to the SABER contract with the government2 and that

Southwind is the only party to the bond agreement with Fidelity.

      The Fourth Circuit has held that it may be possible to treat the prime

contractor and its subcontractor as a unitary prime contractor for the purposes of the

Miller Act, but “only where ordinary principles of corporate law permit the courts to

disregard corporate forms.” U.S. ex rel. Global Bldg. Supply, Inc. v. WNH Ltd.

P’ship, 
995 F.2d 515
, 519 (4th Cir. 1993). The district court here held that, under

Oklahoma law,

      to disregard the separate corporate existence of an entity, a party must
      show either 1) that the separate corporate existence of that entity is a
2
  In fact, Services was not formed until 2007, well after Southwind entered into the
SABER contract and performed substantial work under it.


                                         -8-
      design or scheme to perpetrate a fraud, defeat public convenience,
      justify a wrong or defend a crime; or 2) that one corporation is so
      organized and controlled and its affairs so conducted that it is merely an
      instrumentality or adjunct of another corporation, a dummy or a sham.

Aplt. App., Vol. 3, at 935. It concluded that Ozark failed to establish a basis for

disregarding the separate corporate existence of Southwind or Services, or even to

create a genuine issue of fact on the matter.

      Ozark does not disagree with the district court’s statement of Oklahoma law or

its conclusion that Ozark failed to meet this legal standard. Ozark argues only that it

did not have to meet this standard, because, according to Glens Falls, it had only to

show that Southwind and Services “act[ed] interchangeably” and that “[t]he

substance of the parties[’] conduct was that of a unitary contractor rather than a

prime contractor and a subcontractor.” Aplt. Br. at 21. But as we have already

explained, the plain language of the Miller Act does not permit us to use a functional

approach to determine the identity of the prime contractor, because the Act itself

defines who is a prime contractor.3




3
   Because Ozark does not dispute the district court’s conclusion that the evidence
did not establish grounds for piercing the corporate veil, we need not decide whether
the existence of such grounds would ever permit a court to treat a nominal
second-tier subcontractor as a first-tier subcontractor or to treat a nominal first-tier
subcontractor as a prime contractor under the Miller Act. Cf. A & M 
Gregos, 607 F.2d at 48
(declining to decide “whether Bateson ever permits an application of a
sham rule or whether in the case of a truly illusory subcontractor this circuit should
apply a sham rule” in light of its conclusion that contract between prime contractor
and first-tier subcontractor was bona fide).


                                          -9-
      Finally, treating Services as the prime contractor in order to elevate Ozark

from its position as a third-tier subcontractor to that of a second-tier contractor would

not benefit Ozark, because Services--regardless of the role it may have played--is not

a party to the bond agreement with Fidelity. Fidelity’s obligations on the bond

extend only to the failure of Southwind to “promptly make[] payments.” Aplt. App.

at 103. The court cannot unilaterally alter the terms of the bond agreement to extend

Fidelity’s obligations to Services. See 15 Okla. Stat. § 373 (“A surety cannot be held

beyond the express terms of its contract . . . .”). So treating Services as the de facto

prime contractor would not permit Ozark to make a claim against the payment bond.

      As a third-tier subcontractor, Ozark is simply in too remote a relationship to

Southwind to be protected by the payment bond. “It was Congress that drew a line

between sub-subcontractors and those in more remote relationships to the prime

contractor. If the scope of protection afforded by the Miller Act payment bond is to

be extended, it is Congress that must make the change.” 
Bateson, 434 U.S. at 594
(citations omitted) (internal quotation marks omitted).

      The judgment of the district court is affirmed.


                                                   Entered for the Court


                                                   Wade Brorby
                                                   Senior Circuit Judge




                                          - 10 -

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer