Filed: Oct. 08, 2009
Latest Update: Mar. 02, 2020
Summary: 07-4974-cv(L); 08-6184-cv(CON); 08-6188-cv(CON) Telenor Mobile Communications AS v. Storm LLC 1 UNITED STATES COURT OF APPEALS 2 FOR THE SECOND CIRCUIT 3 August Term, 2008 4 (Argued: February 4, 2009 Decided: October 8, 2009) 5 Docket Nos. 07-4974-cv(L); 6 08-6184-cv(CON); 08-6188-cv(CON) 7 - 8 TELENOR MOBILE COMMUNICATIONS AS, 9 Petitioner-Appellee, 10 - v. - 11 STORM LLC, 12 Respondent-Appellant, 13 ALTIMO HOLDINGS & INVESTMENTS LIMITED, 14 ALPREN LIMITED, HARDLAKE LIMITED, 15 Additional Conte
Summary: 07-4974-cv(L); 08-6184-cv(CON); 08-6188-cv(CON) Telenor Mobile Communications AS v. Storm LLC 1 UNITED STATES COURT OF APPEALS 2 FOR THE SECOND CIRCUIT 3 August Term, 2008 4 (Argued: February 4, 2009 Decided: October 8, 2009) 5 Docket Nos. 07-4974-cv(L); 6 08-6184-cv(CON); 08-6188-cv(CON) 7 - 8 TELENOR MOBILE COMMUNICATIONS AS, 9 Petitioner-Appellee, 10 - v. - 11 STORM LLC, 12 Respondent-Appellant, 13 ALTIMO HOLDINGS & INVESTMENTS LIMITED, 14 ALPREN LIMITED, HARDLAKE LIMITED, 15 Additional Contem..
More
07-4974-cv(L); 08-6184-cv(CON); 08-6188-cv(CON)
Telenor Mobile Communications AS v. Storm LLC
1 UNITED STATES COURT OF APPEALS
2 FOR THE SECOND CIRCUIT
3 August Term, 2008
4 (Argued: February 4, 2009 Decided: October 8, 2009)
5 Docket Nos. 07-4974-cv(L);
6 08-6184-cv(CON); 08-6188-cv(CON)
7 -------------------------------------
8 TELENOR MOBILE COMMUNICATIONS AS,
9 Petitioner-Appellee,
10 - v. -
11 STORM LLC,
12 Respondent-Appellant,
13 ALTIMO HOLDINGS & INVESTMENTS LIMITED,
14 ALPREN LIMITED, HARDLAKE LIMITED,
15 Additional Contemnors-Appellants.
16 -------------------------------------
17 Before: SACK and PARKER, Circuit Judges, and STANCEU, Judge.*
18 Consolidated appeals from a judgment and post-judgment
19 orders of the United States District Court for the Southern
20 District of New York. In the judgment, the district court
21 (Gerard E. Lynch, Judge) confirmed a final arbitral award in
22 favor of the petitioner and denied the respondent's cross-motion
23 to vacate. We agree with the district court that the arbitration
24 panel did not "manifestly disregard" the law either by failing to
*
The Honorable Timothy C. Stanceu, of the United States
Court of International Trade, sitting by designation.
1 give preclusive effect to Ukrainian court judgments that the
2 parties' dispute was not arbitrable because the respondent's
3 agent lacked authority to execute the agreement giving rise to
4 the dispute, or by failing to require a trial to determine the
5 agreement's arbitrability pursuant to Sphere Drake Ins. Ltd. v.
6 Clarendon Nat'l Ins. Co.,
263 F.3d 26 (2d Cir. 2001). We also
7 agree with the district court that the agreement was arbitrable
8 as a matter of law because the respondent's agent had the
9 apparent authority to execute it.
10 Affirmed.
11 ROBERT L. SILLS, Orrick, Herrington &
12 Sutcliffe LLP (Jay K. Musoff, of
13 counsel), New York, NY, for Petitioner-
14 Appellee.
15 PIETER VAN TOL, Lovells LLP (Gonzalo S.
16 Zeballos, of counsel), New York, NY, for
17 Respondent-Appellant.
18 RONALD S. ROLFE, Cravath, Swaine & Moore
19 LLP, New York, NY, for Additional
20 Contemnors-Appellants.
21 SACK, Circuit Judge:
22 Telenor Mobile Communications AS ("Telenor"), a
23 Norwegian company, and Storm LLC ("Storm"), a Ukrainian company,
24 own Kyivstar G.S.M. ("Kyivstar"), a Ukrainian mobile
25 telecommunications company. A shareholders agreement among the
26 three companies dated January 30, 2004 (the "2004 Agreement")
27 sets forth the terms of such ownership and provides that any
28 disputes that arise in connection with the agreement will be
2
1 submitted to arbitration. The present consolidated appeals1
2 result from an arbitration, commenced by Telenor, seeking relief
3 for Storm's alleged breach of the 2004 Agreement.
4 This opinion addresses appeal No. 07-4974-cv, in which
5 Storm challenges a judgment of the United States District Court
6 for the Southern District of New York.2 The district court
7 (Gerard E. Lynch, Judge) granted Telenor's petition to confirm
8 the arbitral award in its favor and denied Storm's cross-motion
9 for vacatur.
10 On appeal, Storm argues that the arbitration panel
11 "manifestly disregarded" the law in two respects. First, Storm
12 contends it was reversible error for the panel to fail to give
13 preclusive effect to Ukrainian court judgments concluding that
14 the 2004 Agreement was not arbitrable because, according to the
15 Ukrainian courts, the agent who signed the agreement on behalf of
16 Storm was not authorized to do so. In the alternative, Storm
17 contends, the panel manifestly disregarded our decision in Sphere
18 Drake Ins. Ltd. v. Clarendon Nat'l Ins. Co.,
263 F.3d 26 (2d Cir.
19 2001), by failing to require a trial on the arbitrability issue
20 in the district court. We conclude that the panel had colorable
1
On October 5, 2009, the parties sought by stipulation to
"withdraw [this appeal] from active consideration." We decline
to do so. Cf. Khouzam v. Ashcroft,
361 F.3d 161, 167 (2d Cir.
2004) ("Action by the court is not a subject that the parties may
negotiate among themselves, and a judicial act, such as a
dismissal of a petition, is normally taken only when the
appellate court determines that such action is warranted on the
merits.")
2
We address appeals from post-judgment orders of the
district court in an accompanying summary order.
3
1 reasons for rejecting both arguments and it therefore did not
2 manifestly disregard the law in either respect. Storm also
3 contends, on the merits, that the 2004 Agreement is not
4 arbitrable. We conclude, as did the arbitration panel and the
5 district court, that Storm's agent had at least the apparent
6 authority to execute the 2004 Agreement on behalf of Storm, and,
7 therefore, that the agreement is arbitrable.
8 The judgment of the district court is therefore
9 affirmed.
10 BACKGROUND
11 Events Prior to 2004
12 In 2002, a shareholders agreement dated March 26, 1998,
13 (the "1998 Agreement") set forth the terms of the ownership of
14 Kyivstar's shares. The 1998 Agreement contemplated the existence
15 of five stakeholders, including Telenor and Storm. At some point
16 in early 2002, however, Telenor and Storm agreed to attempt to
17 buy out the other three stakeholders. By August of that year,
18 they had nearly succeeded: only Omega JSC ("Omega") remained. In
19 light of Kyivstar's newly altered ownership structure and in
20 anticipation of Omega's eventual capitulation, Storm and Telenor
21 negotiated an interim voting agreement between themselves (the
22 "Voting Agreement"), which supplemented and altered their rights
23 and obligations as to each other under the 1998 Agreement.
24 The Voting Agreement was executed on September 2, 2002.
25 Valeriy Nilov, Storm's "General Director," signed for Storm.
26 Three days earlier, Storm had sent Telenor a copy of a unanimous
4
1 resolution by Storm shareholders authorizing Nilov to do so. See
2 Storm LLC, Notice Regarding Resolutions Adopted by Written
3 Polling, Aug. 30, 2002, at 2-3 ("Authorization of the General
4 Director of . . . 'Storm', Nilov Valeriy Vladimirovich, to
5 execute and deliver [inter alia, the Voting Agreement]
6 and . . . take or cause to be taken any and all other actions, as
7 are required or desirable in connection with this Resolution and
8 the above-referenced agreements.").
9 The Voting Agreement contained a promise by each of the
10 parties to execute a new shareholders agreement once Storm bought
11 Omega's shares or the 1998 Agreement was terminated, whichever
12 occurred first. See Voting Agreement § 2.05 (providing that,
13 within three days after the earlier of either condition, "the
14 Shareholders [viz., Telenor and Storm] agree to, and to cause
15 [Kyivstar] to, execute and deliver the New Shareholders
16 Agreement"). A form for the contemplated new shareholders
17 agreement was attached to the Voting Agreement as an exhibit. It
18 was in all substantive respects but one -- a provision setting
19 forth the terms of material breach, which was later amended at
20 Storm's request identical to what would be the 2004 Agreement.
21 On October 29, 2002, Storm sent Telenor a document,
22 signed by Nilov, entitled "Certificate of Senior Officer of
23 Purchaser." The Certificate included, among other things, a copy
24 of the Storm shareholders resolution authorizing Nilov to execute
25 the Voting Agreement, and minutes of a meeting occurring on
26 October 7, 2002, which confirmed the resolutions adopted by
5
1 written polling on August 30, 2002. The Certificate provided
2 that those documents "constitute[] valid approval under the laws
3 of Ukraine of [Storm's] execution, delivery and performance of
4 [inter alia, the Voting Agreement] and any other documents in
5 implementation of [inter alia, the Voting Agreement]."
6 The 2004 Agreement
7 In January 2004, Storm purchased the outstanding
8 Kyivstar shares from Omega. After negotiations between Storm and
9 Telenor about possible alteration of the material breach
10 provision of the contemplated new shareholders agreement, a
11 negotiator for Storm wrote to Telenor by email on January 29,
12 saying: "Storm reviewed the language of the New Shareholders
13 Agreement that you distributed yesterday and agreed to it. We
14 are ready to sign it tomorrow."
15 The following day, Nilov and representatives from
16 Telenor and Kyivstar signed the 2004 Agreement. Storm sent
17 Telenor two documents, each entitled "Certificate of Incumbency
18 and Authority of Storm," which were signed by the chairman of
19 Storm and another Storm official, respectively. The documents
20 each certified that Nilov was "duly authorized to sign, on behalf
21 of Storm[,] . . . the Shareholders Agreement dated January 30,
22 2004 between and among Telenor, Storm, Omega and Kyivstar."
23 Unlike the 2002 "Certificate of Senior Officer of Purchaser,"
24 however, the "Certificate[s] of Incumbency and Authority of
25 Storm" did not attach or incorporate by reference copies of
26 documentation of the shareholder authorization.
6
1 The 2004 Agreement contains an arbitration provision
2 stating that "[a]ny and all disputes and controversies arising
3 under, relating to or in connection with this Agreement shall be
4 settled by arbitration by a panel of three (3) arbitrators under
5 the United Nations Commission on International Trade Law
6 (UNCITRAL) Arbitration Rules then in force." 2004 Agreement §
7 12.01(a). It precludes any other sort of action "in connection
8 with any matter arising out of or in connection with this
9 Agreement," except for actions in connection with arbitration.
10
Id. § 12.01(b).
11 The Arbitration and the Ukrainian Proceedings
12 Pursuant to the 2004 Agreement's arbitration provision,
13 Telenor instituted an arbitration against Storm on February 7,
14 2006, alleging that Storm had breached the 2004 Agreement by (1)
15 violating its obligation thereunder not to frustrate Kyivstar
16 board activities through Storm's absence; (2) violating a
17 noncompete provision therein by "acquiring an equity interest in
18 at least one other company engaged in the mobile
19 telecommunications business in Ukraine"; and (3) violating the
20 arbitration provision therein by "prosecut[ing] a series of court
21 actions throughout Ukraine, attacking provisions of the
22 Shareholders Agreement and Kyivstar's charter." Telenor sought,
23 among other relief, a declaration that Storm had breached the
24 2004 Agreement, an injunction requiring Storm to participate in
25 the governance and management of Kyivstar, an anti-suit
26 injunction, and damages.
7
1 On April 14, 2006 -- the day of the first conference of
2 the arbitration panel -- Alpren Limited ("Alpren"), a Cyprus-
3 based subsidiary of Altimo Holdings & Investment Limited
4 ("Altimo"), brought suit in a Ukrainian court against Storm.
5 Alpren and Altimo are the owners of Storm, and Alpren, Altimo,
6 and Storm all belong to the same Russian corporate group, the
7 Alfa Group Consortium. Alpren applied to the Ukrainian court for
8 a declaration that the 2004 Agreement was invalid because Nilov
9 lacked the authority to execute it on Storm's behalf.
10 Apparently, neither Telenor nor the arbitration panel were
11 notified of the Alpren lawsuit.
12 Storm retained no counsel and submitted no written
13 defense to the Alpren suit. Instead, Vadim Klymenko, an Altimo
14 officer responsible for that company's "litigation" and
15 "arbitration" but who is not an attorney-at-law, appeared for
16 Storm and registered an oral opposition on the ground that the
17 arbitration panel had jurisdiction over Alpren's claim. The
18 proceeding lasted approximately 20 minutes.
19 On April 25, 2006, the Ukrainian court concluded that
20 Nilov lacked the authority to execute the 2004 Agreement on
21 behalf of Storm. The court's decision "rendered" that agreement
22 "null and void in full, including the arbitration clause, from
23 the time of [Nilov's] execution [of the document]." Storm
24 appealed. On May 25, 2006, the Ukrainian appeals court affirmed.
8
1 Five days later, Storm filed a statement of defense in
2 the arbitration panel arguing, among other things, that Telenor's
3 claims were not arbitrable in light of the Ukrainian judgment.
4 Storm also moved before the panel to dismiss the arbitration. On
5 October 22, 2006, the panel issued a partial final award and
6 denied the motion. The panel concluded that it had jurisdiction
7 to determine the 2004 Agreement's arbitrability. It also
8 concluded that the dispute was arbitrable, notwithstanding the
9 Ukrainian decision in the Alpren suit, because it found that
10 Storm and Telenor "had a clear intent to have their disputes
11 resolved through arbitration," and that the arbitration provision
12 of the 2004 Agreement was severable and thus not subject to the
13 Ukrainian judgment. Partial Final Award 11-13. The panel noted
14 that the Ukranian court did not address the severability
15 question, because Alpren and Storm did not present the question
16 to the court and because Telenor was never even notified of the
17 proceeding.
Id. at 14.
18 Shortly thereafter, Storm asked the Ukrainian court of
19 appeals to clarify whether, in the court's opinion, the
20 arbitration provision of the 2004 Agreement and the agreement as
21 a whole were invalid in light of the potential severability of
22 the arbitration clause. On November 8, 2006, the court
23 concluded, by now unsurprisingly, that the arbitration agreement
24 was invalid and that any arbitration pursuant to it was in
25 violation of the court's prior order.
9
1 On November 13, 2006, Storm applied in New York State
2 Supreme Court for an injunction terminating the arbitration
3 proceedings and vacating the partial final award in light of the
4 Ukrainian decisions. Telenor removed the New York lawsuit to the
5 United States District Court for the Southern District of New
6 York. Storm then made a motion in that forum seeking a
7 preliminary injunction. The district court denied the motion on
8 the grounds that the panel's order was interlocutory and
9 therefore not ordinarily subject to appeal, and that Storm was
10 unlikely to prevail on the merits.
11 A Ukrainian court then, upon Alpren's application,
12 enjoined Telenor, Storm, and Klymenko from participating in the
13 arbitration. Telenor received no notice of the injunction and
14 was not a party to this new Alpren lawsuit. Storm twice applied
15 to the arbitration panel to stop the arbitration pursuant to the
16 Ukrainian injunction, but the panel denied each application.
17 In an attempt to put a stop to the Ukrainian
18 litigation, Telenor applied in these federal district court
19 proceedings for an anti-suit injunction against Storm and its
20 related entities. The district court issued such a temporary
21 restraining order.
22 Following an evidentiary hearing, the district court
23 issued an anti-suit injunction, writing that "there is no doubt
24 that [the Ukrainian] litigation has been designed to, and has had
25 the effect of, interfering in the arbitration process" -- indeed,
26 that it was "conducted in the most vexatious way possible" -- and
10
1 that the court substantially agreed that "Nilov . . . had at
2 least apparent authority to sign the [2004 Agreement]" under
3 either New York or federal law. Storm LLC v. Telenor Mobile
4 Commc'ns AS, No. 06 Civ. 13157(GEL),
2006 WL 3735657, at *8-*9,
5
2006 U.S. Dist. LEXIS 90978, at *23-*26 (S.D.N.Y. Dec. 18, 2006).
6 With the injunction in place, the arbitration hearings
7 continued. Storm refused to participate.
8 On July 2, 2007, the arbitration panel issued a final
9 award, which reaffirmed the partial final award's findings in
10 light of subsequent events. See Final Award 33-36. The panel
11 held, as relevant to this appeal, that Nilov had both actual and
12 apparent authority under New York law to execute the 2004
13 Agreement on Storm's behalf, see
id. at 36, 43-53, and that Storm
14 was in breach of the agreement in several respects, see
id. at
15 55. Telenor was granted injunctive relief but no damages. See
16
id. at 65-68.
17 The Confirmation of the Award
18 Telenor petitioned the district court for a
19 confirmation of the final arbitral award. Storm cross-moved for
20 vacatur. With a lengthy opinion that appears to reflect
21 decreasing patience with Storm's tactics, Telenor Mobile Commc'ns
22 AS v. Storm LLC,
524 F. Supp. 2d 332 (S.D.N.Y. 2007), the court
23 granted Telenor's application and denied Storm's. The court
24 rejected Storm's contentions that the panel had manifestly
25 disregarded the law by failing to give determinative effect to
26 the Ukrainian judgments that the 2004 Agreement was never
11
1 executed by Storm and thus not arbitrable. After conducting its
2 own independent assessment of arbitrability, the district court
3 concluded that Storm had proffered insufficient evidence to
4 warrant a trial on the issue. The court wrote:
5 Storm provided every conceivable assurance to
6 Telenor that its signatory officers were
7 empowered to bind it to [the 2004 Agreement].
8 When Storm breached the agreement, it was
9 provided with precisely the fair and
10 impartial hearing it had bargained for . . .
11 despite making repeated efforts to renege on
12 its agreement and to torpedo the proceeding
13 by collusive and vexatious litigation.
14
Id. at 369.
15 Storm appeals.
16 DISCUSSION
17 I. Governing Legal Standards
18 A. Review of Arbitral Awards Under the New York Convention
19 Federal jurisdiction over the final arbitral award in
20 favor of Telenor arises from Chapter 2 of the Federal Arbitration
21 Act ("FAA"), 9 U.S.C. §§ 201-08, which empowers the federal
22 courts to enforce arbitrations, such as this one, governed by the
23 New York Convention on the Recognition and Enforcement of Foreign
24 Arbitral Awards, June 10, 1958, 21 U.S.T. 2517, 330 U.N.T.S. 38
25 (the "New York Convention" or the "Convention"). See 9 U.S.C.
26 § 201 ("The Convention . . . shall be enforced in United States
27 courts in accordance with this chapter.");
id. § 203 ("An action
28 or proceeding under the Convention shall be deemed to arise under
29 the laws and treaties of the United States. The district courts
30 of the United States . . . shall have original jurisdiction over
12
1 such an action or proceeding . . . ."); Vaden v. Discover Bank,
2
129 S. Ct. 1262, 1271 n.9 (2009).3
3 "Given the strong public policy in favor of
4 international arbitration, review of arbitral awards under the
5 New York Convention is very limited in order to avoid undermining
6 the twin goals of arbitration, namely, settling disputes
7 efficiently and avoiding long and expensive litigation."
8 Encyclopaedia Universalis S.A. v. Encyclopaedia Britannica, Inc.,
9
403 F.3d 85, 90 (2d Cir. 2005) (citation, internal quotation
10 marks, and ellipsis omitted). Storm's arguments on appeal
11 implicate three types of such limited review.
12 1. Defenses to Enforcement of the Arbitral Award.
13 Pursuant to the New York Convention as incorporated by the FAA, a
14 district court, upon petition by a party to a qualifying arbitral
15 award, "shall confirm the award unless it finds one of the
16 grounds for refusal or deferral of recognition or enforcement of
17 the award specified in the . . . Convention." 9 U.S.C. § 207.
18 The Convention sets forth seven grounds for denial of
19 confirmation, including, of relevance to this appeal, if
3
The parties assume that the New York Convention governs
this commercial dispute, and, because the dispute is between two
foreign corporations, we conclude that that assumption is
correct. See Yusuf Ahmed Alghanim & Sons, W.L.L. v. Toys "R" Us,
Inc.,
126 F.3d 15, 19 (2d Cir. 1997) (holding that New York
Convention governed dispute involving conduct occurring in the
Middle East between nondomestic parties and a domestic
corporation, because Convention encompasses awards "pronounced in
accordance with foreign law or involving parties domiciled or
having their principal place of business outside the enforcing
jurisdiction" (quoting Bergesen v. Joseph Muller Corp.,
710 F.2d
928, 932 (2d Cir. 1983)), cert. denied,
522 U.S. 1111 (1998).
13
1 "recognition or enforcement of the award would be contrary to the
2 public policy of [the] country [in which that relief is sought],"
3 New York Convention, art. V(2)(b).4
4
The grounds are:
(a) The parties to the agreement [to
arbitrate] were, under the law applicable to
them, under some incapacity, or the said
agreement is not valid under the law to which
the parties have subjected it or, failing any
indication thereon, under the law of the
country were the award was made; or
(b) The party against whom the award is
invoked was not given proper notice of the
appointment of the arbitrator or of the
arbitration proceedings or was otherwise
unable to present his case; or
(c) The award deals with a difference not
contemplated by or not falling within the
terms of the submission to arbitration, or it
contains decisions on matters beyond the
scope of the submission to arbitration,
provided that, if the decisions on matters
submitted to arbitration can be separated
from those not so submitted, that part of the
award which contains decisions on matters
submitted to arbitration may be recognized
and enforced; or
(d) The composition of the arbitral authority
or the arbitral procedure was not in
accordance with the agreement of the parties,
or, failing such agreement, was not in
accordance with the law of the country where
the arbitration took place; or
(e) The award has not yet become binding on
the parties, or has been set aside by a
competent authority of the country in which,
or under the law of which, that award was
made.
New York Convention art. V(1). And:
(a) The subject matter of the difference is
not capable of settlement by arbitration
14
1 "The party opposing enforcement of an arbitral award
2 has the burden to prove that one of the seven defenses under the
3 New York Convention applies." Encyclopaedia Universalis,
403
4 F.3d at 90. "The burden is a heavy one, as the showing required
5 to avoid summary confirmance is high."
Id. (citations, ellipsis,
6 and internal quotation marks omitted); see also Zeiler v.
7 Deitsch,
500 F.3d 157, 164 (2d Cir. 2007) (same).
8 2. Arbitrability. A dispute is arbitrable only if the
9 parties contractually bind themselves to arbitrate it. See,
10 e.g., AT&T Techs., Inc. v. Commc'ns Workers of Am.,
475 U.S. 643,
11 648 (1986) (noting that "arbitration is a matter of contract");
12 see also First Options of Chicago, Inc. v. Kaplan,
514 U.S. 938,
13 943 (1995) ("[T]he arbitrability of the merits of a dispute
14 depends upon whether the parties agreed to arbitrate that
15 dispute."). A question of arbitrability is therefore raised
16 when, as here, someone asserts that an arbitral award should not
17 be enforced because there was no effective agreement to arbitrate
18 the dispute.
19 Review of arbitrability questions is subject to two
20 important presumptions: First, "the federal policy in favor of
21 arbitration requires that 'any doubts concerning the scope of
under the law of that country [i.e., the
country where recognition and enforcement is
sought]; or
(b) The recognition or enforcement of the
award would be contrary to the public policy
of that country.
Id. art. V(2).
15
1 arbitrable issues' be resolved in favor of arbitration.'" Shaw
2 Group Inc. v. Triplefine Int'l Corp.,
322 F.3d 115, 120 (2d Cir.
3 2003) (quoting Moses H. Cone Mem. Hosp. v. Mercury Constr. Corp.,
4
460 U.S. 1, 24-25 (1983)). Second, arbitrability questions are
5 presumptively to be decided by the courts, not the arbitrators
6 themselves. See
id. ("[W]hen the doubt concerns who should
7 decide arbitrability . . . [t]he law [presumptively] favor[s]
8 judicial rather than arbitral resolution."); see also First
9
Options, 514 U.S. at 944-45. We have written that the latter
10 presumption can be rebutted only by "clear and unmistakable
11 evidence from the arbitration agreement, as construed by the
12 relevant state law, that the parties intended that the question
13 of arbitrability shall be decided by the arbitrator." Bell v.
14 Cendant Corp.,
293 F.3d 563, 566 (2d Cir. 2002) (internal
15 quotation marks and emphasis omitted); see also Shaw Group,
322
16 F.3d at 120-21.5
5
In Buckeye Check Cashing, Inc. v. Cardegna,
546 U.S. 440
(2006), the Supreme Court made clear that in light of the
severability of agreements to arbitrate generally, see
id. at
445, the presumption of judicial resolution of arbitrability
applies only when a party has specifically challenged the
arbitration agreement -- "unless the challenge is to the
arbitration clause itself, the issue of the contract's validity
is considered by the arbitrator in the first instance,"
id. at
445-46. But Buckeye expressly limited its holding to challenges
to a "contract's validity," as distinguished "from the issue
whether any agreement between the alleged obligor and obligee was
ever concluded," including, as relevant to this appeal, "whether
the signor lacked authority to commit the alleged principal."
Id. at 444 n.1.
We have not modified our previous ruling that such questions
about whether a contract was ever made -- like the question
before us in the instant case -- are presumptively to be decided
by the court even without a specific challenge to the agreement
16
1 The presumption that the court should decide
2 arbitrability questions also applies when a party seeks to compel
3 arbitration under the New York Convention. See New York
4 Convention, art. II(3) (providing that the court "shall, at the
5 request of one of the parties, refer the parties to arbitration,
6 unless it finds that the . . . agreement is null and void,
7 inoperative or incapable of being performed"). We addressed such
8 a motion to compel in Sphere Drake Ins. Ltd. v. Clarendon Nat'l
9 Ins. Co.,
263 F.3d 26 (2d Cir. 2001), writing that when "the
10 making of the agreement to arbitrate is placed in issue . . . the
11 court must set the issue for trial," so long as "the party
12 putting the agreement to arbitrate in issue . . . present[s]
13 'some evidence' in support of its claim."
Id. at 30 (quoting
14 Interocean Shipping Co. v. Nat'l Shipping & Trading Corp., 462
15 F.2d 673, 676 (2d Cir. 1972)). Depending on the type of claimed
16 inarbitrability, we noted that the party might also be required
17 to make a specific challenge to the arbitration clause. See
id.
to arbitrate. See Sphere Drake Ins. Ltd. v. Clarendon Nat'l Ins.
Co.,
263 F.3d 26, 31-32 (2d Cir. 2001) (holding that if a party
alleges that an agreement is "void" -- as distinct from
"voidable" -- the agreement's validity is subject to judicial
resolution by "trial" without the party's having to challenge the
arbitration clause in particular, so long as the party alleges
"that [the] contract is void and provides some evidence in
support"). Because we conclude below that even if Storm
challenged the arbitration clause of the 2004 Agreement in
particular, it has still failed to provide sufficient evidence
that this dispute was not arbitrable, we need not decide whether
this aspect of Sphere Drake survives Buckeye. Cf. Rubin v. Sona
Int'l Corp.,
457 F. Supp. 2d 191, 193 (S.D.N.Y. 2006) (concluding
that, in light of Buckeye, "[whether a party] argues that [an]
agreement is void or voidable, [the party] may only avoid
arbitration if it can successfully challenge the validity of the
arbitration clause itself").
17
1 at 31-32 (noting that in setting an arbitrability issue for
2 trial, a party alleging that a contract is void need not
3 challenge the arbitration clause, but a party alleging that a
4 contract is voidable must challenge the arbitration clause in
5 particular); see also supra n.[4].
6 3. Manifest Disregard. Federal courts with
7 jurisdiction to enforce an arbitral award may also consider
8 whether the award was in "manifest disregard" of the law. See
9 Stolt-Nielsen SA v. Animalfeeds Int'l Corp.,
548 F.3d 85, 91-92,
10 94-95 (2d Cir. 2008).6 The boundaries of the manifest disregard
6
In Hall St. Assocs., L.L.C. v. Mattel, Inc.,
128 S. Ct.
1396 (2008), the Supreme Court observed that the "manifest
disregard" doctrine might be a ground for review independent of
the FAA, or might instead be a name for some, or all, of the
grounds for vacatur of arbitral awards set forth in Section 10(a)
of the FAA, 9 U.S.C. § 10(a), including circumstances "where the
arbitrators were guilty of misconduct,"
id. § 10(a)(3), or
"exceeded their powers, or so imperfectly executed them that a
mutual, final, and definite award upon the subject matter
submitted was not made,"
id. § 10(a)(4). See Hall St. at 1403-04
("Maybe the term 'manifest disregard' was meant to name a new
ground for review, but maybe it merely referred to the § 10
grounds collectively, rather than adding to them."). In Stolt-
Nielsen, we read Hall St. to hold that the FAA set forth the
"exclusive" grounds for vacating an arbitration award, and that
the term "manifest disregard" was merely a "judicial gloss" on
some of those grounds.
Stolt-Nielsen, 548 F.3d at 94.
The Supreme Court has granted certiorari to review Stolt-
Nielsen explicitly on another issue, see
129 S. Ct. 2793 (2009),
but even if it confirms or rejects our interpretation of the term
"manifest disregard," that will not affect this appeal. If the
Stolt-Nielsen interpretation is correct, we may review this
arbitral award for manifest disregard because the arbitration
took place in the United States and therefore is "subject to the
FAA provisions," like Section 10(a), "governing domestic
arbitration awards." See
Zeiler, 500 F.3d at 164; see also 9
U.S.C. § 208. If our interpretation was incorrect, this opinion
will be applying a judicially created "non-statutory defense to
enforcement." Telenor Mobile Commc'ns AS v. Storm LLC, 524 F.
Supp. 2d 332, 344 (S.D.N.Y. 2007).
18
1 concept are not precisely defined, but the term "clearly means
2 more than error or misunderstanding with respect to the law."
3 Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Bobker,
808 F.2d
4 930, 933 (2d Cir. 1986). A mere demonstration that an
5 arbitration panel made "the wrong call on the law" does not show
6 manifest disregard; "the award should be enforced . . . if there
7 is a barely colorable justification for the outcome reached."
8 Wallace v. Buttar,
378 F.3d 182, 190 (2d Cir. 2004) (emphasis in
9 original) (internal quotation marks omitted). Examples of
10 manifest disregard therefore tend to be extreme, such as
11 "explicitly reject[ing] controlling precedent" or otherwise
12 reaching a decision that "strains credulity" or lacks even a
13 "barely colorable" justification.
Stolt-Nielsen, 548 F.3d at 92-
14 93 (internal quotation marks omitted). It is, in a word, "rare"
15 to obtain relief from an arbitral award under this doctrine.
Id.
16 at 91 & n.7 (internal quotation marks omitted).
17 The "manifest disregard" inquiry has three steps:
18 First, we must consider whether the law that
19 was allegedly ignored was clear, and in fact
20 explicitly applicable to the matter before
21 the arbitrators. . . .
22 Second, once it is determined that the law is
23 clear and plainly applicable, we must find
24 that the law was in fact improperly applied,
25 leading to an erroneous outcome. . . .
26
27 Third, once the first two inquiries are
28 satisfied, we look to the subjective element,
29 that is, the knowledge actually possessed by
30 the arbitrators. In order to intentionally
31 disregard the law, the arbitrator must have
32 known of its existence, and its applicability
33 to the problem before him.
19
1
Id. at 93 (quoting Duferco Int'l Steel Trading v. T. Klaveness
2 Shipping A/S,
333 F.3d 383, 389-90 (2d Cir. 2003)).
3 B. Standard of Review
4 As a general matter, "[w]e review a district court's
5 decision to confirm an arbitration award de novo to the extent it
6 turns on legal questions, and we review any findings of fact for
7 clear error."
Duferco, 333 F.3d at 388. Accordingly, here we
8 review de novo the question whether the arbitration panel erred
9 in a respect explicitly set forth by the FAA as a ground for
10 vacatur of an arbitral award. See, e.g., Westerbeke Corp. v.
11 Daihatsu Motor Co.,
304 F.3d 200, 219-23 (2d Cir. 2002).
12 Similarly, "'[w]hen a party challenges the district
13 court's review of an arbitral award under the manifest disregard
14 standard, we review the district court's application of the
15 standard de novo.'"
Wallace, 378 F.3d at 189 (quoting The GMS
16 Group, LLC v. Benderson,
326 F.3d 75, 77 (2d Cir. 2003)).
17 II. Analysis
18 A. The Ukrainian Judgments
19 Storm argues that the arbitration panel manifestly
20 disregarded the law governing the preclusive effect of foreign
21 judgments when it failed to give such effect to the Ukrainian
22 court judgments holding that the 2004 Agreement was never
23 executed by Storm and is therefore not arbitrable. Storm also
24 argues that its compliance with the arbitral award as enforced by
25 the district court would entail actions that would place it in
20
1 contempt of the Ukrainian courts, contrary to New York public policy.
2 1. Manifest Disregard. In Ackermann v. Levine, 788
3 F.2d 830 (2d Cir. 1986), we reiterated the "well-settled rule"
4 that
5 a final judgment obtained through sound
6 procedures in a foreign country is generally
7 conclusive as to its merits unless (1) the
8 foreign court lacked jurisdiction . . . ; (2)
9 the judgment was fraudulently obtained; or
10 (3) enforcement of the judgment would offend
11 the public policy of the state in which
12 enforcement is sought.
13
Id. at 837 (emphasis in original). Storm contends that the
14 arbitration panel manifestly disregarded this rule by failing to
15 give conclusive weight to the Ukrainian judgments that the 2004
16 Agreement is not arbitrable.7
17 The district court disagreed. It concluded that the
18 judgments obtained by Alpren against Storm had contravened the
19 rule against "friendly litigation," see Lord v. Veazie,
49 U.S.
20 (8 How.) 251, 256 (1850) (concluding that such litigation results
21 in a judgment which "is a mere form" and is therefore "a
22 nullity"). The district court remarked that it and the
23 arbitration panel had both previously found the Alpren litigation
24 to have been collusive.
Telenor, 524 F. Supp. 2d at 346-47. The
25 district court also concluded that the Ukrainian proceedings had
26 afforded Telenor no notice or opportunity to be heard prior to
27 the entry of the judgment, and that they were intended to
7
The first and third steps of the manifest disregard
inquiry -- that the Ackermann rule was clear, plainly applicable,
and made known to the arbitration panel -- are undisputed.
21
1 undermine a possible confirmation of an award in Telenor's favor.
2
Id. at 347. In light of those conclusions, the court found that
3 the Ukrainian procedures were not "sound" for Ackermann purposes
4 and therefore not binding on the arbitration panel.
Id. at 348.
5 Storm argues that the arbitration panel did not
6 actually find that the Ukrainian actions by Alpren were
7 collusive. To be sure, the panel did not employ the word
8 "collusive" in its partial or final award. But the panel does
9 mention, repeatedly, that the Alpren litigation was conducted
10 among related corporate entities, see, e.g., Final Award 21 ("As
11 previously noted, Alpren and Storm were under the direct or
12 indirect control of Altimo, and the ultimate control of Alfa."),
13 without notice to or appearance by Telenor, see, e.g.,
id. at 17
14 ("Telenor . . . had no notice of the Ukrainian proceedings until
15 after the order of the Ukrainian appellate court . . . .");
id.
16 ("[T]he April-May 2006 Ukrainian court proceedings came as a
17 surprise to both the Tribunal and to Telenor . . . ."). The
18 panel's repeated observations along these lines make clear that
19 the panel considered the Ukrainian proceedings to have been
20 collusive, even though the panel understandably elected to avoid
21 using that term in relation to proceedings before a duly
22 constituted foreign court. See
id. at 25 (noting that the panel
23 had previously "made clear" that it was not "ignoring the
24 decisions of the Ukrainian courts . . . [or] impugning the
25 integrity of those courts or their decisions").
22
1 Politic or not, in light of the "strong presumption
2 that an arbitration tribunal has not manifest[ly] disregarded the
3 law,"
Westerbeke, 304 F.3d at 212 n.8, the panel's multiple
4 references to the Alfa-internal and ex parte nature of the Alpren
5 litigation supply a sufficiently "colorable" justification for
6 its refusal to give the Ukrainian judgments controlling weight.
7 Cf. Motorola Credit Corp. v. Uzan,
388 F.3d 39, 60-61 (2d Cir.
8 2004) (affirming denial of comity to injunctions entered by
9 Turkish courts that "were the product of collusion").
10 Storm does not seriously dispute that the Alpren
11 litigation was a cooperative venture among allied interests.8 It
12 argues, instead, that Storm "had no contact" with its adversary
13 during the litigation, that it "presented a defense" in the
14 proceedings, and that it "appealed." Appellant Br. 42. But
15 these assertions, if true, would not refute the panel’s finding
16 of collusion on the facts of this case and would not be a basis
17 upon which the district court was required to overturn that
18 finding. The panel was not obliged to interpret Storm's
19 decidedly modest efforts in the Alpren suit to be material or
20 meaningful.9
8
Storm does rely upon a declaration from Klymenko,
submitted after judgment was entered by the district court, which
says that Storm, Alpren, and Altimo are not "the same entities."
We decline to find clear error on the basis of a self-serving
declaration that the district court had no opportunity to
consider.
9
Moreover, Storm offers no good reason why we should not
affirm on the district court's finding of collusion. See
Telenor, 524 F. Supp. 2d at 346-47.
23
1 Moreover, "the force of" the Ukrainian judgments as
2 against Telenor is "further reduced" by the fact that Telenor was
3 not a party to the Alpren litigation and was continually denied
4 notice of the proceedings. Final Award 34; see also
id. at 21-
5 22, 25-27;
Telenor, 524 F. Supp. 2d at 346-47. The failure of
6 the Ukranian court to afford Telenor what we would regard as
7 rudimentary due process, see Parklane Hosiery Co. v. Shore, 439
8 U.S. 322, 327 n.7 (1979) ("It is a violation of due process for a
9 judgment to be binding on a litigant who was not a party or privy
10 and therefore never had an opportunity to be heard."), provides
11 an independent colorable justification for the panel's conclusion
12 that the Ukrainian proceedings were unsound for Ackermann
13 preclusion purposes.
14 It was the opinion of a witness whom Storm proffered as
15 an expert that "Telenor . . . could have intervened" in the
16 Alpren litigation after it was notified of the judgment against
17 it "for purposes of filing an appeal to Ukraine's highest court"
18 but "chose not to do so." That is beside the point for at least
19 two reasons. First, this opinion testimony, if assumed to
20 constitute competent evidence of the process actually available
21 to Telenor in the Alpren litigation, would fail to demonstrate
22 that Telenor, after intervening solely for purposes of appeal,
23 would have been afforded a full and fair opportunity to be heard
24 on the merits of the issues decided in that litigation. Second,
25 it would not in any event be sufficient to have warranted a
26 reversal by the district court under the "manifest disregard"
24
1 standard. See
Stolt-Nielsen, 548 F.3d at 91 ("We do not . . .
2 'recognize manifest disregard of the evidence as proper ground
3 for vacating an arbitrator's award.'" (quoting Wallace,
378 F.3d
4 at 193) (emphasis added in Stolt-Nielsen)).
5 The Ukrainian decisions therefore provide no basis for
6 a denial of enforcement of the final arbitral award on "manifest
7 disregard" grounds.
8 2. Public Policy.
9 Storm argues that the arbitral award should nonetheless
10 be vacated pursuant to Article V(2)(b) of the New York Convention
11 because, Storm says, it is contrary to New York public policy to
12 force a party to comply with an arbitral award that will cause it
13 to violate a foreign judgment. We do not think that Storm can
14 properly invoke the protection of any such policy.
15 Two factfinders have concluded that Storm brought the
16 Ukrainian judgments upon itself through use of highly
17 questionable litigation tactics. See Final Award 21, 25;
18
Telenor, 524 F. Supp. 2d at 346-47, 356-58. Storm's situation,
19 like that of the apocryphal parricide seeking mercy because he
20 had been orphaned, is entirely of its own making.
21 Our view, in light of the findings of the arbitration
22 panel and the district court, is that it is Storm's improper
23 collateral litigation, not the arbitral award, that is contrary
24 to public policy, viz., the well-established federal public
25 policy in favor of arbitration. See, e.g., Chelsea Square
26 Textiles, Inc. v. Bombay Dyeing & Mfg. Co.,
189 F.3d 289, 294 (2d
25
1 Cir. 1999) ("Through the FAA, Congress has declared a strong
2 federal policy favoring arbitration as an alternative means of
3 dispute resolution." (internal quotation marks omitted)).
4 Collateral and unilateral litigation of arbitrability – or any
5 other issue pertinent to an arbitration, for that matter --
6 undertaken in a foreign forum by a party to that arbitration in
7 an attempt to protect itself from an adverse arbitral award
8 would, if indulged, tend seriously to undermine the underlying
9 scheme of the FAA and the New York Convention.
10 Article V(2)(b) must be "construed very narrowly" to
11 encompass only those circumstances "where enforcement would
12 violate our most basic notions of morality and justice."
13 Europcar Italia S.p.A. v. Maiellano Tours, Inc.,
156 F.3d 310,
14 315 (2d Cir. 1998) (internal quotation marks omitted).
15 Consistent with that rule, we conclude that enforcing the
16 arbitral award as against Storm would not be contrary to public
17 policy.
18 B. Sphere Drake and Arbitrability
19 Storm argues that the panel manifestly disregarded
20 Sphere Drake when it failed to arrange for a trial to be held on
21 the arbitrability of the 2004 Agreement. Storm also argues that
22 the district court erred in making its own determination, de
23 novo, that the 2004 Agreement was executed by Storm. We conclude
24 to the contrary that Storm failed to present "some evidence" of a
25 dispute as to arbitrability so as to warrant a trial under Sphere
26
1 Drake.10 In particular, Storm has not provided sufficient
2 evidence to support its allegation that Nilov lacked apparent
3 authority to execute the agreement on behalf of Storm.
4 Under New York law,11 an agent has apparent authority
5 if "a principal places [the] agent in a position where it appears
6 that the agent has certain powers which he may or may not
7 possess." Masuda v. Kawasaki Dockyard Co.,
328 F.2d 662, 665 (2d
8 Cir. 1964). The apparent authority question is susceptible to
9 judgment as a matter of law against the principal. See, e.g.,
10 Warnock Cap. Corp. v. Hermitage Ins. Co.,
21 A.D.3d 1091, 803
11 N.Y.S.2d 606 (2d Dep't 2005). Here, there is no genuine issue of
12 fact, let alone a material one, as to Nilov's apparent authority:
13 There is substantial evidence that Telenor received multiple
14 notices from Storm that Nilov had the authority to execute the
15 2004 Agreement and there is no evidence, at least that has been
10
We do not reach the question of whether Storm was
required to challenge the arbitrability of the arbitration
clause, in particular, or whether it in fact did so. Even if
Storm challenged the arbitration clause itself, as it contends,
we would reach the same result.
11
The 2004 Agreement provides that it "shall be governed
by, and construed in accordance with," New York law, "without
giving effect to any conflicts of laws principles . . . which
would result in the application of the laws of another
jurisdiction." 2004 Agreement § 13.06. This choice of law
clause governs Storm's arbitrability challenge. See Motorola
Credit Corp. v. Uzan,
388 F.3d 39, 50 (2d Cir. 2004) ("[A]
choice-of-law clause in a contract will apply to disputes about
the existence or validity of that contract."), cert. denied,
544
U.S. 1044 (2005). By the terms of the clause, Storm is incorrect
that Ukrainian law applies to the dispute as a matter of New York
conflicts principles.
27
1 brought to our attention, that Telenor should have thought
2 otherwise.
3 The record reflects that Storm sent Telenor a variety
4 of signals that Nilov had the authority to execute the 2004
5 Agreement. Among them:
6 ! In 2002, Telenor received a copy of the August 20,
7 2002 Storm shareholders resolution, which referenced
8 both the Voting Agreement and the draft shareholders
9 agreement that ultimately became the 2004 Agreement and
10 authorized Nilov "to execute and deliver [those]
11 agreements" and to "take or cause to be taken any and
12 all other actions, as are required or desirable in
13 connection with this Resolution and the above-
14 referenced agreements." Storm LLC, Notice Regarding
15 Resolutions Adopted by Written Polling, Aug. 30, 2002,
16 at 3.
17 ! Nilov executed -- with actual authority -- the
18 Voting Agreement providing that Storm "agree[d]
19 to . . . execute and deliver the New Shareholder
20 Agreement." Voting Agreement § 2.05.
21 ! Telenor received an email from a Storm negotiator
22 stating that Storm was "ready to sign" the 2004
23 Agreement, and discussing Nilov's availability to sign
24 it, the day before Nilov actually signed it.
25 ! Telenor received documentation from Storm signed by
26 Storm's chairman and another official, stating that
27 Nilov was "duly authorized" to execute the agreement on
28 Storm's behalf. See Storm LLC, Certificate of
29 Incumbency and Authority of Storm, Jan. 30, 2004.
30 Storm does not challenge the validity of these
31 representations to Telenor of Nilov's apparent authority to
32 execute the agreement. Rather, Storm argues that Telenor should
33 have deduced from the Storm charter and from having not received
34 documentation of any shareholder meeting specifically authorizing
35 Nilov to sign the 2004 Agreement, despite Storm's repeated
36 statements that he was so authorized, that Nilov's execution
28
1 required a shareholder meeting for authorization. This fails to
2 raise a genuine issue of material fact. For one thing, Storm
3 cites nothing in the record (including in the charter) to support
4 the proposition that Nilov required shareholder approval to
5 execute the 2004 Agreement on his company's behalf. For another,
6 there is no evidence from which a rational juror might infer that
7 Telenor should have concluded that there was no such meeting, in
8 light of Storm's repeated assurances that Nilov was indeed duly
9 authorized.
10 Storm has, moreover, failed to explain why Nilov would
11 sign the agreement without authorization.
12 In any event, the record evidence shows that everyone
13 at the relevant time, including Storm, thought that Nilov had the
14 authority to execute the agreement. That is sufficient ground on
15 which to conclude that Storm has failed to proffer sufficient
16 evidence from which a rational juror could conclude that Nilov
17 lacked apparent authority to execute the 2004 Agreement and that
18 no trial was required to find out if the agreement was, or was
19 not, arbitrable.
20 CONCLUSION
21 For the foregoing reasons, the judgment of the district
22 court is affirmed.
29