Filed: Jul. 07, 2017
Latest Update: Mar. 03, 2020
Summary: 16-4309 EDF v. County of Suffolk UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT SUMMARY ORDER RULINGS BY SUMMARY ORDER DO NOT HAVE PRECEDENTIAL EFFECT. CITATION TO A SUMMARY ORDER FILED ON OR AFTER JANUARY 1, 2007 IS PERMITTED AND IS GOVERNED BY FEDERAL RULE OF APPELLATE PROCEDURE 32.1 AND THIS COURT’S LOCAL RULE 32.1.1. WHEN CITING A SUMMARY ORDER IN A DOCUMENT FILED WITH THIS COURT, A PARTY MUST CITE EITHER THE FEDERAL APPENDIX OR AN ELECTRONIC DATABASE (WITH THE NOTATION “SUMMARY ORDER
Summary: 16-4309 EDF v. County of Suffolk UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT SUMMARY ORDER RULINGS BY SUMMARY ORDER DO NOT HAVE PRECEDENTIAL EFFECT. CITATION TO A SUMMARY ORDER FILED ON OR AFTER JANUARY 1, 2007 IS PERMITTED AND IS GOVERNED BY FEDERAL RULE OF APPELLATE PROCEDURE 32.1 AND THIS COURT’S LOCAL RULE 32.1.1. WHEN CITING A SUMMARY ORDER IN A DOCUMENT FILED WITH THIS COURT, A PARTY MUST CITE EITHER THE FEDERAL APPENDIX OR AN ELECTRONIC DATABASE (WITH THE NOTATION “SUMMARY ORDER”..
More
16-4309
EDF v. County of Suffolk
UNITED STATES COURT OF APPEALS
FOR THE SECOND CIRCUIT
SUMMARY ORDER
RULINGS BY SUMMARY ORDER DO NOT HAVE PRECEDENTIAL EFFECT. CITATION TO A
SUMMARY ORDER FILED ON OR AFTER JANUARY 1, 2007 IS PERMITTED AND IS GOVERNED BY
FEDERAL RULE OF APPELLATE PROCEDURE 32.1 AND THIS COURT’S LOCAL RULE 32.1.1. WHEN
CITING A SUMMARY ORDER IN A DOCUMENT FILED WITH THIS COURT, A PARTY MUST CITE
EITHER THE FEDERAL APPENDIX OR AN ELECTRONIC DATABASE (WITH THE NOTATION
“SUMMARY ORDER”). A PARTY CITING TO A SUMMARY ORDER MUST SERVE A COPY OF IT ON
ANY PARTY NOT REPRESENTED BY COUNSEL.
1 At a stated term of the United States Court of Appeals for the Second Circuit, held at
2 the Thurgood Marshall United States Courthouse, 40 Foley Square, in the City of New York,
3 on the 7th day of July, two thousand seventeen.
4
5 PRESENT:
6 ROBERT D. SACK,
7 SUSAN L. CARNEY,
8 CHRISTOPHER F. DRONEY,
9 Circuit Judges.
10 _____________________________________
11
12 EDF RENEWABLE DEVELOPMENT, INC.,
13
14 Plaintiff-Appellee,
15
16 v. No. 16-4309
17
18 COUNTY OF SUFFOLK,
19
20 Defendant-Appellant.
21 _____________________________________
22
23 FOR APPELLANT: JOHN R. PETROWSKI, Assistant County
24 Attorney, for Dennis M. Brown, Suffolk
25 County Attorney, Hauppauge, NY.
26
27
28 FOR APPELLEE: HARRIS N. COGAN (Rither Alabre, on the
29 brief), Blank Rome LLP, New York, NY.
1 Appeal from a judgment of the United States District Court for the Eastern District of
2 New York (Shields, M.J.).1
3 UPON DUE CONSIDERATION, IT IS HEREBY ORDERED,
4 ADJUDGED, AND DECREED that the December 1, 2016 judgment of the District Court
5 is AFFIRMED.
6 Defendant-Appellant County of Suffolk (the “County”) appeals the District Court’s
7 entry of judgment, following a bench trial, in favor of Plaintiff-Appellee EDF Renewable
8 Development, Inc. (“EDF”). The court found that the County violated a provision of the
9 parties’ contract that required the County to cooperate with EDF’s efforts to obtain a permit
10 to build solar carports on a plot of land in Ronkonkoma that EDF leased from the County.2
11 Rejecting the County’s arguments that EDF was required to comply with a purported notice
12 of breach provision in the contract before suing, and that EDF had not demonstrated that it
13 suffered cognizable damages, the District Court made detailed factual findings about the
14 County’s breach based on the testimony of several witnesses involved in the underlying events
15 and other record evidence, and awarded EDF damages of $10,884,225.70. We assume the
16 parties’ familiarity with the underlying facts and the procedural history of the case, to which we
17 refer only as necessary to explain our decision to affirm.
18 Here, having reviewed the court’s legal determinations de novo and its factual findings
19 for clear error, see Bessemer Trust Co., N.A. v. Branin,
618 F.3d 76, 85 (2d Cir. 2010), we conclude
20 that the District Court properly found that the County breached its contractual obligations,
21 that EDF was entitled to damages resulting from the breach, and that, in the circumstances
22 presented, EDF’s failure to give the County a formal notice of the breach did not preclude it
23 from bringing suit. Moreover, EDF was not required to bring its breach of contract claim in an
24 Article 78 proceeding. See Abiele Contracting v. NYC Sch. Constr. Auth.,
91 N.Y.2d 1, 8-9 (1997).
1This case was assigned to Magistrate Judge Shields for all purposes with the consent of both parties.
See 28 U.S.C. § 636(c); Fed. R. Civ. P. 73.
2EDF is in fact a successor to enXco, the relevant counterparty to the contract with the County;
enXco assigned its contractual claims to EDF.
2
1 We therefore affirm for substantially the reasons stated by the court in its thorough and
2 well-reasoned opinion of November 17, 2016.
3 ***
4 We have considered the County’s remaining arguments and conclude that they are
5 without merit. Accordingly, we AFFIRM the judgment of the District Court.
6
7 FOR THE COURT:
8 Catherine O’Hagan Wolfe, Clerk of Court
3