Summary: United States Court of Appeals, Fifth Circuit. No. 92-3556. AVONDALE INDUSTRIES, INC., Plaintiff-Appellant, v. INTERNATIONAL MARINE CARRIERS, INC. and The United States of America, Defendants- Appellees. March 4, 1994. Appeal from the United States District Court for the Eastern District of Louisiana. Before KING and JOLLY, Circuit Judges, and PARKER,1 District Judge. ROBERT M. PARKER, District Judge: Avondale Industries Inc. (Avondale) brought a maritime tort and contract action against the Uni
More
                                    United States Court of Appeals,

                                              Fifth Circuit.

                                              No. 92-3556.

                        AVONDALE INDUSTRIES, INC., Plaintiff-Appellant,

                                                    v.

INTERNATIONAL MARINE CARRIERS, INC. and The United States of America, Defendants-
Appellees.

                                             March 4, 1994.

Appeal from the United States District Court for the Eastern District of Louisiana.

Before KING and JOLLY, Circuit Judges, and PARKER,1 District Judge.

          ROBERT M. PARKER, District Judge:

          Avondale Industries Inc. (Avondale) brought a maritime tort and contract action against the

United States and its vessel operator, International Marine Carriers, Inc. (IMC) for allision damages

to Avondale shipyard property which occurred on November 18, 1989.

          The United States counterclaimed against Avondale for damages suffered by the USNS

BELLATRIX, the vessel involved in the allision, and for contractual indemnity on the Avondale

claim.

          The matter was tried by the district court sitting without a jury. The district court issued a

judgment on June 3, 1992 dismissing Avondale's claims and awarding the United States $637,380.00

in damages. Avondale is before this Court appealing both the dismissal and the damage award.

                                                 FACTS

          USNS BELLATRIX is a 946 foot long steamship owned by the United States Navy. She is

fitted with two 60,000 horsepower steam engines each driving a separate propeller. IMC contracted

with the Navy's Military Sealift Command to operate and maintain the vessel. As a part of IMC's

services to the Navy, IMC took bids and awarded contracts for the routine dry docking and regular

"topside" repairs and maintenance of the BELLATRIX in the Fall of 1989.


   1
       Chief Judge of the Eastern District of Texas, sitting by designation.
       Avondale was awarded the contract. Avondale provided tugs, pilots and line handlers to

BELLATRIX, towing her dead ship from her berth in Violet, Louisiana to the Avondale shipyard on

the Mississippi River. This initial movement and a subsequent return to Violet were part of the

original contract. Later, it was determined that BELLATRIX's topside repairs were to be performed

by a shipyard located in Jacksonville, Florida.

       On November 18, 1993, Avo ndale had completed its repair work on the vessel. The

BELLATRIX was towed, dead ship, out of dry dock by two tugs, AVON II, owned by Avondale and

MISS SARAH, hired by Avondale from E.N. Bisso and Son. A third tug, PEGGY H., also hired by

Avondale from Bisso, stood by unattached. The dry dock was parallel to shore and BELLATRIX's

bow was pointing upriver. After the repairs were completed, the tugs towed the BELLATRIX, dead

ship to the opposite side of the Mississippi River and held her there with her bow pointed upstream

while she took on water ballast and made steam. Ballasting was necessary to lower the vessel in the

water to allow her to pass under overhead electric cables and the Huey Long Bridge.

       BELLATRIX was manned by IMC employees, including Captain Rivera and his crew. A

compulsory pilot, Pilot Thomas, was also on board during the ballasting and turning of BELLATRIX,

as required by law. Avondale, as part of the contract, hired and paid Pilot Thomas. Captain Rivera

discussed the vessel's handling characteristics with the pilot when he came on board before

BELLATRIX left the dry dock. Both Captain Rivera and Pilot Thomas stayed on the bridge

throughout the subsequent maneuvers. Pilot Thomas gave all the orders and Captain Rivera,

although nearby, had turned his attention to the repair of a faulty instrument.

       The engines were placed on standby at 0754 hours. Ballasting was completed at about 0810

hours. At approximately 0816 hours, before the down river turn was started, the chief engineer

reported to third mate Barton, who immediately notified Captain Rivera and Pilot Thomas, that the

starboard engine was unavailable for use. Pilot Thomas determined that BELLATRIX could be

turned with the port engine and the assisting tugs, without the starboard engine and proceeded,

knowing it was unavailable. The port engine was kept dead slow astern, which had the effect of

slowly turning the BELLATRIX to the left until she was perpendicular in the river with her bow
pointed at the Avondale facility.

       At this time, Pilot Thomas released MISS SARAH from the bow. Unbeknownst to Captain

Rivera and the crew on the bridge, Pilot Thomas previously allowed the tug AVON II to cast off

from the stern because she was having a problem with her lines to the BELLATRIX. Because of the

configuration of BELLATRIX's bridge, the stern was not visible from the bridge, so Captain Rivera

could not have seen the release of the AVON II. In compliance with Pilot Thomas' direction, one of

BELLATRIX's crew members had released AVON II's lines. He reported his action to the bridge,

but did not get confirmation that the message was received, as he was required to do. The message

was not received by the bridge and Pilot Thomas did not tell Captain Rivera about releasing AVON

II.

       At 0828, while the vessel was still perpendicular in the river, Pilot Thomas ordered dead slow

ahead on the port engine, which was followed by a slow ahead at 0829 hours and full ahead at 0831

hours. The rudder at this time was at hard left.

       It soon became clear that the ship could not make the turn. Pilot Thomas tried to call the

MISS SARAH back to the vessel to assist, but the tug could not make it back. The port engine

remained on full ahead until 0834 hours, when Pilot Thomas ordered full astern on the port engine

and drop anchor. At 0836 hours, the BELLATRIX made contact with Avondale's dry dock.

                                    STANDARD OF REVIEW

        Avondale challenges both the findings of fact and the conclusions of law entered by the

district court. In an admiralty action tried by the court without a jury, the factual findings of the

District Court are binding unless clearly erroneous. Todd Shipyards Corp. v. Turbine Service, Inc.,

674 F.2d 401
(5th Cir.1982). Questions concerning the existence of negligence and causation are

treated as factual issues subject to the clearly erroneous standard. Todd at 405.

        Questions of contract interpretation, as well as all other questions of law are subject to de

novo review. Dow Chemical Company v. M/V ROBERTA TABOR, 
815 F.2d 1037
, 1042 (5th

Cir.1987).

                                           CAUSATION
       The district court found that the casualty was caused by Pilot Thomas because he (1) failed

to wait until the BELLATRIX had both of her engines available before commencing the left turn

down river; (2) prematurely released the AVON II from the turning maneuver; and (3) released the

MISS SARAH before the BELLATRIX fully completed her turn and was safely headed down river.

The district court further found that no act or omission on the part of Captai n Rivera or his crew

contributed to the accident. Appellant, Avondale, does not challenge the finding that Pilot Thomas'

negligence was a cause of the allision. Rather they contend that they affirmatively showed that the

loss or damage to the BELLATRIX was also proximately caused by the acts and omissions of

Captain Rivera and his crew.

       In order to determine the causation question, we must first explore the relationship between

and relative responsibilities of the master of a ship and a compulsory pilot. In The CHINA, 
74 U.S. 53
, 
7 Wall. 53
, 
19 L. Ed. 67
(1868) the Supreme Court held that the master has a duty to intervene

when a compulsory pilot is on board only "in cases of the pilot's intoxication or manifest incapacity,

in cases of danger he does not foresee, and in all cases of great necessity." After a discussion of then

existing authority the Supreme Court concluded:

       The statute giving t he immunity [to a vessel and her owner] where a licensed pilot is
       employed, abridges the natural right of the injured party to compensation, and is therefore to
       be construed strictly.

               The exemption applies only where the pilot is actually in charge of the vessel, and
       solely in fault.

              If there be anything which concurred with the fault of the pilot, in producing the
       accident, the exemption does not apply, and the vessel, master, and owners are liable.

               The colliding vessel is in all cases prima facie responsible. The burden of proof rests
       upon the party claiming the benefit of the exemption. He must show affirmatively that the
       pilot was in fault, and that there was no fault on the part of the officers or crew, "which might
       have been in any degree conducive to the damage'.

       The pilot's responsibilities are broad and he supersedes the master for the time being in the

command and navigation of the ship and his orders must be obeyed in all matters connected with

navigation. However, "the master is not wholly absolved from his duties while the pilot is on board

and may advise him and even displace him in case he is intoxicated or manifestly incompetent. He

is still in command of the vessel, except so far as her navigation is concerned, and bound to see that
there is sufficient watch on deck and that the men are attendant to their duties." The OREGON, 
158 U.S. 186
, 194-195, 
15 S. Ct. 804
, 808, 
39 L. Ed. 943
(1895).

        The master is entitled to assume that the pilot is an expert on local conditions and practices,

until it becomes manifest that the pilot is steering the vessel into danger. Kim Crest, S.A. v. M/V

SVERDLOVSK, 
753 F. Supp. 642
, 646 (S.D.Tex.1990). In M/V SVERDLOVSK, the master did

intervene and take responsibility away from the pilot, but not early enough to prevent the collision.

Although that court's discussion of whether the master was negligent in not intervening earlier is very

fact specific, and distinguishable from the case before us, M/V SVERDLOVSK, supports the

conclusion that the master has a responsibility to monitor the pilot's decision making. If the master's

responsibility to intervene in cases of great necessity means anything, it must require that he have an

adequate level of information to determine when "great necessity" arises. Captain Rivera's omission

was not simply in failing to intervene, but rather in failing to pay attention so that he would know that

he needed to intervene. His responsibility to observe and ask questions increased as the margin of

error decreased. The original plan was to turn the BELLATRIX with three tugs and two engines.

Prior to the allision, Captain Rivera was aware that the turn was being attempted with one failed

engine and one tug (which in fact had also been released.)

        The master and the pilot both testified, without contradiction in the record, that the master

was in charge at all times. The master testified that he has countermanded a pilot's orders on previous

occasions during his command of the BELLATRIX and that he would have done so in this case had

he known that the AVON II had been released.

        Appellees argue, without authority, that it would set dangerous precedent to require the

master to intervene to avoid a finding of negligence, as masters should normally rely on the greater

knowledge and familiarity of the local pilot. This Court is not convinced that finding the master

negligent in this situation would disrupt the normal reliance on pilots by masters.

        It is clear in the evidence that the master failed to monitor the progress of the turn and failed

to intervene when it was necessary to avoid the allision.

        Further, testimony established that when the pilot released the AVON II, the tug captain told
the first mate to let her go. The first mate did release her, and reported his action to the bridge.

However because of noise and static interference, the information was not received on the bridge or

acknowledged. The first mate made no further attempts to communicate the information to the

bridge. Captain Rivera properly had standing orders that such information should be repeated until

acknowledgement is received. Captain Rivera's testimony that he would have countermanded the

pilot's order to release the MISS SARAH if he had known that the AVON II had already been

released, convinces us that the first mate's negligence was also a proximate cause of the allision.

       For these reasons, we are convinced that the district court's finding that no act or omission

on the part of Captain Rivera or his crew contributed to the accident is clearly erroneous.

                                         THE CONTRACT

       IMC, as agent for the United States entered into a contract with Avondale that, among other

things, altered the normal maritime liability scheme by setting out which party would be responsible

for damages that occurred during the course of the contract. Under the heading Contractor

Responsibilities and Insurance, the parties agreed as follows:

               11(d) The Contractor [Avondale] hereby indemnifies and holds harmless the
       Government, its agencies and instrumentalities, the vessel and the Operator, against all suits,
       actions, claims, costs or demands (including, without limitation, suits, actions, claims, costs
       or demands resulting from death, personal injury and property damage) to which the
       Government, its agencies and instrumentalities, the vessel or the Operator may be subject by
       reason of damage or injury (including death) to the property or person of anyone other than
       the Government, its agencies, personnel and instrumentalities, the vessel or the Operator,
       arising or resulting from the default, negligence, wrongful act, or omission of the Contractor
       or any subcontractor, his or their servants, agents, or employees.

               11(e) The Contractor shall be responsible for and make good at his own cost and
       expense any and all loss of, or damage of whatsoever nature to, the vessel (or portion
       thereof), its equipment, movable stores and cargo, and Government owned materials and
       equipment for the repair, completion, alteration or addition to the vessel in the possession of
       the Contractor, whether at the Contractor's plant or elsewhere, arising or growing out of the
       performance of the work, except where the Contractor can affirmatively show that such loss
       or damage was due to causes beyond the Contractor's control, was proximately caused by
       agents or employees of the Operator or the Government, or which loss or damage the
       Contractor by the exercise of reasonable care was unable to prevent; provided that the
       Contractor shall not be responsible for any such loss or damage discovered after completion
       of the work and redelivery of the vessel to the Operator, unless (i) such loss or damage is
       discovered no more than 90 days after completion of the work and such redelivery, and (ii)
       such loss or damage is affirmatively shown to have been the result of the fault or negligence
       of the Contractor. (emphasis added)

             AVONDALE'S CLAIM FOR DAMAGES UNDER THE CONTRACT
        Under clause 11(d), Avondale must indemnify the Government and IMC against damages

to the dry dock and barges caused by the negligence of its subcontractors. It is therefore necessary

to determine if Pilot Thomas was Avondale's subcontractor.

        Avondale contends that Pilot Thomas was an independent contractor and therefore Avondale

is not precluded from recovering for damages caused by the allision. The Appellees contend here,

as they did below, that Pilot Thomas was Avondale's subcontractor, and that Avondale must therefore

indemnify the Government and IMC for the damages. The district court found that Pilot Thomas was

not an independent contractor, and that Avondale was therefore not entitled to recover from the

Government and IMC for damages to the dry dock and the barges.

        A subcontractor is one who takes a portion of a contract from the principal contractor or

another subcontractor. Hardware Mut. Casualty Co. v. Hilderbrandt, 
119 F.2d 291
(10th Cir.1941).

The record reflects that Avondale contracted to provide "tugs, pilots, [and] linehandlers." Pilot

Thomas then contracted with Avondale to perform the piloting duties that Avondale was obligated

to provide under the contract. Pilot Thomas was a subcontract or for purposes of the indemnity

clause of the contract. The lower court's discussio n concerning whether or not Thomas could be

considered an independent contractor is irrelevant to this analysis. The two terms are not mutually

exclusive. A subcontractor may or may not have an agency relationship with the contractor and that

relationship does not control whether or not a subcontract has been struck.

        Based on the conclusion that Pilot Thomas was Avondale's subcontractor, Avondale is

precluded by paragraph 11(d) of the contract from recovering from the Government and IMC the

damages to its facilities caused by the negligence of the pilot.

        When two or more parties have contributed by their fault to cause property damage in a

maritime collision, liability for such damage is to be allocated among the parties proportionately to

the comparative degree of their fault. If the parties are equally at fault or when it is not possible to

fairly measure the comparative degree of their fault, liability for such damage is to be allocated

equally. United States v. Reliable Transfer Company, Inc., 
421 U.S. 397
, 409-411, 
95 S. Ct. 1708
,

1715, 
44 L. Ed. 2d 251
, 262 (1975), Sincere Navigation Corporation v. United States, 
529 F.2d 744
(5th Cir.1976). Under these comparative negligence provisions of general maritime law, Avondale

is entitled to recover from the Government that portion of the damages to the Avondale facilities

caused by the negligence of the Government's agents.

 THE GOVERNMENT'S CONTRACT CLAIM AGAINST AVONDALE FOR DAMAGES TO
THE VESSEL

       Pursuant to clause 11(e), set out above, Avondale is responsible for the damage to the vessel,

arising or growing out of the performance of the work, unless the damage was proximately caused

by agents or employees of IMC or the Government.

        First we must determine whether the turning maneuver was part of the services contemplated

by the contract. We conclude that is was. The record demonstrates that Avondale contracted to

provide services of tugs, a pilot, and linehandlers during the turn.

        Second, Avondale has affirmatively shown that a portion of the damage to the vessel was

proximately caused by agents and employees of the Government and IMC. The "except" clause of

paragraph 11(e) of the contract does not require Avondale to show that acts or omissions of the

agents and employees of the Government and IMC were the sole proximate cause of the damage, and

indeed, in this case they were not. Having found that acts and omissions of the master and crew of

the BELLATRIX were a proximate cause of the allision, we conclude that Avondale is not

responsible for that portion of the damage to the vessel proximately caused by the Government's

agents or employees, even if that damage arose or grew out of the performance of the contract.

Therefore, under the contract, Avondale is respo nsible only for that portion of the damage not

proximately caused by the government.

       LIABILITY FOR PILOT NEGLIGENCE UNDER GENERAL MARITIME LAW

       The United States also makes a claim against Avondale for damages to the vessel under

general maritime law. Having found that the contract controls the relationship of the parties in so far

as responsibility for the negligence of Avondale's subcontractors, and the master and agents of the

United States is concerned, we need not reach the question of how the United States' claim would

be decided under general maritime law.

                                           CONCLUSION
       We REVERSE the lower court's finding that no action or omission of the master and crew

contributed to the allision. The government is liable to Avondale for damages to Avondale's facilities

to the extent of the fault attributable to the government. The contract provision making Avondale

responsible for damages to the vessel arising out of the performance of the contract imposes liability

on Avondale for that portion of the damages not proximately caused by the Government, its agents

or employees.

       Based on the foregoing, the judgment for the United States in the amount of $637,380.00 is

VACATED. The judgment for IMC and the United States, dismissing Avondale's claim for damages

is REVERSED. The case is REMANDED, in order that the district court may determine the

appropriate apportionment of damages to each party under the rule of comparative negligence.
