Elawyers Elawyers
Washington| Change

Nottingham Const Co v. City of Waveland, 08-60255 (2008)

Court: Court of Appeals for the Fifth Circuit Number: 08-60255 Visitors: 5
Filed: Sep. 10, 2008
Latest Update: Feb. 21, 2020
Summary: IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit FILED September 10, 2008 No. 08-60255 Charles R. Fulbruge III Summary Calendar Clerk NOTTINGHAM CONSTRUCTION COMPANY, L.L.C. Plaintiff-Appellant v. CITY OF WAVELAND Defendant-Appellee Appeal from the United States District Court for the Southern District of Mississippi USDC No. 1:07-CV-1151-LG-RHW Before JOLLY, BENAVIDES, and HAYNES, Circuit Judges. PER CURIAM:* This case arises from a compla
More
           IN THE UNITED STATES COURT OF APPEALS
                    FOR THE FIFTH CIRCUIT United States Court of Appeals
                                                   Fifth Circuit

                                                                            FILED
                                                                        September 10, 2008

                                     No. 08-60255                     Charles R. Fulbruge III
                                   Summary Calendar                           Clerk


NOTTINGHAM CONSTRUCTION COMPANY, L.L.C.

                                                  Plaintiff-Appellant
v.

CITY OF WAVELAND

                                                  Defendant-Appellee



                   Appeal from the United States District Court
                     for the Southern District of Mississippi
                       USDC No. 1:07-CV-1151-LG-RHW


Before JOLLY, BENAVIDES, and HAYNES, Circuit Judges.
PER CURIAM:*
       This case arises from a complaint filed by Nottingham Construction
Company, L.L.C. (“Nottingham”) against the City of Waveland (“Waveland”) as
a result of Waveland’s award of a construction project to Hemphill Construction
Company (“Hemphill”) pursuant to a public bidding process. Nottingham alleges
that the contract resulted from collusion, bid rigging and/or favoritism. The
district court granted Waveland’s motion to dismiss on the basis of a statutory


       *
         Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
R. 47.5.4.
                                  No. 08-60255

requirement that any appeal of a decision by a municipality be filed within ten
days from the date of the decision. For the reasons stated herein, we affirm.
                                        I.
      In December 2006, Waveland received bids from numerous contractors for
a sewer and water system reconstruction project (the “Project”). During the
bidding process, Waveland’s engineer, Digital Engineering and Imaging, Inc.,
told Nottingham that it could not use excavated materials as select backfill on
the project. This information was significant because Nottingham alleges that
the use of excavated materials as select backfill, as opposed to hauling in new
material to use as backfill, can dramatically reduce the expense of the project.
The written communications concerning use of excavated materials as backfill
were attached to Contract Addendum No. 2 for the Project at the request of
Nottingham.
      Nottingham’s bid of $27,472,620.00 was the second lowest among the
contractors. Nottingham asserts that the use of excavated materials as select
backfill would have reduced its bid for the project by $4,000,000.00. The lowest
bid for the project was submitted by Hemphill in the amount of $23,639,425.00.
Waveland awarded the contract to Hemphill, which was executed on April 4,
2007. Nottingham does not dispute that it knew the contract was awarded to
Hemphill.
      After the project had been underway for several months, a Nottingham
representative witnessed Hemphill using excavated materials as backfill.
Nottingham contacted the engineering firm regarding the use of excavated
materials as backfill and alleges that a representative of the engineering firm
admitted that the materials were being used and also admitted that Hemphill
was not required to use a deductive change order to reflect the lower costs.
Nottingham alleges that since Hemphill was allowed to use excavated materials
as backfill, the contract resulted from collusion, bid rigging, and/or favoritism.


                                        2
                                  No. 08-60255

      On August 29, 2007, Nottingham notified Waveland of its claim for
damages and its protest of the award of the Project. Waveland sent a letter
through its attorney denying Nottingham’s request for a hearing on its claim for
damages. On October 19, 2007, Nottingham filed a Complaint against Waveland
seeking damages it allegedly suffered when it was not awarded the contract for
the Project.
      In response to the complaint, Waveland filed a motion to dismiss
challenging the timeliness of Nottingham’s complaint under MISS. CODE ANN.
§ 11-51-75. The district court agreed that Nottingham’s complaint was not
timely filed and dismissed it pursuant to FED. R. CIV. PROC. 12(b)(6).
                                        II.
      We review de novo the district court’s order on a motion to dismiss under
Rule 12(b)(6). In re Katrina Canal Breaches Litig., 
495 F.3d 191
, 205 (5th Cir.
2007), cert. denied, Chehardy v. Allstate Indem. Co., --- U.S. ---, 
128 S. Ct. 1231
(2008) and Xavier Univ. of La. v. Travelers Cas. Prop. Co. of Am., --- U.S. ---, 
128 S. Ct. 1230
(2008). “The court accepts all well-pleaded facts as true, viewing
them in the light most favorable to the plaintiff.” 
Id. (internal quotations
omitted). Because this case is in federal court based on diversity jurisdiction, we
must follow Mississippi’s substantive law as interpreted by Mississippi’s highest
court. See Erie R.R. Co. v. Tompkins, 
304 U.S. 64
, 78 (1938); Am. Nat’l Gen. Ins.
Co. v. Ryan, 
274 F.3d 319
, 328 (5th Cir. 2001).
      MISS. CODE ANN. § 11-51-75 provides:
      Any person aggrieved by a judgment or decision of the board of
      supervisors, or municipal authorities of a city, town, or village, may
      appeal within ten (10) days from the date of adjournment at which
      session the board of supervisors or municipal authorities rendered
      such judgment or decision, and may embody the facts, judgment and
      decision in a bill of exceptions which shall be signed by the person
      acting as president of the board of supervisors or of the municipal
      authorities.


                                         3
                                  No. 08-60255

The Mississippi Supreme Court has held that the ten-day time limit is
mandatory.     Newell v. Jones County, 
731 So. 2d 580
, 582 (Miss. 1999).
Accordingly, an action challenging a municipality’s decision to enter into a
contract must be filed within ten-days of date of adjournment of session where
the decision was made or the claims will be dismissed. 
Id. It is
undisputed that
Nottingham’s claims challenging Waveland’s contract with Hemphill were not
filed within ten days from the date of the contract.
      Nottingham asserts that § 11-51-75 does not apply to the present case
because Waveland has not made any final decision with respect to Nottingham’s
protest. We disagree. The decision to award the contract to Hemphill, not the
resolution of Nottingham’s protest, is the basis of Nottingham’s claims.
Nottingham cannot restart the clock on its deadline to challenge the award of
the contract to Hemphill by filing an untimely protest. Otherwise, the ten-day
requirement of § 11-51-75 would be meaningless.
      In support of its argument, Nottingham relies almost entirely on Shepard
v. City of Batesville, No. 2:04-CV-330, 
2007 WL 108288
, (N.D. Miss. Jan. 8,
2007). In Shepard, the plaintiff demonstrated that he was the lowest and best
bidder on several contracts to perform earthmoving work for the City of
Batesville. 
2007 WL 108288
at *6. Although the city found him to be the lowest
and best bidder, the city only gave him one of the jobs. 
Id. The city
claimed that
it hired other contractors to perform the rest of the work because it could not
reach the plaintiff by telephone. 
Id. The court
held there was no evidence that
the city ever made a final decision awarding the other jobs to different bidders
or gave notice of any such decision. 
Id. As a
result, the court held that the ten-
day time limit provided for under § 11-51-75 was never triggered. 
Id. Shepard is
not binding on this court. To the extent that it is persuasive
authority, it is clearly distinguishable. The pivotal fact in Shepard was that the
city decided that the plaintiff was the lowest and best bidder but then used other

                                        4
                                  No. 08-60255

bidders without notice to the plaintiff. 
Id. In the
present case, Nottingham was
never declared the lowest and best bidder, Waveland gave notice that the
contract was awarded to Hemphill, and the decision to award the contract to
Hemphill was a final decision. Therefore, Nottingham’s reliance on Shepard is
misplaced.
      Nottingham also argues on appeal that it did not become a “person
aggrieved” under § 11-51-75 until it witnessed Hemphill’s use of excavation
materials as backfill several months after the decision to award the contract was
made. In its response to Waveland’s motion to dismiss, Nottingham never
asserted to the district court that it was not a “person aggrieved” when the
contract was awarded to Hemphill. Rather, Nottingham’s argument to the
district court was based on its contention that there was no final decision to
appeal pursuant to § 11-51-75. Because Nottingham raises this argument for
the first time on appeal, we will review only for plain error. See Crawford v.
Falcon Drilling Co., 
131 F.3d 1120
, 1123 (5th Cir. 1997). Under plain error
review, “we must determine (1) if there was error, (2) if that error was plain, (3)
if the error affects substantial rights, and (4) whether allowing that error to
stand seriously affects the fairness, integrity, or public reputation of judicial
proceedings.” 
Id. at 1124
(emphasis added). The test is conjunctive, meaning
that before we can reverse, all four prongs must be met. Even assuming,
arguendo, that the district court erred, any such error was not plain.
      Nottingham’s claims are based on the theory the contract awarded to
Hemphill by Waveland resulted from collusion, bid rigging, and/or favoritism.
If Nottingham’s allegations of bid rigging are true, as we assume for purposes
of this appeal, then Waveland’s wrongful conduct and Nottingham’s injury




                                        5
                                       No. 08-60255

occurred when the contract was awarded to Hemphill, not when Nottingham
became aware of the alleged bid rigging.1
       Nottingham fails to cite any authority for the proposition that a person
who is injured by a final decision of a municipal authority is not a “person
aggrieved” until he becomes aware that the decision was the result of wrongful
conduct. The two Mississippi Supreme Court cases it cites only stand for the
proposition that a “person aggrieved” must have some interest in the decision
appealed, although that interest need not be recognized as a property interest.
See Nelson v. City of Horn Lake, 
968 So. 2d 938
, 944-45 (Miss. 2007) (holding
that a losing bidder was a “person aggrieved” under § 11-51-75 although it did
not have a property interest in the contract awarded to another bidder);
Thornton v. Town of Charleston, 
68 So. 169
, 171 (Miss. 1915) (“we have
construed ‘persons aggrieved’ and ‘persons interested’ as synonymous terms”).
Nothing in either Nelson or Thornton suggests that an unsuccessful bidder is not
a “person aggrieved” until he becomes aware of wrongful conduct that occurred
during the bidding process. The district court did not plainly err in holding that
Nottingham was a “person aggrieved” under § 11-51-75 when the contract was
awarded to Hemphill.
       Nottingham’s arguments essentially boil down to the contention that
§ 11-51-75 is bad public policy because it allows undiscovered acts of bid rigging
to go unchecked. Of course, as Nottingham itself notes, the statutes regarding
bidding are designed to protect the taxpaying public. There are several criminal
statutes that protect taxpayers from fraudulent and collusive bidding in public
works contracts. See, e.g., Miss Code Ann. §§ 97-7-11, 97-11-31, 97-11-53, 97-15-


       1
         If there was no bid rigging at the time the contract was entered into, then Nottingham
has no interest in the contract and lacks standing to challenge the failure of Waveland to
require a deductive change order for the use of excavated materials as select backfill on the
project. See Nelson v. City of Horn Lake, 
968 So. 2d 938
, 945 (Miss. 2007) (holding that lowest
priced bidder did not have property interest in contract awarded to competitor).

                                              6
                                         No. 08-60255

11. Thus, the implication that this court must fashion some remedy to avoid the
effects of § 11-51-75 in order to promote public policy against bid rigging is
unavailing. If Hemphill has committed wrongdoing, redress for taxpayers exists.
       Although not raised by Nottingham in response to Waveland’s motion to
dismiss,2 the district court also considered whether the “discovery rule” could
save Nottingham’s claims. The district court concluded that the discovery rule
does not apply to § 11-51-75. In its briefs to this court, Nottingham again does
not discuss whether the discovery rule applies to § 11-51-75.3                          Because
Nottingham does not assert in its briefs that the discovery rule tolls the ten-day
time limit under § 11-51-75, that issue has been waived on appeal. See Audler
v. CBC Innovis Inc., 
519 F.3d 239
, 255 (5th Cir. 2008) (“A party waives an issue
if he fails to adequately brief it” (internal quotation marks omitted)); see also
FED. R. APP. P. 28(a)(9)(A) (“The appellant’s brief must contain . . . appellant’s
contentions and the reasons for them, with citations to the authorities and parts
of the record on which the appellant relies.”).
       Accordingly, the judgment of the district court is AFFIRMED.




       2
          The closest it came in the district court was the following, which was part of a section
containing no citation to cases discussing the discovery rule: “Nottingham had no knowledge
of its claims against Waveland nor could it possibly have been expected to have knowledge of
such claims. . . . It was impossible for Nottingham to learn of Waveland’s illegal actions . . . .”
       3
        The Mississippi Supreme Court recently addressed this question in Caves v.
Yarbrough, No. 2006-CA-01857-SCT, 
2007 WL 3197504
(Miss. Nov. 1, 2007), motion for reh’g
argued and submitted (June 10, 2008).

                                                7

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer