Elawyers Elawyers
Ohio| Change

In Re: Katrina Canal Breaches, 09-30438 (2010)

Court: Court of Appeals for the Fifth Circuit Number: 09-30438 Visitors: 79
Filed: Sep. 14, 2010
Latest Update: Feb. 21, 2020
Summary: IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit FILED September 14, 2010 Lyle W. Cayce Clerk No. 09-30449 IN RE: KATRINA CANAL BREACHES LITIGATION. STEERING COMMITTEE, Plaintiff-Appellant, versus WASHINGTON GROUP INTERNATIONAL, INC., Defendant-Appellee. *************** No. 09-30428 IN RE: KATRINA CANAL BREACHES LITIGATION. QUINTESSA HUEY, CARYN L. FONG, as Trustees of the Huey & Fong Trust; AMY HUEY, as Trustee of the Kenneth Huey Family
More
         IN THE UNITED STATES COURT OF APPEALS
                  FOR THE FIFTH CIRCUIT United States Court of Appeals
                                                 Fifth Circuit

                                                              FILED
                                                        September 14, 2010

                                                             Lyle W. Cayce
                                                                  Clerk


                              No. 09-30449



IN RE: KATRINA CANAL BREACHES LITIGATION.

STEERING COMMITTEE,

                                      Plaintiff-Appellant,

versus

WASHINGTON GROUP INTERNATIONAL, INC.,

                                      Defendant-Appellee.

                         ***************
                        No. 09-30428


IN RE: KATRINA CANAL BREACHES LITIGATION.

QUINTESSA HUEY,
CARYN L. FONG, as Trustees of the Huey & Fong Trust;
AMY HUEY, as Trustee of the Kenneth Huey Family Trust;
RADIO PARTS, INC.; ENTERCOM COMMUNICATIONS CORPORATION;
ET AL.,

                                 Plaintiffs-Appellants,

versus

WASHINGTON GROUP INTERNATIONAL, INC.,

                                 Defendant-Appellee.

                    ***************


                        No. 09-30438


IN RE: KATRINA CANAL BREACHES LITIGATION.

BETTY LUNDY; FREDERICK ADAMS; JEAN ADDISON;
JONATHAN AKERS; OLLIE P. ALEXANDER; ET AL.,

                                 Plaintiffs-Appellants,

versus

WASHINGTON GROUP INTERNATIONAL, INC.,

                                 Defendant-Appellee.



                             2
                Appeals from the United States District Court
                    for the Eastern District of Louisiana




Before SMITH, WIENER, and ELROD, Circuit Judges.
JERRY E. SMITH, Circuit Judge:


      Washington Group International, Inc. (“WGI”) provided engineering, con-
struction, and management services. The United States Army Corps of Engin-
eers (“the Corps”) contracted with WGI for a large project in New Orleans. The
plaintiffs sued WGI, claiming that its negligent and improper actions in fulfilling
the contract were a cause of flood damage resulting from Hurricane Katrina.
The district court granted summary judgment for WGI based on government-
contractor immunity (“GCI”). Because the specifications for the work at issue
were not reasonably precise, WGI has no GCI, so we reverse the summary judg-
ment and remand.


                                        I.
      In 1994, the Corps and WGI entered into an indefinite delivery/indefinite
quantity contract for the remediation of some hazardous, toxic, and radioactive
waste sites in the southwestern United States. That “umbrella contract,” known
as the Total Environmental Restoration Contract (“TERC”), set forth general re-
quirements for all of WGI’s anticipated work in the region, with the understand-
ing that the Corps would approve a specific Statement of Work (“SOW”) for each
Task Order it would issue to WGI.


                                        3
                      Nos. 09-30449, 09-30428, 09-30438

      In 1999, the Corps began its Inner Harbor Navigation Canal Lock Replace-
ment Project in New Orleans, one aspect of which was the cleanup of the East
Bank Industrial Area. Pursuant to the TERC, WGI was obligated (1) to demol-
ish existing structures in that area by removing surface and subsurface obstruc-
tions, (2) to characterize contaminants on the site, and (3) to remediate the site
in accordance with any applicable environmental standards. This specific task
was contracted for and identified as Task Order 26 of the TERC.
      In June 1999, the Corps issued a SOW for Task Order 26 that was brief
and provided only a general description of the work to be done. From that SOW,
WGI submitted a more detailed work plan to the Corps. After receiving the work
plan, the Corps engaged WGI in a review process during which the Corps would
comment on issues it had with WGI’s proposals, solicit a response from WGI on
those comments, and continue in such a back-and-forth manner until the Corps
and WGI had come to an agreement regarding any matters that were in conflict.
      The review process included the completion of various technical analyses
and recommendation reports by the Corps and additional work plans by WGI.
A final Recommendation Report was formally issued in January 2000, after
which it became “the basis of subsequent specifications for work and work orders
and proposals.”
      After completion of the Recommendation Report process, the Corps issued
another SOW that, once again, provided general directions to WGI. From that
SOW, WGI drafted eight work plans for the specific project and submitted them
to the Corps for comment and approval. The most important of those work
plans, for our purposes, was the Project Work Plan, which dealt with the equip-
ment, the excavation, and the remediation process for the areas at issue in the
plaintiffs’ claim.

                                        4
                          Nos. 09-30449, 09-30428, 09-30438

       Once work had begun, WGI discovered previously unknown subsurface
structures in the area to be remediated. In August 2001, the Corps issued an-
other SOW to address the excavation and disposal of those newly discovered
structures. Pursuant to that SOW, and in compliance with all the previously ap-
proved plans, WGI submitted Proposal #113, which dealt with the excavation
and disposal of the new subsurface structures.
       In its Technical Analysis of Proposal #113, the Corps deemed WGI’s pro-
posal too costly, rejected it, and suggested several elements of the proposal as to
which cost savings could be achieved. One of those suggestions was to use on-
site borrow matter as the primary source of backfill material.1 The final propos-
al submitted by WGI, and approved by the Corps, incorporated that suggestion
by stating that “[t]he excavations . . . will be backfilled with borrow material
obtained from either the on-site borrow source or an off-site source.”
       The final approved proposal also stated that the backfill “material will be
placed in lifts and compacted; however, no compaction testing will be required.”2
The work plans derived from the final proposal also specified that compaction
should occur “with previous excavated soil in 2' lifts,” that “[i]nitial backfill oper-
ations will be to the bottom of the whalers inside the [subsurface obstruction],”
and that backfilling should be completed “to the top of sheet piles with material
to be provided by WGI after whalers are removed.” Working from that approved
proposal and from subsequent work plans derived from it, WGI completed the
project in the spring of 2005.

       1
        Backfill material is the physical matter used to refill holes created by the removal of
subsurface structures.
       2
         Compaction is the process of increasing the bulk density of an aggregate of matter by
driving out air.

                                              5
                       Nos. 09-30449, 09-30428, 09-30438

      In August 2005, Hurricane Katrina made landfall near New Orleans. As
a result, the flood protection system in the Inner Harbor Navigation Canal pro-
ject, consisting of levees and floodwalls, failed. Two of the breaches in the levees
were near areas that were part of the zone where WGI had conducted extensive
work. The plaintiffs claim that the failure of those levees was a result of the
negligent and improper backfilling and compaction of the excavated locations by
WGI in violation of a state-law duty of care. Specifically, the plaintiffs allege
that the method of excavation and backfilling employed by WGI allowed for un-
derseepage, which undermined the integrity of the levees, resulting in their fail-
ure and the subsequent flooding of New Orleans East, the Lower Ninth Ward,
and St. Bernard Parish.


                                        II.
      In 2007, the plaintiffs, in several consolidated actions, sued WGI, the
Corps, and numerous other defendants for harm resulting from Hurricane Ka-
trina-related damages. In 2008, WGI moved for summary judgment, asserting
the GCI defense. The plaintiffs opposed summary judgment on the grounds that
(1) GCI does not apply because there was no conflict with state law, and (2) even
assuming such a conflict, WGI failed to satisfy the Supreme Court’s three-part
test for GCI. The district court granted summary judgment for WGI, concluding
that displacement of state law is built into the GCI defense and that WGI had
satisfied all the requirements for GCI.


                                        III.
      We review a summary judgment de novo, “using the same standard as that
employed by the district court under Rule 56.” Kerstetter v. Pac. Scientific Co.,

                                          6
                           Nos. 09-30449, 09-30428, 09-30438

210 F.3d 431
, 435 (5th Cir. 2000). Summary judgment is warranted where
“there is no genuine issue as to any material fact and [] the movant is entitled
to judgment as a matter of law.” FED. R. CIV. P. 56(c)(2). There is no genuine is-
sue for trial “[i]f the record, taken as a whole, could not lead a rational trier of
fact to find for the nonmoving party.” Kipps v. Caillier, 
197 F.3d 765
, 768 (5th
Cir. 1999).


                                               A.
       The Supreme Court first recognized the federal GCI defense to state tort
law in Boyle v. United Technologies Corp., 
487 U.S. 500
(1988). The GCI defense
preempts state law to immunize government contractors from liability in spite
of the absence of legislation specifically immunizing them.3 The rationale for
GCI flows from two basic principles: “[S]tate tort law is preempted by federal
common law in areas of unique federal interests” and “the procurement of equip-
ment by the United States is such an area.” Trevino v. Gen. Dynamics Corp.,
865 F.2d 1474
, 1479 (5th Cir. 1989). In Boyle, the Court specified the precise
scope of the displacement of state law, using a three-part test:

       Liability for design defects in military equipment cannot be im-
       posed, pursuant to state law, when (1) the United States approved
       reasonably precise specifications; (2) the equipment conformed to
       those specifications; and (3) the supplier warned the United States
       about the dangers in the use of the equipment that were known to
       the supplier but not to the United States.

       3
          In their reply brief, the plaintiffs contend that the GCI defense from Boyle is applica-
ble only to military contractors and should not be extended. That argument is waived, because
it was not made in the plaintiffs’ opening brief. Morgan v. Swanson, 
610 F.3d 877
, 884 n.10
(5th Cir. 2010) (stating that issues raised for the first time in appellant’s reply brief are
waived).

                                                7
                        Nos. 09-30449, 09-30428, 09-30438


Boyle, 487 U.S. at 512
.

                                         B.
        The plaintiffs argue that the district court erred in failing to conduct a
threshold inquiry into the existence of a significant conflict between federal poli-
cy and state law. They incorrectly assert that this inquiry is necessary to an
application of the Boyle test. Although a conflict between federal policy and
state law is a necessary element of any finding of GCI, a threshold inquiry on
that specific issue is not necessary but, rather, is built into the three-part Boyle
test.
        Following oral argument in the instant case, a different panel of this court
decided Jowers v. Lincoln Electric Co., No. 09-60396, 
2010 U.S. App. LEXIS 17862
(5th Cir. Aug. 26, 2010). There, the district court had included in the jury
instructions a threshold inquiry that the government contractor challenged on
appeal. This court held that “an additional instruction that the jury find a ‘sig-
nificant conflict’ between federal interests and Mississippi law in the instant
matter is superfluous and forces the jury to construe an issue of law, which is
outside its purview as a fact-finder.” 
Id. at *9.
Though the panel focused on the
role of the jury as a factfinder, its conclusion that a threshold inquiry is “super-
fluous” is a statement on the general applicability of the GCI defense.
        Additionally, though this circuit never had occasion, before Jowers, to ad-
dress the “significant conflict” issue, we have consistently applied the Boyle test
without conducting any sort of threshold inquiry similar to the one these plain-




                                          8
                           Nos. 09-30449, 09-30428, 09-30438

tiffs request.4 Preemption of state law by federal law without a statutory man-
date can occur only where “a ‘significant conflict’ exists between an identifiable
federal policy or interest and the operation of state law, or the application of
state law would frustrate specific objections of federal legislation,” 
Boyle, 487 U.S. at 507
(internal quotation marks and citations omitted), but, importantly,
“[t]he first two of these conditions assure that the suit is within the area where
the policy of the ‘discretionary function’ would be frustrated,” 
id. at 512.
       By assuring that the suit involves a situation in which the discretionary
function is frustrated, the first of the three Boyle conditions necessarily satisfies
the earlier-stated requirement of a significant conflict. See Lewis v. Babcock In-
dus., Inc., 
985 F.2d 83
(2d Cir. 1993); 
Kerstetter, 210 F.3d at 438
. “Whether [the
GCI defense] will apply to a particular claim depends only upon whether Boyle’s
three conditions are met with respect to the particular product feature upon
which the claim is based.” 
Bailey, 989 F.2d at 801-02
(5th Cir. 1993) (emphasis
in original). A threshold inquiry into whether there is a significant state conflict
has never been required by any court,5 nor should it be. The only analysis

       4
         See, e.g., Miller v. Diamond Shamrock Co., 
275 F.3d 414
, 419 (5th Cir. 2001); Kerstet-
ter, 210 F.3d at 435
; In re Air Disaster at Ramstein Air Base, Germany, 
81 F.3d 570
, 574 (5th
Cir. 1996); Bailey v. McDonnell Douglas Corp., 
989 F.2d 794
, 798 (5th Cir. 1993); Stout v.
Borg-Warner Corp., 
933 F.2d 331
, 334 (5th Cir. 1991); 
Trevino, 865 F.2d at 1479
.
       5
         In 
Lewis, 985 F.2d at 83
, the court directly addressed the issue of whether the Boyle
test requires a threshold inquiry into the presence of a “significant conflict” with state law. It
held that “answering the question whether the Government approved reasonably precise
specifications for the design feature in question necessarily answers the question whether the
federal contract conflicts with state law.” 
Id. at 86.
       The plaintiffs argue that Lewis was implicitly overruled by In re World Trade Center
Disaster Site Litigation, 
521 F.3d 169
(2d Cir. 2008), in which the court stated that “[a]s a
threshold matter, the defense only arises in an area of uniquely federal interest, where a sig-
                                                                                 (continued...)

                                                9
                           Nos. 09-30449, 09-30428, 09-30438

necessary to determine the application and scope of government contractor im-
munity is the three-step Boyle test.


                                                C.
       The first Boyle step requires that the government approved reasonably
precise specifications. That entails both the existence of reasonably precise spe-
cifications and the approval of those specifications by the government.
       Specifications are reasonably precise “as long as the specifications address,
in reasonable detail, the product design feature, alleged to be defective.” Kerstet-
ter, 210 F.3d at 438
. See also 
Trevino, 865 F.2d at 1481
. “The requirement that
the specifications be precise means that the discretion over significant details
and all critical design choices will be exercised by the government.” 
Id. Reason- ably
precise specifications for one aspect of a large project do not create an um-
brella of protection for an entire project. Instead, the requirement of reasonably




       5
           (...continued)
nificant conflict exists between an identifiable federal policy or interest and the [operation] of
state law.” 
Id. at 194
(internal quotation marks and citations omitted). The plaintiffs read too
much into the wording of that sentence. The court in World Trade Center did not believe a
threshold inquiry was necessary. Rather, it merely stated that, as a matter of first principles
(i.e., as a “threshold matter”), GCI arises from the significant conflict between federal interests
and state law.

        Importantly, the court went on to apply the Boyle factors without conducting, or even
mentioning again, any sort of threshold inquiry. Furthermore, the court specifically stated
that the first Boyle factor was “designed to ensure that a conflict with state law exists, and,
along with the second requirement, to assure that the suit is within the area where the policy
of the discretionary function would be frustrated.” 
Id. at 196
(internal quotation marks and
citations omitted). With this statement, World Trade Center not only did not implicitly over-
rule Lewis but explicitly reaffirmed it.

                                               10
                           Nos. 09-30449, 09-30428, 09-30438

precise specifications must be met by the specific feature at issue in the claim.6
In this case, the specific features at issue are the backfill material used and the
method of compaction employed by WGI.7


                                               1.
       The Corps, driven by cost concerns, approved specifications that mandated
on-site material as the primary source of the backfill material. The Corps also
specified that if there was insufficient on-site material, WGI should import off-
site backfill material to complete the project. Two factors render those specifica-
tions imprecise.
       First, the specifications that authorized the use of on-site backfill material
were not reasonably precise in regard to how WGI should parse through all the
on-site material to determine which was suitable. The Corps neither mandated
the composition of the backfill material nor established precise procedures to test
material for its suitability as backfill. The only Corps specification was that the
material had to be clean, not contaminated, and not full of debris. Given, how-


       6
         See 
Trevino, 865 F.2d at 1486
(“The government contractor defense as reformulated
in Boyle protects government contractors from liability for defective designs if discretion over
the design feature in question was exercised by the government.” (emphasis added)).
       7
         At various points in their briefs, the plaintiffs seem to urge that the government failed
to provide reasonably precise specifications for dealing with the possibility of underseepage in
the area near the project. That argument, however, is irrelevant to our current analysis of the
scope of GCI, because the reasonably precise specifications that are required by the first prong
of the Boyle test “need not address the specific defect alleged; the government need only
evaluate the design feature in question.” Kerstet
ter, 210 F.3d at 435
(emphasis added). The
underseepage erosion of the flood walls is not a design feature; it is a defect that is alleged to
be the result of two design features (i.e., the backfill material used and the compaction method
employed). Thus, under the first prong, the government must only have approved precise spe-
cifications for the backfill material and the method of compaction; it need not have addressed
underseepage erosion specifically.

                                               11
                         Nos. 09-30449, 09-30428, 09-30438

ever, the wide variety in the types of matter that could be used as backfill mate-
rial, that specification is not reasonably precise.8 The composition of the backfill
used by WGI serves as one factor in plaintiffs’ tort claim, so it cannot be said
that “the specifications address, in reasonable detail, the product design feature,
alleged to be defective.” 
Kerstetter, 210 F.3d at 438
.
       The Corps did not approve any specifications regarding the precise compo-
sition of the on-site backfill material. As Guillory noted in his deposition,

       Q: And there were no real specifications for backfill in terms of what
       they could use and the degree of compaction, right?

       A: Right. We just backfilled with the adjacent soil that was excavat-
       ed out, removed, stockpiled on the side. After the lift station was re-
       moved, that soil was put back in layers and compacted to the com-
       paction of the adjacent soil.

Later in that deposition, Guillory confirmed that the specifications were “gen-
eral” and did not indicate the type of backfill material that could be used to back-
fill the hole:

       Q: And Number 7 is a discussion of the backfill. It says, the excava-
       tion resulting from concrete foundation removal will be backfilled
       with borrowed material obtained from either the on-site borrow
       source or an off-site source as required. An estimated 900 Cys will
       be needed . . . . Okay, so would you regard this as a general specifi-
       cation?

       A: Yes.



       8
         As the Corps’s Contracting Officer Representative, Lee Guillory, acknowledged, back-
fill material need not be homogenous and could consist of various types of matter, including
crushed stone, clays, silts, sand layers, wood debris, and more.

                                             12
                       Nos. 09-30449, 09-30428, 09-30438

      Q: Okay. It’s certainly not a prescribed specification, right?

      A: Right.

      Q: And it doesn’t indicate what kind of material you can use to back-
      fill the hole, does it?

      A: No, it doesn’t.

      The second reason that the specifications are imprecise concerns the off-
site material imported by WGI and used as backfill material. The Corps provid-
ed no reasonably precise specifications regarding the composition of that off-site
backfill material. The Corps was not even fully aware of the contents of the
backfill material used to fill the holes it had created. Guillory’s statements dur-
ing his deposition are indicative of the degree of precision of the Corps’s specifi-
cations:

      Q: Okay. So we really don’t know what’s in the hole, do we?
      ...

      A: I cannot tell you for a fact of everything that’s in that hole, no.

      Q: All right. It says, additional fill material necessary to complete
      the backfill operations will be provided by WGI.

      Q: Doesn’t that allow WGI to use other kinds of material to fill up
      the hole?

      A: It just says provided to the subcontractor. It could be indigenous,
      on site clay material, it could have been commercially truck hauled
      clay material.

      It is true that in addition to the Corps’s standing requirement that the
backfill material be clean, not contaminated, and not full of debris, any off-site

                                        13
                           Nos. 09-30449, 09-30428, 09-30438

backfill material imported by WGI had to receive some sort of approval from the
Corps before it could be used. But there is no information in the record indicat-
ing that the Corps imposed additional requirements regarding the composition
of the off-site material, nor is there any indication that the Corps applied any
testing process to evaluate the off-site backfill material before approving its use.9
Given the absence of reasonably precise specifications in the proposal under
which WGI was operating, any such additional evidence is necessary to find that
the Corps approved reasonably precise specifications and did not merely allow
WGI to exercise principal discretion over the composition of the off-site backfill
material.
       Significantly, the evidence in the record shows that the sole consideration
for the Corps in evaluating the backfill was the cost of the material. If that was
the extent of its analysis, the Corps cannot be said to have approved reasonably
precise specifications regarding the composition of the off-site backfill material.
       Given that the Corps provided imprecise, and at times non-existent, speci-
fications regarding the composition of the on-site and off-site backfill material,
WGI is not entitled to claim GCI for its exercise of discretion in choosing the
composition of that material.



       9
         There is also no evidence that the approval given by the Corps for the off-site backfill
material was anything more than a rubber stamp, which is unacceptable under the Boyle test.
See 
Trevino, 865 F.2d at 1480
(“If the government contractor exercised the actual discretion
over the defective feature of the design, then the contractor will not escape liability via the gov-
ernment contractor defenseSSthe government’s rubber stamp on the design drawings not-
withstanding.”). We focus our discussion, however, on the precision of the specifications, not
the process of approval. Although those two issues are intertwined as elements of the first
prong of Boyle, they are still two separate conditions that can be analyzed independently. If
the specifications are not reasonably precise, it does not matter whether the imprecise specifi-
cations were properly approved: The first prong would not be satisfied.

                                                14
                        Nos. 09-30449, 09-30428, 09-30438

                                           2.
      The Corps specified that the backfill “material will be placed in lifts and
compacted.” The Corps also directed that compaction occur “with previous exca-
vated soil in 2' lifts,” that “[i]nitial backfill operations will be to the bottom of the
whalers inside the [subsurface obstruction],” and that backfilling should be com-
pleted “to the top of sheet piles with material to be provided by WGI after whal-
ers are removed.”
      The WGI Project Manager, Dennis O’Connor, described, in his deposition,
his understanding of the specifications for compaction in his deposition:

      Q: Tell me what was the specification for compaction?

      A: There were no specifications for compaction.

      Q: OK.

      A: Simply a general directive that if we backfilled the hole, depend-
      ing on the piece of equipment and size of the hole, we would compact
      the soil mechanically, be it with an excavator or backhoe if it was
      very small, or a wheel roller if it was extremely small. And it would
      depend on the size of the lifts and we would bring it up to grade.

As O’Connor admitted, WGI understood there to be no precise specifications for
compaction. Additionally, though we do not ascribe a legal conclusion to O’Con-
nor’s declaration that the Corps’s directive was a “general” specification, his de-
tailed statement of what the general directive entailed shows the lack of rea-
sonable precision. By his own terms, WGI could have used an excavator, back-
hoe, or wheel roller for compaction, based on the size of the hole and the size of
the lifts. There is no information in the record, however, to show that the Corps
provided specifications for when a certain piece of equipment should be used for

                                           15
                          Nos. 09-30449, 09-30428, 09-30438

a particular type of hole.
       Furthermore, the specifications are not reasonably precise, because they
fail to dictate any standards for compaction. The extent of compaction can be
measured using a proctor compaction test. The Corps chose not to require any
specific standard that could be measured by that test. Instead, it unequivocally
emphasized its lack of interest in mandating specifications for compaction densi-
ty by stating that “no compaction testing will be required.” To explain this lack
of specification, the Corps cited cost concerns and the fact that the Corps could
visually observe the result of the compaction method that WGI used. That ex-
planation, even if it is credible, has no effect on our conclusion that the specifica-
tions that were approved were not reasonably precise.
       The Corps’s failure to specify a standard for compaction also meant that
WGI could choose a method of compaction that did not require a particular final
result. For example, if the Corps had specified that the holes should be compact-
ed to 95% Standard Proctor density,10 WGI would be limited, in its choice of a
compaction method, to a process that would achieve that result. By not specify-
ing any compaction method, the Corps allowed WGI the discretion to choose a
method without a required result.
       One could argue that the Corps’ failure to provide standards for compac-



       10
           These plaintiffs suggest the “95 percent Standard Proctor density” standard. We use
it, however, only as an example of a possible standard of compaction, not as an approval of that
standard. The issue is not whether the government chose the correct standard, because the
GCI defense is meant to prevent the second-guessing of such decisions. See 
Boyle, 487 U.S. at 511
(stating that “permitting ‘second guessing” of these judgments through state tort suits
against contractors would produce the same effect sought to be avoided by the FTCA exemp-
tion”) (internal citation omitted). Rather, the issue is whether the government chose any stan-
dard of compaction at all. There is no second-guessing here of a government decision, because
none was made.

                                              16
                       Nos. 09-30449, 09-30428, 09-30438

tion or to provide details for the equipment to be employed was, in itself, a pre-
cise specification. The approved work plan stated that “[t]he material will be
placed in lifts and compacted” and affirmed that “no compaction testing will be
required.” Given that those general specifications were the result of an intricate
approval process, it is reasonable to conclude that the decision not to specify
more than basic compaction was a decision made by the Corps, as WGI contends
in its brief.
       The question, however, is not whether the Corps approved of any decision
regarding the compaction method. The relevant inquiry, instead, is whether the
Corps approved sufficiently precise specifications, such that it is evident that the
government was the primary agent of decision over the compaction method. “If
the government approved imprecise or general guidelines, then discretion over
important design choices would be left to the government contractor.” 
Trevino, 865 F.2d at 1481
. By providing only general instructions regarding the compac-
tion method, the Corps ensured that WGI would have significant discretion over
the method chosen. The exercise of that discretion by WGI is not protected by
the GCI doctrine.
       To decide otherwise would lead to an absurdity: The government could
provide general specifications, inform the court that it “precisely” chose to ap-
prove only general specifications, and thus render all subsequent, discretionary
decisions of a government contractor protected under the GCI doctrine. Such an
analysis would controvert the very purpose of the GCI defense. The government
contractor defense in Boyle, “[s]tripped to its essentials,” is fundamentally a




                                        17
                          Nos. 09-30449, 09-30428, 09-30438

claim that “[t]he Government made me do it.”11 To adhere to this basic principle,
it is essential that the specifications approved by the government are reasonably
precise. “If the government approved imprecise or general guidelines, then dis-
cretion over important design choices would be left to the government contrac-
tor.” 
Trevino, 865 F.2d at 1481
.
       The Corps did not “make” WGI use the exact backfill material that was
utilized, nor did it “require” WGI select the compaction method that was em-
ployed. In the absence of reasonably precise Corps specifications, those decisions
were made by WGI. Thus, WGI fails the first step of the Boyle test and is not en-
titled to GCI for its choice of backfill material and compaction method. The sum-
mary judgment is REVERSED, and this matter is REMANDED for further pro-
ceedings as needed. We impose no limitations on what matters the district court
can consider on remand, and we express no view as to what decisions that court
should make.




       11
         In re Joint E. & S. Dist. N.Y. Asbestos Litig., 
897 F.2d 626
, 632 (2d Cir. 1990). See
also 
Trevino, 865 F.2d at 1482
(“[T]he purpose of the [Boyle] test is to deny the defense to a
government contract that is itself ultimately responsible for the defect.”) (internal quotation
marks and citation omitted).

                                              18

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer