Elawyers Elawyers
Ohio| Change

J.A.M. Promotions, Inc. v. Tunica County Arena & E, 11-60432 (2012)

Court: Court of Appeals for the Fifth Circuit Number: 11-60432 Visitors: 12
Filed: Mar. 07, 2012
Latest Update: Feb. 22, 2020
Summary: Case: 11-60432 Document: 00511780948 Page: 1 Date Filed: 03/07/2012 IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit FILED March 7, 2012 No. 11-60432 Lyle W. Cayce Clerk J.A.M. PROMOTIONS, INC., Plaintiff-Appellant v. TUNICA COUNTY ARENA & EXPOSITION CENTER, INC.; W.A. PECK BOUCHILLON; and TUNICA COUNTY, MISSISSIPPI, Defendants-Appellees Appeal from the United States District Court for the Northern District of Mississippi USDC No. 2:09-cv-0
More
     Case: 11-60432    Document: 00511780948         Page: 1     Date Filed: 03/07/2012




           IN THE UNITED STATES COURT OF APPEALS
                    FOR THE FIFTH CIRCUIT  United States Court of Appeals
                                                    Fifth Circuit

                                                                           FILED
                                                                          March 7, 2012

                                      No. 11-60432                        Lyle W. Cayce
                                                                               Clerk

J.A.M. PROMOTIONS, INC.,

                                                  Plaintiff-Appellant

v.

TUNICA COUNTY ARENA & EXPOSITION CENTER, INC.; W.A. PECK
BOUCHILLON; and TUNICA COUNTY, MISSISSIPPI,

                                                  Defendants-Appellees


              Appeal from the United States District Court for the
                        Northern District of Mississippi
                           USDC No. 2:09-cv-00016


Before KING, BENAVIDES, and DENNIS, Circuit Judges.
PER CURIAM:*
        This appeal presents a contract dispute between Plaintiff-Appellant J.A.M.
Promotions, Inc. (“JAM”) and Defendants-Appellees Tunica County Arena and
Exposition Center, Inc. (“Arena”), W.A. “Peck” Bouchillon, and Tunica County,
Mississippi. The district court granted summary judgment for the Defendants
on all claims, finding that, starting in 2008, there was no contract between the
parties, but merely an agreement to enter a future contract. JAM now appeals.


       *
        Pursuant to FIFTH CIRCUIT RULE 47.5, the Court has determined that this opinion
should not be published and is not precedent except under the limited circumstances set forth
in FIFTH CIRCUIT RULE 47.5.4.
   Case: 11-60432    Document: 00511780948      Page: 2   Date Filed: 03/07/2012




                                  No. 11-60432

Because we agree that JAM has failed to show the existence of a binding
contract, we AFFIRM.
                 I. FACTUAL AND PROCEDURAL BACKGROUND
      JAM is a corporation that promotes go-kart races. Its owner/operator and
sole shareholder is Lanier James. Currently, JAM promotes one go-kart race per
year, the National Go-Kart Racing Championship.
      In 2000, the Arena contacted JAM about having the National
Championship race in Tunica. JAM agreed, and it held the race at the Arena for
the first time in 2001. The race grew from 800 entries in 2001 to 1200 in 2007.
For those six years, the race was held on Thanksgiving weekend, and it became
the largest indoor go-kart race in the world.
      JAM and the Arena had a contract each year the race was held. According
to JAM, the parties had always contemplated that the contract would be
renewed year-to-year, as reflected in a deposit clause contained in the 2007
contract. Roger Newman, the Arena director from April 2000 to February 2006,
drafted the deposit clause, which was approved by the Arena’s attorney. Each
year, when JAM and the Arena settled after the race, JAM would leave a $2,000
deposit to secure the race for the following year. JAM states that once it had left
its deposit, it was the only party who could cancel the event.
      Newman was responsible for soliciting JAM to bring the go-kart race to
Tunica County. Bouchillon, who had worked under Newman, became the Arena
director in 2006, when Newman left.         JAM alleges that “[t]he first year
Bouchillon was in charge, Lanier James had numerous problems with the race
because of Bouchillon’s negligence and/or deliberate indifference.” According to
JAM, the Arena floor was packed with the wrong kind of dirt for a track, the


                                        2
   Case: 11-60432      Document: 00511780948         Page: 3    Date Filed: 03/07/2012




                                      No. 11-60432

facility ran out of toilet paper in the bathrooms, the plumbing stopped up, and
Bouchillon could not be located to deal with these problems. 2006 was the best
attendance year for the event yet, however, and JAM still made a profit.2
       JAM alleges that there were also problems with the National
Championship race in 2007, again due to Bouchillon’s negligence. This time,
JAM lost money on the race. JAM claims that if it weren’t for the problems
encountered with the race in 2006 when Bouchillon was first director of the
Arena, JAM would have turned a profit in 2007.
       On January 15, 2008, Bouchillon wrote a letter to James canceling the go-
kart race for 2008 and returning the $2,000 deposit James had left with the
Arena. JAM alleges that Bouchillon cancelled the race because he had to work
hard during the event, and because James would not give him a kickback. JAM
also states that the Arena’s given reason for cancelling the go-kart race, that it
caused environmental problems, was pretextual because the Arena tried to
attract other motorized events in 2008.
       JAM sued the Arena and the County for breach of contract, tortious breach
of contract, and lack of good faith and fair dealing with a contract. JAM also
sued Bouchillon in his individual capacity for malicious interference with a
contract. On June 6, 2011, the district court granted all of the Defendants’
motions for summary judgment. The court found that there was no contract
between JAM and the Arena for 2008 or any year thereafter. Because a valid
contract did not exist, JAM could not have claims for lack of good faith and fair


       2
        JAM also alleges that after the 2006 race, Bouchillon “tried to shake James down for
a kickback while falsely accusing James of a crack in the floor.” While we assume this
incident is included in support of JAM’s claim against Bouchillon for malicious interference
with a contract, no further reference to it is made in JAM’s brief.

                                             3
   Case: 11-60432        Document: 00511780948          Page: 4     Date Filed: 03/07/2012




                                        No. 11-60432

dealing or malicious interference with that contract. The district court also held
that JAM had failed to show a genuine issue of material fact in regards to its
conversion claim, because the only discussion of that claim in its briefs spanned
two pages, and “[t]here is no law cited, nor is there evidence cited other than
conclusory statements.”3
                                II. STANDARD OF REVIEW
       This Court reviews a district court’s grant of summary judgment de novo
and applies the same standard as the district court. Holt v. State Farm Fire &
Cas. Co., 
627 F.3d 188
, 191 (5th Cir. 2010). Under that standard, summary
judgment is appropriate when “there is no genuine dispute as to any material
fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.
56(a). “If the evidence is merely colorable, or is not significantly probative,
summary judgment may be granted.” Anderson v. Liberty Lobby, Inc., 
477 U.S. 242
, 249-50 (1986) (citations omitted). When reviewing a motion for summary
judgment, the Court construes all the evidence and reasonable inferences in the
light most favorable to the nonmoving party. Amazing Spaces, Inc. v. Metro
Mini Storage, 
608 F.3d 225
, 234 (5th Cir. 2010) (quoting Xtreme Lashes, LLC v.
Xtended Beauty, Inc., 
576 F.3d 221
, 226 (5th Cir. 2009)).




       3
         Similarly, beyond stating in its brief that the “Arena converted property to its own
use by continuing to utilize pictures of Plaintiff’s go-kart event in order to promote the Arena,”
JAM makes no arguments regarding its conversion claim on appeal, nor does it cite any
caselaw. Therefore, JAM has waived its conversion claim. See Batiste v. Theriot, 
2012 WL 89414
, at *8 (5th Cir. Jan. 10, 2012) (per curiam) (stating that plaintiffs “present no evidence
or even more than a passing reference to these arguments in their briefs and, as such, those
arguments are waived”).

                                                4
   Case: 11-60432    Document: 00511780948      Page: 5   Date Filed: 03/07/2012




                                  No. 11-60432

                                 III. ANALYSIS
      In this diversity case, the district court properly applied Mississippi law.
H.E. Butt Grocery Co. v. Nat’l Union Fire Ins. Co. of Pittsburgh, Pa., 
150 F.3d 526
, 529 (5th Cir. 1998).      Under Mississippi law, questions of contract
construction are questions of law, rather than questions of fact committed to the
factfinder. Facilities, Inc. v. Rogers-Usry Chevrolet, Inc., 
908 So. 2d 107
, 110
(Miss. 2005). In order to be enforceable, a contract “must be reasonably complete
and its essential terms reasonably certain.” Leach v. Tingle, 
586 So. 2d 799
, 801
(Miss. 1991). Courts use a reasonableness standard in deciding if a contract is
definite enough to be enforced. 
Id. at 802.
Only when agreements are “‘vague,
indefinite and uncertain’ . . . in which the promises and performances to be
rendered by each party are not reasonably certain, are [they] not enforceable as
contracts.” Massengill v. Guardian Mgmt. Co., 
19 F.3d 196
, 202 (5th Cir. 1994)
(quoting First Money, Inc. v. Frisby, 
369 So. 2d 746
, 751 (Miss. 1979)).
      Mississippi   courts   have    a   “three-tiered    approach   to   contract
interpretation.” Royer Homes of Miss., Inc. v. Chandeleur Homes, Inc., 
857 So. 2d 748
, 752 (Miss. 2003). First, they look to the words in the contract to determine
intent or purpose. Id.; see also Facilities 
Inc. 908 So. 2d at 111
. They do this by
looking to the “four corners” of the contract, and reading it “as a whole, so as to
give effect to all of its clauses.” 
Royer, 857 So. 2d at 752
. A court should look to
the parties’ words, not to their unspoken intent, and the court cannot “infer an
intent contrary to that emanating from the text at issue.” Id.; see also One
South, Inc. v. Hollowell, 
963 So. 2d 1156
, 1162 (Miss. 2007) (“In order to
determine and record the intent of the contracting parties, we focus upon the
objective language of the contract.”). Only if the contract is ambiguous or


                                         5
   Case: 11-60432    Document: 00511780948       Page: 6   Date Filed: 03/07/2012




                                   No. 11-60432

unclear should the court try to harmonize its provisions with the parties’
apparent intent, and go beyond the text to do so. 
Royer, 857 So. 2d at 752
-53.
“[T]he mere fact that the parties disagree about the meaning of a contract does
not make the contract ambiguous as a matter of law.” 
Id. at 753
(quoting Turner
v. Terry, 
799 So. 2d 25
, 32 (Miss. 2001)).
      Second, if the court cannot determine the parties’ intent from the text, it
“should apply the discretionary ‘canons’ of contract construction.” 
Royer, 857 So. 2d at 753
(citation omitted). If the language of the contract is susceptible to
more than one reasonable reading, “the reading applied will be the one most
favorable to the non-drafting party.” 
Id. (citation omitted).
Third, if the contract
is still unclear as to the parties’ intent, the court may consider extrinsic or parol
evidence. Id.; see also Facilities, 
Inc., 908 So. 2d at 116
. “It is only when the
review of a contract reaches this point that prior negotiation, agreements and
conversations might be considered in determining the parties’ intentions in the
construction of the contract.” 
Royer, 857 So. 2d at 753
.
      In this case, the district court held that the deposit clause in the 2007
contract between JAM and the Arena “does not create a perpetual reservation
for the plaintiff’s event.” Instead, the court found that “the deposit clause is an
agreement to enter into a future contract and such agreements are
unenforceable as a matter of Mississippi law unless all material and essential
terms have been agreed upon.” Because the specifics of the dates and times of
future events, as well as the price, were not included in the deposit clause, the
parties had not agreed on all of those essential and material terms. Therefore,
“there was no contract to breach.”




                                         6
   Case: 11-60432   Document: 00511780948      Page: 7   Date Filed: 03/07/2012




                                 No. 11-60432

      On appeal, JAM again argues that the deposit clause in its 2007 contract
with the Arena was a contract to make a contract, and because it contained all
the essential and material terms, it was unambiguous and binding. JAM argues
that the National Go-Kart Racing Championship always occurred over
Thanksgiving weekend, and the rental fee had been the same for several years.
In the alternative, JAM argues that the contract was ambiguous, and therefore
must be applied against the drafters, Tunica and the Arena. According to JAM,
extrinsic evidence shows that the parties intended for the $2,000 deposit to
create a binding contract for the following year’s event. JAM also avers that the
contract’s plain wording and the parties’ course of dealings show that they
intended for the contract to continue from year to year. The Defendants respond
that the district court correctly found that the 2007 contract was unambiguous,
and that JAM’s deposit was a non-binding agreement to enter into a future
contract, because it did not contain the essential terms of time and price.
      The deposit clause in the 2007 Facility Use Agreement between JAM and
the Arena reads as follows:
            ADVANCE PAYMENT/DEPOSIT POLICY

            User agrees to pay the following advance non-
            refundable payment/deposit schedule:

            USER may leave the deposit from year to year to secure
            future dates for which a contract will be issued for
            future dates/events at a later time. The deposit will
            secure a date or dates TBD but not necessarily the
            same dates covered under this agreement. A variety of
            reasons could result in the need to change the date(s) of
            the event. ARENA will hold those dates agreed upon at
            the end of the current contract event but if at any time
            during the period prior to a new contract being issued

                                       7
   Case: 11-60432   Document: 00511780948      Page: 8   Date Filed: 03/07/2012




                                  No. 11-60432

            and signed USER cancels the event for any reason the
            deposit will be forfeited in accordance to the same terms
            of the contract without penalty to either party.

According to JAM, the fact that the clause employs the phrase “USER may leave
the deposit from year to year to secure future dates,” as well as the word “will,”
means that: the Arena did not have the choice to cancel; only the user, JAM,
could cancel; and as long as JAM chose to leave a deposit, it would secure a date
for the go-kart race for the following year. The district court found that it was
not reasonable to interpret the deposit clause to require the Arena to perpetually
host the go-kart race. We agree. Mississippi does not favor perpetual leases.
Indeed, Mississippi law does not allow a perpetual lease unless the language
employed in the contract clearly and unambiguously indicates that it was the
intent and purpose of the parties to do so. Stampley v. Gilbert, 
332 So. 2d 61
, 63
(Miss. 1976). Such clear and unequivocal language of intent and purpose is not
present here.
      Furthermore, as the district court noted, the deposit clause does not
contain all of the material and essential terms necessary to create an enforceable
agreement between JAM and the Arena. Mississippi courts have found that
“price is an essential [contract] term.” 
Leach, 586 So. 2d at 803
. “It must be
stated with specificity”; if not, “the contract fails.” 
Id. When material
terms
such as price are missing, then an agreement is not a contract, but “merely a
memorandum of intent.” Duke v. Whatley, 
580 So. 2d 1267
, 1273 (Miss. 1991);
see also Betty Lee Shoes, Inc. v. Karl’s Shoe Stores, Ltd., 
293 F.2d 429
, 432 (5th
Cir. 1961) (“If the document or contract that the parties agree to make is to
contain any material term that is not already agreed on, no contract has yet been
made; and the so-called ‘contract to make a contract’ is not a contract at all.”

                                        8
   Case: 11-60432       Document: 00511780948         Page: 9     Date Filed: 03/07/2012




                                       No. 11-60432

(quoting 1 Corbin, Contracts, § 29, pp. 67-71)). JAM argues that it is sufficient
that the contract contained a minimum rental fee,4 but a base rental fee still
leaves open the material term of final price. Furthermore, it is clear from the
2007 contract that the parties negotiated specific prices for specific dates and
activities associated with the race, and then finalized the contract. There is no
way for a court to determine whether in 2008 the parties would agree to the
same number of days and services for the same prices. See 
Duke, 580 So. 2d at 1274
(“[W]ithout knowledge of the parties[’] intent of an essential term, this
Court, and any court, is unable to determine what performance should be
required.”).
       Furthermore, the deposit clause itself states that a “deposit will secure a
date or dates TBD,” and that a “contract will be issued for future dates/events
at a later time.” The clause clearly contemplates that the parties would enter
into a separate agreement later, and that they have not yet agreed to the dates
for the 2008 event (or any event thereafter). See J. Russell Flowers, Inc. v. Itel
Corp., 
495 F. Supp. 88
, 91 (N.D. Miss. 1980) (“The letter addressed itself to
financing only, and it openly contemplated further negotiations as to a ‘more
definitive document.’ It cannot be said, on the basis of this letter, that all
material provisions have been agreed upon, and that there is nothing left for
future settlement.”). For an event held once per year, the dates that it will take
place are clearly a material term of the contract. JAM states that the race was



       4
         It should be noted that JAM seems to confuse whether the deposit clause or the entire
2007 contract creates a contract for 2008 and the years following. If, as JAM argues, “the
deposit clause at issue was a valid and binding contract to make a contract,” then the deposit
clause should contain all of the material terms, such as price. However, the minimum rental
fee, and the breakdown of that fee, is found in a different section of the 2007 contract.

                                              9
  Case: 11-60432      Document: 00511780948        Page: 10    Date Filed: 03/07/2012




                                     No. 11-60432

always held Thanksgiving weekend, but the document does not contain that
information, and generally a court should look no further than the document
itself. 
Id. The 2007
contract does not contain enough information in the deposit
clause, or anywhere else, for a court to determine the parties’ intentions as to
any go-kart race to be held in 2008. Consequently, the district court correctly
held that the deposit clause does not constitute a binding contract between JAM
and the Arena, but merely an agreement to enter into a future contract.
      JAM argues in the alternative that the contract is ambiguous, and the
Court should apply the canons of contract construction. See 
Royer, 857 So. 2d at 753
. However, as 
detailed supra
, the deposit clause is not an ambiguous
contract – it is simply not a contract at all. Thus, JAM’s arguments about
construing the contract against its drafter, the Arena, and employing parol
evidence to elucidate the parties’ intent, are non-starters. Those canons would
be useful to the Court only if there were a contract to which they could be
applied.
      Finally, JAM argues that there are issues of material fact as to whether
there was a contract between it and the Arena for the years after 2008.
According to JAM, “the course and proceedings of the parties created a contract
for future events.” Id.5 JAM references Scott v. Magnolia Lady, Inc., 
843 So. 2d 94
(Miss. App. 2003) for the premise that when one party relies on a course of
business dealings to its detriment, “courts have found the existence of a valid
contract.” 
Id. at 96.
However, in Scott, the court also held that “[t]o avoid such

      5
         JAM cites the Mississippi Uniform Commercial Code in support of this course-of-
dealing argument, but the Uniform Commercial Code only “applies to transactions in goods.”
Miss. Code Ann. § 75-2-102.

                                           10
  Case: 11-60432    Document: 00511780948      Page: 11   Date Filed: 03/07/2012




                                  No. 11-60432

a claim, the party seeking to alter the established course of dealings must clearly
and timely indicate the intent to alter the established pattern of conduct.” 
Id. Here, Bouchillon
told James in January of 2008 that the Arena would not host
the go-kart race that year. Since, according to JAM, the race was usually held
on Thanksgiving weekend, Bouchillon gave James approximately 11 months’
notice that he was altering their “established pattern of conduct.” 
Id. For a
yearly event, 11 months is surely “sufficient to put [James] on notice that [the
Arena] declined to do business under the old practices.” 
Id. Therefore, even
if
JAM had been able to show that it relied on a course of business dealing to its
detriment, the Arena, through Bouchillon, timely indicated its intent to alter the
pattern of conduct. Accordingly, the Arena avoided the claim of a valid contract
binding it after 2008.
                                IV. CONCLUSION
      For the foregoing reasons, the judgment of the district court is
AFFIRMED.




                                        11

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer