Summary: Case: 16-11645 Document: 00514348343 Page: 1 Date Filed: 02/15/2018 IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals No. 16-11645 Fifth Circuit FILED February 15, 2018 BALFOUR BEATTY RAIL, INCORPORATED, Lyle W. Cayce Clerk Plaintiff - Appellant v. KANSAS CITY SOUTHERN RAILWAY COMPANY, Defendant - Appellee Appeal from the United States District Court for the Northern District of Texas USDC No. 3:10-CV-1629 Before DAVIS, HAYNES, and COSTA, Circuit Judges.
More
     Case: 16-11645      Document: 00514348343         Page: 1    Date Filed: 02/15/2018




           IN THE UNITED STATES COURT OF APPEALS
                    FOR THE FIFTH CIRCUIT

                                                                       United States Court of Appeals

                                      No. 16-11645
                                                                                Fifth Circuit

                                                                              FILED
                                                                       February 15, 2018
BALFOUR BEATTY RAIL, INCORPORATED,                                       Lyle W. Cayce
                                                                              Clerk
              Plaintiff - Appellant

v.

KANSAS CITY SOUTHERN RAILWAY COMPANY,

              Defendant - Appellee




                   Appeal from the United States District Court
                        for the Northern District of Texas
                             USDC No. 3:10-CV-1629


Before DAVIS, HAYNES, and COSTA, Circuit Judges.
GREGG COSTA, Circuit Judge:*
       The Kansas City Southern Railway Company (Southern) hired Balfour
Beatty Rail, Inc. (Balfour) to complete a new railroad track in Texas.
Southern contends that because of Balfour’s poor workmanship, it was forced
to pay for tens of thousands of tons of ballast in excess of what should have
been required to finish the track. The district court determined after a bench
trial that Balfour had breached its contract and Southern was entitled to


       * Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
be published and is not precedent except under the limited circumstances set forth in 5TH
CIR. R. 47.5.4.
    Case: 16-11645      Document: 00514348343     Page: 2   Date Filed: 02/15/2018



                                   No. 16-11645
several million dollars in compensatory damages for wasted materials. Except
for a minor adjustment to the final amount awarded, we affirm the district
court.
                                        I.
         Southern originally hired Gulf Coast to construct 85 miles of new
railroad track between Victoria and Rosenberg, Texas.            After becoming
dissatisfied with the quality and timeliness of the construction, Southern
solicited a bid from Balfour to finish the remaining 65 miles of the track.
Balfour submitted a bid and was awarded the contract. Southern agreed to
pay Balfour a flat rate of $12.2 million and to purchase and deliver the
necessary track materials such as welded rail and ballast. Ballast is crushed
stone used to support the track and maintain a level height along potentially
uneven terrain.
         Problems arose that caused significant delays and overuse of materials.
After the track was completed, Balfour sued Southern in Texas state court.
Southern removed the case to federal court and counterclaimed. Following
cross motions for summary judgment and a nine day bench trial, the district
court decided that Balfour had wasted ballast in violation of its contractual
obligations and awarded Southern $2,353,299.40 in compensatory damages for
the cost of the material, $721,858.66 in prejudgment interest, and
$1,069,934.33 in attorney’s fees. 1
         This appeal concerns only Southern’s successful counterclaim to recover
the costs of wasted ballast. We must determine whether the evidence was
sufficient to support the district court’s ruling; whether the amount of ballast
wasted was properly calculated; and whether Balfour is entitled to any



        The court awarded Balfour $47,561.43 for claims associated with four Change
         1

Orders, which was subtracted from Southern’s ultimate award.
                                        2
     Case: 16-11645      Document: 00514348343         Page: 3    Date Filed: 02/15/2018



                                      No. 16-11645
affirmative defenses. We detail only the evidence that relates to this challenged
award.
       The Master Agreement required Balfour’s work to be (a) “in a
workmanlike manner and . . . first class in execution and quality,” and (b) “in
accordance with the specifications referenced in the applicable Statement of
Work.” The Statement of Work called for at least ten inches of ballast under
the railroad ties to lift the track to the proper elevation, with an acceptable
variance of plus or minus two inches, and no more than twelve inches of
shoulder on each side of the railroad ties. Balfour was obligated to exercise
care “not to distribute ballast in excess of the amount required for the lift to be
made.”
       As the project continued, Balfour began to request more and more ballast
from Southern. At the beginning of construction, Southern delivered 1,750
tons of ballast per day. The demand for ballast eventually increased to 3,700
tons per day and then to 4,646 tons per day. To meet the higher demand for
ballast, Southern obtained rock from quarries in Arkansas, Georgia, and
Mexico. Because of the flat rate payment structure, every additional ton of
ballast increased Southern’s construction costs.
       The court heard extensive testimony on how to calculate the amount of
ballast “wasted.” Ballast is wasted in one of two ways: (1) when too much rock
is spread on the outside edges of the track, thus no longer providing structural
support; or (2) when too much rock is placed in the center, thus raising the
track unnecessarily high. The undisputed total amount of ballast delivered by
Southern was 412,511 tons. 2          The amount wasted is this amount of rock
delivered minus both the amount Balfour should have needed to complete the


       2  This amount of total ballast may actually underestimate the rock available to
Balfour. Balfour had access to an undetermined amount of ballast in a stockpile already on
site that was not included in the total amount when the district court did its calculations.
                                             3
    Case: 16-11645     Document: 00514348343    Page: 4   Date Filed: 02/15/2018



                                 No. 16-11645
project and the amount diverted from Balfour to other contractors.          This
difference represents how much Balfour used beyond what the project
required, and that number can be multiplied by the average cost per ton to get
the final calculation of damages. The following formulas demonstrate this:
      • Total Wasted Ballast (in tons) = Amount Delivered – (Amount
        Diverted + Amount Needed)

      • Damages for Wasted Ballast = Total Wasted Ballast * KC Southern’s
        Average Out-of-Pocket Cost per Ton
      Balfour blamed the use of the additional ballast on the poor quality of
the subgrade on which the track was built. That land was flattened by a
separate contractor.    Balfour raised this concern with Southern during
construction and argues that because the height of the subgrade was too low
in some places and too narrow in others, the additional ballast was necessary
to get the track to the specifications required under the contract. Southern
counters that it had warned Balfour that it was using too much ballast and
says it took this subgrade variation into account when calculating how much
ballast should have been used. Southern presented expert testimony that the
subgrade was properly constructed and, regardless of height, ballast had been
poured too far on the sides where it did not provide any structural support.
      Southern’s Director of Track Projects, Lee Peek, testified that Balfour
wasted 74,260 tons of ballast. Peek detailed how he reached this number. He
surveyed the track following the completion of the project and measured the
top rail, the subgrade elevation, and the actual depth of ballast along the rail.
He then explained how he calculated that the project should have needed only
327,591 tons of ballast. Balfour argues that there are two other potential
estimates of wasted ballast. One, presented by Southern’s expert witness
David Brookings, was determined using a general rule of thumb of about one
ton of ballast per foot of track; based on the length of the track, he estimated
                                       4
     Case: 16-11645       Document: 00514348343          Page: 5     Date Filed: 02/15/2018



                                       No. 16-11645
about 349,000 tons of ballast would be required. The second, a Balfour revised
internal estimate, estimated 340,560 tons of ballast were needed to finish
construction.     Both of these alternative estimates would result in Balfour
owing less.
       The district court credited Southern’s evidence and concluded that it was
Balfour’s deficient workmanship, rather than any problem with the subgrade,
that caused ballast to be wasted. The court also determined that the project
should have required 327,591 tons of ballast, that 10,660 tons of ballast were
diverted to other contractors, and thus 74,260 tons had been wasted by Balfour.
       The court then heard testimony concerning how much each ton of ballast
cost. Southern’s Director of Accounting, Lynn Carnes, provided testimony
about ballast’s cost per ton. Carnes testified that Southern paid $15.03 per ton
on average for the raw material that was delivered to the construction site
during the relevant time period. Carnes also calculated that Southern paid an
additional $7.76 per ton to transport the ballast to the construction site and
$8.90 per ton to lease the rail cars. 3 Carnes concluded that the average cost
per ton of ballast was $31.69, that the number was out-of-pocket cost not
including profit, and that the calculations conformed to “General Accounting
Principles.” The district court accepted this testimony and used this cost in its
damages calculation. Multiplying this average cost per ton times the 74,260
tons of ballast it found was wasted, the district court concluded that Southern
was entitled to $2,353,299.40 ($31.69 * 74,260) in compensatory damages.
                                              II.
       Balfour challenges the district court’s damages award on several
grounds: (1) that the evidence is insufficient to sustain the award because


       3 A portion of the excess ballast did not require these additional locomotive and ballast
car costs based on which quarry the rock came from; that difference was taken into account
in the final calculation of per ton cost.
                                               5
      Case: 16-11645   Document: 00514348343      Page: 6   Date Filed: 02/15/2018



                                  No. 16-11645
Southern failed to prove the reasonableness of the cost of supplying ballast; (2)
that the district court miscalculated the amount of ballast wasted; (3) that the
district court failed to credit Balfour for the total amount of ballast diverted to
other contractors; and (4) that the “undifferentiated” damages model used by
the district court failed to exclude from its calculations ballast that had not
actually been wasted or ballast wasted because of the actions of a third party.
        Whether Southern Proved the Reasonableness of the Ballast Costs
       Balfour argues that Texas law requires Southern to prove the cost of the
excess ballast was “reasonable,” and that it failed to do so. The evidentiary
reasonableness requirement arises in construction contract cases when the
court is awarding remedial or cost-to-complete damages. McGinty v. Hennen,
372 S.W.3d 625
, 627 (Tex. 2012) (per curiam); Mustang Pipeline Co. v. Driver
Pipeline Co., 
134 S.W.3d 195
, 200 (Tex. 2004). McGinty highlights that there
are
       “two measures of damages for the breach of a construction
       contract: (1) remedial damages, which is the cost to complete or
       repair less the unpaid balance on the contract price, and (2)
       difference-in-value damages, which is the difference between the
       value of the building as constructed and its value had it been
       constructed according to the contract.”
McGinty, 372 S.W.3d at 627
. When a party is seeking to recover remedial
damages that party “must prove that the damages sought are reasonable and
necessary.” 
Id. The district
court believed that this reasonableness requirement did not
apply for the cost of the wasted ballast because the damages were expectation
damages, not remedial, and thus not subject to the evidentiary requirements
of Mustang Pipeline. Balfour Beatty Rail, Inc. v. Kansas City S. Ry. Co., 
173 F. Supp. 3d 363
, 459 (N.D. Tex. 2016). We do not need to decide whether the
unusual type of construction damages in this case—overuse of supplies the
nonbreaching party was responsible for purchasing at ordinary levels—falls
                                    6
    Case: 16-11645    Document: 00514348343     Page: 7   Date Filed: 02/15/2018



                                 No. 16-11645
outside of Mustang Pipeline. Even assuming the reasonableness requirement
applies, Southern presented sufficient evidence to establish it. See In re Am.
Hous. Found., 544 F. App’x 516, 523 (5th Cir. 2013) (applying the rule that an
appellate court may “affirm on any grounds in the record” to the appeal of a
bench trial).
      A party trying to prove reasonableness must introduce more than just
the amount it paid for the extra costs. Mustang 
Pipeline, 134 S.W.3d at 200
–
01 (“Evidence of the amounts charged and paid, standing alone, is no evidence
that such payment was reasonable and necessary.”). That the party went out
and purchased goods or services from a third party does not automatically
establish that the price paid, even in an arms-length transaction, was
reasonable. But Southern was not required to produce a witness to say “magic
words” such as “reasonable” or “necessary.” CCC Grp., Inc. v. S. Cent. Cement,
Ltd., 
450 S.W.3d 191
, 200 (Tex. App. 2014); see also Prime Tree & Landscaping
Servs. v. Americon Servs. Co., 
2011 WL 947004
, at *8 (Tex. App. Mar. 17, 2011).
And the reasonableness requirement is not rooted in abstract formalism. The
theme from the Texas cases is that the reasonableness requirement addresses
the concern that a plaintiff, knowing the defendant will have to cover the costs
after breach, will overpay when remedying damages. See generally Dickey v.
Jackson, 
1 S.W.2d 577
, 577 (Tex. Comm’n App. 1928) (discussing the origin of
the reasonableness requirement in cases when the court assumed a jury had
little common knowledge about the prices of “medicines and personal
services”).
      The reasonableness of the ballast costs is supported by circumstances
present in this case that were absent from the Texas cases cited by Balfour.
Most importantly, Southern is not just relying on the price it paid for the extra
ballast for which Balfour is responsible. It is also relying on the price it paid
for ballast for which it was responsible. Southern presented evidence that the
                                       7
    Case: 16-11645    Document: 00514348343     Page: 8   Date Filed: 02/15/2018



                                 No. 16-11645
ballast was purchased and shipped based on a purchase order that it
negotiated to cover the entire quantity for the project before any breach
occurred. This makes sense as there was not a separate order for “extra”
ballast attributable to Balfour’s breach.     The breach instead resulted in
increased daily requests for ballast, the price of which was previously
negotiated. That is why there was so much debate at trial over how much
ballast was wasted; the “extra” ballast was part of the same purchases as the
expected ballast so it took a lot of after-the-fact analysis to separate the two.
Southern thus had every incentive to negotiate the lowest possible price for the
ballast because, without a breach, Southern would have been fully responsible
for the entire cost. The evidence shows a fixed price at each quarry, not the
highly variable pricing one might see in other businesses. This generally
accepted pricing structure is also true for much of the costs incurred
transporting the ballast, such as railroad rates. Reasonableness can thus be
demonstrated by the general market prices Southern was paying for these
expenses before it had any knowledge that some excess ballast costs would be
passed on to Balfour via litigation. 
McGinty, 372 S.W.3d at 628
(noting that in
some cases the process of explaining how pricing figures were derived “will
reveal factors that were considered to ensure the reasonableness of the
ultimate price”). We reject the reasonableness challenge to the district court’s
award.
                 Calculating How Much Ballast Was Wasted
      We can dispose more readily of most of the remaining arguments because
we largely agree with the thorough reasoning of the district court. Balfour
contends that the district court erred in its calculation of how much ballast was
wasted (as opposed to the price of the ballast, which we just addressed).
Balfour argues that the baseline amount for expected use should have been the
amount Southern expected to use when the contract was signed rather than
                                       8
     Case: 16-11645       Document: 00514348343          Page: 9     Date Filed: 02/15/2018



                                       No. 16-11645
the after-the-fact assessment of what amount would have been reasonable. 4
We disagree. Benefit-of-the-bargain damages are calculated by “the difference
between the value as represented and the value received.” Arthur Andersen &
Co. v. Perry Equip. Corp., 
945 S.W.2d 812
, 817 (Tex. 1997); see also
DaimlerChrysler Motors Co. v. Manuel, 
362 S.W.3d 160
, 180 (Tex. App. 2012)
(finding the calculation depends on an “expectancy theory”). The contract
required Balfour to exercise care “not to distribute ballast in excess of the
amount required for the lift to be made.” Southern expected Balfour to do its
job professionally and without waste; that was the expectation that was
breached. The remedy thus should be calculated by subtracting how much
ballast Balfour would have used had it performed in a “workmanlike manner”
(what Southern expected) from the cost Southern ultimately had to pay (value
received). Had the contract been properly performed, Balfour would have used
the amount of rock estimated by the district court. We see no requirement for
disregarding that amply supported factual finding and instead using an
estimated amount listed in Southern’s bid package.
                              Amount of Ballast Diverted
       The district court determined based on Balfour’s daily reports and the
testimony of Lee Peek that 10,660 tons of ballast were diverted to other
contractors. Balfour contends that the court failed to include 16,000 additional
tons of diverted ballast. But our review of the record reveals a finding of clear
error only for 261 tons of diverted ballast from March 28, 2009. 5 This is an


       4  We note that Balfour’s argument here that the court use expectation damages
conflicts with its insistence above that this court use remedial damages, which are subject to
McGinty’s reasonableness requirement.
        5 The court relied on the testimony of Lee Peek to make its diverted ballast
calculation. Peek testified that he failed to count three cars when doing his calculation; this
omission would result in an error of 261 tons of diverted ballast. The district court failed to
include this additional diverted ballast in its final calculation

                                              9
    Case: 16-11645     Document: 00514348343       Page: 10   Date Filed: 02/15/2018



                                   No. 16-11645
error Southern acknowledges. The damages will be reduced to reflect this
change. But the other challenges Balfour makes to the diversion findings
involve conflicting evidence within the province of the factfinder to resolve.
        Whether the District Court Used an Erroneous Damages Model
      In its final challenge to the damages award, Balfour contends that the
court failed to isolate the ballast attributable to the breach so the damages
awarded are too speculative.          Southern, however, presented technical
testimony supporting its calculations. Peek explained that ballast can be
wasted two ways: by spreading the ballast out past where the regulator can
bring it in and by raising the track too much. The district court was entitled
to credit this testimony and include both types of waste. Peek’s testimony also
accounted for the subgrading done by other contractors to which Balfour tries
to assign some blame. Peek stated that his calculations were based on the
“actual conditions of the project” and that he took into account the “actual
elevation” when calculating how much ballast was “needed.” The district court
sufficiently differentiated between wasted and properly used ballast.
                                         ***
       The only clear error we find in the damages calculation of wasted ballast
is the 261 tons of diverted ballast that the district court failed to credit Balfour.
The award is otherwise affirmed.
                                        III.
      Balfour asserts that the affirmative defenses of waiver and quasi
estoppel preclude Southern’s recovery.         But the quasi estoppel claim fails
because Balfour did not prove that Southern’s wasted ballast claim is
inconsistent with its previous position on wasted ballast or that allowing the
claim to go forward would be unconscionable. See Steubner Realty 19, Ltd. v.
Cravens Rd. 88, Ltd., 
817 S.W.2d 160
, 164 (Tex. App.—Houston [14th Dist.]
1991, no writ) (explaining the doctrine of quasi estoppel).
                                         10
   Case: 16-11645    Document: 00514348343      Page: 11   Date Filed: 02/15/2018



                                 No. 16-11645
      Balfour also does not establish that Southern waived its rights to seek a
remedy for work not performed in a “workmanlike manner.” Agreeing to
supply the additional ballast at Balfour’s request does not indicate that
Southern “intentional[ly] relinquish[ed]” its right to enforce this guarantee.
Ulico Cas. Co. v. Allied Pilots Ass’n, 
262 S.W.3d 773
, 778 (Tex. 2008). Southern
was caught between hundreds of thousands of tons of rock and a hard place.
It could have refused to ship additional ballast at Balfour’s request, but that
would have necessitated stopping the project, finding a new contractor, and
resuming later, all of which likely would have cost substantially more than the
damages awarded here. Southern had a duty to mitigate as much as possible.
It did so by allowing Balfour to finish the project and then determining the
extent of damages. The district court did not err in disregarding Balfour’s
waiver and estoppel arguments.
                                      IV.
      Because we find that Southern was entitled to its damages for Balfour’s
breach of contract, it is also entitled to reasonable attorney’s fees. MBM Fin.
Corp. v. Woodlands Operating Co., 
292 S.W.3d 660
, 666 (Tex. 2009). Although
we did alter the ultimate award by 261 tons, or $8,271.09, this change
represents less than one-half of one percent of the total damages and does not
merit recalculation of attorney’s fees.     Contrast Thomas v. Tex. Dep’t of
Criminal Justice, 
297 F.3d 361
, 367, 373 (5th Cir. 2002) (vacating and
remanding attorney’s fees because it allowed plaintiff to choose between a
nearly 20 percent reduction in damages or a new trial); Williams v. Trader
Publ’g Co., 
218 F.3d 481
, 488 (5th Cir. 2000) (vacating and remanding
attorney’s fees because it reduced the damages award by 40 percent).
                                     ***
      The judgment is AFFIRMED except for the reduction of wasted ballast
from 74,260 tons to 73,999 tons, which changes the damages calculation by
                                      11
   Case: 16-11645     Document: 00514348343     Page: 12   Date Filed: 02/15/2018



                                 No. 16-11645
$8,271.09.   The case is REMANDED for entry of an amended judgment
(including recalculated interest) that reflects the reduction.




                                       12
