NGUYEN, Circuit Judge:
Avenal Power Center LLC ("Avenal Power") applied to the United States Environmental Protection Agency ("EPA") for a Prevention of Significant Deterioration Permit ("Permit"), to build and operate the Avenal Energy Project, a 600 megawatt natural gas-fired power plant in the city of Avenal, California. Although EPA had a statutory duty under the Clean Air Act to either grant or deny the Permit application within one year, 42 U.S.C. § 7475(c), it failed to do so. After the deadline passed but before taking any final action, EPA tightened the applicable air quality standards. Avenal Power filed suit and sought to compel EPA to issue the Permit under the old standards that would have applied had EPA acted within the statutory deadline. Initially, EPA responded that it could not legally do so, because the Clean Air Act explicitly requires any newly constructed facility to employ the best available control technology ("BACT") for regulated pollutants and meet air quality standards in effect at the time a permit is issued. See 42 U.S.C. § 7475(a)(3)-(4). Months later, however, EPA reversed course and granted Avenal Power the Permit without regard to the new regulations, which by then had gone into effect. EPA contends that, under narrow circumstances, it has the authority to grandfather certain permit applications like Avenal Power's, and that its decision is entitled to deference under Chevron, U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 842, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984). The Sierra Club, Greenaction for Health and Environmental Justice, Center for Biological Diversity, and El Pueblo para el Aire y Agua Limpio (collectively "Petitioners"), challenge EPA's action.
Applying Chevron, we hold that the Clean Air Act unambiguously requires Avenal Power to demonstrate that the Avenal Energy Project complies with the
Avenal Power proposes to build and operate a power plant, the Avenal Energy Project, near the agricultural communities of Avenal, Huron, and Kettleman City, within California's San Joaquin Valley Pollution Control District. The facility would generate electricity from two 180-megawatt natural gas combustion turbine generators, and a 300-megawatt steam turbine generator that utilizes heat from the combustion turbines. According to EPA, the facility "will be equipped with state-of-the-art control technology and will be one of the lowest emitting power plants of its kind." It is undisputed, however, that its expected emissions of several pollutants, including nitrogen dioxide ("NO
On February 15, 2008, Avenal Power submitted an application to EPA for a Permit. The Regional Administrator determined the application to be administratively complete on March 19, 2008. As of that date, EPA had not yet promulgated national ambient air quality standards ("NAAQS") for NO
On June 16, 2009, after the one-year decision making period had elapsed, see 42 U.S.C. § 7475(c), the Regional Administrator finally issued a Statement of Basis describing the reasons for the proposed approval of the Permit. The Statement of Basis is subject to notice and comment procedures that afford the public an opportunity to participate in the review process by submitting written comments and appearing at a hearing to voice support or concern. See 42 U.S.C. § 7475(a)(2); 40 C.F.R. §§ 124.10-12. During the comment period in this case, EPA held an informational meeting and two hearings. Concerned that the Avenal Energy Project would adversely impact the environment and health and quality of life of local residents, Petitioners filed comments opposing issuance of the Permit.
While Avenal Power's Permit application was still under consideration, EPA adopted more stringent NAAQS and revised the BACT requirement. Specifically, EPA tightened NAAQS for NO
Facing a slew of new regulations, and frustrated by the delay, Avenal Power filed suit on March 9, 2010, in the United States District Court for the District of Columbia, to compel EPA to issue the Permit. Two months later, EPA requested that Avenal Power complete a cumulative air impact assessment of the Avenal Energy Project's hourly NO
In late August 2010, after the new NO
At this point, after conducting what it described as a "policy review," EPA reversed course. In a declaration submitted to the D.C. district court, EPA contended that "EPA believes it is appropriate to grandfather," i.e., exempt, Avenal Power's application from the NO
Petitioners submitted comments to EPA objecting to issuance of the Permit, and EPA's assertion of grandfathering authority.
Petitioners appealed to the Environmental Appeals Board, which declined to exercise jurisdiction to review EPA's asserted grandfathering authority, given the time constraint imposed by the D.C. district court for a final administrative action, but otherwise upheld issuance of the Permit.
We have jurisdiction pursuant to 42 U.S.C. § 7607(b)(1), and consolidated the two petitions for review. Avenal Power successfully moved to intervene in these proceedings, and the United Association of Plumbers and Pipefitters Local 246, International Brotherhood of Electric Workers Local 100, and Insulators Local 16 successfully moved to file a brief as amici curiae.
As an initial matter, Avenal Power, though not EPA, suggests that Petitioners lack standing. It falls to Petitioners, as the parties invoking federal jurisdiction, to demonstrate standing.
"An association has standing to bring suit on behalf of its members when its members would otherwise have standing to sue in their own right, the interests at stake are germane to the organization's purpose, and neither the claim asserted nor the relief requested requires the participation of individual members in the lawsuit." Wilderness Soc'y, Inc. v. Rey, 622 F.3d 1251, 1256 (9th Cir.2010) (quoting Friends of the Earth, Inc. v. Laidlaw Envt'l Servs. (TOC), Inc., 528 U.S. 167, 181, 120 S.Ct. 693, 145 L.Ed.2d 610 (2000)). The record reflects, and Avenal Power does not dispute, that "the interests at stake are germane" to Petitioners' organizational interests, and that personal participation by Petitioners' individual members is not necessary. Id.
The only question remaining, therefore, is whether Petitioners' individual members have standing in their own right. On that score, Petitioners must first show that their members "have suffered an injury in fact — an invasion of a
We first consider whether Petitioners, through the declarations of their members, have established an injury in fact. "An individual bringing a substantive claim related to environmental harms may establish an injury in fact by showing `a connection to the area of concern sufficient to make credible the connection that the person's life will be less enjoyable — that he or she really has or will suffer in his or her degree of aesthetic or recreational satisfaction — if the area in question remains or becomes environmentally degraded.'" W. Watersheds Project v. Kraayenbrink, 632 F.3d 472, 484 (9th Cir.2011) (quoting Ecol. Rights Found. v. Pac. Lumber Co., 230 F.3d 1141, 1149 (9th Cir.2000)). In addition, "evidence of a credible threat to the plaintiff's physical well-being from airborne pollutants" may establish an injury in fact. Hall v. Norton, 266 F.3d 969, 976 (9th Cir.2001).
Here, although we have doubts as to the Sierra Club's standing, we are satisfied that Greenaction for Health and Environmental Justice, Center for Biological Diversity, and El Pueblo para el Aire y Agua Limpio, possess associational standing to challenge EPA's action.
Marciela Mares-Alatorre, the leader of El Pueblo para el Aire y Agua Limpio, lives in Kettleman City, which is located approximately 10 miles from the site of the Avenal Energy Project. She was recently diagnosed with breathing difficulty and symptoms that indicate asthma, problems she avers are exacerbated when the air is more polluted. She fears that the pollution expected from the Avenal Energy Project will impair her health. Likewise, Mavi Sandoval, a member of El Pueblo para el Aire y Agua Limpio, as well as Center for Biological Diversity, lives in Kettleman City, works in Avenal, and states that she is concerned that her respiratory problems will also be exacerbated by pollution from the proposed plant. Maria Saucedo, a member of Greenaction for Health and Environmental Justice, lives in Avenal and avers that her husband and daughter suffer from serious respiratory problems associated with air pollution. She believes that air pollution created by the proposed facility may further jeopardize the health of her family, and impact her husband's ability to work. These health threats are credible, concrete, and, assuming the Project goes forward, imminent — in sum, cognizable injuries in fact. Id.
As to causation and redressability, it is undisputed that the Avenal Energy Project will generate many tons of air pollutants known to threaten public health, including NO2 and SO
Accordingly, we conclude that at least Greenaction for Health and Environmental Justice, Center for Biological Diversity, and El Pueblo para el Aire y Agua Limpio, have association standing to proceed. We need not decide whether Sierra Club has standing. See Kaahumanu v. Hawaii, 682 F.3d 789, 798 (9th Cir.2012) (citing Watt v. Energy Action Educ. Found., 454 U.S. 151, 160, 102 S.Ct. 205, 70 L.Ed.2d 309 (1981) ("Because we hold that [one plaintiff] has Article III standing, we need not reach the question whether [another plaintiff] also has Article III standing")).
We now turn to the substance of Petitioners' challenge, that is, whether EPA exceeded its authority under the Clean Air Act. When we review an agency's interpretation of a statute that it is responsible for administering, "[f]irst, always, is the question whether Congress has directly spoken to the precise question at issue." Chevron, 467 U.S. at 842, 104 S.Ct. 2778. "If the intent of Congress is clear, that is the end of the matter; for the court, as well as the agency, must give effect to the unambiguously expressed intent of Congress." Id. at 842-43, 104 S.Ct. 2778. Only if "the statute is silent or ambiguous," id. at 843, 104 S.Ct. 2778, "`must [we] decide how much weight to accord an agency's interpretation.'" McMaster v. United States, 731 F.3d 881, 889 (9th Cir.2013) (quoting Tualatin Valley Builders Supply, Inc. v. United States, 522 F.3d 937, 940 (9th Cir.2008)).
EPA contends there is ambiguity or tension between two mandates in the Clean Air Act — one, requiring it to enforce current NAAQS and BACT requirements, 42 U.S.C. § 7475(a)(1), (3)-(4), and the other, requiring EPA to act on applications within one year, id. § 7475(c). More specifically, EPA argues that the statute does not specify what it should do when, as was the case here, it failed to act by the statutory deadline, and revised air standards have been promulgated since the deadline passed. Thus, the argument goes, EPA's decision to grant Avenal Power the Permit is entitled to Chevron deference. Petitioners, on the other hand, insist that the statutory language is clear — EPA must enforce the regulations in effect at the time the Permit was issued.
We begin with the statute "`to determine whether the language at issue has a plain and unambiguous meaning....'" Barnhart v. Sigmon Coal Co., 534 U.S. 438,
The Clean Air Act states that "[n]o major emitting facility ... may be constructed... unless":
42 U.S.C. § 7475(a)(3)-(4) (emphasis added). The referenced portion of § 7410(j), in turn, provides:
Id. § 7410(j) (emphasis added). The plain language of the statute — which prohibits the construction of any "major emitting facility" and refers to "any ... national ambient air quality standard," and "the standards of performance which are to apply to such source[,]" as the applicable regulations — clearly requires EPA to apply the regulations in effect at the time of the permitting decision. 42 U.S.C. §§ 7475(a)(4), 7410(j); see also 40 C.F.R. § 52.21(k) (referring to "any national ambient air quality standard in any air quality control region").
Up until now, there has never been any doubt that Permit applicants must comply with current air quality control regulations and BACT requirements. Indeed, EPA initially advanced precisely this position against Avenal Power before the D.C. district court, based on the public guidance it had previously provided in the form of the Page Memo. To wit:
Page Memo at 2 (emphasis added).
EPA's prior interpretation is supported by Supreme Court case law. For example, in Ziffrin, Inc. v. United States, 318 U.S. 73,
Id. (citations omitted).
General Motors Corp. v. United States, 496 U.S. 530, 540, 110 S.Ct. 2528, 110 L.Ed.2d 480 (1990), also provides support for the same basic principle that EPA is bound to enforce administrative guidelines in effect when it takes final action. Under certain provisions of the Clean Air Act not relevant to the present case, the states are required to propose State Implementation Plans to implement, maintain, and enforce NAAQS. See generally 42 U.S.C. § 7410(a)(1). The states also periodically revise the State Implementation Plans, with approval from EPA, which enforces them. Id. § 7410(a)(2)(H). In General Motors, EPA moved to enforce certain provisions of Massachusetts' existing State Implementation Plan. General Motors argued that EPA lacked the authority to initiate enforcement proceedings because, under the Administrative Procedure Act, EPA had "unreasonably" delayed review of certain proposed revisions to the State Implementation Plan that would have relieved General Motors of liability. Id. at 539-42, 110 S.Ct. 2528. The Supreme Court disagreed. It held that EPA was authorized to enforce the then-existing State Implementation Plan regulations against General Motors, even assuming that, but for EPA's alleged unreasonable delay, a superseding State Implementation Plan relieving the company of liability would be in effect. Id. at 540, 110 S.Ct. 2528. The Court noted that "[t]here is nothing in the statute that limits EPA's authority to enforce the `applicable implementation plan' solely to those cases where EPA has not unreasonably delayed action on a proposed [State Implementation Plan] revision." Id. at 541, 110 S.Ct. 2528.
The same is true here. Nothing in the statute precludes EPA from enforcing current NAAQS and BACT requirements even if it unreasonably delays taking action on a Permit. Moreover, the Clean Air Act is not silent about the consequences of such delay. "Congress has directly spoken to [that] precise issue" — namely, by providing a private right of action to compel timely action. Chevron, 467 U.S. at 842, 104 S.Ct. 2778 (emphasis added). Under 42 U.S.C. § 7604(a)(2):
Avenal Power, of course, availed itself of this remedy and brought suit in the D.C. district court. That court, correctly in our view, did not find the appropriate remedy to be issuance of the Permit without regard to the newly-promulgated regulations.
Although EPA now maintains that, having missed the deadline to act, it cannot determine from the statute which substantive standards to enforce against Avenal Power, we discern no such uncertainty, and reject the agency's position that it possesses the power to resolve the matter as it sees fit. First of all, as a general matter, the agency's "authority and responsibility to resolve some questions left open by Congress that arise during the law's administration" does not extend to "include a power to revise clear statutory terms that turn out not to work in practice." Utility Air Regulatory Grp. v. EPA, ___ U.S. ___, 134 S.Ct. 2427, 2446, 189 L.Ed.2d 372 (2014) (citing Barnhart, 534 U.S. at 462, 122 S.Ct. 941). In other words, "[a]n agency confronting resource constraints may change its own conduct, but it cannot change the law." Id.
Moreover, as for the particular proceedings at issue here, we do not believe EPA's legal or practical options were so conflicted, or even very uncertain. Although Petitioners suggest that EPA must deny a Permit application if it cannot perform the required review within the one-year limit, that does not appear to have been the agency's only option.
In an effort to bolster its position, EPA points out that it has long exercised authority to grandfather certain permit applications from revised regulations. That is true: EPA first asserted grandfathering authority shortly after the 1977 Amendments to the Clean Air Act passed. The issue at that time was a conflict between two apparently inconsistent provisions of the Clean Air Act — § 165's enforcement requirements, and § 168's statutory grandfathering measures. See Citizens to Save Spencer Cnty. v. EPA, 600 F.2d 844, 853-54 (D.C.Cir.1979) ("[§ ] 168 would have the practical effect of allowing permits to be issued for the construction of many projects for which permits would be barred by the rigorous environmental standards of [§ ] 165"). EPA ultimately chose not to make § 165 immediately effective, and grandfathered certain projects from its requirements. See 1977 Clean Air Act Amendments to Prevent Significant Deterioration, 43 Fed.Reg. 26,388, 26,391 (June 19, 1978) (adopting grandfathering for new permitting requirements for "any source the evaluation of which EPA would have completed before March 1, 1978, but for an extension of the public comment period pursuant to a meritorious request for such an extension"). The D.C. Circuit upheld the agency's decision in an opinion rendered prior to Chevron. Id. at 881-84. But EPA's decision, and the court's analysis, in that distinct statutory context does not resolve the question presented here.
Since then, EPA has invoked grandfathering authority from time to time to exempt certain projects from newly-implemented NAAQS and BACT regulations. But EPA's traditional exercise of grandfathering authority does not at all resemble the ad hoc discretion the agency now claims to wield. When EPA implemented grandfathering in the past, it consistently did so through formal notice and comment rulemaking procedures, as expressly authorized by the Clean Air Act, 42 U.S.C. § 7601(a)(1), and the Administrative Procedure Act, 5 U.S.C. § 553. For example, just last year, when EPA implemented new standards for particulate matter ("PM"), it implemented grandfathering to smooth the transition process. As the agency explained:
There is a significant difference between EPA's traditional grandfathering and its waiver of current applicable regulations in this case. On almost every prior occasion, EPA grandfathered a limited set of applications, in effect, by specifying an operative date (or dates) for each new regulation, as it was formally adopted.
The issue here is distinct. EPA now claims the authority to waive the law's requirements at will, without regard to the regulations it has passed,
Finally, EPA relies heavily on the argument that the equities weigh in favor of Avenal Power. In short, we agree. Avenal Power filed its application over six years ago, and endeavored to work with EPA for years, even after filing suit, to obtain a final decision. But however regrettable EPA's treatment of Avenal Power has been, we simply cannot disregard
For the foregoing reasons, we