Summary: ORDER TO SHOW CAUSE RE: RESCHEDULING OTIS D. WRIGHT, II , District Judge . Due to the Court's case load and scheduling conflicts, the Court wishes to continue the claim construction hearing, currently scheduled for April 29, 2016 (ECF No. 99.), until October 14, 2016. However, the Court does not wish to prejudice any party in pursuit of its scheduling needs, and therefore asks parties to SHOW CAUSE, in writing by February 29, 2016, if the amended schedule below will unduly prejudice any
More

ORDER TO SHOW CAUSE RE: RESCHEDULING

Due to the Court's case load and scheduling conflicts, the Court wishes to continue the claim construction hearing, currently scheduled for April 29, 2016 (ECF No. 99.), until October 14, 2016. However, the Court does not wish to prejudice any party in pursuit of its scheduling needs, and therefore asks parties to SHOW CAUSE, in writing by February 29, 2016, if the amended schedule below will unduly prejudice any party. Should a party fail to respond to this Order, their silence will be taken as acceptance of the modified schedule.

The proposed schedule is thus:

Date Event Governing Rule Tuesday SUBMITTED: Joint Claim Patent Rule 4-3 February 16, 2016 Construction Prehearing Statement Thursday Completion of Claim Patent Rule 4-4 September 2, 2016 Construction Discovery Friday Plaintiff's Claim Patent Rule 4-5(a) September 16, 2016 Construction Brief Friday Defendants' Claim Patent Rule 4-5(b) September 30, 2016 Construction Brief Friday Plaintiff's Reply Brief Patent Rule 4-5(c) October 7, 2016 Friday Technology tutorial Court's Patent October 14, 2016 Standing Order 9am - 10am Friday Claim Construction Hearing Patent Rule 4-6 October 14, 2016 10am - 12pm Friday Post Claim Construction October 14, 2016 Status Conference (TBD)

The parties shall adhere to the foregoing schedule. At the Post Claim Construction Status Conference, the parties should be prepared to set a trial date, to set dates for any further fact discovery, expert discovery, and dates for filing dispositive motions and pretrial motions.

IT IS SO ORDERED.