In this action concerning a latent construction defect, Brisbane Lodging, L.P. (Brisbane), appeals from a summary judgment entered in favor of respondents Webcor Builders, Inc., and Webcor Builders (collectively, Webcor). The construction contract executed by the parties included a clause which provided that all causes of action relating to the contract work would accrue from the date of substantial completion of the project. This contract provision clearly and unambiguously abrogated the so-called delayed discovery rule, which would otherwise delay accrual of a cause of action for latent construction defects until the defects were, or could have been, discovered. The trial court concluded the clause was valid and enforceable, noting that the agreement "was one between sophisticated parties seeking to define the contours of their liability." Summary judgment was then granted for Webcor after finding that Brisbane's action for latent construction defects was time-barred.
In the nonpublished portion of the opinion, we consider Brisbane's alternative arguments: (1) the trial court's interpretation of the disputed clause was in direct conflict with other provisions of the contract; (2) Webcor's acceptance of responsibility for making repairs to its defective work more than four years after substantial completion of the project raised a triable issue of fact as to whether Webcor itself believed that the parties had not waived the delayed discovery rule; (3) even if the delayed discovery rule was abrogated by contract, Webcor's postcompletion conduct indicated it waived its right to rely on this provision; and (4) a new statute of limitations period began from the point in time when Webcor participated in making repairs after the project had been completed. We reject these alternative arguments as well.
On July 12, 1999, Brisbane and Webcor entered into a contract for the design and construction of a 210-room, eight-story hotel, to be known as the Sierra Pointe Radisson Hotel (the Radisson). Before execution, the agreement had been extensively negotiated between the parties. For example, on March 8, 1999, Brisbane wrote to Webcor: "It is understood and agreed that negotiation of contract documents and satisfaction of customary closing conditions and due diligence must be satisfactory in form and substance to the parties and their respective counsel." Revisions were made by both parties to early contract drafts by striking out unacceptable provisions and by inserting additional terms. The form of agreement with "mutually acceptable language," was approved by Brisbane.
The final contract contained the 1997 American Institute of Architects (AIA) "Standard Form of Agreement Between Owner and Contractor (Cost Plus Fee), the AIA Document A201 General Conditions" (AIA A201), and several attachments relating to design requirements, construction allowances, the "Radisson Hotel Design Standards," and standard specifications required by Brisbane's parent company.
"
"13.7.1 As between the Owner and Contractor:
".1
It is undisputed that the Radisson was substantially completed on July 31, 2000.
In early 2005, Brisbane learned that there was a kitchen sewer line break which caused waste to flow under the Radisson. It notified Webcor of the problem and undertook temporary repairs to address the issue. By late March 2005, Webcor visited the site. It determined that the plumbing problem was a latent defect, and that Therma Corporation (Therma), the plumbing contractor, was responsible for the problem. Therma made repairs to the kitchen sewer line in July 2005.
About two years later, additional problems with the plumbing system arose. In October 2007, Brisbane again informed Webcor and Therma of the situation. Both Webcor and Therma returned to the Radisson to inspect the problem. Webcor thereafter notified Brisbane that it preferred to have Therma perform the necessary exploratory work to identify the source of the leakage in the kitchen sewer system. Therma did not make repairs, but did run a camera through a different portion of the kitchen drainage pipe. The camera fell out of the pipe, indicating the pipe had become disconnected. Therma failed to provide this information to Brisbane. In January 2008, Webcor notified Brisbane that both Webcor and Therma considered the issue closed. Brisbane took issue with that statement and responded that the matter "is certainly not closed." Ultimately, Brisbane discovered, among other things, that Therma had used ABS pipe material rather than cast iron pipe for the sewer line, in violation of the Uniform Plumbing Code.
In May 2008, Brisbane filed a complaint against Webcor for breach of contract, negligence, and breach of implied and express warranties. Webcor moved for summary judgment contending that the action was barred by
The trial court ruled as a matter of law that Article 13.7.1.1 clearly and unambiguously abrogated the delayed discovery rule and the provisions of section 337.15 which apply to claims arising out of latent construction defects. Under Article 13.7.1.1, the latest date upon which Brisbane could have commenced suit on its claims against Webcor was July 31, 2004, four years after substantial completion of the project (§§ 337, 337.1). Brisbane commenced its action on May 27, 2008, nearly four years later, making Brisbane's action untimely as a matter of law, and subject to dismissal on summary judgment.
We review a trial court's grant of summary judgment de novo. (Dore v. Arnold Worldwide, Inc. (2006) 39 Cal.4th 384, 388-389 [46 Cal.Rptr.3d 668, 139 P.3d 56].) "In performing our de novo review, we must view the evidence in a light favorable to [the] plaintiff as the losing party [citation], liberally construing [its] evidentiary submission while strictly scrutinizing [the] defendant['s] own showing, and resolving any evidentiary doubts or ambiguities in [the] plaintiff's favor. [Citations.]" (Saelzler v. Advanced Group 400 (2001) 25 Cal.4th 763, 768-769 [107 Cal.Rptr.2d 617, 23 P.3d 1143].) Summary judgment is proper "if all the papers submitted show that there is no triable issue as to any material fact and that the moving party is entitled to a judgment as a matter of law...." (§ 437c, subd. (c); see Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 843 [107 Cal.Rptr.2d 841, 24 P.3d 493].)
The "interpretation of a contract is subject to de novo review where the interpretation does not turn on the credibility of extrinsic evidence. [Citation.]" (Morgan v. City of Los Angeles Bd. of Pension Comrs. (2000) 85 Cal.App.4th 836, 843 [102 Cal.Rptr.2d 468]; accord, People ex rel. Lockyer v. R.J. Reynolds Tobacco Co. (2003) 107 Cal.App.4th 516, 520 [132 Cal.Rptr.2d 151].) Moreover, the question of whether a contract provision is illegal or
"This discovery rule takes into account the policy of deciding cases on the merits as well as the policies underlying the statute of limitations (to prevent stale claims and to require diligent prosecution). `Because a plaintiff is under a duty to reasonably investigate and because a suspicion of wrongdoing, coupled with a knowledge of the harm and its cause, will commence the limitations period, suits are not likely to be unreasonably delayed, and those failing to act with reasonable dispatch will be barred. At the same time, plaintiffs who file suit as soon as they have reason to believe that they are entitled to recourse will not be precluded.' [Citation]." (Goldrich v. Natural Y Surgical Specialties, Inc. (1994) 25 Cal.App.4th 772, 779 [31 Cal.Rptr.2d 162].)
"[F]aced with a developing body of common law on the subject, [the Legislature] carefully considered how to provide a fair time to discover construction defects, ... while still protecting a vital industry from the damaging consequences of indefinite liability exposure. For latent deficiencies, the lawmakers rejected shorter periods in favor of a limit in the upper range of those previously adopted by other jurisdictions." (Lantzy, supra, 31 Cal.4th at p. 377.)
In relevant part, section 337.15 provides: "(a) No action may be brought to recover damages from any person ... who develops real property or performs or furnishes the design, specifications, surveying, planning, supervision, testing, or observation of construction or construction of an improvement to real property more than 10 years after the substantial completion of the development or improvement for any of the following: [¶] (1) Any latent deficiency in the design, specification, surveying, planning, supervision, or observation of construction or construction of an improvement to, or survey of, real property[ and] [¶] (2) Injury to property ... arising out of any such latent deficiency. [¶] (b) As used in this section, `latent deficiency' means a deficiency which is not apparent by reasonable inspection."
As noted, the parties agreed in Article 13.7.1.1 that "any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion...." This provision is the AIA standard accrual provision and, at the time, was in wide usage throughout the United States. It has been recognized that "[f]or the construction industry the standard form contract — particularly the AIA Standard Document set — has in several respects served as a surrogate for a commercial code. The AIA contract developed gradually over the generations in company with an expanding body of experience in the field and in the courts, and was adopted verbatim, adapted, or parroted in a vast percentage (perhaps the majority) of private commercial contracts. It offers industry actors a degree of coherence, certainty and uniformity. Depending on one's point of view, it may also serve as a backdrop for performance which more or less reflects commercial realities and competing participant concerns." (Stipanowich, Reconstructing Construction Law: Reality and Reform in a Transactional System (1998) Wis. L.Rev. 463, 485.)
While the enforceability of the 1997 AIA standard contract accrual waiver presents a question of first impression in California, numerous out-of-state authorities have examined this same clause and without exception have concluded the provision altered the normal rules governing accrual of causes of action, including the delayed discovery rule, and was valid and enforceable. (See, e.g., Old Mason's Home v. Mitchell (Ky.Ct.App. 1995) 892 S.W.2d 304, 305-307; College of Notre Dame v. Morabito (2000) 132 Md.App. 158 [752 A.2d 265, 271-276]; Northridge Homes, Inc. v. John W. French & Associates, Inc. (Mass.Super.Ct. 1999) 10 Mass.L.Rptr. 690 [1999 WL 1260285]; Oriskany Central School Dist. v. Edmund J. Booth Architects (N.Y.App.Div. 1994) 206 A.D.2d 896 [615 N.Y.S.2d 160], affd. (1995) 85 N.Y.2d 995 [630 N.Y.S.2d 960, 654 N.E.2d 1208]; Gustine Uniontown v. Anthony Crane Rental (2006) 2006 PASuper 12 [892 A.2d 830, 836-837].)
The reasoning of these out-of-state cases is fairly consistent and is ably represented by Harbor Court Associates v. Leo A. Daly Co. (4th Cir. 1999) 179 F.3d 147 (Harbor). That case involved a lawsuit by the developer of a condominium tower, office building, hotel, health club, and parking garage against the project's architect for tort and breach of contract claims alleging defective design work by the architect. (Id. at p. 148.) The court, applying Maryland law, enforced a contractual provision which specified that a cause of action between the owner and contractor commenced to run upon substantial completion of the work in accordance with the applicable statute of
The Harbor court observed that Maryland had expressed "considerable reluctance to strike down voluntary bargains on public policy grounds." (Harbor, supra, 179 F.3d at p. 150.) Therefore, "[i]n light of this established judicial commitment to protecting individuals' efforts to structure their own affairs through contract, we cannot conclude that the Maryland Court of Appeals would decline to allow parties to contract around the state's default rule establishing the date on which a relevant statute of limitations begins to run. This is especially true where, as here, the parties to the agreement are sophisticated business actors who sought, by contract, to allocate business risks in advance. That is, rather than rely on the `discovery rule,' which prolongs the parties' uncertainty whether or if a cause of action will lie, the parties to this contract sought to limit that period of uncertainty by mutual agreement to a different accrual date." (Id. at pp. 150-151, italics added.) In concluding that Maryland law would allow the parties to waive the delayed discovery rule by contract, it noted that all other states which had addressed the precise issue, including Kentucky, New York, and Wisconsin, had similarly allowed the delayed discovery rule to be waived or modified by contract. (Id. at p. 151.)
Although we are not bound to follow these out-of-state authorities, they reflect a broad consensus as to the proper interpretation of the AIA's standard agreement's accrual provision under circumstances identical to the circumstances present in this case — that is, where the provision was freely entered into by parties represented by legal counsel engaged in a sophisticated commercial construction project.
Since latent defects in construction are usually the types of defects an owner may not learn about until years after completion, litigation often results over exactly when the owner discovered, or should have discovered, the defect. (See, e.g., Creekridge Townhome Owners Assn., Inc. v. C. Scott Whitten, Inc. (2009) 177 Cal.App.4th 251, 257-259 [99 Cal.Rptr.3d 258]; Renown, Inc. v. Hensel Phelps Construction Co. (1984) 154 Cal.App.3d 413, 420-421 [201 Cal.Rptr. 242]; Leaf, supra, 104 Cal.App.3d at pp. 407-408.) By tying the running of the applicable statute of limitations to a date certain, the parties here negotiated to avoid the uncertainty surrounding the discovery rule for the security of knowing the date beyond which they would no longer
Notwithstanding the consistent line of out-of-state authorities enforcing the contract provision adopted by the parties here, Brisbane argues that the contract provision should not be enforced because it violates California's public policy. Specifically, Brisbane argues Article 13.7.1.1 is void as against public policy because it "served to preclude Brisbane from relying on the delayed discovery doctrine in pursuing its claims for the latent defects in Webcor's work that did not manifest themselves until years after the construction project was complete."
The foregoing legal authorities reflect the broader, long-standing established public policy in California which respects and promotes the freedom of private parties to contract. (Carma Developers (Cal.), Inc. v. Marathon Development California, Inc. (1992) 2 Cal.4th 342, 363 [6 Cal.Rptr.2d 467,
Brisbane calls our attention to Moreno, supra, 106 Cal.App.4th 1415, a case in which the court refused to enforce contractual language that had the effect of not only shortening the limitations period, but also waiving the delayed discovery rule. Brisbane claims Moreno stands for the proposition that "a contractual provision which purports to eliminate the delayed discovery doctrine is not enforceable." We do not believe Moreno can be so broadly interpreted.
After the buyers purchased the home, they became ill. (Moreno, supra, 106 Cal.App.4th at p. 1420.) An environmental evaluation of the house revealed that the air ducts in the home were insulated with asbestos. (Id. at p. 1421.) In addition, an unsealed air return was discovered that permitted dust, dirt, and rust to enter the heating system. (Ibid.) Fourteen months after the inspection, the buyers sued the home inspector for breach of contract, negligence, and negligent misrepresentation. (Ibid.) The trial court sustained the home inspector's demurrer, based on the one-year limitation of actions provision in the home inspection contract. (Id. at p. 1422.)
The court based its ruling on the judicial concern for protection of homeowners, and the fact that the homeowners must rely on the greater expertise of home inspectors to discover latent defects in the home. The court stated that although the delayed discovery rule originated in cases involving the acts of licensed professionals, the rule may also be applied to trades-people who hold themselves out as having a special skill, or who are required by statute to possess a certain level of skill. (Moreno, supra, 106 Cal.App.4th at p. 1424.) The court reasoned, "Although not as regulated as some fields, the Legislature has recognized the significance of the role home inspectors occupy in this state's economy, as well as the potential hazards of fraudulently or negligently performed inspections. As with other forms of professional malpractice, specialized skill is required to analyze a residence's
The Moreno court believed that public policy required the application of the delayed discovery rule as a contractual requirement in all home inspection contracts. In the court's words: "[C]auses of action for breach of a home inspector's duty of care should accrue in all cases, not on the date of the inspection, but when the homeowner discovers, or with the exercise of reasonable diligence should have discovered, the inspector's breach." (Moreno, supra, 106 Cal.App.4th at pp. 1428-1429.) The court "attach[ed] no special significance" to the fact that the Legislature itself did not provide for a rule of delayed discovery when it enacted Business and Professions Code section 7199, which set a maximum four-year outside limitations period for actions against home inspectors measured from the date of inspection. (Moreno, at p. 1430.)
While Moreno has been followed in subsequent cases,
Unlike the parties here, the plaintiffs in Moreno were persons unsophisticated in construction matters (indeed, that is why they hired the home inspector in the first place). The importance of the special relationship between the parties, where the home inspector was a professional in possession of special skills and knowledge upon whom the homeowners relied completely for counsel and advice, was emphasized throughout the court's opinion in Moreno. (See Parsons v. Tickner (1995) 31 Cal.App.4th 1513, 1526 [37 Cal.Rptr.2d 810] [stressing "`importance of the relationship between
Furthermore, unlike this case, Moreno involved a contract clause that not only waived the delayed discovery rule, but also reduced the statute of limitations from four years to one. In our case, Brisbane had the benefit of the full statute of limitations period, up to four years, to conduct any inspections believed necessary to uncover latent defects — a period of time the Moreno court itself acknowledges would be reasonable. (Moreno, supra, 106 Cal.App.4th at p. 1434.)
Lastly, we note that one court, In re Brocade Communications Systems, Inc. (N.D.Cal. 2009) 615 F.Supp.2d 1018 (Brocade), has found the reasoning in Moreno to be unpersuasive in circumstances similar to those presented here where "an agreement between sophisticated parties" was entered into "that defines the contours of their liability." (Id. at p. 1040.) The court distinguished Moreno, which "merely stands for the limited proposition that a cause of action may not accrue in a suit against a home inspector until the injury is discovered. [Citation.]" (Ibid.) The court believed "Moreno simply cannot be extended far enough to relieve [the corporation] of the indemnification it agreed to provide...." (Ibid.) We find the reasoning of Brocade persuasive and agree that this distinction makes Moreno inapposite and inapplicable to control the result in this case.
Therefore, based on our review of relevant case authorities, both in California and uniformly throughout the nation, we conclude that Article 13.7.1.1 of the Brisbane/Webcor contract was a valid, enforceable provision freely entered into by sophisticated parties engaging in a commercial construction project. Accordingly, the trial court was correct in granting summary judgment after finding that Brisbane's claims against Webcor were time-barred.
5.-7.
The judgment is affirmed. Webcor is awarded its costs on appeal.
Reardon, J., and Rivera, J., concurred.