The Eastern Municipal Water District (EMWD) hired general contractor S.J. and Burkhardt, Inc. (SJB), for a public works construction project in 2006. Safeco Insurance Company (Safeco) executed performance and payment bonds for the project. Plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB), was a subcontractor for the project, completing its work by September 2006, but it did not receive payment of $577,038.37 owed.
In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to interplead retained sums. Safeco made a motion for summary judgment on the cause of action for payment under the bond on the ground that GSB's claim was untimely. The trial court granted the motion as to that cause of action, finding that there had been three cessations of labor that triggered GSB's duty to file a stop notice in order to
GSB appeals the summary judgment ruling claiming (a) the trial court erroneously overruled its objections to evidentiary matters presented in support of Safeco's summary judgment, and (b) the court erred in finding the action was untimely. We affirm.
From the pleadings we discern the following facts:
EMWD hired SJB as general contractor on "Specification No. 934W, Nuevo Road/I-215 Water Transmission Pipeline Project, Perris California" (the Project). On April 26, 2006, SJB entered into a subcontract agreement with GSB to perform the tunneling portion of the project. For these services, SJB originally agreed to pay GSB $565,150. After GSB agreed to provide additional services, SJB agreed to pay an additional $27,912.20, for a total project price of $593,062.20 On April 18, 2006, Safeco executed a payment bond for the Project. GSB completed its portion of the work on the Project in September 2006.
Prior to completion of the Project, there were three cessations of labor which exceeded 30 days: the first occurred between November 11, 2006, and December 17, 2006; the second occurred between April 4, 2007, and May 20, 2007, and the third occurred between May 20, 2007, and October 4, 2007. The overall Project was completed in 2008. GSB alleged that it filed a stop notice with EMWD on January 2, 2008, in the amount of $577,038.37.
In July 2008, GSB filed suit against SJB for nonpayment under the contract, as well as in common counts. The fourth cause of action included EMWD as a defendant for enforcement of stop notice, and the fifth cause of action named Safeco in a claim on the stop notice release bond and payment bond. In October 2008, EMWD recorded a notice of acceptance signifying completion of the Project.
On December 22, 2010, Safeco filed a motion for summary judgment as to the fifth cause of action relating to the payment bond. In support of its motion, Safeco submitted a declaration of one of its counsel, Brian Lang, as well as a declaration regarding the summary of voluminous documents received during discovery from EMWD. Those documents related to the daily performance and nonperformance of work on the Project, including certified payroll reports, inspector's reports, EMWD safety inspection reports, and statement of nonperformance. The motion was also based on GSB's responses to interrogatories propounded by Safeco, and EMWD's response to Safeco's request for production of documents.
In response to the motion, GSB generally objected to both declarations, citing hearsay, lack of personal knowledge, opinion, speculation, and that the declarant was not an expert. However, GSB did not dispute that there were cessations of labor, arguing instead that the issue of cessation of labor is not relevant unless there has been no notice of completion. Nor did GSB object to EMWD's responses to the request for production of documents, by which Safeco obtained the documents summarized by Lang.
The trial court overruled GSB's objections and granted Safeco's motion for summary judgment. Notice of entry of the order and judgment on the fifth cause of action was filed on August 2, 2011. GSB filed notice of appeal from that order on September 19, 2011.
The matter proceeded to court trial on the remaining causes of action based on various stipulated facts and evidence. On the first three causes of action against SJB, the court awarded GSB $577,038.37 under the contract, plus penalties pursuant to Business and Professions Code section 7108.5 in the amount of $590,016.60, plus interest on progress payments in the amount of $242,981.62, plus penalties pursuant to Business and Professions Code section 7107 in the amount of $50,863.50, plus interest on that sum in the amount of $6,834.39, for a grand total of $1,467,734.48. On the fourth cause of action,
GSB appealed from the judgment in favor of Safeco on the fourth cause of action on January 6, 2012.
GSB argues that the trial court erred in overruling its objections to the declarations of Bryan Lang, one of Safeco's counsel, and the exhibits attached thereto. GSB argues that the declarations and exhibits were inadmissible hearsay and unauthenticated, requiring reversal of the summary judgment. We disagree.
During summary judgment proceedings, GSB objected to the declarations of Safeco's counsel, Bryan Lang, on the grounds of "Hearsay (Evid. Code Section 1200), Lack of Personal Knowledge (Evid. Code Section 702), Opinion (Evid. Code Section 803), Speculation (Evid. Code Section 800), Irrelevant (Evid. Code sections 210, 350-351); Not an Expert (Evid. Code Section 720)."
The same rules of evidence that apply at trial also apply to the declarations submitted in support of and in opposition to motions for summary judgment. (Bozzi v. Nordstrom, Inc. (2010) 186 Cal.App.4th 755, 761 [111 Cal.Rptr.3d 910].)
We review the trial court's evidentiary rulings on summary judgment for abuse of discretion. (Park v. First American Title Co. (2011) 201 Cal.App.4th 1418, 1427 [136 Cal.Rptr.3d 684], citing Carnes v. Superior Court (2005) 126 Cal.App.4th 688, 694 [23 Cal.Rptr.3d 915]; see DiCola v. White Brothers Performance Products, Inc. (2008) 158 Cal.App.4th 666, 679 [69 Cal.Rptr.3d 888].) As the party challenging the court's decision, it is plaintiff's burden to establish such an abuse, which we will find only if the trial court's order exceeds the bounds of reason. (DiCola v. White Brothers Performance Products, Inc., supra, 158 Cal.App.4th at p. 679.) On review, we view the evidence in the light most favorable to plaintiff as the losing party and liberally construe plaintiff's evidentiary submissions while strictly scrutinizing defendant's evidence, in order to resolve any evidentiary doubts in plaintiff's favor. (McDonald v. Antelope Valley Community College Dist. (2008) 45 Cal.4th 88, 96-97 [84 Cal.Rptr.3d 734, 194 P.3d 1026].)
Code of Civil Procedure, section 437c, subdivision (b)(1), expressly provides that a motion for summary judgment shall be supported by "affidavits, declarations, admissions, answers to interrogatories, depositions, and matters of which judicial notice shall or may be taken." It further provides that the supporting papers shall include a separate statement setting forth plainly and concisely all material facts which the moving party contends are undisputed and that each of the material facts shall be followed by a reference to the supporting evidence.
Code of Civil Procedure, section 437c, subdivision (b)(2), provides for an opposition to the motion, which, where appropriate, shall consist of affidavits, declarations, admission, answers to interrogatories, depositions, and matters of which judicial notice shall or may be taken. Supporting and opposing affidavits or declarations shall be made by any person on personal knowledge, shall set forth admissible evidence, and shall show affirmatively that the affiant is competent to testify to the matters stated in the affidavits or declarations. (Code Civ. Proc., § 437c, subd. (d).)
Ordinarily, declarations are considered "`hearsay and are inadmissible at trial, subject to specific statutory exceptions, unless the parties stipulate to the admission of the declarations or fail to enter a hearsay objection. [Citations.]' [Citation.]" (Oiye v. Fox (2012) 211 Cal.App.4th 1036, 1050 [151 Cal.Rptr.3d 65].) By requiring parties to use affidavits and declarations in connection with summary judgment motions, Code of Civil Procedure section 437c, subdivision (b)(1), is a statutory exception to the hearsay rule.
The statutory provisions adequately address the hearsay objections to Lang's declarations. The objection based on Lang's personal knowledge was properly overruled because the declaration states that Lang had personal knowledge of the matters that had been produced in response to Safeco's discovery requests. GSB's contention that Lang was not present when EMWD turned over the documents is not well taken, where Lang's declaration did not represent he was present, and where GSB's own counsel indicated that he was present at the time of the document production. None of the objections claim the exhibits were not the same exhibits turned over during the production of documents, or that they were not properly authenticated.
As to the documentary evidence attached to Lang's declaration, Safeco included a copy of its request for production of documents, which was propounded to EMWD, and EMWD's responses to demand for documents. EMWD's responses established the foundation for the documents, including the contract, subcontract, payment bond, certified payroll records, documents relating to cessations of labor, and the notice of acceptance.
Although it objected to Lang's declarations, GSB did not object to EMWD's responses or the exhibits themselves, and it did not dispute the material terms of the writings attached as exhibits. They were properly considered by the court in ruling on the motion.
GSB provided no reference to supporting evidence as to each material fact it contended was disputed. Nor did it submit evidence to contradict the showing of Safeco, or to support the existence of a factual dispute as to whether there were three separate cessations of labor. Thus, a favorable ruling on the evidentiary objections would not have changed the outcome; GSB did not show by "`specific facts'" that the requisite triable issue of material fact was present. (Tibor v. Superior Court (1997) 52 Cal.App.4th 1359, 1368, 1369 [61 Cal.Rptr.2d 326].) Instead, it merely provided a different legal interpretation of what triggered the duty to file its stop notice, an issue of law. (See Twaite v. Allstate Ins. Co. (1989) 216 Cal.App.3d 239, 254 [264 Cal.Rptr. 598] [where plaintiff concluded counteraffidavits were unnecessary, the issue was a matter of law].)
Notwithstanding GSB's objections, there was no dispute as to whether there had been cessations of labor, so there was no triable issue as to that material fact; there was only a question of law as to whether GSB's stop notice was timely. The purpose of the law of summary judgment is to provide courts with a mechanism to cut through the parties' pleadings in order to determine whether, despite their allegations, trial is in fact necessary to resolve their dispute. (Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 843 [107 Cal.Rptr.2d 841, 24 P.3d 493].)
In the absence of a triable issue on this factual issue, summary judgment was proper. (Bartholomew v. SeaRiver Maritime, Inc. (2011) 193 Cal.App.4th 699,
GSB argues its action on the payment bond was timely because the limitations period began to run from the date the notice of acceptance was recorded pursuant to Civil Code former sections 3249 and 3184, subdivision (a). We disagree.
We have italicized the word "after" in quoting the statutory provision because in an unbroken, albeit older, line of cases dealing with similar claims, it has been held that a claim of lien filed before the notice of completion (or acceptance) has been recorded is premature and ineffectual. (Davis v. MacDonough (1895) 109 Cal. 547, 550 [42 P. 450] [claim of lien filed before completion of building provided no right of recovery]; Gross v. Hazeltine (1930) 107 Cal.App. 446, 455 [290 P. 673]; McCreary v. Toronto Midway Oil Co., Ltd. (1918) 38 Cal.App. 17, 20 [175 P. 87] [premature claim of lien conferred no rights].)
These cases are instructive because the language of the claim-of-lien statutes at issue used the same language as the statutory scheme governing
GSB observes that in a public works context, completion occurs upon acceptance of the project by the awarding body. (Civ. Code, former § 3086; Department of Industrial Relations v. Fidelity Roof Co. (1997) 60 Cal.App.4th 411, 418 [70 Cal.Rptr.2d 465].) If so, GSB failed to file a timely stop notice within 30 days after the notice of acceptance. However, if there was a 30-day cessation of labor within the meaning of former section 3086, then that work stoppage was a "completion" pursuant to former sections 3086 and 3184, and commenced the running of the stop notice period. (Hayward, supra, 16 Cal.App.4th at pp. 1108, 1110.) This construction of the statutory language is
GSB also argues that subdivision (a) of Civil Code former section 3184 provided that the recordation of the notice of acceptance triggers the time limit, and that EMWD recorded a notice of acceptance respecting the project after GSB had filed its lawsuit. The dissent agrees with this reasoning. However, this argument fails to take into account the plain language of former section 3184 requiring that the stop notice be filed after the notice of acceptance has been recorded. As we have pointed out, the stop notice in the present case was premature and thus ineffectual. If the notice of acceptance triggered the commencement of the time limit for filing the stop notice, no stop notice was filed after that event.
Finally, GSB argues that to find that the cessation of labor constituted a completion would require subcontractors and suppliers to monitor work almost daily and that it ignores the realities of phased construction work, which is frequently halted while plans are changed, easements are perfected, or permits are obtained. Unfortunately, GSB failed to present any competent evidence (declarations, exhibits, etc.) supporting an assertion that the cessations of labor were excused in this manner. Further, GSB's responses to interrogatories acknowledged that its last day of work on the project was "Sometime in late September of 2006; believed to be the beginning of the week of the 25th."
In order to defeat the summary judgment motion, it was incumbent upon GSB to establish either that the recording of the notice of acceptance was the sole triggering event, or that there had been no cessation of labor. Otherwise, the cessations of labor constituted "completion" pursuant to the definition in Civil Code former section 3086 and commenced the period for filing stop notices regarding public works (Hayward, supra, 16 Cal.App.4th at p. 1110), and the tardily recorded notice of acceptance did not recommence it.
The exhibits submitted in support of the summary judgment motion established three separate and distinct periods in which all work stopped on the Project. These periods occurred between 2006 (after GSB completed its portion of the work) and 2007. GSB did not provide any counterevidence to show that work had not stopped, so there was no triable issue of material fact as to whether a cessation of labor had occurred. For this reason, the trial court concluded it had to accept the timeline presented in Safeco's papers, and found the action was time-barred.
The judgment is affirmed. Safeco is entitled to costs on appeal.
Codrington, J., concurred.
I disagree with the majority on two accounts. First, I believe the action was filed in a timely manner under Civil Code former section 3184, subdivision (a).
A simple reading of the relevant statutes shows that the present matter was timely filed and that the beginning of the limitations period was the date of the recordation of the notice of completion, which was October 9, 2008. The pertinent statutes provide:
"Suit against the surety or sureties on the payment bond may be brought by any claimant, or his assigns, at any time after the claimant has furnished the last of the labor or materials, or both, but must be commenced before the expiration of six months after the period in which stop notices may be filed as provided in Section 3184."
"To be effective, any stop notice pursuant to this chapter must be served before the expiration of:
"(a) Thirty days after the recording of a notice of completion (sometimes referred to in public works as a notice of acceptance) or notice of cessation, if such notice is recorded.
"(b) If no notice of completion or notice of cessation is recorded, 90 days after completion or cessation."
"`Completion'" means, in the case of any work of improvement other than a public work, actual completion of the work of improvement. Any of the following shall be deemed equivalent to a completion:
"(a) The occupation or use of a work of improvement by the owner, or his agent, accompanied by cessation of labor thereon.
"(b) The acceptance by the owner, or his agent, of the work of improvement.
"(c) After the commencement of a work of improvement, a cessation of labor thereon for a continuous period of 60 days, or a cessation of labor thereon for a continuous period of 30 days or more if the owner files for record a notice of cessation.
In viewing the statutes together, a suit against a surety must be filed within six months of the time for the filing of a stop notice. Under former section 3184, the stop notice must be filed within 30 days of the recordation of the notice of completion or notice of cessation. In a case in which neither a notice of completion or notice of cessation is recorded, the stop notice must be filed within 90 days of the actual cessation or completion of the work. In the absence of a recording of either of these notices, a public work of improvement is deemed completed when there has been a cessation of labor for a continuous period of 30 days.
Here, the notice of completion was recorded on October 9, 2008. Plaintiff, Golden State Boring & Pipe Jacking, Inc. (GSB), had until May 9, 2009, in which to file its action. The action was filed on July 3, 2008, more than 10 months before the running of the limitations period. Thus, it was timely filed under former section 3184, subdivision (a). As such, we never get to the issue of whether there was a "cessation of labor" for a period of 30 days or more.
Both EMWD and the majority rely almost exclusively on W. F. Hayward Co. v. Transamerica Ins. Co. (1993) 16 Cal.App.4th 1101 [20 Cal.Rptr.2d 468] for the proposition that GSB did not timely file its action after there had been a cessation of work longer than 30 days. Both EMWD and the majority ignore, however, the facts and the basic premise upon which the decision was based.
In W. F. Hayward Co. v. Transamerica Ins. Co., supra, 16 Cal.App.4th 1101, Cates Construction, Inc. (Cates), contracted with the County of Los Angeles (the County) to construct the Lost Hills sheriff's station. The plaintiff contracted with Cates to provide certain labor and materials for the job. A dispute arose between Cates and the County; the County notified Cates that it was suspended from the job. Thereafter Cates and the County entered into an agreement titled "Termination for Convenience Agreement and Mutual Release," wherein Cates was relieved from performing the job and the County released Cates from any liability. Pursuant to the agreement, all of the contracts entered into between Cates and its subcontractors were assigned to
Of importance to that case, however, was that there was no notice of completion recorded. As pointed out by the court at the beginning of its discussion, "the issue here is whether the complaint was filed within six months after the period in which appellant could file stop notices. The parties' dispute centers on what constitutes the period for filing stop notices [¶] Section 3184, referenced in section 3249, provides that any stop notice `must be served before the expiration of: [¶] (a) Thirty days after the recording of a notice of completion (sometimes referred to in public works as a notice of acceptance) or notice of cessation, if such notice is recorded. [¶] (b) If no notice of completion or notice of cessation is recorded, 90 days after completion or cessation.' With regard to Cates's work on the project, the parties do not dispute that neither a notice of completion nor a notice of cessation was filed or recorded. Subdivision (b) is therefore the applicable portion of section 3184. Application of this provision presents the question: When was there a `completion or cessation'? [¶] Because it provides a definition of `completion,' section 3086 comes into play." (W. F. Hayward Co. v. Transamerica Ins. Co., supra, 16 Cal.App.4th at p. 1106, fns. omitted, italics added.)
As is evident from this discussion in W. F. Hayward Co., former section 3086 and the cessation of work concept comes into play only when there has been no recordation of a notice of completion or notice of cessation. Here, a notice of completion was recorded; we need go no further. GSB's action was timely filed based on the recordation of the notice of completion.
EMWD's entitlement to summary judgment was premised on the notion that GSB's filing of its complaint was untimely. EMWD's argument is based on the "fact" that there were three cessations of work for 30 days or more, each of which it contends commenced the limitations period. To this end, EMWD submitted the following undisputed facts and supporting evidence:
"5. There was a continuous 30-day cessation of labor on the Project between the dates of November 11, 2006 and December 17, 2006. [¶]
"6. There was a continuous 30-day cessation of labor on the Project between the dates of April 4, 2007 and May 20, 2007. [¶]
"7. There was a continuous 30-day cessation of labor on the Project between the dates of May 20, 2007 and October 4, 2007. [¶]
The "Summary of Voluminous EMWD Records ..." was prepared by Bryan Lang, an attorney representing the moving party. In his one-and-one-half-page declaration, he avers that he has "personal knowledge of the foregoing, except as to those matters stated on information and belief...." He indicates that he reviewed the documents produced by EMWD to defendant, Safeco Insurance Company's (Safeco), request to produce documents and, based on that review, compiled an Excel spreadsheet which tracked the dates of work on the project.
GSB's objections were meritorious and should have been sustained.
On a motion for summary judgment "[t]he moving party must `support[]' the `motion' with evidence including `affidavits, declarations, admissions, answers to interrogatories, depositions, and matters of which judicial notice'... may `be taken.' [Citation.]" (Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 843 [107 Cal.Rptr.2d 841, 24 P.3d 493].) "Supporting and opposing affidavits or declarations shall be made by any person on personal knowledge, shall set forth admissible evidence, and shall show affirmatively that the affiant is competent to testify to the matters stated in the affidavits or declarations...." (Code Civ. Proc., § 437c, subd. (d), italics added; see Regents of University of California v. Superior Court (1996) 41 Cal.App.4th 1040, 1044 [48 Cal.Rptr.2d 922].) "The affidavits must cite evidentiary facts, not legal conclusions or `ultimate' facts. [Citation.] [¶] Matters which would be excluded under the rules of evidence if proffered by a witness in a trial as hearsay, conclusions or impermissible opinions, must be disregarded in supporting affidavits." (Hayman v. Block (1986) 176 Cal.App.3d 629, 639 [222 Cal.Rptr. 293].)
Here, both EMWD and the majority rely on Evidence Code section 1523, subdivision (d), for the proposition that the trial court could consider Lang's summary of EMWD's records, along with its attachments, as substantive evidence of cessations of work during the project.
As provided by Evidence Code section 1523, subdivision (d): "Oral testimony of the content of a writing is not made inadmissible by subdivision (a) if the writing consists of numerous accounts or other writings that cannot be examined in court without great loss of time, and the evidence sought from them is only the general result of the whole." Evidence Code section 1523 is a best evidence rule allowing secondary evidence to prove the content of a writing. "Secondary evidence, of course, must comply with the rules governing the admissibility of evidence generally, including relevance [citation] and the hearsay rule [citation]." (Dart Industries, Inc. v. Commercial Union Ins. Co. (2002) 28 Cal.4th 1059, 1070, fn. 2 [124 Cal.Rptr.2d 142, 52 P.3d 79].)
Here, there was no showing that the documents reviewed for purposes of putting together the Evidence Code section 1523 record summary were
Specifically, the documents reviewed for purposes of the summary were produced by EMWD to Safeco, pursuant to a request to produce documents. The 24 requests sought "[a]ny and all" documents in the possession of EMWD that were responsive to the individual requests. The requests were not limited to "business records" of EMWD. Further, the request to produce documents did not ask that any custodian of records submit a verification coinciding with the foundational requirements of Evidence Code section 1271 or 1280. The request merely sought "a verification executed under penalty of perjury that the copies provided are adequate and true and complete copies of the materials in question."
In looking to the documents in our record which were reviewed and attached to Lang's summary, it is evident that very few of the documents reviewed could be characterized as "business records" of EMWD. Of the 80 pages that are attached to the declaration and spreadsheet, 18 pages would appear to be EMWD documents. The remaining 62 pages are documents of SJ Burkhardt, Inc., SJ & B Group, Inc., and Cozad & Fox, Inc. In the absence of foundation, none of these documents can properly serve as the basis for Lang's summary of records.
In discussing Evidence Code former section 1509, the predecessor to Evidence Code section 1523, the court in Vanguard Recording Society, Inc. v. Fantasy Records, Inc. (1972) 24 Cal.App.3d 410, 418-419 [100 Cal.Rptr. 826], stated: "Pursuant to Evidence Code, section 1509, a summary of business records consisting of numerous accounts or other writings that cannot be examined in court without great loss of time, is admissible in evidence upon a showing that the actual business records are entitled to admission in evidence...." "A person who directs or supervises the preparation of business records may testify to their contents." (Kirby v. Alcoholic Bev. etc. Appeals Bd. (1970) 8 Cal.App.3d 1009, 1017 [87 Cal.Rptr. 908].)
Pajaro Valley Water Management Agency v. McGrath (2005) 128 Cal.App.4th 1093 [27 Cal.Rptr.3d 741] is perhaps most instructive. There, the plaintiff sued the defendant for unpaid charges for water extracted from the defendant's well. On its motion for summary judgment, the plaintiff submitted a declaration of its general manager which averred that the general
The appellate court disagreed. "[T]he McNiesh declaration explicitly describes the `amount owed' (i.e., the matter asserted) as being derived from yet a third level of documentary hearsay, the `bills' containing the `amounts' that were `reflected in' the final figure. The original bills might be admissible over a hearsay objection as business records (Evid. Code, § 1271) or perhaps official records (Evid. Code, § 1280), but to establish either exception would require a showing of the time and circumstances of the documents' creation. (Evid. Code, §§ 1271, 1280.) No such showing was attempted.... [¶] In overruling [the defendant's] objections, the trial court cited Evidence Code section 1521 ... while alluding to unspecified hearsay exceptions. [Evidence Code s]ection 1521 permits the introduction of `otherwise admissible secondary evidence' to prove the contents of a writing. It does not excuse the proponent from complying with other rules of evidence, most notably, the hearsay rule. [Citation.] As applicable here, [Evidence Code] section 1521 means only that the [plaintiff] could introduce secondary evidence to establish the contents of bills if (1) the contents themselves were admissible, and (2) the secondary evidence was `otherwise admissible.' [Citation.] Here the contents of the bills were hearsay. In the absence of a showing that they came within an exception, secondary evidence of their contents was no more admissible than the bills themselves, which is to say, not at all. [¶] ... If [the summary] is offered to prove the actual values on which a party's damages calculation rests, the summary is hearsay and must, on proper objection, be brought within an exception or excluded from evidence. Since the [plaintiff] failed to do this here, [the defendant's] hearsay objection should have been sustained." (Pajaro Valley Water Management Agency v. McGrath, supra, 128 Cal.App.4th at pp. 1107-1108; see Prato-Morrison v. Doe (2002) 103 Cal.App.4th 222, 229-230 [126 Cal.Rptr.2d 509].)
Here, just as in Pajaro Valley Water Management Agency v. McGrath, the documents relied upon by Lang were hearsay for which no foundation was laid. As a result, his record summary was inadmissible.