EDWIN A. LOMBARD, Judge.
This suit arises from a construction contract dispute between the Appellants, condominium owner Michael Brenner and his mother, Jackie Brenner ("the Brenners"), and carpenter, Donald Zaleski. The Brenners seek review of First City Court's August 18, 2014 judgment dismissing their breach of contract claims with prejudice. Finding that the First City Court made a legal error in determining that the contract at issue was not breached, we reverse. Additionally, this matter is remanded for a determination of damages.
The Brenners retained Mr. Zaleski to build a wooden loft
After Mr. Zaleski began building the loft,
Subsequently, home inspector and civil engineer Friedrich Gurtler was hired by the Brenners to inspect Mr. Zaleski's work, particularly the condition of the subflooring. Mr. Gurtler opined that Mr. Zaleski's work was substandard and not structurally sound. He recommended the loft be reinforced with steel support columns, which the Brenners installed.
The Brenners
A trier of fact's factual conclusions respecting a breach of contract claim are governed by the manifest error or clearly wrong standard of review. See Tarifa v. Riess, 02-1179, p. 10 (La.App. 4 Cir. 5/7/03), 856 So.2d 21, 27, as clarified on reh'g (9/3/03), writ denied, 03-2776 (La. 12/19/03), 861 So.2d 574 and writ denied, 03-2755 (La. 12/19/03), 861 So.2d 577. Where there is conflicting testimony, reasonable evaluations of credibility and inferences of fact should not be disturbed by the reviewing court. Rosell v. ESCO, 549 So.2d 840, 844 (La.1989). Where there are two permissible views of the evidence, the trier of fact's choice between them cannot be manifestly erroneous or clearly wrong. Id. However, where one or more trial court legal errors interdict the fact-finding process, the manifest error standard is no longer applicable, and, if the record is otherwise complete, the appellate court should make its own independent de novo review of the record and determine a preponderance of the evidence. Evans v. Lungrin, 97-0541, 97-0577, pp. 6-7 (La.2/6/98), 708 So.2d 731, 735.
A contract is the law between the parties, and the parties will be held to full performance in good faith of the obligations flowing from the contract. Henderson v. Ayo, 11-1605, p. 5 (La.App. 4 Cir. 6/13/12), 96 So.3d 641, 645 (citing La. Civ.Code art.1983). It is implicit in every building contract that the contractor's work be performed in a good, workmanlike manner, and free from defects in materials or work. Id. [Citations omitted.] See La. Civ.Code art. 2756.
The Brenners' aver that their breach claim is based upon La. Civ.Code art. 2769, entitled Contractor's liability for non-compliance with contract, which states:
Furthermore, they also contend that they had the right to terminate Mr. Zaleski's employment at any time pursuant to La. Civ.Code art. 2765, entitled Cancellation of contract by owner, which provides:
While the Brenners are correct in asserting that they had the right to terminate Mr. Zaleski at any time under La. Civ. Code art. 2765, our court has explained that claims under La. Civ.Code arts. 2765 and 2769 are distinct.
In Henderson, 11-1605, pp. 5-6, 96 So.3d at 645, we reasoned that pursuant to La. Civ.Code. art. 2765, Louisiana law recognizes the right of the owner of a construction project to terminate a contract to build after work has commenced on a project. It is the owner's obligation, nevertheless, to pay the contractor for the work he or she completed. Id., 11-1605, p. 6, 96 So.3d at 645. We further clarified that La. Civ.Code art. 2769 applies where a contractor does not perform the work he or she has contracted to do:
Id.
The Brenners further rely upon Vazquez v. Gairens, 26 So.2d 319, 320 (La.App.Orleans 1946), wherein our predecessor court considered the application of both La. Civ. Code arts. 2765 and 2769:
Id. at 320.
Pursuant to the holdings of Henderson and Vazquez, La. Civ.Code art. 2769 applies where the cancellation of a contract is founded on just grounds. To establish a contractor's liability for damages due to defective workmanship, the owner must prove: 1) the existence and nature of the defects; 2) that the defects are due to faulty materials or workmanship, and 3) the cost of repairing the defects. Cascio v. Carpet, 42,653, p. 10 (La. App. 2 Cir. 10/24/07), 968 So.2d 844, 850.
Regarding whether the Brenners' demonstrated the existence and nature of defects, we note that in its judgment, denying the Brenners' breach of contract claim, the First City Court reasoned:
The First City Court refers to the existence of "deficiencies" in Mr. Zaleski's work; however, it held that Mr. Zaleski was not permitted to complete the job and cure deficiencies. This is legal error. As noted above in Vazquez, "[t]here is no obligation on the part of the owner to allow a contractor, who has breached his undertaking by the performance of an unskilled and unsuitable job, additional time or opportunity to rectify his work." Vazquez, 26 So.2d at 320. Also, Ms. Brenner testified more than once at trial that she terminated the contract not only because of Mr. Zaleski's work, but also because of his attitude. The First City Court determined
Nevertheless, having determined that the First City Court made a legal error, we conduct a de novo review as to whether the Brenners met their three-prong burden of proof set forth in Cascio.
Our review of the record shows that the Brenners did establish that cosmetic and subfloor defects existed and that these defects are due to Mr. Zaleski's workmanship. The Brenners testified that just prior to Mr. Zaleski's termination they collaborated in the drafting of an e-mail to Mr. Zaleski detailing the errors they observed. Ms. Brenner, who sent the e-mail, testified that they noted the following cosmetic errors: incorrectly or inconsistently hinged doors; an uneven air hole; incorrectly installed door tongs; ill-fitting air conditioning cabinet doors, and sloppily cut sheetrock. Furthermore, post-termination, they noticed that there was movement in the subflooring installed by Mr. Zaleski. The Brenners also argue that Mr. Zaleski fell behind on the work schedule he contracted to follow. The contract, they contend, provided that the flooring be completed within five days, but he took six to eight weeks to complete the flooring system, according to the testimony of Mr. Brenner.
Mr. Gurtler, who was accepted by the First City Court as an expert in home inspections and civil engineering, testified that the floor joists installed by Mr. Zaleski provided inadequate support of the floor framing system. He testified that the floor framing system was not structurally sound and not functional for its intended purpose. He recommended that the loft be reinforced with steel support columns to correct this issue. He additionally noted cosmetic defects, such as unevenly cut doors and poorly cut miter joints. A report Mr. Gurtler prepared was admitted into evidence. No other experts testified at trial. In consideration of the above testimony, we find that the Brenners did establish the existence and nature of the defects they alleged and that those defects are due to the faulty workmanship of Mr. Zaleski.
The third and final factor the Brenners must prove is the cost of repairing the defects. Cascio, 42,653, p. 10, 968 So.2d at 850. "If the owner meets the burden of proof, the remedy is to reduce the contract price in an amount necessary to perfect or complete the work according to the terms of the contract." Id., 42,653, p. 10, 968 So.2d at 851.
Mr. Zaleski avers that he was working under a cost-plus or percentage contract;
The Brenners argue that the cost of the remedial work that needed to be performed was $10,829.67, based on the testimony of Mr. Gurtler and Ms. Brenner.
For the foregoing reasons, the judgment of the First City Court is reversed, and this matter is remanded for a determination of damages. Each party is to bear its own costs. See La.Code Civ. Proc. art. 2164.
$1,450.00 $575.00 $3,076.59 $2,780.00 _________ $7,881.59