Elawyers Elawyers
Washington| Change

Indianapolis Power & Light Company v. United States Environmental Protection Agency, Environmental Defense Fund, Intervenors, 93-1197 (1995)

Court: Court of Appeals for the D.C. Circuit Number: 93-1197 Visitors: 9
Filed: Jun. 23, 1995
Latest Update: Feb. 22, 2020
Summary: 58 F.3d 643 41 ERC 1097 , 313 U.S.App.D.C. 83, 64 USLW 2063, 25 Envtl. L. Rep. 21,217 INDIANAPOLIS POWER & LIGHT COMPANY, Petitioner, v. UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, Respondent, Environmental Defense Fund, et al., Intervenors. No. 93-1197. United States Court of Appeals, District of Columbia Circuit. Argued May 18, 1995. Decided June 23, 1995. Stephen E. Roady, argued the cause, for petitioner. On brief were Thomas E. Starnes and Bryan G. Tabler. Patricia Ross McCubbin, Atty.,
More

58 F.3d 643

41 ERC 1097, 313 U.S.App.D.C. 83, 64
USLW 2063,
25 Envtl. L. Rep. 21,217

INDIANAPOLIS POWER & LIGHT COMPANY, Petitioner,
v.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, Respondent,
Environmental Defense Fund, et al., Intervenors.

No. 93-1197.

United States Court of Appeals,
District of Columbia Circuit.

Argued May 18, 1995.
Decided June 23, 1995.

Stephen E. Roady, argued the cause, for petitioner. On brief were Thomas E. Starnes and Bryan G. Tabler.

Patricia Ross McCubbin, Atty., Dept. of Justice, argued the cause, for respondent. On brief were Lois J. Schiffer, Asst. Atty. Gen., Patricia A. Embrey, Atty., Dept. of Justice, and Alan W. Eckert, Associate Gen. Counsel, E.P.A.

David G. Hawkins, entered an appearance, for intervenors Natural Resources Defense Council, Inc. and Adirondack Council.

Howard I. Fox, entered an appearance, for intervenor Environmental Defense Fund.

Before: SILBERMAN, SENTELLE and HENDERSON, Circuit Judges.

Opinion for the court filed by Circuit Judge HENDERSON.

Separate concurring opinion filed by Circuit Judge SENTELLE.

KAREN LeCRAFT HENDERSON, Circuit Judge:

1

Petitioner Indianapolis Power & Light Company (IPL) challenges regulations promulgated by the Environmental Protection Agency (EPA) pursuant to the acid rain program begun under 42 U.S.C. Secs. 7651-7651o (Clean Air Act). IPL argues that the regulations relating to the calculation and allocation of "extension allowances" should allow for the adjustment of a utility unit's 1988-1989 emissions data if the unit was out of operation for an extended period during those two years. Because the Clean Air Act is silent on the issue of adjusting a utility unit's 1988-1989 emissions data and the EPA's interpretation is permissible, we deny IPL's petition for review.

I. Background

2

Title IV of the Clean Air Act establishes an acid rain program to reduce emissions of sulfur dioxide and nitrogen oxides, the primary precursors of acid rain. See 42 U.S.C. Secs. 7651-7651o. Title IV imposes a national cap of 8.90 million tons of sulfur dioxide emissions per year on electric utilities. 42 U.S.C. Secs. 7651b(a)(1), 7651d(a)(3). The emissions reductions are to occur in two phases. In Phase I, at issue here, 110 utilities with the largest coal-fired utility electric generating units must reduce their emissions to 2.50 pounds of sulfur dioxide per million British thermal units (Btus) of fuel consumed by each power-generating unit in the "baseline" years of 1985, 1986 and 1987. 42 U.S.C. Sec. 7651c.1 Each utility unit is allocated a number of fully marketable pollution allowances so that it may emit sulfur dioxide at this level. 42 U.S.C. Sec. 7651c. Each allowance authorizes the emission of one ton of sulfur dioxide during one calendar year and may be bought, sold, traded or banked for future use or resale. 42 U.S.C. Secs. 7651a(3), 7651b(b).

3

Beginning in 1995, the emissions from each Phase I unit may not exceed the number of allowances that unit holds. 42 U.S.C. Sec. 7651c(a). Emissions from a Phase I unit that exceed the number of allowances allocated to it are unlawful and are subject to various fines and penalties. 42 U.S.C. Secs. 7651b(g), 7651j. To comply with Title IV requirements and ensure that its emissions do not exceed its allowances, a utility has three options. A utility can switch from coal with a high sulfur content to low-sulfur coal, purchase allowances from other utilities or install costly sulfur dioxide control technology known as "scrubbers." Congress encouraged the installation of scrubbers by establishing an extension allowance program. 42 U.S.C. Sec. 7651c(d).

4

Under the program, utilities that install and operate scrubbers on their Phase I units to reduce sulfur dioxide emissions qualify for "extension allowances" in addition to the allowances initially allocated. 42 U.S.C. Sec. 7651c. The EPA is authorized to "approve an extension proposal in whole or in part, and with such modifications or conditions as may be necessary, consistent with the orderly functioning of the allowance system...." 42 U.S.C. Sec. 7651c(d)(3). Utilities whose extension proposals are approved are not exempt from the Title IV prohibition on emissions in excess of allowances. Instead, the EPA raises their emissions limitation and grants a corresponding number of extension allowances for a two-year period according to the following formula:

5

[T]he difference between the lesser of the average annual emissions in calendar years 1988 and 1989 or the projected emissions tonnage for calendar year 1995 [and 1996] of each eligible phase I extension unit ..., and the product of the unit's baseline multiplied by an emission rate of 2.50 lbs/mmBtu, divided by 2,000.

6

42 U.S.C. Sec. 7651c(d)(4)(A); 40 C.F.R. Sec. 72.42(c). That is, the EPA bases the number of extension allowances on the difference between the maximum emissions level set by Congress (i.e., 2.50 pounds of sulfur dioxide per million Btus of fuel consumed by the unit in the baseline years of 1985-1987) and the lesser of the unit's expected emissions in 1995 and 1996 or its actual emissions in 1988 and 1989.

7

Seventeen utilities, including IPL, decided to install scrubbers and applied for extension allowances. According to the formula, the utilities were entitled to 4.0-4.5 million extension allowances. The Clean Air Act, however, capped the number of available extension allowances at 3.5 million. 42 U.S.C. Sec. 7651c(a)(2). The EPA therefore held a lottery in March 1993 to determine the selection priority for granting extension allowances to the applicants. The seventeen utilities had prepared for this eventuality, however, by entering an extension allowance pooling agreement in March 1992 (Agreement). Under the Agreement, the utilities agreed to pool the extension allowances and to re-allocate them, based in part on the formula used by the EPA, so that each applicant, regardless whether it was selected in the lottery, received a percentage of the number of allowances it would have received in the lottery had it been selected. Although IPL was not selected in the lottery it nonetheless received extension allowances under the Agreement.

8

IPL's Petersburg, Indiana Unit # 2, a Phase I unit, was out of operation from October 1, 1988, through April 6, 1989, for unexpected major repairs. As a result, the unit's sulfur dioxide emissions during the two-year period were lower than usual.2 According to the EPA's calculations using actual emissions data for 1988 and 1989, Petersburg Unit # 2 is entitled to approximately 14,000 extension allowances. According to IPL's calculations, however, if the emissions data were normalized or annualized to reflect what emissions would have been in 1988 and 1989 but for the outage, Petersburg Unit # 2 would be entitled to at least 20,000 additional extension allowances. Consequently, the number of extension allowances to which IPL is entitled under the EPA formula, and thus under the Agreement, varies dramatically according to whether actual or normalized emissions data for 1988 and 1989 are used.

9

The EPA considered the issue of adjustments to emissions data in its proposed rulemaking. 56 Fed.Reg. 63,002 (1991) (Joint Appendix (JA) 2). In December 1991, in requesting comment "on the appropriateness of allowing an adjustment in the limited situations where a forced outage occurred," the EPA explained that allowing adjustments was not warranted for several reasons:

10

First, the Phase I Extension is voluntary. If a utility finds that it is not favorable to apply for a Phase I Extension, it can chose [sic] another compliance option. Second, the information is historical, actual data reported by the utility itself and the statute does not provide for adjustment.... Third, the Agency is attempting to respond to industry's need for certainty at an early date regarding allocation of allowances from the Phase I Extension reserve. Allowing an opportunity for adjustments to be made to essential historical data would delay certainty.

11

56 Fed.Reg. 63,017 (JA 9). The EPA did not allow for adjustments in the final rules issued on January 11, 1993. 58 Fed.Reg. 3,590, 3,669 (1993) (JA 57, 63); 40 C.F.R. Sec. 72.42(c)(3) (JA 63).3 In the final acid rain permit issued to IPL, the EPA affirmed that it intended to allocate allowances without adjusting the emissions data to account for the fact that Petersburg Unit # 2 was out of operation for six months in 1988 and 1989. IPL petitions the court to vacate the regulations which do not provide for adjustments and to remand the matter to the EPA with instructions to adjust the emissions data for Petersburg Unit # 2.

II. Discussion

12

IPL makes three principal arguments. First, it claims that the Clean Air Act obliges the EPA to adjust a utility unit's 1988-1989 emissions data to account for an unexpected prolonged outage. Second, IPL argues that even if the statute is silent on the issue, the EPA mistakenly interpreted the statute as prohibiting it from adjusting the 1988-1989 emissions data. Finally, IPL maintains that the EPA interpretation is unreasonable. We reject each argument. We may set aside the regulations promulgated pursuant to the acid rain program only if they are:

13

(A) arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law;

14

(B) contrary to constitutional right, power, privilege, or immunity;

15

(C) in excess of statutory jurisdiction, authority, or limitations, or short of statutory right; or

16

(D) without observance of procedure required by law....

17

42 U.S.C. Secs. 7607(d)(9), 7607(d)(1)(F). The EPA's interpretation of the Clean Air Act must be reviewed under Chevron, U.S.A., Inc. v. Natural Resources Defense Council, 467 U.S. 837, 104 S. Ct. 2778, 81 L. Ed. 2d 694 (1984) (Chevron ). Applying these standards, we uphold the EPA regulations.

18

The Clean Air Act provides that extension allowances are to be allocated in part on the "average annual emissions in calendar years 1988 and 1989." 42 U.S.C. Sec. 7651c(d)(4)(A). It does not define "average annual emissions" nor does it explicitly authorize or prohibit adjustment of a utility unit's 1988-1989 emissions data for any reason, including an unexpected prolonged outage. Accordingly, the language cannot be read, as IPL argues, to compel EPA to adjust emissions data.

19

We conclude that the statutory language reasonably supports only two readings. First, the language can be construed to require that the EPA use actual emissions data. Under this reading, the EPA may not exercise any discretion but must mechanically calculate a utility unit's average annual emissions by dividing the total emissions during calendar years 1988 and 1989 by two.4 But the EPA did not read the language this way.5 Rather, the EPA concluded that the statute was silent regarding whether emissions data could be adjusted, thus allowing it to exercise its discretion, apply its expertise and adopt and implement a reasonable interpretation. See Ohio v. EPA, 997 F.2d 1520, 1527 (D.C.Cir.1993) (where agency regulation "represents a reasonable and permissible construction of the statute," court will defer under Chevron ). We agree that the statute is silent on the issue and uphold as a permissible construction of the statute the EPA's decision not to adjust emissions data.

20

The EPA articulated a reasoned basis for not adjusting a utility unit's emissions data. It sought to explain to the affected utilities in unequivocal terms how it proposed to allocate extension allowances. By relying solely on the historical emissions data previously reported to the Department of Energy,6 the EPA made it possible for each affected utility to calculate how many extension allowances could be claimed by other utilities and how many extension allowances it could claim and would likely obtain for itself. Each affected utility could then compute the costs and the benefits of installing a scrubber as opposed to other means of complying with the Title IV emissions reduction requirements. By contrast, if the EPA were to permit adjustments to the reported emissions data in special circumstances, utilities, lacking information on how the EPA would define the special circumstances and whether other utilities' units would meet the specified criteria for adjustment, would be less able to determine whether participation in the extension allowance program would be beneficial. It was reasonable, then, for the EPA to conclude that allowing adjustments to emissions data could significantly reduce the incentives to participate in the voluntary extension allowance program.

21

We reject IPL's argument that section 404(d)(3) of the Clean Air Act indicates that Congress intended the EPA to base its extension allowance calculations on emissions data adjusted to reflect "normal" operating circumstances. Section 404(d)(3) does authorize the EPA to "approve an extension proposal in whole or in part, and with such modifications or conditions as may be necessary, consistent with the orderly functioning of the allowance system, and to ensure the emissions reductions contemplated by the subchapter." 42 U.S.C. Sec. 7651c(d)(3). The provision, however, notably does not refer to outages, emissions or adjustments because it relates only to whether a utility qualifies for the extension allowance program, not to the allocation of extension allowances to utilities that qualify for and participate in the program. It authorizes the EPA to review and amend the terms of a utility's proposal to ensure that the utility in fact installs scrubbers and makes the structural changes which qualify it for the program and which extension allowances are designed to reward.

22

Congress did not need to specify "average annual actual emissions" for the court to uphold EPA's decision not to adjust emissions data. If Congress had intended the EPA to use only emissions data that took into account the time a unit was not in operation in 1988 or 1989, it could have expressly mandated that extension allowances be calculated according to adjusted data as it did in determining fuel consumption during the baseline years under 42 U.S.C. Sec. 7651c. But Congress remained silent on the issue. We therefore uphold under Chevron the EPA's reasoned decision not to adjust emissions data. Accordingly, the petition for review is

23

Denied.

SENTELLE, Circuit Judge, concurring:

24

I write separately not because I disagree with the majority's conclusion that the EPA's interpretation of 42 U.S.C. Sec. 7651c(d)(4)(A) is a reasonable one, but rather because I agree with the majority's conclusion more firmly than the majority itself does. That is, I would hold that the EPA's interpretation is not merely a reasonable construction, but the only reasonable construction. I do not agree that Congress was silent on the question of whether the EPA should "mechanically calculate a utility unit's average annual emission by dividing the total emission during calendar years 1988 and 1989 by two." Maj. op. at 86. Rather, I do not see how Congress could have said any more explicitly than it did that this is precisely what it was mandating. We have observed in the past that "some will find ambiguity even in a 'No Smoking' sign...." International Union, United Auto. Aerospace & Agric. Implement Workers of America v. General Dynamics Land Sys. Div., 815 F.2d 1570, 1575 (D.C.Cir.1987). I see little more ambiguity in the present statute on the question before the EPA than in such a sign. I would therefore reach the same conclusion as the majority, but I would reach it under the first step of the Chevron analysis without proceeding to the second.

1

The statute provides that, in calculating the "baseline" and in her "sole discretion," the EPA Administrator

may exclude periods during which a unit is shutdown [sic] for a continuous period of four calendar months or longer, and make appropriate adjustments under this paragraph. Upon petition of the owner or operator of any unit, the Administrator may make appropriate baseline adjustments for accidents that caused prolonged outages.

42 U.S.C. Sec. 7651a(4)(A).

2

According to IPL, Petersburg Unit # 2 emitted 52,380 tons of sulfur dioxide in 1987, 38,263 tons in 1988, 40,672 tons in 1989 and 58,030 tons in 1990. Petitioner IPL's Brief at 10-11. IPL projects that but for the forced outage, Petersburg Unit # 2 would have emitted an average of 52,263 tons of sulfur dioxide per year in 1988 and 1989. Id

3

The EPA responded to comments from IPL and other utilities urging adjustments to emissions data:

The Agency agrees that adjustments to the 1988 and 1989 data used to calculate Phase I extension reserve allowances should not be allowed for the reasons stated in the proposed preamble (56 FR 63017, section 3(d)). The Agency notes in particular that the statute does not provide for adjustment of this [sic] data and adjustment would add uncertainty since an increase in Phase I extension allowances for one applicant reduces them for another.

Response to Comments, Issue #P-8.7.8, at P8-29 (October 26, 1992) (JA 55).

4

This reading is supported by the fact that Congress considered the problem of outages and expressly authorized the EPA in a related context to adjust data to take prolonged outages into account. Title IV established maximum emissions levels according to a utility unit's fuel consumption during the "baseline" years, 1985, 1986 and 1987. 42 U.S.C. Sec. 7651c. In defining "baseline," Congress authorized the EPA to "exclude periods during which a unit is shutdown [sic] for a continuous period of four calendar months or longer" and to "make appropriate baseline adjustments for accidents that caused prolonged outages." 42 U.S.C. Sec. 7651a(4). The formula established by Congress for calculating extension allowances was based in part on the baseline. 42 U.S.C. Sec. 7651c(d)(4)(A). Yet Congress did not expressly authorize the EPA to adjust emissions data in calculating the extension allowances

5

IPL maintains that the EPA declined to adjust emissions data because it believed that the Clean Air Act prohibited it from doing so. We disagree. The EPA acknowledged that adjustment of emissions data was not barred by the statute when it requested comment on the "appropriateness" of doing so. 56 Fed.Reg. at 63,017 (JA 9). The EPA cited several reasons why adjustment of emissions data "is not warranted," including that "the statute does not provide for adjustment." Id. The EPA's statement that the Clean Air Act "does not provide for adjustment" does not express the agency's belief that the statute forbids adjustment; to the contrary, it merely recognizes that the statute does not expressly mandate or authorize adjustment. Moreover, in its response to IPL's comments, the EPA referred to the reasons listed in the proposed regulations for not adjusting emissions data and emphasized that "the statute does not provide for adjustment of this [sic] data and adjustment would add uncertainty since an increase in Phase I extension allowances for one applicant reduces them for another." JA 55. The EPA thus declined to adjust emissions data on policy grounds; it was not statutorily prohibited from doing so

6

Utilities report fuel consumption data to the Department of Energy on Form EIA 767

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer