GARLAND E. BURRELL, Senior District Judge.
Plaintiff Conservation Congress and Defendant United States Forest Service ("Forest Service") each move for summary judgment on all claims in Plaintiff's Complaint. The County of Siskiyou filed an amicus curiae brief in support of the Forest Service's motion.
Plaintiff alleges in its Complaint that the Forest Service's decision authorizing the Environmental Assessment ("EA") and Finding of No Significant Impact ("FONSI") for the Porcupine Vegetation and Road Management Project ("the Project") violated the National Environmental Policy Act ("NEPA") and the National Forest Management Act ("NFMA"). The Forest Service identified the purposes of the Project as (1) improving forest health by thinning trees, thereby reducing fuels that pose a risk of igniting a catastrophic fire in the Shasta-Trinity National Forest ("the Forest"), (2) maintaining a fuel break, and (3) restoring meadow and aspen habitat. (Project Administrative Record ("PAR") 1, 4, 370, ECF No. 11.) "The project area is located near Porcupine Butte approximately 20 miles northeast of McCloud," California. (PAR 1.)
"Agency decisions that allegedly violate . . . NEPA and NFMA are reviewed under the Administrative Procedure Act (`APA'), and may be set aside only if they are `arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with the law.'"
A party seeking summary judgment bears the initial burden of demonstrating the absence of a genuine issue of material fact.
Plaintiff seeks in its reply brief to supplement the Project Administrative Record ("PAR") by having judicial notice taken of the Forest Service's Annual Progress Report. (Pl.'s Reply Supp. Summ. J. ("Pl. Reply") 2 n.1, ECF No. 31.) However, the district court need not consider a request made for the first time in a reply brief.
"Generally, judicial review of agency action is limited to review of the administrative record."
Plaintiff alleges in its Complaint that the Forest Service violated NEPA by (1) conducting an arbitrary and capricious cumulative effects analysis on the northern spotted owl, (2) failing to consider a reasonable range of alternatives to the Project, (3) failing to take a "hard look" at the environmental impacts of the Project, and (4) failing to prepare an Environmental Impact Statement ("EIS"); and that the Forest Service violated the NFMA by failing to comply with the Forest Plan's snag retention standard.
Plaintiff alleges in its Complaint that the Forest Service used an inappropriately narrow geographic boundary for its cumulative impacts analysis to assess the Project's impact on the northern spotted owl. (Compl. ¶¶ 46-47.) Plaintiff argues the narrowness of this analysis fails to comply with the Council on Environmental Quality ("CEQ") guidelines that require analyzing the Project's effects using the largest area occupied by the owls, which in this case is the owl's natal dispersal distance of 10 to 15 miles, and that the Forest Service abused its discretion when only analyzing the Project's impact using the owls 1.3 mile median home range. (Pl.'s Am. Mot. Summ. J. ("Pl. Mot.") 12:23-13:9; 13:15-25; 14:24-26, ECF No. 20.)
NEPA requires that an agency's assessment of the environmental impacts of a proposed Project include an analysis of the action's cumulative impact.
The Forest Service's cumulative effects analysis "includes the effects from habitat modification within an owl's home range, which is
The Forest Service explains its analysis is "scientifically valid" and consistent with the CEQ guidelines since the owl's natal dispersal distance does not represent the "geographic area [they] occup[y]" but instead "represents the transient/movement phase of young owls . . . en route to establishing new permanent territory." (Fed. Def.'s Mem. Opp'n Pl.'s Mot. Summ. J. ("Def. Opp'n") 2:2-4; 5:4-15, ECF No. 24.)
Further, the Forest Service states in the administrative record, in relevant part:
(PAR 1291.)
"The Forest Service's choice of home range as the physical scope for cumulative effects analysis was not arbitrary or capricious," and there is no evidence indicating that the CEQ guidelines consider the natal dispersal distance a better scope of analysis.
Therefore, the Forest Service's motion on this claim is granted and Plaintiff's motion is denied.
Plaintiff argues the Forest Service violated NEPA by failing to consider a reasonable range of alternatives to the Project in its EA. (Compl. ¶¶ 53-56.)
Before approving a proposed action, NEPA requires the Forest Service to "study, develop, and describe appropriate alternatives." 42 U.S.C. § 4332(2)(E). "[A]n agency's obligation to consider alternatives under an EA is a lesser one than under an EIS."
The Forest Service considered "[a]n alternative that precludes the harvest of trees above . . . 21 inches" in diameter, but did "not consider[] [it] in detail because [the alternative] would not reasonably meet the [P]roject purpose and need." (PAR 99.) Plaintiff argues this conclusion was arbitrary or capricious since it was not supported by evidence and because the Forest Service unfairly considered the 21-inch alternative in combination with other more restrictive diameter-based alternatives. (Pl. Mot. 16:5-9; 18:16-20.)
The Forest Service responds it was not required to consider the 21 inch alternative in isolation and its analysis sufficiently explained why the alternative did not meet the Project's purpose of improving forest health, since it "would allow disease-infected . . . trees . . . to continue to infect adjacent young [trees]" and "would prevent the species-composition of mixed stands from shifting back to pine, leaving more stands vulnerable to wildfire." (Def. Opp'n 12:12-22.)
The Forest Service discussed the Project's goals in the PAR, specifically stating its objectives included "improve[ing] forest health and growth" and "reducing the risk of catastrophic fire." (PAR 4065-66, 370.)
When considering the 21-inch alternative, the Forest Service stated in part:
(PAR 99.)
The Forest Service provided "satisfactory explanation[s]" for concluding Plaintiff's alternative would not further the Project's purposes of improving forest health and reducing the risk of catastrophic wildfire, by stating that Plaintiff's alternative would allow disease-infected trees to infect nearby trees, would not properly redistribute the species composition mix in dry areas, and would leave the forest open to catastrophic fires.
Plaintiff argues that the Forest Service's conclusion that "an alternative that does not affect [northern spotted owl] habitat and specifically does not propose activity within critical, suitable (nesting, roosting, foraging) capable or dispersal habitat," "fail[ed] to adequately meet the major aspects of the purpose and need" of the Project is arbitrary or capricious since the Forest Service's reasoning is contradictory and inconsistent with prior Forest management decisions. (PAR 99, 100.)
Plaintiff argues the Forest Service's stated reasons for dismissing the alternative that does not affect northern spotted owl habitat are inconsistent with each other and therefore arbitrary.
The Forest Service stated in the relevant part of its discussion of the alternative:
(PAR 100) (emphasis added.)
NEPA does not require that the Forest Service consider alternatives "beyond those reasonably related to the purposes of the project."
Plaintiff argues that when the Forest Service dismissed the alternative because it simultaneously did not meet the Project's purpose and was "very similar" to alternatives that met the Project's purpose, its analysis was internally inconsistent. (Pl. Mot. 24:18-27.)
The Forest Service responds that it "described several ways in which the proposed alternative would fail to adequately meet . . . the Project's purpose and need" and that "[w]hile the Forest Service recognized that the predicted effects of [other alternatives analyzed in detail] would be similar to the proposed alternative
The Forest Service provided a reasoned explanation for its conclusion that Plaintiff's alternative did not meet the Project's purpose of promoting forest health since it would not alleviate inter-tree stress, which causes stress-induced tree mortality. (PAR 99-100.) Its conclusion is reasonable even though the alternative was "very similar" to alternatives that met the Project's purpose and need, since their similarity only concerned their "effects to [northern spotted owl] habitat" and the Forest Service's reasons for determining Plaintiff's alternative did not meet the Project's purpose and need are unrelated to its effects on northern spotted owl habitat. (PAR 100.) For these reasons, NEPA did not require the Forest Service to consider the alternative in further detail.
Therefore, the Forest Service's motion on this claim is granted and Plaintiff's motion is denied.
Plaintiff argues that because the Forest Service decided at an earlier date not to log northern spotted owl habitat in other parts of the forest, it now cannot reject an alternative that would prevent logging in northern spotted owl habitat in the Project area. (Pl. Mot. 24:18-23; 22:22-24:5.) Specifically, Plaintiff argues the Forest Service previously considered logging northern spotted owl habitat in a part of the forest referred to as the Porcupine Late Successional Reserve ("LSR"), but ultimately decided against logging there and, as a result, the Forest Service cannot now log northern spotted owl habitat in the Project area without further explanation. (Pl. Mot. 24:2-5.)
The Forest Service contends Plaintiff's focus on the LSR is a red herring because of the geographic differences between the Project area and the LSR. (Fed. Def.'s Reply Supp. Def.'s Mot. Summ. J. ("Def. Reply") 7:15-18, ECF No. 30.)
"In order to balance environmental and economic needs, the [Forest Service] designates certain forest areas for logging and reserves other areas, called late successional reserves (LSRs), for conservation."
The Forest Service previously considered, but decided against logging in the LSR in part because "several public commenters expressed concern." (PAR 61.) The Forest Service explained in its EA in relevant part:
(PAR 44 n.2.)
The location of northern spotted owl habitat in the LSR is geographically distinct from the location of northern spotted owl habitat in the Project area. (
The geographic distinction, between the LSR and the Project area, combined with the LSR's unique purpose of "maintain[ing] the few late-successional stands on the far eastern edge of the Shasta-Trinity National Forest and to help provide for connectivity of . . . the northern spotted owl," make it reasonable for the Forest Service to reject an alternative that would prevent logging northern spotted owl habitat in the Project area while "defer[ring] treatments . . . within the LSR." (PAR 247-75, 44 n.2.) Therefore, the Forest Service's summary judgment motion on this claim is granted and Plaintiff's motion is denied.
The Forest Service seeks summary judgment on Plaintiff's remaining "reasonable range of alternative" claims, in which Plaintiff alleges the Forest Service "considered only near-identical alternatives" and "prepared an unreasonably narrow purpose and need statement." (Compl. ¶¶ 53, 56.) The Forest Service argues it is entitled to summary judgment on these claims since it considered fourteen alternatives and gave detailed consideration to five, which "span a tremendous range, including numerous permutations of actions and treatment locations;" and therefore, the PAR does not support Plaintiff's claims. (Fed. Def.'s Mot. Summ. J. ("Def. Mot.") 15:7-11; 17:17-18, ECF No. 13.)
Plaintiff did not address these allegations in the Complaint or respond to the Forest Service's arguments.
The Forest Service prevails on this portion of its motion since it "point[ed] out that there is an absence of evidence to support the nonmoving party's case."
Plaintiff alleges the Forest Service failed to take a "hard look" at the environmental impacts of the Project. (Compl. ¶ 62.) "The hallmarks of a `hard look' are thorough investigation into environmental impacts and forthright acknowledgment of potential environmental harms."
Plaintiff argues the Forest Service failed to take a "hard look" at whether the number of snags in the Project area met or exceeded the Forest Plan's snag retention standard. (Compl ¶ 62.)
Rittenhouse, 305 F.3d at 961 (citations omitted).
The Forest Plan for Shasta-Trinity Forest states: at "a minimum, snags are to be retained . . . at levels sufficient to support species of cavity-nesting birds at 40 percent of potential population levels . . . [with] an average of
(PAR 1259.)
Plaintiff argues that the Forest Service relied on "conclusory allegations" when stating the Project will satisfy the Forest Plan snag retention standard, and therefore failed to demonstrate that the agency took a "hard look" at the issue. (Pl. Mot. 28:1-7.) Specifically, Plaintiff contends the Forest Service did not disclose the data on which it relied in reaching its conclusion and did not address conflicting 2003 survey results.
The Forest Service contends it disclosed data in the EA supporting its conclusion that the Forest Plan snag retention standard was being met and that it was not required to address prior conflicting survey results since those results had "been superseded by more recent and more site-specific evaluations." (Def. Opp'n 15:4-9; 16:10-13; 19:6-20.)
The PAR reveals that the Forest Service has conducted several analyses of snag levels in the Forest; relevant here are analyses conducted in 2003 and 2011. The 2003 analysis concluded: "[c]urrent snag levels in the watershed are unknown. Snag distribution is not uniform across the landscape (Snag distribution may be correlated with landtype associations). Snag surveys for existing and past projects . . . indicate that snag levels are lower than Forest Plan minimums." (PAR 4070.) The 2011 analysis observed: "snag . . . habitat continues to increase over time as a result of wildfire events and insect and disease outbreak" and determined that the Project's "[p]roposed treatment units have at least two snags per acre greater than 15 inches dbh [diameter at breast height] . . . [b]ased on unit assessment[s] [conducted] in October 2011." (PAR 1259, 1261.)
The Forest Service concluded based on the 2011 survey data that the Project would not reduce snag levels below the Forest Plan snag retention standard, stating:
(PAR 1261.)
Further, the Forest Service opined:
(PAR 77.)
The Forest Service's analysis of the 2011 survey data shows it took a "hard look" at snag levels. The Forest Service sufficiently disclosed the data on which it relied, stating: "[p]roposed treatment units have at least two snags per acre greater than 15 inches dbh. . . . [b]ased on unit assessment[s] [performed] in October 2011." (PAR 1259.) Further, it was reasonable for the Forest Service to conclude that snag levels exceeded the Forest Plan snag retention standard since its most recent 2011 survey data showed snag levels increased over time and exceeded the Forest Plan snag retention standard. (PAR 1259, 1261.) It was also reasonable for the Forest Service to conclude that implementing the Project would not cause snag levels to fall below the Forest Plan snag retention standard since insect and disease activity continue to recruit new snags and the Project will not log existing snags except where they occur in groups of ten or more or where a snag poses a threat to life or property. (PAR 1261, 77.)
The data and conclusions in the EA demonstrate the Forest Service "carefully consider[ed] detailed information concerning significant environmental impacts" of the Project on snag levels.
Plaintiff's remaining "hard look" claims allege the Forest Service did not "adequately analyze":
(Compl. ¶ 62.)
The Forest Service argues it is entitled to summary judgment on Plaintiff's remaining "hard look" claims since the "EA and its Appendices span over 500 pages," "rest[] upon dozens of individual specialists' reports spanning thousands of more pages" and do not support Plaintiff's allegations. (Def. Mot. 21:27-22:1; 22:1-5.) Plaintiff has not addressed the Forest Service's argument.
The Forest Service's motion is granted since it "point[ed] out that there is an absence of evidence to support the [Plaintiff's] case" and Plaintiff failed to come forward with "specific facts showing there is a genuine issue for trial."
Plaintiff argues the Forest Service violated the NFMA by failing to ensure the Project satisfied the Forest Plan snag retention standard. (Pl. Mot. 35:10-21.) The Forest Service contends its analysis was sufficient. (Def. Opp'n 23:22-24.)
"It is well-settled that the Forest Service's failure to comply with the provisions of a Forest Plan is a violation of NFMA" and for an agency action to comply with the NFMA, a reviewing court must be "[]able to determine from the [administrative] record that the agency is complying with the forest plan standard[s]."
The Forest Service has shown it complied with the Forest Plan snag retention standard and that it "articulate[d] a rational connection between the facts found and the conclusions reached."
Plaintiff alleges the Forest Service violated NEPA by failing to prepare an EIS for the Project. (Compl. ¶¶ 70-71.)
In 42 U.S.C. § 4332(2)(C), NEPA requires that all federal agencies must include "a detailed statement . . . on the environmental impact of the proposed action" "in every . . . major Federal action[]
The term "significantly" is explained in 40 C.F.R. § 1508.27 as requiring consideration of the intensity of the proposed action's impact. 40 C.F.R. § 1508.27(b)(1)-(10) identifies "intensity factors" an agency must consider when evaluating a Project's impact, including
An EIS is not required each time an "intensity factor" is implicated; instead it is only required if the "degree to which an action may adversely affect" one of the intensity factors is significant.
The Forest Service considered the "intensity factors" in the EA and concluded that "an environmental impact statement will not be prepared" because the Project "will not have a significant effect on the quality of the human environment, considering the . . . intensity of impact[]." (PAR 25.)
Plaintiff argues NEPA required the Forest Service to prepare an EIS for the Project since it will have a significant impact on northern spotted owls by logging "within . . . critical [northern spotted owl] habitat." (Pl. Mot. 31:5-9.)
The Forest Service responds that the Project will not have a significant impact on critical owl habitat since the Project will improve treated foraging and dispersal habitat and "any impact the Project[] . . . [is] expected to have on northern spotted owl habitat [is] . . . predicted to be beneficial over the long-term even though in the short-term, there would be some habitat elements reduced." (Def. Opp'n 22:9-24.)
The Forest Service addressed the Project's impact on northern spotted owl habitat in the EA, stating in relevant part:
(PAR 371.)
The Forest Service adequately explained that the Project will not have a significant impact on northern spotted owl habitat since it will not log in areas that serve as "nesting/roosting habitat or high-quality foraging habitat," and that in the areas where the Project intersects northern spotted owl foraging and dispersal habitat, the logging will not interfere with the owl's use of the land. (PAR 371.) This provides "a convincing statement of reasons explaining why the project will impact [the spotted owls critical habitat] no more than insignificantly," even though it proposes logging in 201 acres of northern spotted owl habitat.
Plaintiff additionally argues an EIS was required since the Project aims to support northern spotted owls by reducing the risk of wildfire yet, "there is significant uncertainty as to whether [the prevention of wildfire] . . . is beneficial or adverse to the northern spotted owl." (Pl. Mot. 31:21-32:2.)
The Forest Service acknowledges "some uncertainty as to the extent to which northern spotted owls used burned forest to forage" but argues "the effects of the Project as a whole . . . are [not] highly uncertain" since "[t]here is no serious uncertainty that. . . . the loss of nesting and roosting habitat from catastrophic wildfire remains among the primary threats to the survival of the owl." (Def. Reply 12:22-13:7.)
The "scientific uncertainty" concerning northern spotted owls' use burned habitat is addressed in the EA where the Forest Service states in relevant part:
(PAR 143.)
The Forest Service states in the PAR that this research calls into question conventional wisdom that northern spotted owls do not prefer high-severity burn areas for foraging, but does not suggest the owls prefer high-severity burn areas for
Scientific controversy over whether northern spotted owls prefer to use severely burned forests is not relevant to the question whether wildfire's overall effect on the northern spotted owl is highly uncertain since stand replacing wildfire "reset[s]" the Forest and produces habitat containing "small tree size and large openings that would be unsuitable" for the northern spotted owl. (PAR 143.) These stand replacing fires eliminate rather than create new northern spotted owl habitat and the Project is designed to "reduc[e] the risk of [just such] catastrophic fire[s]." (PAR 370.) Since uncertainty over whether northern spotted owls prefer to forage in burned habitat does not raise concerns as to whether the Project's overall effect on the owls would be highly uncertain, no EIS was required.
Therefore, the Forest Service's motion is granted and Plaintiff's motion is denied.
For the stated reasons, Plaintiff's summary judgment motion is DENIED and the Forest Service's summary judgment motion is GRANTED. The Clerk of the Court shall enter judgment in favor of the Forest Service and close this action.