MORRISON C. ENGLAND, JR., Magistrate Judge.
Through this action, the United States of America for the Use and Benefit of Urata & Sons Concrete, Inc., and Urata & Sons Concrete Inc. ("Plaintiff") seek confirmation and enforcement of an arbitration award against Defendants Gilbane Federal ("Gilbane") and Travelers Casualty and Surety Company of America (collectively, "Defendants"). Presently before the Court is Plaintiff's Motion for Order Lifting Stay, Confirming Final Arbitration, and Entry of Judgment. ECF No. 15. Plaintiff also moves for attorney's fees and costs. Concurrently before the Court is Defendants' Counter-Motion to Vacate Arbitration Award. ECF No. 17. For the reasons set forth below, Plaintiff's Motion is GRANTED and Defendants' Counter-Motion is DENIED.
In 2014, Gilbane entered into a written design-build construction contract with the United States Army Corps of Engineers ("USACE") for the construction of a general purpose warehouse at the Defense Distribution Depot in Tracy, California (the "Project"). In May 2015, Plaintiff and Gilbane entered into a written subcontract whereby Plaintiff agreed to provide and install specific concrete work according to Gilbane's plans and specifications (the "Subcontract"). The Subcontract further provided that Plaintiff "shall perform all Work required to complete the Project in strict accordance with the [Statement of Work documents]" and that Plaintiff "agrees to be fully bound by all [Statement of Work] Documents to be later provided." Ex. 1, ECF No. 1, at 15. The original Project specifications did not require the use of air entrained concrete. After the Subcontract was executed, Gilbane provided Plaintiff with revised specifications, which were changed to require air entrained concrete. At the same time, a note was included stating that "[e]ntrained air should not be used for concrete to be given a smooth, dense, hard-troweled finish because blistering and delamination may occur." In December 2015, Gilbane provided Plaintiff with its Issued for Construction ("IFC") specifications, which required Plaintiff to install the warehouse slab on grade with a "smooth, dense hard-trowel finish, along with the placement of air entrained concrete," thus creating a design conflict.
In March 2016, Plaintiff submitted air entrained concrete mix designs to Gilbane, who approved those designs for use in areas with a hard trowel finish such as the warehouse slab on grade. Plaintiff notified Gilbane of additional costs associated with the changed concrete specifications, and alerted Gilbane to the design conflict between the requirements for air entrained concrete and the hard trowel finish, which Gilbane acknowledged. Gilbane communicated with USACE about removing air entrainment from the concrete mix design.
In August 2016, Plaintiff and Gilbane executed Change Order No. 1 to the Subcontract, which included the increased cost for air entrained concrete in the areas that did not require a hard trowel finish. Based on their prior discussions and written memorialization, Plaintiff and Gilbane excluded from Change Order No. 1 the cost for the air entrained concrete in the warehouse slab on grade, reserving the issue for future adjustment if the specification requirement was not changed by USACE.
Plaintiff was scheduled to perform its concrete work from December 2016 to February 2017. Having not received any notice or revisions to the specifications that deleted the air entrainment requirement from the warehouse slab on grade, Plaintiff began performing its work in accordance with the specifications, including those requiring the use of air entrained concrete with a hard trowel finish for the warehouse slab on grade. Gilbane was responsible for quality control on the Project and was fully aware that Plaintiff was placing the warehouse slab on grade in accordance with the specifications and the approved mix design and participated in that placement by, among other things, testing the concrete at the time of delivery for compliance with the approved mix design and signing off on the placement of the concrete for the warehouse slab on grade. After completion, Plaintiff billed Gilbane for this concrete installation, and Gilbane paid Plaintiff for its work, excluding retention.
It was not until after work under the Subcontract was complete that Plaintiff learned USACE actually approved a design change deleting the air entrainment from the warehouse slab on grade prior to the execution of Change Order No. 1; Gilbane never conveyed or provided any such approval or design change to Plaintiff in any form. Further, USACE alerted Gilbane to the occurrence of delamination of the warehouse slab on grade due to the air entrainment. Gilbane issued cure notices to Plaintiff, stating the delamination resulted from Plaintiff's unauthorized use of air entrained concrete for the warehouse slab on grade and Plaintiff must remedy its non-compliance by replacing the entire warehouse slab on grade. Plaintiff denied responsibility for the issues, and Gilbane refused to pay Plaintiff amounts due for work completed.
On December 18, 2017, Plaintiff filed this action against Defendants for, among other things, breach of contract and Miller Act violations. ECF No. 1. Subsequently, this Court entered an order staying the action pending arbitration, pursuant to the parties' stipulation. ECF No. 8. Kenneth C. Gibbs (the "Arbitrator") served as the arbitrator for this dispute, and arbitration took place on November 12-14, 2018. ECF No. 15-1. On March 21, 2019, the Arbitrator issued the Final Award (the "Award"), which concluded that Plaintiff's installation of the air entrained concrete constituted performance, or, alternatively, that Plaintiff was excused from performing under the Subcontract.
It is well established that a federal court's review of an arbitrator's decision is "
Federal courts are not empowered to second guess an arbitrator's findings and will enforce an arbitration award if it represents a "plausible interpretation of the contract in the context of the parties' conduct."
Thus, as long as the arbitrator's decision "draws its essence from the contract, meaning that on its face it is a plausible interpretation of the contract, then the courts must enforce it."
The Arbitrator found that Plaintiff's installation of the air entrained concrete constituted performance under the Subcontract.
The "completely irrational" standard is extremely narrow and is satisfied only where the arbitration decision fails to draw its essence from the agreement.
Defendants contend that the Arbitrator erred in determining Change Order No. 1 was a pricing agreement instead of a change in scope because Change Order No. 1 excluded air from the warehouse slab on grade. Defs.' Counter-Motion, ECF No. 17, at 9. However, the Arbitrator concluded Change Order No. 1 did not change the scope of the Subcontract because Gilbane was still communicating with USACE about removing the air entrainment requirement and Gilbane failed to inform Plaintiff that USACE deleted the requirement. Arbitration Award, ECF No. 15-2, at 20-21.
Ultimately, Defendants have failed to show that the Arbitrator exceeded his power. There is no evidence in the record that the Award failed to draw its essence from the contract therefore rendering it "completely irrational."
Plaintiff seeks to recover the following: (1) additional attorneys' fees for time associated with filing the instant motion and reply, totaling $16,605, plus $845 for federal court costs; (2) attorneys' fees and costs for enforcement and collection of judgment; (3) prejudgment interest in an amount of $574.54/day from March 21, 2019, to the entry of judgment; and (4) post-judgment interest at the legal rate until satisfaction of the judgment. ECF No. 15. Such recovery is allowed under the Subcontract, the Award, and by law.
For the foregoing reasons, Plaintiff's Motion for Order Lifting Stay, Confirming Final Arbitration, and Entry of Judgment, ECF No. 15, is GRANTED and Defendants' Counter-Motion to Vacate Arbitration Award, ECF No. 17, is DENIED. The arbitration award is hereby confirmed and enforced. The Clerk of the Court is hereby ordered to enter judgment for Plaintiff and to close this case.
IT IS SO ORDERED.