WANG v. PALO ALTO NETWORKS, INC., 3:12-cv-05579-WHA. (2013)
Court: District Court, N.D. California
Number: infdco20130905a00
Visitors: 6
Filed: Sep. 04, 2013
Latest Update: Sep. 04, 2013
Summary: STIPULATION PROPOSING DATES FOR CLAIM CONSTRUCTION AND [PROPOSED] ORDER WILLIAM H. ALSUP, District Judge. Pursuant to Civil Local Rule 7-12, plaintiff Qiang Wang ("Wang") and defendant Palo Alto Networks, Inc. ("PAN"), by and through their respective attorneys, hereby stipulate to the dates identified below for the service and filing of claim construction disclosures required by the Patent Local Rules: Event Date Exchange of Proposed T
Summary: STIPULATION PROPOSING DATES FOR CLAIM CONSTRUCTION AND [PROPOSED] ORDER WILLIAM H. ALSUP, District Judge. Pursuant to Civil Local Rule 7-12, plaintiff Qiang Wang ("Wang") and defendant Palo Alto Networks, Inc. ("PAN"), by and through their respective attorneys, hereby stipulate to the dates identified below for the service and filing of claim construction disclosures required by the Patent Local Rules: Event Date Exchange of Proposed Te..
More
STIPULATION PROPOSING DATES FOR CLAIM CONSTRUCTION AND [PROPOSED] ORDER
WILLIAM H. ALSUP, District Judge.
Pursuant to Civil Local Rule 7-12, plaintiff Qiang Wang ("Wang") and defendant Palo Alto Networks, Inc. ("PAN"), by and through their respective attorneys, hereby stipulate to the dates identified below for the service and filing of claim construction disclosures required by the Patent Local Rules:
Event Date
Exchange of Proposed Terms for Construction (Patent L.R. 4-1) October 7, 2013
Exchange of Preliminary Claim Constructions and Extrinsic October 28, 2013
Evidence (Patent L.R. 4-2)
Joint Claim Construction and Prehearing Statement (Patent L.R. November 22, 2013
4-3)
Completion of Claim Construction Discovery (Patent L.R. 4-4) December 23, 2013
Opening Claim Construction Brief (Patent L.R. 4-5) January 6, 2014
Opposition Claim Construction Brief (Patent L.R. 4-5) January 22, 2014
Reply Claim Construction Brief (Patent L.R. 4-5) January 29, 2014
In addition, plaintiff Wang and defendant PAN respectfully request that the Court set a claim construction hearing at a time and date convenient to the Court, and consistent with Patent Local Rule 4-6, propose February 13, 2014 at 1:30 pm.
IT IS SO ORDERED.