Summary: ORDER GRANTING DEFENDANTS' MOTION FOR SUMMARY JUDGMENT Re: Dkt. No. 38. NATHANAEL M. COUSINS , Magistrate Judge . In this employment case, plaintiff Ian McCray asserts that his former employer, defendant Marriott Hotel Services, failed to pay the San Jose minimum wage in compliance with a municipal wage ordinance. A collective bargaining agreement governs McCray's employment, and the CBA provides for a waiver of the San Jose minimum wage ordinance. In addition, the San Jose ordinance appea
More

ORDER GRANTING DEFENDANTS' MOTION FOR SUMMARY JUDGMENT

Re: Dkt. No. 38.

In this employment case, plaintiff Ian McCray asserts that his former employer, defendant Marriott Hotel Services, failed to pay the San Jose minimum wage in compliance with a municipal wage ordinance. A collective bargaining agreement governs McCray's employment, and the CBA provides for a waiver of the San Jose minimum wage ordinance. In addition, the San Jose ordinance appears to provide a waiver for CBAs. In order to determine if Marriott's admittedly low hourly rate was lawful, the Court must first assess which law to apply to this dispute. Defendants Marriott Hotel Services and SJMEC Inc. argue that CBAs are governed by federal law, so federal preemption applies, and the Court should begin its analysis with the provisions of the Labor Management Relations Act (LMRA). McCray argues that his complaint is based on violations of municipal law, so the Court must begin its inquiry by interpreting the San Jose minimum wage ordinance.

The Court considered these questions on a motion to remand and determined that for purposes of federal jurisdiction, McCray's complaint raised substantial issues of federal law. Dkt. No. 22. The Court then denied defendants' motion to dismiss, stating that it was premature to determine whether McCray failed to follow the CBA's grievance and arbitration mechanisms. Dkt. No. 23. Defendants now move for summary judgment on all claims, arguing that (1) the LMRA preempts the municipal claims; (2) McCray failed to exhaust the grievance procedure; (3) McCray's claims are time-barred; and (4) McCray's claims fail as a matter of law because the San Jose ordinance expressly permits collectively-bargained waivers of the ordinance. Dkt. No. 38.

The parties do not dispute that McCray was subject to the CBA, that Marriott did not pay him minimum wage but did offer him other benefits, and that McCray did not bring a formal grievance or seek arbitration with defendants prior to filing this lawsuit. Dkt. Nos. 38, 42.

The Court concludes that the LMRA preempts the municipal claims, and thus McCray's failure to exhaust administrative remedies under the CBA is fatal to his claims. The Court GRANTS defendants' motion for summary judgment.

I. LEGAL STANDARD

Summary judgment may be granted only when, drawing all inferences and resolving all doubts in favor of the nonmoving party, there is no genuine dispute as to any material fact. Fed. R. Civ. P. 56(a); Tolan v. Cotton, 134 S.Ct. 1861, 1863 (2014); Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). A fact is material when, under governing substantive law, it could affect the outcome of the case. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A dispute about a material fact is genuine if "the evidence is such that a reasonable jury could return a verdict for the nonmoving party." Id. Bald assertions that genuine issues of material fact exist are insufficient. Galen v. Cnty. of L.A., 477 F.3d 652, 658 (9th Cir. 2007).

The moving party bears the burden of identifying those portions of the pleadings, discovery, and affidavits that demonstrate the absence of a genuine issue of material fact. Celotex, 477 U.S. at 323. Once the moving party meets its initial burden, the nonmoving party must go beyond the pleadings, and, by its own affidavits or discovery, set forth specific facts showing that a genuine issue of fact exists for trial. Fed. R. Civ. P. 56(c); Barthelemy v. Air Lines Pilots Ass'n, 897 F.2d 999, 1004 (9th Cir. 1990) (citing Steckl v. Motorola, Inc., 703 F.2d 392, 393 (9th Cir. 1983)). All justifiable inferences, however, must be drawn in the light most favorable to the nonmoving party. Tolan, 134 S. Ct. at 1863 (citing Liberty Lobby, 477 U.S. at 255).

II. DISCUSSION

The Court first addresses whether federal or municipal law governs the analysis of McCray's complaint.

A. Preemption of State Law Claims under LMRA

Under Section 301 of the LMRA, disputes regarding collective bargaining agreements are exclusively governed by federal jurisdiction. Section 301 provides, "[s]uits for violation of contracts between an employer and a labor organization representing employees in an industry affecting commerce as defined in this chapter, or between any such labor organizations, may be brought in any district court of the United States having jurisdiction of the parties." 29 U.S.C. § 185(a).

In Allis-Chalmers Corp. v. Lueck, 471 U.S. 202, 220 (1985), the Supreme Court interpreted Section 301 to provide jurisdiction not only over causes of action based on a CBA, but also to cases whose resolution "is substantially dependent upon analysis of the terms of an agreement made between the parties in a labor contract." When state law claims require a court to interpret the terms of a CBA, a court must treat those claims as preempted by the exclusive federal jurisdiction provided by the LMRA. Id. at 211.

"The pre-emptive force of § 301 is so powerful as to displace entirely any state cause of action `for violation of contracts between an employer and a labor organization.'" Franchise Tax Bd. of Cal. v. Construction Laborers Vacation Trust for So. Cal., 463 U.S. 1, 23 (1983) (quoting 29 U.S.C. § 185(a)). That a plaintiff has not framed his or her state-law claim so that it explicitly refers to a CBA will not defeat federal preemption. International Bhd. of Elec. Workers v. Hechler, 481 U.S. 851, 859 n.3 (1987). If a plaintiff's claims are founded on rights created by a CBA or are "substantially dependent on analysis of a CBA" and can only be resolved by looking to the terms of the CBA, they are preempted. Caterpillar Inc. v. Williams, 482 U.S. 386, 394 (1987).

The Court already concluded that the central question in this case is whether the CBA waiver of state and municipal law is applicable, so federal jurisdiction is appropriate. Dkt. No. 22; see Burnside v. Kiewit Pacific Corp., 491 F.3d 1053, 1060 (9th Cir. 2007) (finding that federal jurisdiction and preemption are appropriate when the Court is required to interpret the CBA to resolve whether the CBA or state law applies). Because the Court concluded that federal jurisdiction is appropriate, the Court also now finds that the LMRA preempts McCray's state law causes of actions.

In doing so, the Court acknowledges that the LMRA requires the Court to start its analysis by looking at applicable federal law and the provisions in the CBA. McCray brings claims for (1) failure to pay minimum wages in violation of San Jose's minimum wage ordinance; (2) failure to timely pay wages in violation of state law; (3) knowing and intentional failure to comply with itemized employee wage statements in violation of state law; and (4) unlawful and unfair business practices. "A claim is not preempted if it poses no significant threat to the collective bargaining process and furthers a state interest in protecting the public transcending the employment relationship." Young v. Anthony's Fish Grottos, Inc., 830 F.2d 993, 1001 (9th Cir. 1987). However, in Young, the Ninth Circuit dismissed plaintiff's emotional distress claim because "[t]he claims arise out of the same conduct which formed the basis of her contract claim. As resolution of the claims is inextricably intertwined with the interpretation of the CBA, they are preempted." Id. at 1002. Similarly, here, all of McCray's claims are related to the amount and process of work pay, which is covered by the CBA. Thus, the Court must construe McCray's claims as breaches of the CBA. See Coleman v. Kaiser Permanente, No. 12-cv-02668 JST, 2014 WL 2886293, at *4 (N.D. Cal. June 25, 2014).

B. Failure to Exhaust Grievance Procedure

Because the Court concludes that it is the CBA and federal law that apply to the causes of action in this case, the Court agrees with defendants that McCray must first attempt to exhaust any mandatory or exclusive grievance procedures in the agreement. Soremekun v. Thrifty Payless, Inc., 509 F.3d 978, 986-87 (9th Cir. 2007).

However, an exception to this exhaustion requirement exists where an employee shows that "the union representing the employee in the grievance/arbitration procedure [has acted] in such a discriminatory, dishonest, arbitrary, or perfunctory fashion as to breach its duty of fair representation." DelCostello v. Int'l Brotherhood of Teamsters, 462 U.S. 151, 164 (1983). In this situation, an employee may bring a suit against his or her employer without having exhausted the grievance or arbitration procedure required by the CBA. Id. However, even in an action brought solely against an employer, the employee bears the burden of proving that the employer breached the terms of the CBA and that the labor union breached its duty of fair representation. Soremekun, 509 F.3d at 987. Where an employee is required to show a union's breach of its duty of fair representation, even in an action brought solely against an employer, the claim is not a straightforward breach of contract suit under § 301, but rather "a hybrid § 301/fair representation claim amounting to a direct challenge to the private settlement of disputes under [the CBA]." DelCostello, 462 U.S. at 165; accord Coleman, No. 12-cv-02668 JST, 2014 WL 2886293, at *5.

McCray argues that the union refused to file a grievance on his behalf, and that even now, the Union has written as an amicus in support of defendants' position. Dkt. No. 42 at 24. However, McCray has not alleged that the union breached its duty of fair representation and there is no dispute of fact that McCray did not exhaust his contractual remedies under the CBA. Thus, the Court must grant defendants' motion for summary judgment. Id.; Young v. Anthony's Fish Grottos, Inc., 830 F.2d 993, 1002 (9th Cir. 1987).

III. CONCLUSION

The Court concludes that McCray's complaint and its causes of action are preempted under federal law by the LMRA and the provisions of the CBA. Because McCray failed to exhaust his administrative remedies before filing this lawsuit, McCray's case must be dismissed.

The Court GRANTS defendants' motion for summary judgment.

IT IS SO ORDERED.