EDWARD J. DAVILA, District Judge.
This is one of two actions between a first-tier construction subcontractor and its second-tier electrical subcontractor. In this case, Plaintiff Automated Logic Contracting Services, Inc. ("ALCS"), the first-tier subcontractor, alleges that Defendant Sprig Electric Co. ("Sprig"), the second-tier subcontractor, breached the parties' agreement concerning electrical work for the construction of the Apple Campus 2 in Cupertino. In the other case,
Presently before the court is Sprig's Motion to Dismiss or Stay this action in favor of its own. Dkt. No. 13. ALCS opposes. This motion is suitable for decision without oral argument, and the hearing scheduled for March 8, 2018, will be vacated. Since the causes of action asserted in this case are compulsory counterclaims to the ones asserted in the Sprig Action, the request for a stay will be granted for the reasons explained below.
Sprig initiated an action against ALCS in Santa Clara County Superior Court on October 16, 2017, for breach of contract, breach of the duty of good faith and fair dealing, monies due, quantum meruit, account stated, and action on payment bond. ALCS removed the case to this court on October 26, 2017, and filed an Answer on November 28, 2017.
In its Complaint, Sprig alleges it entered into a $16 million Subcontract Agreement with ALCS in connection with the construction of the Apple Campus 2. Sprig agreed to provide all labor, material, equipment and supervision required to furnish and install a building automation system, or BAS. In return, ALCS agreed to pay Sprig for materials and labor, and would pay Sprig for any additional quantities of work otherwise necessary to complete the BAS. Sprig alleges the Subcontract Agreement included specific change order provisions to account for any different or additional work.
Sprig contends the amount of the Subcontract Agreement was increased by multiple changes, extra work, and delays for which change orders were not issued. Sprig also contends it incurred additional costs and expenses as a result, but that ALCS has failed to pay the full amount owed. Altogether, Sprig claims damages of $17,617,709.53.
This case also relates to the construction of the Apple Campus 2, and ALCS' Subcontract Agreement with Sprig. ALCS asserts causes of action for breach of contract, express contractual indemnity, and negligence.
In the Complaint — also filed on October 16, 2017, but approximately forty minutes later — ALCS alleges that since 2014, Sprig "has struggled to complete its work in a timely manner or in accordance with the terms of the Subcontract." ALCS states that "Sprig claims it performed extra work that was not included in the Subcontract for which it sought additional compensation from ALCS in the form of change orders," but that Sprig failed to provide timely notice of changes and failed to timely provide sufficient cost estimates. ALCS alleges that Sprig eventually threatened to stop work unless ALCS met "unreasonable and unrealistic terms and conditions." Sprig eventually walked off the project, and ALCS hired replacement subcontractors to finish the work.
Sprig moves to dismiss or stay the ALCS action in favor of its own. In support, Sprig argues the ALCS action is subject to the first-to-file rule, or the rule against compulsory counterclaims brought in a separate action. Each of these rules is addressed in turn. One of them applies.
The court quickly dispenses with Sprig's request for relief under the first-to-file rule. That doctrine, based in the notion of comity between different courts of concurrent jurisdiction, "permits a district court to decline jurisdiction over an action when a complaint involving the same parties and issues has already been filed in another district."
Federal Rule of Civil Procedure 13(a) provides that "[a] pleading must state as a counterclaim any claim that — at the time of its service — the pleader has against an opposing party if the claim: (A) arises out of the transaction or occurrence that is the subject matter of the opposing party's claim; and (B) does not require adding another party over whom the court cannot acquire jurisdiction." Much like the first-to-file rule, "[t]he purpose of requiring a defendant to assert his claim as a counterclaim in a pending action is `to prevent multiplicity of actions and to achieve resolution in a single lawsuit of all disputes arising out of common matters.'"
The Ninth Circuit applies the "logical relationship" test to classify a cause of action as a compulsory counterclaim.
Here, there is plainly a "logical relationship" between the causes of action in the Sprig Action and those in the ALCS Action. All of them arise from the same "aggregate set of operative facts;" that is, both involve the Apple Campus 2 construction project and the parties' rights and obligations with respect to the Subcontract Agreement for the installation of a BAS. In fact, the parties' claims against each other are merely two versions of the same events. Whereas Sprig alleges ALCS breached the agreement by not paying for extra work, ALCS accuses Sprig of breach by failing to complete the work in the manner contemplated by the agreement. The court easily finds, therefore, that the ALCS Action is comprised of compulsory counterclaims. Indeed, ALCS does not vigorously argue otherwise.
That determination, however, does not mean the court must exercise its discretion to find that ALCS waived its causes of action by not asserting them in response to Sprig's Complaint.
In light of this discussion, the court finds it appropriate to stay rather than dismiss the ALCS Action during the pendency of the Sprig Action, and permit ALCS leave to amend its Answer in this case to assert its causes of action as compulsory counterclaims. If, as the court suspects, a final resolution of the Sprig Action also resolves the ones raised in the ALCS Action, a dismissal of the ALCS Action can be entered at the appropriate time.
Sprig's Motion to Dismiss or Stay the ALCS Action (Dkt. No. 13) is GRANTED. This case is STAYED pending resolution of the Sprig Action, and the Clerk shall administratively close the file. A copy of this order will also be filed in Case No. 5:17-cv-06135-EJD.
ALCS is granted leave to amend its Answer to assert the causes of action asserted in this Complaint as counterclaims in the Sprig Action, and shall do so within 10 days of the date this order is filed. ALCS is advised the scope of leave to amend permitted by this order is limited and does not include any claims outside of those already asserted against Sprig.
The hearing scheduled for March 8, 2017, is VACATED.