WALKER D. MILLER, Senior District Judge.
This matter is before me on Plaintiff WildEarth Guardians's ("WildEarth") Brief in response to my March 9, 2010 (ECF No. 68), Defendant Public Service Company of Colorado, d/b/a Xcel Energy's ("Xcel") Response to WildEarth's Brief (ECF No. 69), WildEarth's related Motion for Partial Summary Judgment (ECF No. 74), and Xcel's Motion to Strike (ECF No. 80). Being sufficiently advised in the premises, I enter the following order.
This case concerns the permitting process before the Colorado Public Utilities Commission ("PUC") for Xcel's 750 megawatt coal-fired electric generating plant, known as Comanche Unit 3 ("Comanche 3"). Construction and operation of Comanche 3 are subject to the revisions of the Clean Air Act ("CAA"), 42 U.S.C. 7401 et seq., which are administered in Colorado by the Air Pollution Control Division ("APCD") of the Colorado Department of Public Health and Environment ("CDPHE"). The primary issue in contention was whether Xcel was required to obtain a Maximum Achievable Control Technology ("MACT") determination regarding mercury emissions pursuant to section 112(g) of the CAA, 42 U.S.C. § 7412(g), prior to beginning construction and/or thereafter. As discussed in further detail below, when Xcel first began the permitting processes, Electric Utility Generating Units ("EGUs") such as Comanche 3 were initially categorized under the CAA as a major source of hazardous air pollutants ("HAPs"), including mercury, pursuant to 42 U.S.C. § 7412(a)(1) and were subject to MACT limitations of section 312(g). Thereafter, the Environmental Protection Agency ("EPA") initiated and consummated a "delisting" process to remove EGUs from regulation under section 112 and placing them under section 111 to be governed by a Clean Air Mercury Rule ("CAMR"). Although Xcel sought its permit in accordance with section 112, it was ultimately issued pursuant to section 111 (although it in fact still complied with section 112). In 2008, the EPA's delisting was deemed improper in New Jersey v. Envtl. Prot. Agency, 517 F.3d 574 (D.C.Cir.2008) and voided.
The detailed history of Xcel's permit application, construction, and actions after the New Jersey decision is set forth in my
The unresolved issue is whether Xcel's ongoing construction without a prior MACT determination until the revised permit of February 22, 2010, was a continuing violation of section 112(g) which exposes Xcel to civil penalties and liability for WildEarth's costs and attorneys' fees.
WildEarth takes the position that Xcel was required to have a MACT determination before any construction began or, at a minimum, before any continued construction once the New Jersey decision was issued. WildEarth first argues simply that a MACT determination was always required under section 112(g) regardless of the delisting rule, relying heavily on S. Alliance for Clean Energy v. Duke Energy Carolinas, LLC, Civil No. 1:08CV318, 2008 WL 5110894 (W.D.N.C., Dec. 2, 2008).
WildEarth rejects any argument that retroactive application of section 112(g) is prohibited by Harper v. Virginia Department of Taxation, 509 U.S. 86, 113 S.Ct. 2510, 125 L.Ed.2d 74 (1993)
Xcel opposes virtually every assertion by Plaintiff, beginning by challenging Plaintiff's conclusion that New Jersey specifically held that electric utilities remain subject to the MACT requirements of section 112(g). New Jersey, Xcel argues, simply held that the "delisting" was improper
WildEarth was also allowed to file a motion for partial summary judgment which was opposed by Xcel in substance and by a motion to strike. In fact, these new rounds of briefing just afforded both sides with an opportunity to make essentially the same arguments with one exception. WildEarth emphasized two recent decisions as authority for the proposition that after the New Jersey decision, utilities are obligated to obtain a MACT determination before any additional construction can be made. Plaintiff's Motion for Partial Summary Judgment (ECF No. 74) at p. 13. Relying principally on Sierra Club, Inc. v. Sandy Creek Energy Associates, L.P., 627 F.3d 134 (5th Cir.2010) and Wild-Earth Guardians v. Lamar Utilities Board, Civil Action No. 1:09-cv-02974-DME-BNB, 2010 WL 3239242 (D.Colo., Aug. 13, 2010), WildEarth asserts that once the delisting rule was vacated by New Jersey, Xcel should have stopped construction until it obtained a MACT determination. Id. at 14. Xcel disagrees, arguing both Sandy Creek and Lamar are distinguishable.
This dispute is best resolved by placing it within the context of Comanche 3's permit history.
However, virtually contemporaneously with this permit activity, the EPA initiated and consummated the "delisting" process to remove EGUs from regulation under section 112 and placing them under section 111, to be governed by CAMR. The "delisting" rule was published on March 29, 2005, and the CAMR rule on May 18, 2005.
After the delisting rule was adopted the APCD held public hearings and received comments, at which WildEarth did not participate. APCD then issued the final permit for Comanche 3 on July 5, 2005, which contained a CAMR requirement as opposed to a MACT determination which the permit acknowledged Xcel's application had included. In fact, the permit placed limitations on mercury emissions with the
A group of objectors to the permit filed suit in district court which upheld the permit. The ruling was affirmed by a division of the Colorado Court of Appeals. Citizens for Clean Air & Water in Pueblo & S. Colo. v. Colo. Dep't of Pub. Health & Env't, Air Pollution Control Div., 181 P.3d 393 (Colo.App.2008), cert. denied, Case No. 08SC228, 2008 WL 2581591 (Colo., June 30, 2008).
Construction of Comanche 3 commenced in October, 2005 and continued thereafter without interruption.
After the New Jersey decision, the EPA concluded in January 2009, that EGUs such as Comanche 3 must comply with section 112(g) even though construction commenced during the delisting period. On March 13, 2009, the CDPHE specifically requested that Xcel supplement its MACT determination submitted with its original permit application in August 2004.
On July 24, 2009, Xcel submitted its MACT update with a 12-month moving average of 15 × 10
Construction continued uninterrupted and there is no evidence that any emission failed to meet the MACT standard, initially submitted or that reduced standard ultimately approved. Nevertheless, WildEarth seeks to penalize Xcel because it commenced construction without an approved MACT determination and continued until February 22, 2010, still without that approval. The question really becomes whether a party which met the published standard when it commenced the permit process, then meets a new standard published while still meeting the old standard, and then thereafter meets and exceeds the first standard by the third standard adopted by the agency should be penalized.
With this context, the matter is most appropriately resolved applying a retroactivity analysis under Chevron Oil Co. v. Huson, 404 U.S. 97, 92 S.Ct. 349, 30 L.Ed.2d 296 (1991), a case upon which both parties rely. Chevron establishes the factors to be considered in determining whether a new rule should be applied retroactively:
404 U.S. at 106-07, 92 S.Ct. 349 (internal citations and quotations omitted).
The first factor to consider is whether vacating the delisting rule establishes a new principle, regulation by MACT, by overruling a clear and prior rule, regulation by CAMR, upon which Xcel had relied. Plainly, given the fact that Xcel commenced the permitting process assuming regulation by MACT and then revised its submittal to regulation by CAMR upon EPA's adoption of the delisting rule, Xcel relied upon the "past precedent," namely the CAMR rule. Both Xcel and the APCD relied upon that "past
The second factor, whether retrospective application of the precedent will further or retard its operation, is less clear. Arguably, application of the new rule, regulation by MACT analysis, furthers the original purpose of the statute prior to the adoption of the delisting rule. Although this factor might weigh in favor of retrospective application, I consider it of lesser importance in this case because Xcel has submitted acceptable MACT determinations from the outset and remains bound to maintaining those standards by reason of the settlement agreement.
The final consideration is whether retroactive application would be inequitable. Under the circumstances of this case I conclude that it would. Xcel commenced the process by complying with section 112(g) and then agreed with objectors to the permitting process that it would apply that MACT determination, not only to the new construction but to preexisting facilities as well. When the delisting rule was adopted, Xcel complied yet maintained its commitment to the MACT determination because of the settlement. When the delisting rule was annulled, Xcel again complied with directives and established a higher standard of MACT determination, presumably in a public interest. Rather than acknowledging that in the end Xcel's compliance with the directives of its regulator imposed higher standards, WildEarth seeks to impose penalties by retroactive application of the latest determination by the regulators. In essence, WildEarth argues that if Xcel had somehow ignored or avoided the explicit direction from its regulators to rely on CAMR rather than a MACT determination and proceeded with its original MACT determination, it would not be subject to its claims for injunctive relief or penalties. Such a result would not further the objectives of the CAA as much as Xcel's actual course of conduct. Xcel not only met the standard of maintaining a MACT determination, it has significantly raised the applicable standard (and presumably benefitted the public interest
I agree with Xcel that under the circumstances of this case there is no retroactive application of the annulment of the delisting rule, particularly given the MACT determinations obtained both prior to commencement of construction and during construction following the annulment of the rule.