CHAMBERS, J.
¶ 1 There was a catastrophic failure at the Spokane wastewater treatment plant. One man was killed, two others were severely injured. The survivors successfully sued an engineering firm that was working with the city at the time. We must decide whether that firm enjoys Industrial Insurance Act immunity under RCW 51.24.035. The appellants also challenge the trial judge's rulings on duty, cause in fact, legal cause, superseding cause, and 26 specific findings of fact. Finding no error, we affirm.
¶ 2 On May 10, 2004, a digester dome at Spokane's sewage treatment plant collapsed. The collapse dropped Mike Cmos into sewage
¶ 3 The collapse took place at the Spokane Riverside Park Water Reclamation Facility. This plant was built in 1977 and had three sewage digesters. Ex. 57 (after accident report of the Spokane Fire Department). These "digesters" have been described as resembling a small domed sports stadium. Id. Digester 3, where the accident happened, had a capacity of 2.25 million gallons. Id. "The purpose of the digester is to take raw solids [and] circulate[] the solids for 20 to 40 days at approximately 100 degrees Fahrenheit in an anaerobic process until they are stable and able to be used as commercial fertilizer." Id. Generally, one digester was used as a primary digester, one as a secondary digester, and one for storage for times when "the biosolids land application process is hindered by unfavorable weather conditions." Ex. 11.
¶ 4 CH2M is an engineering firm. It had been hired by the city in 1998 as an engineering consultant for a 10-year capital improvement project to upgrade and retrofit the sewage plant. The plant was to continue operating during the improvements. Among other things, CH2M was hired to "design and manage an upgrade to and redesign of the recirculation and heating systems for the" digests. During the anticipated 10 year retrofit, CH2M also contracted to "provide `on-call' services for plant operations." CP at 3110 (Finding of Fact (FOF) 15). Kelly Irving, an engineer and CH2M employee, acted as the on site program manager for CH2M. He is also a named defendant in this action.
¶ 5 It seems that the plant had been struggling to keep the digester tanks warm enough for necessary bacterial activity, especially as the density of biosolids in the digesters increased. Instead of heating the tanks directly, sewage was circulated through heaters and back again to the tanks. Cold raw sludge was also fed directly into the digester tanks. As an interim fix for the temperature problem, Irving suggested separating the incoming unheated sludge flow from the heated sludge flow. On May 3, 2004, one week before the collapse of the digester, this option was discussed at a regularly scheduled meeting of sewage plant employees. Irving suggested using valves to separate the flows. These valves would redirect sludge through a previously unused pipe into a newly isolated line, which had originally been designed as a suction line for removing sludge from the digester, and to close off the intersection between the recirculation line from the heater and the incoming raw feed. City employees suggested using "skillets" instead of valves "because it would be more expedient and less expensive." CP at 3113 (FOF 32). The trial court found, in a challenged finding of fact, that "Irving and CH2M accepted the suggestion." CP at 3113 (FOF 33).
¶ 6 Irving made recommendations as to where the skillets were to be placed. The changes to the pipes were made over the next few days. The trial court found that Irving and CH2M did not perform "any engineering analysis of the effects the flow separation and the skillets would have upon the City's operation of the digesters" and that they did not prepare a written analysis of the changes. CP at 3115 (FOF 40). The installation of the skillets did not merely change some regular pattern of flow: it also necessitated a change in the valving used by plant operators to transfer sludge between the digesters. Unfortunately, neither the plant superintendent, operations supervisor, nor the maintenance supervisor was aware that the
¶ 7 A few days later, the sewage plant shift supervisor, Terry Headley, a city employee, "became concerned that Digester 3 was too full" and ordered his subordinates to transfer some of the sludge to Digester 2. CP at 3116 (FOF 46). Headley knew that the skillets had been installed and where. However, Headley had not been instructed on "the effects of the installation of the skillets on the valving employed by the plant operators for pumped transfers of sludge." CP at 3117 (FOF 49). The workers on shift "twice attempted to trace the piping of the digesters to determine how to valve a pumped transfer from Digester 3 to Digester 2, checked and rechecked their work and believed they had valved correctly for such a pumped transfer in light of the installation of the skillet." CP at 3117 (FOF 51). Unfortunately, the configuration of valves and skillets they chose created a "`deadhead,' and the recirculation pumps were not pumping sludge out of Digester 3." CP at 3118 (FOF 56). Exacerbating the situation, one of Digester 3's overflow systems had been disabled, the other was off, and the internal "SCADA"
¶ 8 Meanwhile, it appears that foam from the sludge was beginning to leak out of pressure relief valves at the top of the dome and run down the outside of Digester 3. The superintendent of the plant, Timothy Pelton, was worried about the sludge entering the Spokane River, and asked Cmos, Evans, and Michaels to help him divert it. Cmos and Evans climbed the dome with a fire hose to siphon off the foam while Pelton and Michaels guided the other end of the hose into a drain.
¶ 9 All the while, the digester continued to fill with sewage sludge. The city employees knew that Digester 3 was getting dangerously full but believed that the fastest way to relieve the pressure was to continue to do what they were doing. Unfortunately, they were wrong, and Digester 3 continued to fill until it collapsed. The trial judge found that Cmos was alive and conscious when he dropped into the 100 degree sewage sludge and that he died in "excruciating physical pain ... in darkness, pain and utter helplessness." CP at 3123 (FOF 81). He left behind a wife and 12-year-old daughter. Evans suffered "a fractured pelvis, fractured tibia, fractured ribs, serious back injuries including compression fractures of vertebrae, [and] sludge aspiration causing a permanent 20% reduction in lung capacity," and Michaels suffered serious knee and back injuries, among other things. CP at 3125 (FOF 85).
¶ 10 The city hired an engineering firm, Exponent, to investigate the disaster. Exponent concluded that the dome actually floated up on the rising sludge and rotated, fracturing the anchors that had held the dome to the digester walls and cracking the dome. It concluded that there were three main causes of the accident: the blocked overflow pipe; a malfunctioning monitoring system inside the digester; and the final, failed attempt to transfer sludge out of the digester. Exponent also concluded that "[t]he pumping of liquid beyond the maximum design level and into the dome was the principal and sufficient cause of the accident." Ex. 71, at 33.
¶ 11 The plaintiffs filed a negligence action against CH2M and Irving. The city of Spokane, as the employer of the plaintiffs, was immune under the Industrial Insurance Act. All parties agreed that the city was negligent. The issue at trial was the negligence, if any, of CH2M, not the city. After a three week bench trial, Judge Austin ruled for the plaintiffs. The Court of Appeals certified the case to this court.
¶ 12 We review de novo questions of law, including the meaning of immunity statutes, duty, and legal cause. Soltero v. Wimer, 159 Wn.2d 428, 433, 150 P.3d 552 (2007) (citing Nordstrom Credit, Inc. v. Dep't of Revenue, 120 Wn.2d 935, 942, 845 P.2d 1331 (1993)); Schooley v. Pinch's Deli Mkt., Inc., 134 Wn.2d 468, 478, 951 P.2d 749 (1998). Cause in fact is a factual question left to the trier of fact unless reasonable minds could not differ. Hertog v. City of Seattle, 138 Wn.2d 265, 275, 979 P.2d 400 (1999) (citing Sherman v. State, 128 Wn.2d 164, 183, 905 P.2d 355 (1995)). We review findings of fact for substantial evidence. Soltero, 159 Wash.2d at 433, 150 P.3d 552.
¶ 13 CH2M contends that it and its agents enjoy Industrial Insurance Act immunity under RCW 51.24.035. This statute has not been considered in any published Washington court opinion. However, the Industrial Insurance Act itself is regularly before Washington courts, and there is a body of law to guide us. The legislature has instructed us that the act "shall be liberally construed for the purpose of reducing to a minimum the suffering and economic loss arising from injuries and/or death occurring in the course of employment." RCW 51.12.010. To accomplish the legislative objective, our "`guiding principle in construing provisions of the Industrial Insurance Act is that the Act is remedial in nature and is to be liberally construed in order to achieve its purpose of providing compensation to all covered employees injured in their employment, with doubts resolved in favor of the worker.'" Cockle v. Dep't of Labor & Indus., 142 Wn.2d 801, 811, 16 P.3d 583 (2001) (quoting Dennis v. Dep't of Labor & Indus., 109 Wn.2d 467, 470, 745 P.2d 1295 (1987)). The act is "the product of a grand compromise" between workers and employers. Birklid v. Boeing Co., 127 Wn.2d 853, 859, 904 P.2d 278 (1995) (citing Stertz v. Indus. Ins. Comm'n, 91 Wn. 588, 590-91, 158 P. 256 (1916), abrogated in part by Birklid, 127 Wn.2d 853, 904 P.2d 278). "Injured workers were given a swift, no-fault compensation system for injuries on the job. Employers were given immunity from civil suits by workers," with exceptions not relevant here. Id. The benefits to injured workers, while comparatively quick and sure, are often far less than would be available to them in tort. Minton v. Ralston Purina Co., 146 Wn.2d 385, 390, 47 P.3d 556 (2002).
¶ 14 Third party tortfeasors are not parties to the grand compromise and injured workers may sue such tortfeasors. RCW 51.24.030; Flanigan v. Dep't of Labor & Indus., 123 Wn.2d 418, 425, 869 P.2d 14 (1994). If such suits are successful, both the worker and the State benefit as the State has a right to recoup some of its workers' compensation payments. RCW 51.24.060. We have long held that the right to sue a third party tortfeasor is a "valuable right to the workman, and, to secure it to him, the act should receive the same liberal construction that is required to be given to other parts of the act in order to secure his rights thereunder." Burns v. Johns, 125 Wn. 387, 392-93, 216 P. 2 (1923) (citing Carlson v. Mock, 102 Wn. 557, 173 P. 637 (1918)). Further, we have long noted, albeit in the context of a predecessor to the current private suit provision, that "[t]he industrial insurance fund is provided for the exclusive benefit of the employer and the workman, and we will in all doubtful cases sustain the right of the injured workman against the third party wrongdoer who has not contributed to the fund." Mathewson v. Olmstead, 126 Wn. 269, 273, 218 P. 226 (1923).
¶ 15 With these principles in mind, we turn to the immunity provision before us.
RCW 51.24.035 (emphasis added). Statutory grants of immunity in derogation of the common law are strictly construed. Plano v. City of Renton, 103 Wn.App. 910, 911-12, 14 P.3d 871 (2000) (citing Matthews v. Elk Pioneer Days, 64 Wn.App. 433, 437-38, 824 P.2d 541 (1992)).
¶ 16 CH2M argues that the entire plant was a construction project, entitling it to immunity under subsection .035(1). It also argues that it had not prepared design plans and specifications and thus the exclusion from immunity under subsection .035(2) does not apply. The plaintiffs argue that a working sewage plant is not a construction site as contemplated by the legislature and that CH2M did negligently prepare design plans and specifications.
¶ 17 The immunity found in RCW 51.24.035(1) is limited by its terms to a design professional performing professional services "on a construction project" or any employee of a design professional assisting or representing the design professional performing professional services on the "site of the construction project." The trial judge found that "the area of the plant where the skillets were installed was not a construction project nor a construction site within the meaning of RCW 51.24.035(1)." CP at 3128 (FOF 94). Whether or not the area where the act of alleged negligence occurred was a construction site is a question of fact. We review questions of fact for substantial evidence. See Soltero, 159 Wash.2d at 433, 150 P.3d 552, (citing Nordstrom Credit, 120 Wash.2d at 942, 845 P.2d 1331). CH2M argues that as a matter of law, the immunity statute "unquestionably applies" to any building complex where some construction was occurring and that no reasonable person could fail to find that the accident took place on a construction project or on a construction site. Br. of Appellant at 43, 45.
¶ 18 Turning first to whether the statute "unquestionably applies," we note that "construction project" and "site of a construction project" are not defined statutory terms under Title 51 RCW or relevant administrative regulations. Undefined common statutory terms are given their common dictionary meanings unless there is strong evidence the legislature intended something else. City of Spokane ex rel. Wastewater Mgmt. Dep't v. Dep't of Revenue, 145 Wn.2d 445, 454, 38 P.3d 1010 (2002) (citing State v. Pacheco, 125 Wn.2d 150, 154, 882 P.2d 183 (1994)). The first nongrammatical definition of "construction" in Webster's is "the act of putting parts together to form a complete integrated object: Fabrication." Webster's Third New International Dictionary 489 (2003). "Construction project" is not defined in Webster's, but "project" is defined primarily as "a specific plan or design," and "site" is defined as "the local position of building, town, monument, or similar work either constructed or to be constructed esp. in connection with its surroundings... a space of ground occupied or to be occupied by a building." Id. at 1813, 2128.
¶ 19 While the trial court made no specific, relevant finding of fact, the findings imply, and the evidence supports, that some parts of the sewage plant campus were under construction. Finding of fact 94 tells us that "at all pertinent times prior to and on May 10, 2004, the area of the plant where the skillets were installed was not a construction project nor a construction site within the meaning of RCW 51.24.035(1)." CP at 3128. Timothy Pelton, the administrative superintendent of the plant, testified that the nearest construction was "several hundred feet away." 8 RP (Sept. 17, 2008) at 1114-15. Thus, it appears that there was construction occurring on the sewage treatment campus. The question is whether the existence of construction somewhere on the campus triggers the immunity of RCW 51.24.035.
¶ 20 We conclude it does not. Clearly, if no construction was occurring on the campus, the immunity provisions of RCW 51.24.035 would not be at issue. CH2M's contract with the city contemplated at least two main activities. One was to retrofit the Spokane Riverside Wastewater Treatment Plant and the other was to maintain the plant to continue to function as it had on a day to day basis.
¶ 21 CH2M argues that whether or not the discrete act of alleged negligence was related to construction is immaterial. CH2M argues it has immunity for any professional services rendered on a construction project site and that the entire wastewater treatment facility was a construction site within the meaning of the statute. An aerial photograph of the Spokane wastewater treatment facility shows at least a dozen buildings and several parking lots, not unlike our own capitol campus. The record before us does not suggest that any construction was taking place within the digesters themselves. At trial, the superintendent of the plant testified that at the time, the closest construction "was either the new aeration basin or rebuilding of the link between the administration building and process building ... several hundred feet away." 8 VRP (Sept. 17, 2008) at 1114-15. We do not believe that the legislature meant that when construction was performed on one building on a campus, engineering professionals were entitled to immunity everywhere on the campus regardless of the nature of their professional services.
¶ 22 We must read statutes in context with the whole statutory scheme, which in this case includes both the injunction to construe the title liberally in favor of reducing suffering and the private suit provision. Rivas v. Overlake Hosp. Med. Ctr., 164 Wn.2d 261, 266-67, 189 P.3d 753 (2008); RCW 51.24.030; RCW 51.12.010. Taken as a whole, it appears to us that the legislature intended to protect design engineers from the sort of liability imposed on general contractors for workplace negligence, but not to protect them from their own negligence.
¶ 23 In addition to limiting the immunity in question to professional services on the site of the construction project, the statute also excludes from immunity "the negligent preparation of design plans and specifications." The trial judge found that "[t]he Irving proposal to separate sludge flows referenced above in these Findings constitutes negligent preparation of a design plan within the meaning of RCW 51.24.035(2)." CP at 3128. CH2M contends that since it put no relevant plans or specifications in writing, this statutory safe harbor for actions based on negligent design plans and specifications does not apply. Br. of App. at 45.
¶ 24 A similar argument was rejected by the Kansas Supreme Court under the Kansas design professional immunity statute.
Id.
¶ 25 We agree with the Kansas Supreme Court and perceive no appreciable difference in recommending a change in the piping of the sludge and the locations of the skillets under CH2M's "on call" service agreement and preparing written plans and specifications to accomplish the same thing. We find it difficult to believe that the legislature intended to allow design professionals to escape liability for negligent work by not writing down their plans or specifications.
¶ 26 The plaintiffs brought a negligence suit, requiring them to "establish the existence of a duty, a breach thereof, a resulting injury, and proximate causation between the breach and the resulting injury." Schooley, 134 Wash.2d at 474, 951 P.2d 749 (citing Pedroza v. Bryant, 101 Wn.2d 226, 228, 677 P.2d 166 (1984)). The trial judge found that CH2M "owed these plaintiffs ... both a contractual and a common law duty to exercise that degree of skill and diligence normally employed by professional engineers or consultants performing the same or similar services at the time said services were performed." CP at 3128-29 (Conclusion of Law 3).
¶ 27 Design professionals have long had a duty of care recognized at law.
¶ 28 Historically, there "are two common bases for civil liability of design professionals—negligent supervision of the worksite and negligent design," at least for work site injuries. Am. Br. Wash. State Ass'n for Justice Found. at 10 (citing Note, Architectural Malpractice: A Contract-Based Approach, 92 HARV. L.REV. 1075, 1094 (1979)). The immunity statute at issue addresses both historical bases for liability; it protects design professionals from general liability for work site safety (unless assumed by contract) but clearly recognizes common law liability for negligent design. CH2M contends that the trial judge erred by imposing on CH2M the city's duty to ensure a safe workplace. E.g., Br. of Appellant at 48-52. It suggests that Burg v. Shannon & Wilson, Inc., 110 Wn.App. 798, 43 P.3d 526 (2002), mandates reversal. In Burg, a landslide damaged or destroyed several homes. An engineering firm had warned the city that the slope was unstable and the city was attempting to stabilize the slope at the time. Several homeowners sued the firm, contending that it had an independent duty to warn them of the danger. Id. at 804, 43 P.3d 526. The court below disagreed, ruling that the firm had no duty to the individual property owners. Id. at 811, 43 P.3d 526. CH2M contends that the same principle applies here: that it had no duty to protect the plaintiffs from the negligence or bad acts of others. Having so framed the issue as a duty to supervise the work site and warn of dangerous conditions
¶ 29 We recently held that an "engineer's duty of care extends to safety risks of physical damage to the property on which the engineer works." Affiliated, 170 Wash.2d at 456, 243 P.3d 521 (lead opinion); id. at 460-61, 243 P.3d 521 (Chambers, J., concurring). Affiliated did not include a claim for personal injury. At least since the time of Hammurabi's code, construction design professionals had a duty not to cause injury or death because of a collapse of a building and we see no reason why tort law would give less protection to workers on that property than to the property itself. See supra n. 8. This is in accord with the general principle that "[a]n actor ordinarily has a duty to exercise reasonable care when the actor's conduct creates a risk of physical harm." RESTATEMENT (THIRD) OF TORTS: LIABILITY FOR PHYSICAL AND EMOTIONAL HARM § 7(a) (2010). In this state, "[w]hen a duty is found to exist from the defendant to the plaintiff then concepts of foreseeability serve to define the scope of the duty owed." Schooley, 134 Wash.2d at 475, 951 P.2d 749 (citing Burkhart v. Harrod, 110 Wn.2d 381, 395, 755 P.2d 759 (1988)). Of course, "[a]n actor's liability is limited to those harms that result from the risks that made the actor's conduct tortious," RESTATEMENT (THIRD) OF TORTS, supra, § 29, but that will be considered more below.
¶ 30 We hold that design professionals have a duty of care to "exercise the degree of skill, care, and learning possessed by members of their profession in the community." 16 DEWOLF & ALLEN, supra, § 15.51, at 504-05. That duty flowed, at the least, to those working on the property at the time the designs were being implemented.
¶ 31 CH2M assigned error to the trial court's findings regarding breach but devoted no specific argument to the issue. We review findings of fact for substantial evidence, and questions of breach are typically reserved for the finder of fact. Soltero, 159 Wash.2d at 433, 150 P.3d 552; Johnson v. State, 77 Wn.App. 934, 937, 894 P.2d 1366 (1995) (citing McLeod v. Grant County Sch. Dist. No. 128, 42 Wn.2d 316, 324-25, 255 P.2d 360 (1953)). Briefly, after a three week trial, the court found that CH2M's failure to perform an "engineering analysis" of
¶ 32 CH2M contends that even if it owed a legal duty to the plaintiffs and breached that duty, it was not the proximate cause of their injuries. Proximate cause can be divided into two elements: cause in fact and legal cause. Schooley, 134 Wash.2d at 478, 951 P.2d 749. As CH2M challenges both elements, we will discuss them in turn.
¶ 33 "`Cause in fact' refers to the actual, `but for,' cause of the injury, i.e., `but for' the defendant's actions the plaintiff would not be injured. Establishing cause in fact involves a determination of what actually occurred and is generally left to the jury." Id. at 478, 951 P.2d 749 (citing King v. City of Seattle, 84 Wn.2d 239, 249-50, 525 P.2d 228 (1974), rejected on other grounds by City of Seattle v. Blume, 134 Wn.2d 243, 260, 947 P.2d 223 (1997) (rejecting the "business judgment rule" of King)). The trial court found that "[t]he Defendants' failure to comply with the applicable engineering standard of care was a proximate cause of the death of Mike Cmos and the bodily injuries of Dan Evans and Larry Michael." CP at 3129.
¶ 34 CH2M contends that "the alleged causation is so implausible as to defy all reasonableness." Br. of Appellants at 61. Essentially, it asks us to substitute our factual judgment for that of the trier of fact. It contends, and we have no reason to doubt, that if the operators had realized that Digester 3 was filling instead of draining, they could have prevented the accident. E.g., 14 RP (Sept. 29, 2008) at 2076-2106 (testimony of defense expert Anderson).
¶ 35 The difficulty with CH2M's argument is that there may be more than one cause in fact. Both sides put on their cases. There was evidence that some of the workers did not believe that the installation of skillets required a change in valving. E.g., 6 RP (Sept. 15, 2008) at 803-06. There was sufficient evidence that because CH2M failed to do an analysis of the effect of the valving change, the city workers believed that they were transferring sludge out of the digester dome when they were not. E.g., 4 RP (Sept. 10, 2008) at 468-69 (testimony of expert Brugger that "they thought they were effecting a transfer using the most expeditious means"). The trial court was the trier of fact. CH2M fails to show that there was not substantial evidence to support the court's findings, or that we should substitute our judgment for that of the trial judge.
¶ 36 "The focus in the legal causation analysis is whether, as a matter of policy, the connection between the ultimate
¶ 37 CH2M contends that any breach of its duty "`is too remote or insubstantial to impose liability.'" Br. of Appellants at 65 (quoting Schooley, 134 Wash.2d at 478-79, 951 P.2d 749). For this contention it relies upon two cases that are inapposite. CH2M analogizes this case to Porter v. Sadri, 38 Wn.App. 174, 685 P.2d 612 (1984) and Hartley, 103 Wn.2d 768, 698 P.2d 77. In Porter, the builder of a house neglected to use safety glass. 38 Wash.App. at 176, 685 P.2d 612. A subsequent owner replaced the window with glass of like quality. A third owner fell through that glass and sued the original builder for using the wrong sort of glass. The court concluded that the scope of the builder's negligence ended when the window he installed was broken and replaced. Id.
¶ 38 In Hartley, Janet Hartley was killed by a drunk, but validly licensed, driver. The driver had a long history of drunk driving charges. Her family sued the State and county, reasoning that if the drunk driver's license had been revoked, he would not have been driving and she would not have been killed. Applying general principles of proximate causation and the public duty doctrine, a doctrine unique to government entities, we held that the government owed no legal duty to the victim of a drunk driver for failing to revoke the driver's license. We cautioned that "[t]his is not to say that there cannot be more than one party who is legally liable; but here the failure of the government to revoke Johnson's license is too remote and insubstantial to impose liability for Johnson's drunk driving." Hartley, 103 Wash.2d at 784, 698 P.2d 77 (citing Kaiser v. Suburban Transp. Sys., 65 Wn.2d 461, 398 P.2d 14, 401 P.2d 350 (1965)).
¶ 39 In essence, CH2M contends that its alleged negligence should not be deemed a legal cause of plaintiffs' injuries because those injuries are too remote. But, again, contractors have been potentially liable for their own negligence at least since the time of Hammurabi. Again, the trial court found that CH2M's breach of duty set into motion events that were one of the causes of the collapse of the digester and the cause of the plaintiffs' injuries, and that but for the breach of duty, the collapse would not have occurred. We find no error.
¶ 40 CH2M also contends that the city's negligent and reckless behavior was an intervening force and a superseding cause. The trial judge did not find the city was reckless.
Campbell v. ITE Imperial Corp., 107 Wn.2d 807, 812-13, 733 P.2d 969 (1987) (quoting RESTATEMENT (SECOND) OF TORTS § 449 (1965)).
¶ 41 CH2M contends there were 10 intervening acts of municipal negligence: (1) that the city did not maintain a reasonable fail-safe overflow system, (2) that it had an inaccurate sludge measuring system, (3) that it did not have a good chain of command, (4) that it did not have good standing orders, (5) that it did not activate an emergency gravity overflow system, (6) that it did not stop transferring sludge into the digester when it got to 28 feet, (7) that it did not stop transferring sewage at 2 p.m., (8) that it did not properly set a valve, (9) that it did not stop when things got bad, and (10) that it put men in harm's way when it should have known better. Br. of Appellants at 68-69. This list, largely speaking, mirrors the testimony of defense expert Anderson. Able trial counsel presented these arguments to the trier of fact who rejected them. See CP at 3129. Instead, the trial court found, among other things, that "[a] reasonably prudent engineer in the position of CH2M could reasonably have anticipated" that the plant might have been modified over the years, that the city would take steps to keep sewage sludge from flowing into the Spokane River, and that the SCADA monitoring system might malfunction. CP at 3120-21 (FOF 64, 65, 66). In short, the trier of fact concluded that had CH2M not breached its duty, and had it performed the engineering analysis, the city employees would not have been confused and the collapse would not have occurred. While reasonable minds may differ, this is a question of fact to be left to the trial judge except in the most extreme cases. The trial court's conclusion that there was no independent intervening cause that superseded the negligence of CH2M and Irving is supported by substantial evidence.
¶ 42 Finding no error, we affirm the trial court's judgment.
WE CONCUR: CHARLES W. JOHNSON, SUSAN OWENS, and MARY E. FAIRHURST, Justices, RICHARD B. SANDERS and DENNIS J. SWEENEY, Justices Pro Tem.
MADSEN, C.J. (concurring).
¶ 43 I agree with the result the majority reached because I agree with its holding that CH2M Hill negligently prepared design plans and specifications. See RCW 51.24.035(2). However, having determined that CH2M negligently prepared design plans and specifications for which it was not entitled to immunity, the majority had no need to reach RCW 51.24.035(1). See RCW 51.24.035(2). Thus, its interpretation of that portion of the statute is dictum. It is also erroneous. In my view, CH2M was "retained to perform professional services on a construction project," and Kelly Irving was "representing [CH2M] in the performance of professional services on the site of the construction project" within the meaning of RCW 51.24.035(1). Because I believe that the majority's interpretation of RCW 51.24.035(1) is not only unnecessary but also impermissible, I write separately.
¶ 44 The majority gives significant deference to the trial court's "finding of fact" that "`the area of the plant where the skillets were installed was not a construction project nor a construction site within the meaning of RCW 51.24.035(1).'" Majority at 539 (quoting Clerk's Papers (CP) at 3128). This deference rests on the majority's erroneous belief, apparently shared by the trial court, that whether the accident involved a construction project or construction site is a question of fact. Id. at 10; see CP at 3128 (trial court's
¶ 45 The majority makes much of RCW 51.12.010, which commands a liberal construction of Title 51 in favor of employees. Majority at 537-38 et seq. This interpretive provision compels us to interpret ambiguities within this title in favor of the injured worker. It does not, however, free us from the confines of unambiguous statutory text. Cf. Mathewson v. Olmstead, 126 Wn. 269, 273, 218 P. 226 (1923) ("[W]e will in all doubtful cases sustain the right of the injured workman against the third party wrongdoer who has not contributed to the fund." (emphasis added)). Thus, in giving RCW 51.24.035(1) a meaning the text cannot bear, the majority goes well beyond the mandate of RCW 51.12.010.
¶ 46 The majority finds further support for its narrow reading of RCW 51.24.035(1) in the notion that statutory grants of immunity in derogation of common law are narrowly construed. Majority at 538-39. However, this statute does not derogate from common law and instead appears to codify the common law.
¶ 47 In Riggins v. Bechtel Power Corp., 44 Wn.App. 244, 722 P.2d 819 (1986), a case that predated RCW 51.24.035 by one year, the Court of Appeals considered whether Bechtel, a consultant engineering firm at the Hanford site charged with construction duties, owed a duty to provide a safe work site for workers at the Hanford plant. Id. at 245-46, 722 P.2d 819. The court's inquiry focused on Bechtel's contractual duties to ensure workplace safety and the level of supervision Bechtel was required to provide. Id. at 249, 722 P.2d 819. This inquiry mirrors that under RCW 51.24.035(1), under which a third party design professional is liable for work site injuries only if it has contractually assumed responsibility for safety or exercised actual control of the work site. Similarly, in Loyland v. Stone & Webster Engineering Corp., 9 Wn.App. 682, 514 P.2d 184 (1973), overruled on other grounds by Bayne v. Todd Shipyards Corp., 88 Wn.2d 917, 922, 568 P.2d 771 (1977), injured workers brought suit against Stone & Webster Engineering Corporation, which had contracted with a public utility district to design, supervise, and execute an extension to a hydroelectric power plant. Id. at 683, 514 P.2d 184. In assessing the design professional's liability, the Court of Appeals held that liability hinged on "[t]he extent of supervision required of Stone & Webster in its contract with the district and the amount and character of inspection which it was to conduct." Id. at 687, 514 P.2d 184; see also Porter v. Stevens, Thompson & Runyan, Inc., 24 Wn.App. 624, 602 P.2d 1192 (1979) (holding that consulting engineer was not liable for workplace injury where it was not contractually responsible for safety precautions and did not exercise actual control of the work site).
¶ 48 In sum, at common law, third party design professionals were liable for work site injuries only when they assumed responsibility for safety or exercised actual control. E.g., Riggins, 44 Wash.App. at 249, 722 P.2d 819; Loyland, 9 Wash.App. at 687, 514 P.2d 184. In ensuring immunity for design professionals who assume no such responsibility and exercise no such control, RCW 51.24.035(1) effectively codifies common law and by no means derogates from it.
¶ 49 With these principles in mind, I would hold that CH2M was retained to provide engineering services on a construction project within the meaning of RCW 51.24.035(1). As the majority correctly notes, we consult a common dictionary for undefined statutory terms in the absence of clear evidence that the legislature intended otherwise. Majority at 539-40 (citing City of Spokane ex rel.
¶ 50 A "site," in contrast, is a physical location, but it is also defined broadly, and— contrary to the majority's interpretation— without reference to a fixed radius. Relevant definitions of "site" in Webster's include "the local position of building, town, monument, or similar work either constructed or to be constructed [especially] in connection with its surroundings," "a space of ground occupied or to be occupied by a building," or "the scene of an action ... or specified activity."
¶ 51 CH2M was retained to provide program management and engineering design
¶ 52 Moreover, even if the statute were read more narrowly, it is indisputable that in assisting with the placement of skillets—the synthesis of parts to form an integrated whole—Mr. Irving performed professional services on the site of a construction project. See id.; Edwards v. Anderson Eng'g, Inc., 284 Kan. 892, 902, 166 P.3d 1047 (2007) (holding that design professional's marking on pipe to indicate how it should be cut was a construction project within the meaning of a Kansas statute similar to RCW 51.24.035(1)). Contrary to the majority's suggestion, it is of no import that these services fell under the umbrella of CH2M's "`on-call'" duties. Majority at 540.
¶ 53 Accordingly, the trial court misinterpreted RCW 51.24.035(1) in concluding that the area of the sewage plant where the skillets were installed was neither a construction project nor a construction site within the meaning of this statute. Similarly, Timothy Pelton's testimony that the nearest construction was "several hundred feet away" does not negate the conclusion that CH2M was retained to perform professional services on a construction project and that the entire sewage treatment plant was the site of a construction project within the meaning of RCW 51.24.035(1). See 8 Verbatim Report of Proceedings (Sept. 17, 2008) at 1114-15. Thus, the majority errs in relying on Mr. Pelton's testimony and the trial court's "finding of fact." Majority at 540.
¶ 54 In addition, the majority misstates the relevant inquiry when it reasons that "[t]he question is whether the existence of construction somewhere on the campus triggers the immunity of RCW 51.24.035." Id. at 12. CH2M's immunity under this statute stems not from discrete construction activities elsewhere on the plant but rather from the engineering firm's managerial role in an ongoing, plant-wide construction project. Thus, the majority's focus on spatial distances is misplaced, and its analogy to our capitol campus inapposite. See id. at 13.
¶ 55 As the majority acknowledges in a footnote, design professionals are particularly vulnerable to suits by injured workers under workers' compensation schemes that immunize employers from such lawsuits. Id. at 14 n. 6. As one commentator noted prior to the enactment of immunity statutes, such as RCW 51.24.035,
Note, Architectural Malpractice: A Contract-Based Approach, 92 HARV. L.REV. 1075, 1095-96 (1979) (footnotes omitted). Workers' compensation schemes are one of several
¶ 56 Thus, RCW 51.24.035, like strikingly similar statutes in other jurisdictions, likely reflects a legislative recognition of design professionals' increased exposure to liability for work site accidents and a desire to reduce this exposure through statutory immunity. See, e.g., CONN. GEN.STAT. § 31-293(b); GA. CODE ANN. § 34-9-11(a); ME.REV.STAT. tit. 39-A, § 104; TENN.CODE ANN. § 50-6-120(a); FLA. STAT. § 440.09(6); PA. STAT. ANN. tit. 77, § 471. The majority's narrow reading of RCW 51.24.035(1) sharply diminishes the impact of this legislative intervention, and in so doing, strips design professionals of an important statutory protection.
¶ 57 Finally, although the majority repeatedly emphasizes the remedial purpose of the Industrial Insurance Act (IIA), Title 51 RCW, its narrow interpretation of the terms "construction project" and "site of the construction project" does not necessarily serve this purpose because a narrow construction of immunity in turn narrows the scope of the design professional's duty to injured workers. If statutory immunity is defined so narrowly as to not apply, the design professional is liable in tort to the injured worker only if the latter can prove negligence on the part of the former. In particular, to make out a negligence claim, the injured worker must establish the design professional's duty to ensure worker safety. Riggins, 44 Wash.App. at 249, 722 P.2d 819. The scope of this duty is likely to correspond to the scope of the construction project for which the design professional was retained. Where a construction project is seen as a long-term undertaking that spans an entire campus, and a court finds that a design professional has a contractual or common law duty to ensure work site safety, that duty will extend to the entire project and persist throughout the duration of the project. In contrast where the construction project is construed more narrowly, a court is likely to limit the scope of the design professional's duties accordingly. Thus, while the majority's narrow conception of construction projects dramatically curtails design professionals' statutory immunity under RCW 51.24.035(1), it does not necessarily advance the remedial purpose of the IIA, namely providing relief to injured workers.
¶ 58 In this case, I would hold that CH2M was negligent in preparing design plans and specifications. See RCW 51.24.035(2). Thus, I agree with the result the majority reached here. However, because immunity under RCW 51.24.035(1) does not apply to the negligent preparation of design plans and specifications, and because the majority held that CH2M's recommendations amounted to the negligent preparation of design plans and specifications, the majority had no need to reach RCW 51.24.035(1). See RCW 51.24.035(2); majority at 541-42. Thus, its construction of the terms "construction project" and "site of the construction project" is dictum. Because I am concerned that the majority's strained reading of RCW 51.24.035(1) was not only gratuitous but also in conflict with the statutory text, I cannot endorse the majority's reasoning.
WE CONCUR: GERRY L. ALEXANDER and JAMES M. JOHNSON, Justices.
Note, Architectural Malpractice: A Contract-Based Approach, 92 HARV. L.REV. 1075, 1094-95 (1979) (footnotes omitted). Read against this backdrop, the immunity statute makes a great deal of sense. It protects architects and similar professionals from liability for work site injuries not caused by their own negligence, but not for injuries that stem from their own professional work.
Kan. Stat. Ann. § 44-501(f). Like Washington's statute, it provides that design professionals are liable for their own negligence in drawing up plans or specifications, but not, absent a contract so providing, responsible for work site safety. Cf. RCW 51.24.035.
CP at 3115-16.