EMMET G. SULLIVAN, District Judge.
Plaintiff Sierra Club brought this action alleging that the Department of Agriculture's Rural Utilities Service ("RUS") and certain officials in the Department of Agriculture (collectively, "the federal defendants") violated the National Environmental Policy Act of 1969 ("NEPA") by failing to produce an environmental impact statement in connection with its involvement in
On March 29, 2011, 777 F.Supp.2d 44 (D.D.C.2011), the Court granted plaintiff's motion for summary judgment, concluding that the federal defendants had violated NEPA. NEPA requires federal agencies to include an environmental impact statement ("EIS") "in every recommendation or report on proposals for legislation and other major Federal actions significantly affecting the quality of the human environment[.]" 42 U.S.C. § 4332(2)(C). "If any significant environmental impacts might result from the proposed agency action then an EIS must be prepared before the [agency] action is taken." Sierra Club v. Van Antwerp, 661 F.3d 1147, 1153 (D.C.Cir.2011) (internal quotations omitted). The Court found that the financial assistance given to Sunflower by RUS in the form of debt forgiveness and consent to a lien subordination, as well as RUS's approvals relating to the expansion of the power plant, amounted to a "major federal action" within the meaning of NEPA such that an EIS was required. 777 F.Supp.2d at 56-57.
The Court ordered the parties to submit supplemental briefing on the appropriate remedy. That issue is now before the Court. Upon consideration of the supplemental briefs, the responses and replies thereto, the applicable law, the entire record, and for the reasons set forth below, the Court will grant declaratory and limited injunctive relief and remand to the agency for any necessary further proceedings.
The factual background of this case is set forth in detail in the Court's March 29, 2011 Memorandum Opinion. Briefly stated, the Rural Electrification Administration (the predecessor agency to RUS) approved a loan and loan guarantees to Sunflower's predecessor in 1980 after an EIS was completed.
After the 1987 restructuring, the company was again unable to make payments on all of the promissory notes. Of particular concern, because the interest was capitalized on one class of notes, the principal owed to RUS on these notes had increased from the $98.3 million owed in 1987 to $413.9 million in 2002. Because the company was at risk of defaulting, Sunflower and its creditors elected to negotiate another restructuring. AR 00004-11. The 2002 corporate and debt restructuring (the "2002 Restructuring") divided the assets owned by Sunflower's predecessor between two new corporations, Sunflower Electric Power Corporation (the party to this action, "Sunflower") and the Holcomb Common Facilities ("HCF"). Significantly, Sunflower purchased the predecessor company's assets by issuing an entirely new set of notes to the holders of the old promissory notes. AR 00173-175. Although HCF did not issue new promissory notes, in exchange for the assets it received, RUS and the other creditors received a security interest in HCF and an assignment of annual rent payments from the use of certain related facilities. AR 00190. The 2002 Restructuring also affected the lien held by RUS. The agency agreed that it will, in the future, release portions of its lien, if and when a second generating plant ("Holcomb Unit 2") is developed. In exchange, Sunflower agreed to grant to RUS a security interest in the rent paid for the use of the relevant facilities.
In connection with the 2002 Restructuring, Sunflower also agreed to obtain approval from RUS before undertaking a variety of activities or entering certain types of contracts. Of particular significance to the issue presently before the Court, Sunflower agreed: (i) that it would not "enter into any agreement or other arrangements ... for the development of Holcomb Unit 2 without the prior written approval of RUS," and "[a]ny RUS approval will be on such terms and conditions as RUS, in its sole discretion, may require at such time" (AR 04391); and (ii) that it would not "enter into any agreement or arrangement ... for Holcomb Site Development... or for other use of the Holcomb Unit 1 site, the fair market value of which would exceed $1 million annually[,] without the prior written approval of RUS," and "[a]ny RUS approval will be on such terms and conditions as RUS, in its sole discretion, may require at such time" (AR 04391).
Since the 2002 Restructuring, Sunflower has sought approval from RUS on a number of occasions in accordance with the conditions outlined above. Most relevant
In addition, on July 26, 2007, RUS also provided Sunflower with a separate letter, referred to by the parties as the "Additional Consideration Letter." AR 08218-8216. The terms of the Additional Consideration Letter modified the earlier arrangement from 2002 whereby RUS and the other creditors had received a security interest in HCF and an assignment of annual rent payments for the use of certain facilities. Under the new terms, for each additional power plant being considered for the Holcomb site, RUS received an entirely new set of promissory notes.
The principal question before the Court in its March 29, 2011 Memorandum Opinion was whether NEPA applied to the actions taken by RUS in connection with the Holcomb Expansion Project.
For the reasons detailed in the Court's Memorandum Opinion, the Court concluded that RUS's involvement in the Holcomb Expansion Project constituted a major federal action, both in connection with the 2002 Restructuring and in connection with the approvals granted in 2007. In short, the Court held that, because RUS gave necessary approvals for the Holcomb Expansion Project and because RUS provided financial assistance to the project, the Holcomb Expansion Project was subject to "Federal control and responsibility," 40 C.F.R. § 1508.18, and therefore RUS's involvement amounted to a major federal action within the meaning of NEPA. Accordingly, by failing to prepare an EIS, the agency violated NEPA.
The sole remaining issue before the Court is the appropriate remedy. At the
According to plaintiff and the federal defendants, at the time of the 2007 approvals, the plans for the Holcomb Expansion Project called for three coal-fired electric generating units, each with a generating capacity of approximately 600-750 megawatts. Since then, however, Sunflower has revised the configuration and now has plans to construct only a single generating unit with a capacity of 875 megawatts. Accordingly, plaintiff and the federal defendants argue that — in light of the contractual arrangements between Sunflower and RUS that obligate Sunflower to seek approval from RUS for plans and agreements relating to the Holcomb expansion — Sunflower is obligated to seek new approvals in light of these drastic changes. The federal defendants, for example, assert that "[d]ue to the material changes in the development of the Holcomb Expansion Project ... RUS has concluded that its approvals and implementing documents require Sunflower to seek new approvals from RUS for the drastic changes to the Holcomb Expansion Project from the proposal RUS previously reviewed and approved in 2007." Fed. Defs.' Supp. Br. at 8. Similarly, Sierra Club asserts that "RUS has an affirmative role going forward because RUS will have to grant additional consents and approvals before the Expansion can lawfully proceed." Pl.'s Supp. Br. at 6. Accordingly, rather than asking the Court to vacate the 2002 restructuring or the 2007 approvals given by RUS in connection with the Holcomb Expansion Project, the plaintiff and the federal defendants ask that the Court simply order RUS to prepare an EIS on the Holcomb Expansion Project.
Sunflower, on the other hand, asserts that the 2007 approvals that it obtained from RUS are still valid, and it need not seek additional approvals before proceeding with the construction of an additional power plant. In particular, Sunflower argues that the relevant agreements "clearly provide for the possibility that anywhere from zero to three new [generating] units could be constructed at Holcomb, and that new generating units could be smaller or larger than 700 MW." Sunflower's Supp. Br. at 7. According to Sunflower, "nothing has occurred to invalidate the 2007 RUS Approvals." Sunflower's Supp. Br. at 9. Sunflower takes the position that "[t]he only appropriate relief in this case is to enter a declaratory judgment setting forth how RUS violated NEPA and to remand to RUS to determine what further action, if any, is appropriate[.]" Sunflower's Supp. Br. at 3.
The Court has authority to grant an injunction to remedy a NEPA violation.
In the instant case, the plaintiff and the federal defendants essentially agree upon two proposals for injunctive relief against RUS. First, the parties ask that the Court order RUS to immediately conduct a review of the Holcomb Expansion Project, including the preparation of an EIS. Specifically, the plaintiff asks that the Court order RUS "to commence forthwith preparation of a legally valid environmental impact statement ... evaluating the impacts of, and alternatives to, further approval or support for the Holcomb Expansion Project." Pl.'s Proposed Order. Similarly, the federal defendants propose that the Court enter an order first directing Sunflower "to seek approval from RUS for the newly proposed 895 MW Holcomb Expansion Project" and then order RUS "to conduct its review of the changes to the configuration of the Holcomb Expansion Project as a `major federal action' within the meaning of 40 C.F.R. § 1508.18 and, for purposes of NEPA and RUS's implementing regulations, to conduct its review of the revised Holcomb Expansion Project as a generation project receiving federal financial assistance from RUS[.]" Fed. Defs.' Proposed Order.
Second, the parties request that the Court enter a prospective injunction that would direct RUS to perform an EIS before proceeding with any future actions in connection with the Holcomb Expansion Project. The language proposed by plaintiff would enjoin RUS "from taking any action, including any approval of or consent to Sunflower's actions pursuant to the governing loan contracts, in support of the Holcomb Expansion Project" until after an EIS is completed. Pl.'s Proposed Order. The federal defendants propose similar language, suggesting that the Court order RUS "not to issue any approvals or consents for agreements or arrangements directly related to the Holcomb Expansion Project" until RUS conducted its review of the project. Fed. Defs.' Proposed Order.
With respect to the first of the parties' proposals, namely one that would essentially order an immediate EIS, the Court finds that such an injunction is not appropriate for the following reasons. First, the Court is not aware of any proposals for any type of major federal action related to the Holcomb Expansion Project presently being considered by RUS. The Court, in its March 29, 2011 Memorandum Opinion concluded that "RUS's involvement in the Holcomb Expansion Project constituted a major federal action, both in connection with the 2002 Restructuring and in connection with the approvals granted in 2007[.]" 777 F.Supp.2d at 57. However, the record does not reflect that the agency is presently considering a similar major federal action. Plaintiff and the federal defendants both propose that the Court enter an injunction that would require the agency to perform an EIS for
Plaintiff and the federal defendants request that the Court remedy this problem by simply entering an order requiring Sunflower to seek additional approval from RUS. Then RUS would have a "major federal action" for which an EIS would be necessary. The plaintiff proposes that the Court "declare[] that previous consents and approvals that specifically reference one or more 600 to 700 MW coal-fired generation facilities do not constitute approval for the current configuration of the Holcomb Expansion Project, and that Sunflower will need additional approval from RUS before taking any additional action with respect to the Project." Pl.'s Proposed Order. The federal defendants similarly propose that the Court order Sunflower "to seek approval from RUS for the newly proposed 895 MW Holcomb Expansion Project." Fed. Defs.' Proposed Order. However, although the federal defendants have made it clear that they consider the 2007 approvals to be insufficient in light of subsequent changes to the scope of the proposed Project, and have taken the position that Sunflower will need to seek additional approvals before proceeding with the Holcomb Expansion Project, the continuing validity of the 2007 approvals is simply not before the Court in this action.
The federal defendants' primary argument in this respect is that Sunflower signed a settlement agreement in May 2009 with the State of Kansas that drastically altered the plans for the Holcomb Expansion Project. (For example, as noted above, instead of three 700 MW generating units, the settlement calls for the construction of a single 895 MW generating unit.) The federal defendants assert that Sunflower failed to consult with or seek approval from RUS before signing the settlement agreement with the State of Kansas and argue that Sunflower should now be ordered to seek such approval. The plaintiff similarly reasons that the existing agreements between RUS and Sunflower will require Sunflower to seek approvals from RUS in the future, and the failure by Sunflower to obtain RUS approval before entering into the settlement with the State of Kansas constituted a breach of their existing contractual obligations.
The plaintiff and the federal defendants would have the Court, at this late stage in the proceedings, delve into the question of whether Sunflower is presently in breach of its contractual obligations toward RUS, based largely on Sunflower's actions in 2009, a full two years after this action was commenced. While RUS has clearly taken the position that Sunflower is, or will be, in breach of its contractual obligation to seek approvals from RUS for certain actions, that question is not properly before this Court. Accordingly, an injunction directing Sunflower to immediately seek approval from RUS is inappropriate at this juncture.
This brings the Court to the next proposal, again supported by both the plaintiff and the federal defendants, for an injunction that would essentially direct RUS to refrain from granting any approvals, financial support or take any other major federal action in connection with the
The Court concludes that plaintiff has met its burden. First, plaintiff has sufficiently demonstrated irreparable harm. Plaintiff argues that "the Holcomb Expansion will emit substantial quantities of air pollutants that endanger human health and the environment" and thereby cause irreparable harm. Pl.'s Supp. Reply Br. at 14. In support of its position, plaintiff relies upon the affidavits submitted in support of its motion for a preliminary injunction, particularly that of Dr. Jonathan Levy, an Associate Professor of Environmental Health and Risk Assessment at the Harvard School of Public Health.
Dr. Levy begins broadly with the assertion that "[c]oal-fired power plants emit a number of pollutants of potential concern for public health, including fine and coarse particulate matter, sulfur dioxide, nitrogen oxides, volatile organic compounds, mercury, and other hazardous air toxics." Levy Decl. ¶ 4. He then discusses certain pollutants in detail. For example, Dr. Levy considers particulate matter pollution, defined as "a broad class of chemically and physically diverse substances that exist as discrete particles (liquid droplets or solids) over a range of sizes." Levy Decl. ¶ 5. Particulate matter pollution can be classified by particle size, and Dr. Levy explains that "PM
Similarly, Dr. Levy states that coal-burning power plants are the "largest human-cause source of mercury emissions to the air in the United States," and that "[i]t is my opinion that construction and operation of the proposed unit at the Holcomb site in Kansas would increase concentrations of mercury in the air, which may then be deposited locally or carried great distances. Once this mercury enters the water, it will pose health risks to persons exposed to it[.]" Levy Decl. ¶¶ 29-30. Plaintiff also relies upon the declaration of Dr. Johannes Feddema, a climate researcher, for an analysis of the increased carbon dioxide emissions associated with
Sunflower's main argument in opposition appears to be that emissions from the planned 894 MW generating unit "will be significantly below those of the average U.S. coal facility[.]" Sunflower's Supp. Br. at 20. In support of this assertion, Sunflower has submitted an affidavit of Scott Bloomberg, a consultant with expertise in "the electric sector, including new investment options (generation choice), environmental risk and compliance, climate policy, transmission, renewable portfolio standards and fuel markets." Bloomberg Aff. ¶ 2. Sunflower also asserts that the Holcomb Expansion Project "has already undergone, and continues to undergo, extensive environmental review of its impact on the air, water, land, endangered species, and human health in order to obtain the various permits and approvals required to operate," and that the Kansas Department of Health and Environment has already evaluated the potential hazardous air pollutant output for the plant. Sunflower's Supp. Br. at 20.
Even assuming Sunflower's assertions to be true, neither adequately counters the declaration of Dr. Levy, which contains specific, detailed estimates of various pollutants that would be emitted by the Holcomb site and the resulting harms. Whether or not some other coal facility emits greater quantities of particulate matter or mercury, for example, has no bearing on whether or not there will be irreparable harm here. Although Sunflower does dispute plaintiff's assertion that one coal facility will create a sufficient quantity of carbon dioxide emissions to have a measurable impact on the climate, Sunflower fails to offer any persuasive evidence that would counter plaintiff's detailed submissions on other pollutants.
With respect to the second factor, neither Sunflower nor defendant disputes "that remedies available at law, such as monetary damages, are inadequate to compensate for th[e] injury," Monsanto, 130 S.Ct. at 2756, and the Court concurs that such a remedy is not available. As the Supreme Court has explained, "[e]nvironmental injury, by its nature, can seldom be adequately remedied by money damages[.]" Amoco Prod. Co. v. Village of Gambell, 480 U.S. 531, 545, 107 S.Ct. 1396, 94 L.Ed.2d 542 (1987).
This brings the Court to the third and fourth factors, which consider the balance of hardships and the public interest. Here, in light of the limited injunction being considered, namely a prospective injunction that would require RUS to perform an EIS before granting approvals or giving financial assistance to Sunflower in connection with the Holcomb Expansion Project, the balance of equities tips in plaintiff's favor.
Finally, Sunflower argues that the public interest is best served by rejecting injunctive relief, citing to the interests of RUS in carrying out its duties and the interests of energy consumers, particularly rural consumers. Sunflower's Supp. Br. at 23-24. However, once again Sunflower's arguments do not address how a delay in the construction of the Holcomb Expansion Project that may be necessary to allow the agency to conduct an EIS will prejudice these interests. On the other hand, the public has an interest in ensuring that federal agency actions taken in connection with the building of coal-fired power plants comply with the requirements of NEPA.
Accordingly, the Court concludes that limited injunctive relief is warranted. Specifically, an order directing RUS not to issue any approvals or consents for agreements or arrangements directly related to the Holcomb Expansion Project, or to take any other major federal actions in connection with the Holcomb Expansion Project, until an EIS is complete, is appropriate.
In addition to an injunction against RUS, plaintiff requests an injunction against Sunflower. Plaintiff has proposed
Plaintiff argues that an injunction against Sunflower is necessary for two reasons. First, plaintiff asserts that if Sunflower were to initiate any construction activity, it would "significantly undermine" the NEPA process and would violate 40 C.F.R. § 1506.1.
In support of its position, plaintiff relies on Foundation on Economic Trends v. Heckler, 756 F.2d 143, 155 (D.C.Cir.1985), in which the D.C. Circuit held that "it is well established that judicial power to enforce NEPA extends to private parties where non-federal action cannot lawfully begin or continue without the prior approval of a federal agency. Were such non-federal entities to act without the necessary federal approval, they obviously would be acting unlawfully and subject to injunction." Id. (internal citations and quotation marks omitted).
The problem with plaintiff's position is that, particularly given the breadth of plaintiff's proposed injunction against Sunflower, plaintiff has not shown that all of the non-federal action it seeks to enjoin "cannot lawfully begin or continue without the prior approval of a federal agency." Id. (emphasis added). In Foundation on Economic Trends, the court affirmed a preliminary injunction enjoining the National Institutes of Health ("NIH"), a federal agency, from approving an experiment that would release genetically engineered organisms into the open environment until an appropriate environmental assessment was complete. Id. In so doing, the Circuit explained that, because federal regulations required that any entity seeking to deliberately release such organisms obtain approval from the NIH before doing so, "the [non-federal party] cannot lawfully go forward with its experiment, and it can thus be enjoined by the court." Id.
Here, however, unlike the plaintiff in Economic Trends, plaintiff has failed to demonstrate that all of the "non-federal action" envisioned by such a broad injunction "cannot lawfully begin or continue without the prior approval of a federal agency." Found. on Econ. Trends, 756 F.2d at 155. This proposed injunction is flawed for the same reasons that the proposed injunction ordering RUS to immediately begin an EIS is flawed. In order for such an injunction to be appropriate, the Court would need to determine that the previous consents and approvals granted
The final question before the Court is whether the agency action, specifically the 2002 restructuring and the 2007 approvals, must be vacated. The Administrative Procedure Act ("APA") provides that the reviewing court "shall ... hold unlawful and set aside agency action ... found to be ... arbitrary, capricious, an abuse of discretion, otherwise not in accordance with law[.]" 5 U.S.C. § 706. While vacatur may be the default remedy for a NEPA violation, the Court is not without discretion. "The decision whether to remand or vacate `depends on [1] the seriousness of the order's deficiencies (and thus the extent of doubt whether the agency chose correctly) and [2] the disruptive consequences of an interim change that may itself be changed.'" Milk Train, Inc. v. Veneman, 310 F.3d 747, 755-756 (D.C.Cir.2002) (quoting Allied-Signal, Inc. v. U.S. Nuclear Regulatory Comm'n, 988 F.2d 146, 150-51 (D.C.Cir.1993)).
In Sugar Cane Growers Cooperative of Florida v. Veneman, 289 F.3d 89 (D.C.Cir. 2002), for example, this Circuit held that the Department of Agriculture failed to comply with certain provisions of the APA when it implemented a "payment-in-kind" program for sugar, essentially offering sugar beet farmers an incentive to destroy a certain amount of their crops. Rather than vacate the agency action, however, the court ordered a remand to the agency, explaining that:
Id. at 97-98 (internal citations and quotation marks omitted).
Similarly, in Milk Train, Inc. v. Veneman, milk producers challenged a subsidy program implemented by the Department of Agriculture. Although the court found flaws in the subsidy program, the court concluded that "there is at least `a serious possibility' that the Secretary on remand could explain [the subsidy program] in a manner that is consistent with the statute or choose an allocation method to correct the problem, a factor that favors remanding rather than vacating." 310 F.3d at 756.
In the instant case, the Court is persuaded that injunctive relief requiring RUS to perform an EIS before any future approvals or consents are given or any other major federal action taken related to the Holcomb Expansion Project, coupled with the federal defendants' own emphatic conclusion that Sunflower must seek additional approvals from RUS before the Holcomb Expansion Project can proceed, create more than "a serious possibility" that RUS will be able to correct the problem caused by the earlier failure to comply
Next, the Court must consider the "the disruptive consequences of an interim change that may itself be changed[.]" Milk Train, Inc., 310 F.3d at 756. Even plaintiff states that "[o]n the complicated facts of this case ... the `default remedy' of vacatur of the 2002 and 2007 decisions is unnecessary" Pl.'s Supp. Br. at 5.
The Court need not reach the question of whether, standing alone, the disruption described by Sunflower is enough to counsel against vacatur. However, in combination with RUS's stated position that Sunflower will need to seek additional approvals from RUS (subject to an EIS), the Court concludes that vacating the 2007 approvals is not warranted in the instant case.
For the foregoing reasons, the Court hereby