MARY F. WALRATH, Bankruptcy Judge.
Before the Court is the Motion of ArcelorMittal Ostrava a.s. (formerly Nova Hut, a.s.) ("Nova Hut") (1) to lift the stay and confirm a 2016 arbitration award and (2) to dismiss with prejudice all claims against Nova Hut set forth in the Third Amended Complaint. Kaiser Group International, Inc. ("Kaiser International") and Kaiser Engineers, Inc. ("Kaiser Engineers") (collectively, the "Debtors") oppose the motion, asserting that the Court has grounds to refuse to enforce the arbitration award. For the reasons set forth below, the Court will grant Nova Hut's Motion.
In 1997, Nova Hut and ICF Kaiser Netherlands B.V. ("Kaiser Netherlands"), a non-debtor wholly-owned subsidiary of Kaiser International, entered into an agreement (the "Agreement") whereby Kaiser Netherlands agreed to design and construct phase I of a steel mill at Nova Hut's facility in Ostrava, Czech Republic. Under the Agreement, the steel mill was required to pass a mandatory quality and quantity standards performance test. Kaiser International guaranteed Kaiser Netherlands' performance under the Agreement and pledged its assets as collateral for a letter of credit (the "Performance Letter of Credit"), which required annual renewal. Nova Hut financed the project with funds loaned to it by the International Finance Corporation ("IFC"). In exchange for the loan, IFC obtained a conditional assignment of Nova Hut's rights under the Agreement.
On June 9, 2000, the Debtors, but not Kaiser Netherlands, filed petitions for relief under chapter 11 of the Bankruptcy Code. In late 2000 the steel plant underwent a production performance test. Nova Hut asserted that it failed; Kaiser Netherlands asserted that it passed. Subsequently, Kaiser Netherlands refused to renew the Performance Letter of Credit, and on February 16, 2001, Nova Hut drew $11.1 million on the Performance Letter of Credit.
On April 9, 2001, the Debtors commenced the instant adversary proceeding by filing a complaint against Nova Hut and IFC (collectively, the "Defendants"), alleging breach of contract and seeking,
Early in the proceeding, the Defendants moved to stay the adversary proceeding and compel arbitration, or alternatively, to dismiss the Complaint. (Adv. D.I. 8, 11, 32, & 37.) Before the motions to dismiss could be decided, the Debtors filed a Second Amended Complaint. (Adv. D.I. 74.) The Defendants thereupon moved to dismiss the Second Amended Complaint. (Adv. D.I. 94, 105.) On October 18, 2002, the Court denied the Defendant's motions to stay the adversary proceeding and to dismiss the Second Amended Complaint. (Adv. D.I. 145.)
On October 21, 2002, the Debtors filed a Third Amended Complaint. The Third Amended Complaint asserted: (1) claims for the return of the $11.1 million drawn on the Performance Letter of Credit under theories of breach of warranty, breach of contract, unjust enrichment, and
On October 28, 2002, the Defendants each filed a motion for reconsideration of the Order denying their requests to stay the adversary proceeding and compel arbitration, or alternatively, to dismiss the Third Amended Complaint. (Adv. D.I. 147, 148, 154 & 155.) On January 6, 2003, the Court denied the motions for reconsideration, and the Defendants appealed. (Adv. D.I. 214, 217 & 218.)
On March 18, 2004, the District Court reversed, stayed the adversary proceeding, and granted Nova Hut's request to compel arbitration.
In the interim, on January 2, 2004, Kaiser Netherlands filed a Request for Arbitration against Nova Hut with the International Chamber of Commerce, International Court of Arbitration (the "ICC"). In that arbitration, Kaiser Netherlands asserted similar claims against Nova Hut as the Third Amended Complaint had. Nova Hut asserted counterclaims against Kaiser Netherlands for breach of the Agreement.
On April 26, 2006, the ICC issued a final award (the "2006 Arbitration Award") concluding that Kaiser Netherlands had failed to build the steel mill in accordance with the performance requirements of the Agreement and that, as a result, Nova Hut was entitled to draw on the Performance Letter of Credit. However, the ICC granted Kaiser Netherlands' claims for $3.5 million for the contingency fee and warranty reserve related to the Memorandum of Understanding and $510,000 in project development costs related to the Letter of Intent.
On December 13, 2006, Nova Hut filed a motion in the instant adversary proceeding to lift the automatic stay and grant summary judgment in its favor on res judicata and collateral estoppel grounds based on the 2006 Arbitration Award. (Adv. D.I. 274.) On January 25, 2007, the Debtors filed a cross-motion for partial summary judgment. (Adv. D.I. 279.) By Opinion and Order dated September 7, 2007, the Court denied the cross-motions for summary judgment, finding a disputed issue of material fact, namely whether the Debtors were in privity with Kaiser Netherlands, such that the award against Kaiser Netherlands would be an award against the Debtors.
In connection with the summary judgment motions, the Debtors also filed a motion for an oral examination and production of documents from IFC, Nova Hut and related parties or, alternatively, an equitable bill of discovery (the "Discovery Motion"). (Adv. D.I. 283.) At the hearing held on April 25, 2007, the Court ruled that the disputes between the parties were subject to arbitration and that, therefore, any discovery relating to those disputes should be conducted in accordance with the applicable arbitration rules. (Adv. D.I. 334.) As a result the Court denied the Discovery Motion. (Adv. D.I. 328.) The Debtors filed a motion for an interlocutory appeal, which was denied by the District Court on January 29, 2009.
Thereafter, on April 6, 2010, the Debtors initiated two separate foreign arbitrations with the ICC, one against IFC (the "IFC Arbitration") and another against Nova Hut (the "Nova Hut Arbitration").
In the IFC Arbitration, the Debtors asserted that IFC had tortiously interfered with the performance guarantee between Kaiser International and Nova Hut regarding the Performance Letter of Credit. The IFC Tribunal found that those claims were not barred by the statute of limitations, but found in favor of IFC on the merits of the underlying claim (the "IFC Award"). (Adv. D.I. 405, Ex. A.) On January 27, 2014, on motion of IFC, the Court confirmed the IFC Award and dismissed IFC from the adversary proceeding. (Adv. D.I. 405.)
Contemporaneously, the Debtors proceeded with the Nova Hut Arbitration proceeding. The Debtors brought claims relating to the Performance Letter of Credit, but did not bring claims relating to the Letter of Intent or the Memorandum of Understanding. On November 13, 2015, the Nova Hut Tribunal heard oral argument on whether the statute of limitations barred the Debtors' claims. On March 29, 2016, the Nova Hut Tribunal found that the statute of limitations barred the Debtors' claims and awarded Nova Hut costs (the "Nova Hut Award"). The Nova Hut Tribunal refused to toll the statute of limitations:
(Adv. D.I. 426, Ex. C, ¶¶ 162-63.)
On July 7, 2017, Nova Hut filed the instant Motion (1) to lift the stay of these proceedings to confirm the Nova Hut Award against the Debtors and (2) to dismiss with prejudice all counts set forth in the Third Amended Complaint. (Adv. D.I. 426.) A notice of completion of briefing was filed on October 29, 2017, and this matter is now ripe for decision. (Adv. D.I. 430.)
The Court has jurisdiction over this adversary proceeding. 28 U.S.C. § 157(b)(2)(G). The Court has the power to enter an order on a motion to dismiss even if the matter is non-core or the Court lacks authority to enter a final order on the merits.
The Convention on the Recognition and Enforcement of Foreign Arbitral Awards (the "Convention") governs the enforcement of foreign arbitrations. June 10, 1958, 21 U.S.T. 2517, 330 U.N.T.S. 38 [hereinafter the "Convention"]; 9 U.S.C. § 201;
9 U.S.C § 207 (emphasis added).
Courts must confirm foreign arbitral awards falling under the Convention "except in very limited circumstances."
The grounds upon which a court may refuse to enforce a foreign arbitration are detailed in Article V of the Convention. Convention, art. V.;
Convention, art. V. (emphasis added). Courts must construe these defenses narrowly.
The Debtors argue they were unable to present their case because the Nova Hut Tribunal found that the claims were barred by the statute of limitations. Nova Hut responds that the Debtors had their day in court to argue their case and that arbitration claims dismissed on statute of limitations grounds are enforceable.
An Article V(1)(b) defense is akin to a "due process defense," and courts will only find a violation when a party was not given an opportunity to be heard at a meaningful time and in a meaningful manner.
The Court agrees with Nova Hut that the Debtors had a meaningful hearing. This case is distinguishable from the
In the instant case, the Nova Hut Tribunal did not inhibit the Debtors from presenting their statute of limitations argument. The Debtors concede that the Nova Hut Tribunal conducted oral argument on November 13, 2015, on the statute of limitations issue. The Debtors fully presented their case that the statute of limitations should be tolled. (Adv. D.I. 426, Ex. C, ¶ 118.) After weighing both parties' arguments, the Nova Hut Tribunal made a well-reasoned decision that the statute of limitations barred the claims. (Adv. D.I. 426, Ex. C, ¶¶ 83-172.)
The Debtors do not raise any flaws with the Nova Hut Arbitration proceeding, but simply challenge the Nova Hut Tribunal's legal conclusions. However to justify vacating an arbitration award, an error must not be "simply an error of law, but [one] which so affects the rights of a party that it may be said that [the party] was deprived of a fair hearing."
Any issues the Debtors had with respect to the underlying decision should have been made by appealing that decision through the proper channels. The Debtors chose not to appeal the Nova Hut Award. (Adv. D.I. 426, Ex. F, § 589.)
Therefore, the Court concludes that Article V(1)(b) does not provide grounds for the Court to refuse enforcement of the Nova Hut Award.
A court may also refuse enforcement of an award if "the arbitral procedure was not in accordance with the agreement of the parties" or the dispute was not "capable of settlement" by arbitration. Convention, art. V(1)(d); V(2)(a). The Debtors argue that both defenses apply because the Debtors never agreed to arbitration. Nova Hut responds that the District Court has already decided that the Debtors could only pursue their claims through arbitration.
The Court agrees with Nova Hut. The District Court expressly held that the Debtors may only pursue their claims against Nova Hut through international arbitration.
The Debtors argue that the Nova Hut Award is unenforceable because it is directly at odds with the IFC Award which held that the statute of limitations did not bar the Debtor's underlying claims against IFC. The Debtors argue that the same activity which the IFC Tribunal found tolled the three-year Austrian statute of limitations in the IFC Arbitration was determined by the Nova Hut Tribunal not to toll the same statute of limitations. The Debtors contend that when the IFC Award became a judgment of this Court in 2014, part of the confirmation was the finding that the statute of limitations should be tolled under Austrian law. (Adv. D.I. 405.)
Nova Hut responds that this argument fails to provide any grounds under Article V of the Convention for refusal to enforce an arbitration award.
The Court agrees with Nova Hut. As noted above, the Debtors provide no ground under the Convention for how a conflict between the Nova Hut Award and the IFC Award would bar the Court from enforcing either. Therefore, the Court declines to set aside the Nova Hut Award because the Debtors' argument is not enumerated in Article V of the Convention.
Nova Hut further notes that neither res judicata nor collateral estoppel bar enforcement of the Nova Hut Award because the parties to the IFC Award and the parties to the Nova Hut Award are different.
Res judicata is a judicial doctrine that precludes a party from relitigating claims that were or could have been asserted in an earlier action.
Under the doctrine of collateral estoppel, once a court of competent jurisdiction determines an issue, that determination is conclusive in subsequent ligation on a different cause of action against a party to the prior ligation.
Consequently, the Court will recognize and confirm the Nova Hut Award.
Nova Hut also asks the Court to lift the stay of the adversary proceeding and to dismiss the Third Amended Complaint. Nova Hut contends that Counts One, Two, Five, and Eight should be dismissed because the confirmation of the Nova Hut Award decided those claims. Nova Hut also contends that the Debtors waived the right to pursue the remainder of the claims in the Third Amended Complaint when they failed to bring them in the Nova Hut Arbitration. The Debtors do not respond to these arguments.
An order confirming an arbitration award, "shall be docketed as if it was rendered in an action" and "[t]he judgment so entered shall have the same force and effect, in all respects, as, and be subject to all the provisions of law relating to, a judgment in an action; and it may be enforced as if it had been rendered in an action in the court in which it is entered." 9 U.S.C. § 13; 9 U.S.C. § 208.
Counts One, Two, Five, and Eight of the Third Amended Complaint are claims for breach of warranty, breach of contract, unjust enrichment, and
Nova Hut further argues that the Court should dismiss the remaining claims, which relate to the Letter of Intent and Memorandum of Understanding, because the Debtors never raised them in the arbitration, even though the District Court directed the Debtors to arbitrate their claims against Nova Hut.
The Court agrees with Nova Hut. A waiver is the intentional relinquishment or abandonment of a known right or privilege.
For the foregoing reasons, the Court will grant Nova Hut's Motion (1) to lift the stay to confirm the Nova Hut Award and (2) to dismiss all counts alleged against Nova Hut in the Third Amended Complaint with prejudice.
An appropriate Order follows.