Elawyers Elawyers
Washington| Change

IN RE: TAMPA ELECTRIC COMPANY, POLK POWER STATION, POLK 2-5 COMBINED CYCLE CONVERSION PROJECT vs *, 12-003369EPP (2012)

Court: Division of Administrative Hearings, Florida Number: 12-003369EPP Visitors: 4
Petitioner: IN RE: TAMPA ELECTRIC COMPANY, POLK POWER STATION, POLK 2-5 COMBINED CYCLE CONVERSION PROJECT
Respondent: *
Judges: BRAM D. E. CANTER
Agency: Department of Environmental Protection
Locations: Bartow, Florida
Filed: Oct. 11, 2012
Status: Closed
Recommended Order on Friday, August 23, 2013.

Latest Update: Dec. 12, 2013
Summary: The issue to be determined in this proceeding is whether the Governor and Cabinet, sitting as the Siting Board, should certify the Polk 2-5 Combined Cycle Conversion Project (“Project”) of Tampa Electric Company ("TEC"), including its associated electrical transmission lines, subject to the proposed Conditions of Certification.It is recommended that the Siting Board certify the Project because it favorably satisfies all of the statutory factors that are to be considered under section 403.509(3),
More
TempHtml


STATE OF FLORIDA SITING BOARD


IN RE: TAMPA ELECTRIC COMPANY, )

POLK POWER STATION, POLK 2-5 ) OGC CASE NO. 12-1566 COMBINED CYCLE CONVERSION ) DOAH CASE NO. 12-3369EPP PROJECT, )

PPSA NO. 92-32-A3 )


FINAL ORDER APPROVING CERTIFICATION


An Administrative Law Judge (“ALJ”) with the Division of Administrative Hearings (“DOAH”) submitted a Recommended Order On Certification (“RO”) on August 23, 2013, in this certification proceeding. The RO indicates that copies were served upon counsel for Tampa Electric Company (“TEC”), counsel for the Department of Environmental Protection (“DEP” or “Department”), and counsel for Hillsborough County. The RO also shows that copies were served to counsel for other designated state, regional and local agencies. A copy of the RO is attached hereto as Exhibit A. On September 9, 2013, TEC and the Department filed a Joint Exception to the RO. This matter is now before the Governor and Cabinet, sitting as the Siting Board, for final action under the Florida Electrical Power Plant Siting Act (“PPSA”), Sections 403.501 et seq., Florida Statutes.

BACKGROUND


In this proceeding, TEC seeks certification of the Polk 2-5 Combined Cycle Conversion Project (“Project”), to be located within the existing boundaries of the previously certified Polk Power Station. The Polk Power Station is located in southwest Polk County, 17 miles south of the City of Lakeland and 28 miles southeast of the City of Tampa. The Polk Power Station has five electric generating units and associated



8


Filed December 11, 2013 4:47 PM Division of Administrative Hearings


facilities. Polk Units 2 through 5 are simple cycle combustion turbine generators fueled primarily with natural gas. The Project involves converting the four existing simple cycle combustion turbine generator units to combined cycle operation. The Project would be a four-on-one combined cycle unit consisting of the four existing combustion turbine generators, each combined with a new heat recovery steam generator, and a new steam turbine generator. The Project would increase ultimate site capacity for the Polk Power Station from the previously approved 1150 megawatts to 1420 megawatts.

TEC requests that the boundaries of the Polk Power Station site be reduced from 4,348 acres to 2,837 acres to reflect that the original certification required a donation of 1,511 acres to the Board of Trustees of the Internal Improvement Trust Fund as a wildlife management area and recreation area. The donation was completed in 2012.

The Project includes two new transmission line corridors. The proposed “Polk- Pebbledale Corridor” would be a 5.5-mile, single-circuit 230 kV transmission line from the Polk Power Station north to the Pebbledale substation in Polk County. The proposed “Polk-Fishhawk Corridor” would be a single-circuit 230 kV transmission line running west from the Polk Power Station to the Mines substation near the intersection of State Road 674 and County Road 39 in Hillsborough County; from there, north and then west again to connect to a new Aspen switching station to be located near the intersection of County Road 672 and Balm-Boyette Road; and from the Aspen station, two separate 230kV transmission lines would run northeast to the existing Fishhawk substation near the intersection of Fishhawk Boulevard and Boyette Road; a total length of 27 miles. TEC exercised its option under Section 403.5064(1)(b), Florida Statutes, to


allow parties to file alternate transmission line corridors. No alternate corridors were filed or reviewed in this proceeding.

TEC sought and obtained on January 8, 2013, from the Public Service Commission (“PSC”) a final order determining the need for the Project. The PSC determined that the most cost effective and reliable alternative to meet future power needs is the construction of the Project at the Polk Power Station. Among other findings, the PSC determined that the Project would improve fuel diversity and supply reliability, incorporate renewable energy and conservation factors, and is needed to maintain electric system reliability and integrity.

DOAH PROCEEDINGS


The DOAH proceeding was conducted under the PPSA to consider TEC’s application for certification of the Project. On October 4, 2012, TEC filed the site certification application (“Application”) with DEP. DEP transmitted the file to DOAH, on October 11, 2012, and by Notice of Hearing dated October 23, 2012, the ALJ scheduled the certification hearing for June 24-28, 2013. On December 17, 2012, DEP issued its determination that the Application was complete.

The various reviewing agencies submitted reports that recommended approval and certification of the Project. Some of the agencies also proposed conditions of certification. (RO ¶¶ 89-91). No agency opposed certification of the Project. (RO ¶ 94). On May 21, 2013, DEP issued its final Project Analysis Report (“PAR”), which incorporated the comments of the reviewing agencies. (RO ¶ 93). DEP recommended certification of the project, subject to a set of Conditions of Certification (“COCs”). See Department Exhibit 8; RO ¶ 95.


Hillsborough County, the Florida Fish and Wildlife Conservation Commission (“FWC”), and the Southwest Florida Water Management District (“SWFWMD”) each filed notices of intent to be parties. Of these agencies, only Hillsborough County appeared at the certification hearing. Hillsborough County also requested that a public hearing be held within its boundaries so that members of the public who were not parties to the certification hearing would have an opportunity to provide testimony regarding the proposed transmission line corridors. The request was granted and the public hearing was held on June 25, 2013. Public testimony was received and Public Testimony Composite Exhibit 1 was received into the record.

All notices required by law were timely published in accordance with Section 403.5115, Florida Statutes. The certification hearing was held on June 26, 2013. At the conclusion of the hearing, the parties were allowed to file proposed recommended orders (“PROs”). The Transcript of the final hearing was filed with the DOAH on July 12, 2013. The ALJ subsequently issued the RO on August 23, 2013.

SUMMARY OF THE RECOMMENDED ORDER


In the RO, the ALJ recommended that the Siting Board enter a Final Order: (a) approving TEC’s Application to construct, operate, and maintain the Project, including its associated transmission lines, subject to the Conditions of Certification set forth in Department Exhibit 8; (b) approving the increase in ultimate site capacity from the previously approved 1150 megawatts to 1420 megawatts; and (c) modifying the Polk Power Station site boundaries from 4,348 acres to 2, 837 acres, as depicted in TEC Exhibit 5. (RO at page 32).


The ALJ found that the parties stipulated that “there are no disputed issues of fact,” (RO ¶ 1), and “there are no disputed issues of law.” (RO ¶ 106). The ALJ concluded that the evidence presented in this proceeding demonstrated that the Project favorably satisfied all of the factors in Section 403.509(3), Florida Statutes, that the Siting Board must consider in determining whether to certify the Project. (RO ¶¶ 98-105, 110).

RULINGS ON EXCEPTIONS


The case law of Florida holds that parties to formal administrative proceedings must alert reviewing agencies to any perceived defects in DOAH hearing procedures or in the findings of fact of ALJs by filing exceptions to DOAH recommended orders. See, e.g., Comm'n on Ethics v. Barker, 677 So.2d 254, 256 (Fla. 1996).

JOINT EXCEPTION


TEC and DEP take exception to lines 3 and 6 of paragraph 36 of the RO, where the ALJ found that the “Polk-Pebbledale Corridor” and “Polk-Fishhawk Corridor” are “250 kV” transmission lines. TEC and DEP state that the ALJ’s reference appears to be a typographical error because the competent substantial record evidence shows that the Polk-Pebbledale and Polk-Fishhawk Corridors are each 230 kilovolt transmission lines. (Lukcic, Tr. p. 24, lines 22-25; p. 25, lines 1-17; TEC Exhibit 4).

Section 120.57(1)(l), Florida Statutes, prescribes that an agency reviewing a recommended order may not reject or modify the findings of fact of an ALJ, “unless the agency first determines from a review of the entire record, and states with particularity in the order, that the findings of fact were not based on competent substantial evidence.”

§ 120.57(1)(l), Fla. Stat. (2010); Charlotte County v. IMC Phosphates Co., 18 So.3d


1089 (Fla. 2d DCA 2009); Wills v. Fla. Elections Comm’n, 955 So.2d 61 (Fla. 1st DCA 2007). The ALJ’s findings that the “Polk-Pebbledale Corridor” and “Polk-Fishhawk Corridor” are each “250 kV” transmission lines, are not supported by competent substantial evidence.

Therefore, based on the foregoing reasons, TEC and DEP’s Joint Exception is granted.

CONCLUSION


The ALJ concluded that the evidence demonstrated that the Project satisfied all of the factors in Section 403.509(3), Florida Statutes; and recommended that the Siting Board enter a Final Order approving the Project subject to the Conditions of Certification. (RO ¶ 110; page 32).

Having reviewed the matters of record and being otherwise duly advised, the Siting Board adopts the ALJ’s recommendation.

It is therefore ORDERED that:


  1. The Recommended Order (Exhibit A) is adopted in its entirety, except as modified by any rulings in this Final Order, and is incorporated by reference herein.

  2. TEC’s Application for Certification to construct, operate, and maintain the Polk 2-5 Combined Cycle Conversion Project, including its associated transmission lines, is APPROVED, subject to the Conditions of Certification set forth in Department Exhibit 8, attached hereto as Exhibit B;

  3. TEC’s request to increase the ultimate site capacity for the Polk Power Station site from the previously approved 1150 megawatts to 1420 megawatts, is APPROVED; and


Docket for Case No: 12-003369EPP
Issue Date Proceedings
Dec. 12, 2013 Tampa Electric Company's and Florida Department of Environmental Protection's Joint Exceptions to Recommended Order filed.
Dec. 11, 2013 Conditions of Certification filed.
Dec. 11, 2013 Agency Final Order filed.
Sep. 09, 2013 Tampa Electric Company's and Florida Department of Environmental Protection's Joint Exception to Recommended Order filed.
Aug. 23, 2013 Recommended Order On Certification (hearing held June 25-26, 2013). CASE CLOSED.
Aug. 23, 2013 Recommended Order cover letter identifying the hearing record referred to the Agency.
Aug. 07, 2013 Order Granting Motion.
Aug. 06, 2013 Motion to Supplement TEC/FDEP Exhibit 4 filed.
Aug. 06, 2013 Notice of Filing Tampa Electric Company's and Florida Department of Environmental Protection's Joint Proposed Recommended Order on Certification filed.
Aug. 05, 2013 Order (granting request for authorization to exceed page limit).
Aug. 02, 2013 Request for Authorization to Exceed Page Limitation filed.
Jul. 12, 2013 Transcript of Proceedings (not available for viewing) filed.
Jul. 12, 2013 Transcript (not available for viewing) filed.
Jul. 12, 2013 Notice of Filing Transcripts of Certification Hearing filed.
Jun. 28, 2013 Petitioner's Proposed Exhibits filed (exhibits not available for viewing).
Jun. 25, 2013 CASE STATUS: Hearing Held.
Jun. 24, 2013 Notice of Filing Revised Proposed Conditions of Certification filed.
Jun. 19, 2013 Notice of Availability and Distribution of Pre-filed Direct Testimony and Exhibits (exhibits not available for viewing) filed.
Jun. 19, 2013 Notice of Availability and Distribution of Pre-filed Direct Testimony and Exhibits filed.
Jun. 10, 2013 Order.
Jun. 07, 2013 Prehearing Stipulation filed.
Jun. 05, 2013 Amended Notice of Hearing (hearing set for June 26, 2013; 10:00 a.m.; Bartow, FL; amended as to dates and hearing locations).
Jun. 04, 2013 Stipulation and Joint Motion to Adjust Hearing Schedule filed.
May 21, 2013 Notice of Filing Revised Project Analysis Report for Plant Portion of Project filed.
Apr. 26, 2013 Notice of Filing Project Analysis Report for Plant Portion of Project filed.
Mar. 25, 2013 Southwest Florida Water Management District's Notice of Filing District Agency's Report filed.
Mar. 25, 2013 Florida Fish and Wildlife Conservation Commission Notice of Intent to be Party filed.
Mar. 11, 2013 Southwest Florida Management District's Notice of Intent to be Party filed.
Jan. 28, 2013 Notice of Filing Project Analysis Report for Transmission Line Portion of Project filed.
Dec. 26, 2012 Order Amending Certification Proceeding Schedule.
Dec. 21, 2012 Amended Stipulation and Joint Motion to Alter Schedule [amended to correct scriveners error in proposed schedule] filed.
Dec. 21, 2012 Stipulation and Joint Motion to Alter Schedule (proposed schedule attached) filed.
Dec. 21, 2012 Stipulation and Joint Moton to Alter Schedule filed.
Dec. 17, 2012 Department of Environmental Protection?s Determination that Power Plant and Transmission Line Portions of Application are Complete filed.
Dec. 07, 2012 Order (granting Hillsborough County's request to become a party).
Dec. 07, 2012 Hillsborough County's Request to Become a Party to Tampa Electric Company's Polk Power Station 2-5 Combined Cycle Conversion Project Site Certification Hearing filed.
Dec. 03, 2012 Polk Power Station 2-5 Combined Cycle Conversion Project Completeness Submittal-Power Plant and Transmission Lines filed.
Nov. 29, 2012 Notice of Public Hearing.
Nov. 26, 2012 Tampa Electric Company's Response to Department of Environmental Protection's Determination that Power Plant and Transmission Line Portions of Site Certification Application are Incomplete filed.
Nov. 26, 2012 Hillsborough County's Request for a Public Hearing Supplementing the Certification Hearing filed.
Nov. 13, 2012 Department of Environmental Protection's Determination that Power Plant and Transmission Line Portions of Application are Incomplete filed.
Oct. 23, 2012 Order of Pre-hearing Instructions.
Oct. 23, 2012 Notice of Hearing (hearing set for June 24 through 28, 2013; 9:00 a.m.; Bartow, FL).
Oct. 23, 2012 Order Establishing Certification Proceeding Schedule.
Oct. 19, 2012 Response to Initial Order filed.
Oct. 16, 2012 Initial Order.
Oct. 15, 2012 Notice of Filing Site Certification Application for Power Plant Certification filed.
Oct. 11, 2012 Polk 2-5 Combined Cycle Conversion Project, Polk Power Station Site Certification Application Volumes 1 and 2, filed.
Oct. 11, 2012 Department of Environmental Protection's Request for Assignment of Administrative Law Judge filed.
Oct. 11, 2012 Proposed Initial Schedule filed.
Oct. 11, 2012 Notice of Additional Agencies Entitled to Copies of the Application and Amendments filed.

Orders for Case No: 12-003369EPP
Issue Date Document Summary
Dec. 11, 2013 Agency Final Order
Aug. 23, 2013 Recommended Order It is recommended that the Siting Board certify the Project because it favorably satisfies all of the statutory factors that are to be considered under section 403.509(3), Florida Statutes.
Source:  Florida - Division of Administrative Hearings

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer