Elawyers Elawyers
Washington| Change

GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC., 18-2972 (2019)

Court: District Court of Appeal of Florida Number: 18-2972 Visitors: 8
Filed: Aug. 28, 2019
Latest Update: Mar. 03, 2020
Summary: DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT GRACE AND NAEEM UDDIN, INC., a Florida corporation, Appellant, v. SINGER ARCHITECTS, INC., BROWARD COUNTY, and ARCH INSURANCE COMPANY, Appellees. No. 4D18-2972 [August 28, 2019] Appeal from the Circuit Court for the Seventeenth Judicial Circuit, Broward County; John B. Bowman, Judge; L.T. Case No. 14-004946 (05) and 13-013834 CACE (02). David R. Elder and Kerry H. Lewis of Elder & Lewis, P.A., Miami, for appellant. Neil P. Robertso
More
          DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA
                                 FOURTH DISTRICT

          GRACE AND NAEEM UDDIN, INC., a Florida corporation,
                           Appellant,

                                        v.

       SINGER ARCHITECTS, INC., BROWARD COUNTY, and ARCH
                     INSURANCE COMPANY,
                            Appellees.

                                 No. 4D18-2972

                                [August 28, 2019]


   Appeal from the Circuit Court for the Seventeenth Judicial Circuit,
Broward County; John B. Bowman, Judge; L.T. Case No. 14-004946 (05)
and 13-013834 CACE (02).

  David R. Elder and Kerry H. Lewis of Elder & Lewis, P.A., Miami, for
appellant.

  Neil P. Robertson of Daniels Rodriguez Berkeley Daniels & Cruz, P.A.,
Coral Gables, for appellees.

MAY, J.

   Whether a supervising architect owes a duty of care to a contractor
hired by the county for an airport improvement project is the question
asked in this appeal. The contractor argues the trial court erred in failing
to apply Moyer 1 and granting final summary judgment for the architect.
We agree and reverse.

    The county entered into separate contracts with the architect and the
contractor for the development of an improvement project at the Fort
Lauderdale Airport. The county’s contract with the architect assigned the
latter with consultant and administrative duties. The county’s contract
with the contractor concerned the scope of work and the architect’s role
as a consultant and administrator.


1   A.R. Moyer v. Graham, 
285 So. 2d 397
(Fla. 1973).
    As the project neared completion, the county terminated its contract
with the contractor. The contractor filed suit against the county and the
architect claiming breach of contract and professional negligence,
respectively. The trial court consolidated the actions for discovery and
trial.

   The architect moved for partial summary judgment, arguing it did not
owe the contractor a duty of care and the contractor could not recover
contract damages in tort. The trial court granted the architect’s motion,
concluding the architect did not owe the contractor a duty of care in its
role as the county’s consultant. From that partial summary judgment, the
contractor now appeals.

      •   The Architect/County Contract

   The contract between the architect and the county outlined the
architect’s role as “CONSULTANT SERVICES FOR MISCELLANEOUS
PROFESSIONAL ARCHITECT, ENGINEER, AND INTERIOR DESIGN
SERVICES.” The contract designated the architect as a “Consultant.”
Article 10.20 declared the parties’ intent not to “create any rights or
obligations in any third person or entity under this agreement.”

   Under Article 3, the “SCOPE OF SERVICES/TASKS/PHASES,” the
architect was responsible for:     (1) visiting the site and attending
construction events and meetings regularly; (2) conducting joint
observations of the work with the county; (3) informing the county of the
progress and quality of the work; (4) managing administrative records
outlined in the contract; (5) assisting the county in determining the
amounts owed to the contractor; and (6) certifying the contractor’s
evaluation for payment.

   The architect was to:

      (1) interpret and give recommendations on disputes arising
          between the county and contractor;

      (2) recommend rejection of work not in conformity with the
          contract;

      (3) review and act on the contractor’s “shop drawings, product
          data and samples”;

      (4) coordinate with the county to review “Change Orders for
          Code Compliance”;

                                    2
      (5) conduct site observations, make recommendations, and
          assist the county in determining the project’s completion;
          and

      (6) manage the finalization of the project by preparing a punch
          list of incomplete or work needing correction and confirm
          the contractor’s “successful demonstration” of the project.

    The architect’s principal described his role as the county’s “eyes and
ears” for the project. He subcontracted a consulting firm to help him “run
the job” because he could not dedicate more than fifteen or twenty percent
of his time on the project. The scope of the consulting firm’s work related
to reviewing construction schedules and other administrative work.

    The principal admitted he recommended the contractor’s termination
to the county and knew termination could happen upon his
recommendation. Conversely, the county’s project manager testified that
although the county and architect had discussions regarding the
contractor’s termination, the architect never expressly recommended
termination. The county’s director of capital improvement and projects
and contract administrator for the project described the architect as the
“architect on the job,” and relied on the principal’s input in reviewing pay
applications, change orders, time extensions, and inspection of the punch
list. He added that the county paid the contractor based on the principal’s
recommendation.

      •   The Appeal

   The contractor argues that Moyer recognized a professional negligence
claim against an architect, who supervises a project resulting in economic
damages to the contractor. Therefore, the contractor argues the trial court
erred in granting partial summary judgment. The architect responds that
the trial court correctly found the architect hired by the county owed no
duty of care to the contractor because Florida case law does not extend
the architect’s duty of care to the contractor. The architect also argues
the contractor cannot recover contract damages against the architect
because those damages would be duplicative.

    We review summary judgments de novo. Chirillo v. Granicz, 
199 So. 3d 246
, 249 (Fla. 2016). “The duty of care in a negligence action is a question
of law . . . .” Cheeks v. Dorsey, 
846 So. 2d 1169
, 1171 (Fla. 2003).

   “Under Florida’s common law a person who is injured by another’s

                                     3
negligence may maintain an action against the other person based on that
other person’s violation of a duty of due care to the injured person.”
Moransais v. Heathman, 
744 So. 2d 973
, 975 (Fla. 1999). “A professional
duty may arise in favor of a third party as a result of a matter of law . . . .”
Trikon Sunrise Assocs. v. Brice Bldg. Co., 
41 So. 3d 315
, 318 (Fla. 4th DCA
2010).

   “[A] third party general contractor, who may foreseeably be injured or
sustained an economic loss proximately caused by the negligent
performance of a contractual duty of an architect, has a cause of action
against the alleged negligent architect, notwithstanding absence of
privity.” 
Moyer, 285 So. 2d at 402
. Moyer relied upon California case law
that recognized the professional liability of a supervising architect to a
third-party contractor.

      Altogether too much control over the contractor necessarily
      rests in the hands of the supervising architect for him not to
      be placed under a duty imposed by law to perform without
      negligence his functions as they affect the contractor. The
      power of the architect to stop the work alone is tantamount to
      a power of economic life or death over the contractor.

Id. at 401
(quoting United States v. Rogers & Rogers, 
161 F. Supp. 132
,
136 (S.D. Cal. 1958)).

    Florida courts have required the existence of “supervisory duties” or
responsibilities and a “close nexus” between the architect and contractor
for Moyer to apply. McElvy, Jennewein, Stefany, Howard, Inc. v. Arlington
Elec., Inc., 
582 So. 2d 47
, 49-50 (Fla. 2d DCA 1991); E.C. Goldman, Inc. v.
A/R/C Assocs., 
543 So. 2d 1268
, 1270-72 (Fla. 5th DCA 1989); see also
Recreational Design & Constr., Inc. v. Wiss, Janney, Elstner & Assocs., 
867 F. Supp. 2d 1234
, 1239 (S.D. Fla. 2011). When the contract does not
require an architect to supervise, the architect does not perform
supervisory duties, and the contractor is more removed from the architect,
liability will not be imposed. 
McElvy, 582 So. 2d at 49
.

    The Southern District of Florida found a duty of care existed in a case
involving the same plaintiff and virtually identical facts. Grace & Naeem
Uddin, Inc. v. Jacobs Facilities, Inc., 
2012 WL 12950012
, at *1-6 (S.D. Fla.
June 7, 2012).          There, the court determined the supervising
architect/engineer may be found to have the requisite control to establish
professional liability even without ultimate decision-making power. 
Id. at *5.

                                       4
   Upon reviewing the record in a light most favorable to the contractor,
the court denied the architect/engineer’s motion for summary judgment.
Id. Applying Moyer,
the court found that despite the architect/engineer
having no decision-making authority, the nexus between it and the
contractor was sufficiently strong. 
Id. The architect/engineer
worked on
the project together with the contractor; and, the contractor was not a
subcontractor. 
Id. Here, the
contractor argues a duty of care existed because he and the
architect had contracts with the county, and testimony revealed that the
architect effectively controlled the project and the contractor’s fate. The
architect was broadly responsible for administration of the
county/contractor contract and sometimes acted as the county’s
representative.      The architect was also responsible for on-site
observational duties, which were later used to certify payment.

    The architect responds that it did not have final decision-making
authority. The architect also argues the facts in this case are more akin
to McElvy, E.C. Goldman, and Recreational Design & Construction, where
the court found the consultants lacked the requisite authority and nexus
to impose liability. We disagree.

    Although the architect was not given absolute authority to stop work,
it had the authority to recommend work stoppage. Article 5.1 provided the
architect, in conjunction with the county’s contract administrator, was
responsible for reviewing final documentation and the architect would
issue “Final Certificate of Payment.” Article 5.3 provided final payment
was contingent on the architect’s certification.

    The architect’s supervisory control over the contractor was further
supported by deposition testimony in which the architect’s principal
described himself as the “eyes and ears” of the project. Both the county’s
project manager and contract administrator confirmed the county’s
reliance on the architect in overseeing the contractor’s performance.

    Although the county had final authority to terminate the contractor or
otherwise stop work, it relied on the architect’s duty as consultant to make
its ultimate determination to terminate the contractor. The architect was
given near absolute authority regarding payments to the contractor,
demonstrating the architect’s influence over the contractor’s economic
vitality.

  The architect’s reliance on McElvy, E.C. Goldman, and Recreational
Design & Construction is misplaced. Unlike the architect in McElvy, who

                                     5
did not have definitive supervisory control over the contractor, here the
architect had supervisory control, both de facto and de jure. And, unlike
the subcontractor in McElvy, the contractor’s status as a general
contractor on the project established the requisite nexus to fall within
Moyer.

   Both E.C. Goldman and Recreational Design & Construction concerned
persons other than a supervising architect. E.C. Goldman involved a
design expert. Recreational involved an engineer. Neither of them
supervised the project, and neither had the requisite nexus with the
contractor. See Recreational Design & Constr., 
Inc., 867 F. Supp. 2d at 1237
; E.C. 
Goldman, 543 So. 2d at 1270-71
. 2

   Lastly, the architect argues Article 10.20 in the county/architect
contract, which declared no duty to third-party beneficiaries, eliminates
any duty of care between the architect and contractor. Once again, we
disagree.

   In Moyer, our supreme court established a supervising architect’s duty
of care to a general contractor based on foreseeability of harm. “[A]
contractor is an incidental beneficiary absent clear intent manifested in
the owner-architect contract to the 
contrary.” 285 So. 2d at 403
. Because
Moyer specifically established tort liability in the absence of any
contractual privity based on foreseeability of harm, the contractor’s status
as a contractual beneficiary is inconsequential.

    Lastly, the architect argues because the contractor seeks to recover
contractual economic damages from the county, tort damages from the
architect are barred. “[U]nder Florida law, a party is not permitted to
recover for the same damages more than once.” Addison Constr. Corp. v.
Vecellio, 
240 So. 3d 757
, 762 (Fla. 4th DCA 2018). “A judgment against
one person liable for a loss does not terminate a claim that the injured
party may have against another person who may be liable therefor.” 
Id. (citation omitted).
A party is not barred from claiming against multiple
parties where there are overlapping claims. 
Id. 2The architect
also relies on a per curiam decision of ours in which the dissent
suggested the economic loss rule barred a contractor from pursuing economic
damages in tort. D.I.C. Commercial Constr. v. Broward County, 
668 So. 2d 697
,
698 (Fla. 4th DCA 1996). Since D.I.C. Commercial Constr., our supreme court
has limited the application of the economic loss rule to products liability actions.
Tiara Condo. Ass’n v. Marsh & McLennan Cos., 
110 So. 3d 399
, 407 (Fla. 2013).


                                         6
    Here, liability has not yet been determined against either defendant.
While a party may not collect the same damages twice, when the judgment
is undetermined, overlapping damages claims are a “post-judgment issue.”
Id. For this
reason, the architect’s argument is premature.

   For the foregoing reasons, we reverse and remand the case to the trial
court to vacate the summary judgment in favor of the architect.

   Reversed and Remanded.

GROSS, J., and NUTT, JAMES, Associate Judge, concur.

                          *         *        *

   Not final until disposition of timely filed motion for rehearing.




                                   7

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer