ELIZABETH A. KOVACHEVICH, District Judge.
This cause comes before the Court on the following:
The Complaint in this case includes the following causes of action:
The Complaint in Intervention includes the same causes of action.
This case is about a construction contract entered into between Posen Construction, Inc. ("Rosen") and Lee County, Florida ("Lee County") to widen Summerlin Road from four to six lanes, and construct a four-lane overpass at College Parkway (the "Project"). Lee County agreed to pay Posen $25,323,685.44 to complete the Project. In addition to naming Lee County as a defendant, Posen names as defendants several other parties involved in the Project. Those named Defendants had been hired by and had contracted with Lee County instead of Posen. Specifically, Posen sues T.Y. Lin International ("TY LIN"), CPH Engineers, Inc. ("CPH"), and Stephen R. Romano ("Romano"). Posen alleges, for example, that Defendants failed to notify Posen of certain sub-surface conditions that caused significant rework. Posen also alleges that the defendants improperly approved fill material that caused several delays and additional work. Ultimately, according to Posen, the actions of Defendants caused several delays and disruptions that increased the cost of Posen's work. Posen filed this lawsuit to recover damages as a result of these various delays.
Federal Rule of Civil Procedure 8(a) requires more than bare legal conclusions in order to survive a motion to dismiss. See Ashcroft v. Iqbal, 556 U.S. 662, 679-81, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009). Concerned that courts were reading too broadly its prior ruling in Conley v. Gibson, 355 U.S. 41, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957), the United States Supreme Court clarified that Rule 8(a) requires a plaintiff to "state a claim to relief that is plausible on its face." Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007). The Court was careful to caution district courts from taking the plausibility requirement too far to a "heightened fact pleading of specifics." Id. Accordingly, this Court will take a two step approach when faced with a motion to dismiss pursuant to Rule 12(b)(6): (1) eliminate from the complaint all allegations that are merely legal conclusions; and (2) take the remaining well pleaded factual allegations as true and determine if there is a plausible claim for relief.
Because the Court has the independent obligation to assure itself that it possesses jurisdiction to adjudicate the dispute, the Court will consider the sovereign immunity issue first.
Lee County moves to dismiss Counts II, IV and V of the Posen Complaint. See Dkt. 28. With regards to Count II, Lee County claims it is entitled to sovereign immunity against Posen's claim (in quantum meruit) for additional expenses because the additional expenses were neither contemplated by the contract nor allowed by a contract change order. The parties have each discussed issues that raise questions about the Court's jurisdiction. There are two: first, the Court lacks jurisdiction because of the Eleventh Amendment; and
Lee County's argument that Count II must be dismissed relies in principal on two state court decisions that narrowly define an implied waiver of sovereign immunity to exclude damages outside the scope of the express terms of a written contract. See County of Brevard v. Miorelli Eng'g, Inc., 703 So.2d 1049 (1998); Southern Roadbuilders, Inc. v. Lee County, 495 So.2d 189 (Fla. 2d DCA 1986). A cursory reading of these cases initially suggests Lee County's desired outcome. Posen, citing only a single case, summarily dismisses the application of these cases in favor of an analysis guided by the Eleventh Amendment of the U.S. Constitution. Whether the defendants can claim sovereign immunity under the state law explained in Miorelli and Southern Roadbuilders is a question that is analytically distinct from whether the Eleventh Amendment serves as a jurisdictional bar to this lawsuit. Both parties miss the mark by conflating the two jurisdictional issues that are potentially at play.
As a general matter, sovereign immunity is defined simply as the privilege of a sovereign not to be sued without its consent. See Hans v. Louisiana, 134 U.S. 1, 16-17, 10 S.Ct. 504, 33 L.Ed. 842 (1890). "The Eleventh Amendment confirmed, rather than established, sovereign immunity as a constitutional principle; it follows that the scope of the States' immunity from suit is demarcated not by the text of the Amendment alone but by fundamental postulates implicit in the constitutional design." Alden v. Maine, 527 U.S. 706, 728, 119 S.Ct. 2240, 144 L.Ed.2d 636 (1999). For that reason the Eleventh Amendment has been described as a jurisdictional gatekeeper for federal courts, as it "deals only with federal jurisdiction to hear suits against the state, not with the state's immunity from suit in any forum."
The Eleventh Amendment is not a jurisdictional bar to the instant claims against Lee County. While a typical Eleventh Amendment analysis is a contextual one that requires a reviewing court to weigh three factors to determine whether a state agency or instrumentality is an arm of the state, Vierling v. Celebrity Cruises, Inc., 339 F.3d 1309 (11th Cir.2003), the Court will not belabor the point because "[i]t is now well established that the bar of the Eleventh Amendment to suit in federal courts extends to States and state officials in appropriate circumstances, but does not extend to counties and similar municipal corporations." Abusaid v. Hillsborough Cty. Bd. of Cty. Comm'rs, 405 F.3d 1298, 1314 (11th Cir.2005) (quoting Mt. Healthy City Sch. Dist. Bd. of Educ. v. Doyle, 429 U.S. 274, 280, 97 S.Ct. 568, 50 L.Ed.2d 471 (1977)) (emphasis added); see also Hutton
Whether Florida's state sovereign immunity law controls the outcome in a lawsuit in federal court sitting in diversity is a much more difficult question, one the parties have not adequately addressed. Posen cites to one case in its brief to summarily dismiss the application of the Miorelli decision in this case.
Whether state sovereign immunity bars the instant quasi-contract claims pending before the Court — or any federal court sitting in diversity — necessarily requires a discussion of the principles espoused in Erie. See Seminole Tribe of Florida v. Florida, 517 U.S. 44, 90, n. 14, 116 S.Ct. 1114, 134 L.Ed.2d 252 (1996) (Stevens, J., dissenting) ("[M]any of the cases decided after Hans in which this Court has recognized state sovereign immunity involved claims premised on the breach of rights that were rooted in state law ... In such cases, the Court's application of the state-law immunity appears simply to foreshadow (or follow) the rule of Erie R. Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938), not to demark the limits of Article III."). "Except in matters governed by the Federal Constitution or by acts of Congress, the law to be applied in any case is the law of the state." Erie, 304 U.S. at 78, 58 S.Ct. 817.
The applicable state law here is the Miorelli decision and it appears inconceivable that it would not apply in this instance. For example, § 768.28 is an express waiver by the legislature of the state's sovereign immunity from tort actions
If the substantive components of § 768.28, including its notice of claim provisions, are controlling in a federal diversity action, see Hattaway v. McMillian, 903 F.2d 1440, 1446 (11th Cir.1990), so should be the Miorelli decision even though it is a recognition of an implied waiver of sovereign immunity under Florida law, in contrast with the express waiver in § 768.28. Both stem from general state law with regards to purely state law claims and, therefore, both should apply equally in a federal diversity action regarding state law claims. See Pan-Am, 471 So.2d at 5; accord Omosegbon v. Wells, 335 F.3d 668, 673 (7th Cir.2003) ("[U]nder Erie state rules of immunity are binding in federal court with respect to state causes of action.") (internal citations omitted). The Court finds additional comfort in the result here because it is consistent with the "twin aims" of Erie, that is, "discouragement of forum-shopping and avoidance of inequitable administration of the laws." Shady Grove Ortho. Assoc., P.A. v. Allstate Ins. Co., 559 U.S. 393, 130 S.Ct. 1431, 1448, 176 L.Ed.2d 311 (2010) (Stevens, J., concurring in part) (quoting Hanna v. Plumer, 380 U.S. 460, 468, 85 S.Ct. 1136, 14 L.Ed.2d 8 (1965)). A rule that permits in the federal forum what is clearly barred in the state forum would invariably lead to forum shopping and, as a result, inequitable results for similar claims.
At bottom, the Miorelli decision is not a jurisdictional bar to this Court's ability to adjudicate a claim; it is merely a rule of decision that will dictate whether the claim being asserted can be successfully prosecuted. In other words, the Florida Supreme Court established in Miorelli the boundaries of Florida's waiver of sovereign immunity in contract actions. The Court agrees with Chief Judge Conway, and as the Eleventh Circuit has implied in many cases, that these particular state law immunity boundaries are as applicable in federal court as they are in state court. To be clear, if Posen's claim is predicated on work "totally outside the terms of the contract" it will fail by application of the Miorelli decision. On the other hand, claims for damages caused by additional work performed in furtherance of either express or implied covenants of the written contract fall within Florida's implied waiver of sovereign immunity as set forth
Count II, as pled and with the benefit of certain reasonable inferences, will survive Lee County's motion to dismiss at this stage. Posen and Lee County make certain admissions against their interests on this point that assist the Court in reaching its conclusion. Posen, for example, alleges that the additional work for which it seeks payment from Lee County "was not required by, or within the scope or contemplation of, the Contract." See Dkt. 1, ¶ 200. This additional work, according to Posen, "required that Posen perform work which materially differed from that which it had bargained for." See Dkt. 1, ¶ 201. These admissions would favor dismissal pursuant to the Miorelli decision. In its response to the Intervenor complaint, Lee County alleges that "the changes did not procure a totally different item or drastically alter the quality, character, nature or type of work contemplated by the original contract." Dkt. 71, p. 10. Lee County, by that admission, confirms the reasonableness of the inference the Court already drew, which is that the additional work is covered at least in part by the expansive contract between Lee County and Posen. Lee County's motion to dismiss Count II of the Posen Complaint is, therefore, denied.
Lee County argues that Counts IV and V should be dismissed, because "[p]ursuant to § 218.735(2), Fla. Stat. (2011), Posen, having consistently missed construction deadlines, the County lawfully rejected notices specifying said deficiencies. (Composite Exhibit 3)." Dkt. 28, p. 13. The referenced statute does not mandate dismissal of a claim brought to adjudicate whether Lee County properly rejected the payment request. Rather, § 218.735(2) outlines the manner in which the local government entity must reject a payment request or invoice; whereas, the subsections that follow discuss how to ultimately resolve a dispute that will typically arise when a payment request is rejected. Lee County's Motion to Dismiss Counts IV and V is, therefore, denied.
Lee County also moves to dismiss Counts II, IV and V of the Intervenor Complaint. See Dkt. 71. The allegations contained in the Intervenor Complaint are substantially similar to the allegations of the Posen Complaint. For the reasons already stated herein, Lee County's motion to dismiss Counts II, IV and V of the Intervenor Complaint is denied.
Defendant T.Y. Lin International ("TY LIN") moves to dismiss Counts VI and VII of the Posen Complaint. See Dkt. 20. TY LIN, although not ordinarily considered a state actor for sovereign immunity purposes, seeks to dismiss both counts due to its status as an agent of the state on this Project. TY LIN also moves to dismiss Count VI for failing to allege sufficient facts to state a plausible claim for relief pursuant to Federal Rule of Civil Procedure 8(a). Finally, TY LIN argues that Count VII fails as a matter of law because Posen failed to allege facts supporting the existence of a legal duty, a critical element of the negligence claim. Each argument will be addressed in turn.
TY LIN's sovereign immunity argument is based on two different provisions of Florida's sovereign immunity statute. See
Section 768.28(9)(a) extends immunity beyond the state and state actors to certain private parties in contractual privity with the state and, at the same time, acting in the capacity as an agent for the state. See M.S. v. Nova Southeastern University, Inc., 881 So.2d 614, 617 (Fla. 4th DCA 2004). That determination is a fact intensive one that turns on the nature and degree of control exercised by the state over the private entity. Stoll v. Noel, 694 So.2d 701, 703 (Fla.1997). Posen alleges it began certain construction operations on the Project based solely on TY LIN's representation that "Lee County D.O.T. has approved the fill material from the Veronica Shoemaker tested stockpile, for the MSE wall, please proceed with operations." Dkt. 1, ¶ 229. After work commenced, Lee County issued a stop work order and ordered Posen to excavate the fill material that TY LIN "represented was approved." Dkt. 1, ¶ 232. TY LIN's representations, according to the Complaint, "were false, and exceeded the scope of their contractual responsibilities regarding the Project." Dkt. 1, ¶ 233. TY LIN, in response, asserts that no factual basis exists for the allegation that TY LIN exceeded its contractual responsibility and takes issue with Posen's failure to attach any contract that defines the contours of TY LIN's contractual undertaking and with whom it was entered. TY LIN, therefore, attached its contract with Lee County to its motion and asks the Court to consider it (as an exception to the general rule) because it is central to Posen's claim for relief. See Dkt. 20, ¶¶ 6-12.
Even considering the contract, there are factual issues that must be thrashed out before the Court can determine whether TY LIN was acting in the requisite capacity to enjoy the extension of sovereign immunity provided for in § 768.28(9)(a). By way of example, TY LIN cites to the attached contract between Lee County and TY LIN for the proposition that "it makes clear that TY LIN provided construction engineering and inspection services, but did not design, supervise or direct control of Posen." Dkt. 20, ¶ 20. This, coupled with the factual averment that "[a]t all times material TY LIN acted within the scope of its employment and in good faith," according to TY LIN, is sufficient to countervail Posen's allegation that TY LIN falsely and negligently misrepresented facts regarding the quality of the fill material. The Court agrees with Posen that TY LIN's attempt to deny what is clearly alleged will not properly support dismissal under Rule 12(b). See Dkt. 31, p. 6. The Court has not — and indeed cannot — weigh the competing allegations proffered by the two parties and will, accordingly, deny the motion to dismiss Counts VI and VII on those grounds. See, e.g., Lewis v. City of St. Petersburg, 260 F.3d 1260, 1264 (11th Cir. 2001); Vasquez v. City of Miami Beach, 895 F.Supp.2d 1275, 1278-79 (S.D.Fla. 2012).
TY LIN directs the Court to § 768.28(10)(e) as yet another provision that extends sovereign immunity to private parties working as agents for the state. It is not clear, however, that TY LIN even meets the criteria for the application of § 768.28(10)(e). TY LIN, again relying on its contract with Lee County (not attached to the original Complaint), takes the seemingly unequivocal stance
It is also worth mentioning that, even if applicable to firms contracting with the county, the statute expressly excludes protection for firms engaged for "design or construction" services. It appears that TY LIN was engaged for the very services that the legislature carved out of the statute. See Dkt. 20, Exhibit 1 at A3, ¶ 1.a. Accordingly, the Court denies TY LIN's motion to dismiss on sovereign immunity grounds.
TY LIN moves to dismiss Count VI on the grounds that it "lacks [the] requisite factual basis" to state a claim for negligent misrepresentation. Under Florida law, a plaintiff must plead and prove the following to establish a claim for negligent misrepresentation: (1) the defendant made a misrepresentation of a material fact; (2) the defendant made the representation without knowledge of its truth or falsity, or under circumstances that it should have known of its falsity; (3) the defendant intended that the representation would induce another to act on it; and (4) and injury resulting from justifiable reliance on the misrepresentation. Souran v. Travelers Ins. Co., 982 F.2d 1497, 1503 (11th Cir.1993) (applying Florida law).
TY LIN's argument misstates Florida law and attempts to obtain a dismissal by either denying facts or improperly injecting facts into the pleading from source documents not attached to the complaint. The most illustrative example is found in footnote 2: "POSEN was expressly advised (numerous times) to proceed at its own risk until final test results/approvals regarding POSEN's proposed fill material were received verifying POSEN's emphatic claims that the proposed fill material complied with the contract specification requirements (TY LIN would be prepared to offer evidence of this fact if this issue were before Court)." Dkt. 20, p. 9. The Court is at a loss as to what persuasive value TY LIN ascribes to this proffer, especially in light of the acknowledgment that it has no relevance at this stage of the proceeding. These matters are more suitably before
Each of the elements is pleaded with the specificity required under Federal Rule of Civil Procedure 9(b). See Dkt. 1, ¶¶ 227-237. In Florida, actions for negligent misrepresentation sound in fraud and, therefore, must be pleaded with specificity as required by Federal Rule of Civil Procedure 9(b). See Postel Indus., Inc. v. Abrams Group Const, LLC, 2012 WL 4194660, at *2 (M.D.Fla. Sept.19, 2012) (citing Morgan v. W.R. Grace & Co., 779 So.2d 503, 506 (Fla. 2d DCA 2000)). Posen met its burden in this particular case by alleging specific statements and attaching several emails that are date and time stamped that form the basis for the alleged misrepresentations and resultant harm flowing from Posen's reliance on those statements. See, e.g., Brooks v. Blue Cross and Blue Shield of Florida, Inc., 116 F.3d 1364, 1371 (11th Cir.1997). TY LIN may not like what the allegations say, but Rule 12(b)(6) is not properly invoked when one simply wants to dispute what is alleged. Therefore, the Court denies the Motion to Dismiss as to Count VI.
TY LIN also moves to dismiss Count VII on the grounds that Posen failed to allege facts that establish TY LIN owes a duty of care to Posen. The parties agree that whether there exists a duty depends at least in part
TY LIN is correct that courts have been reluctant to expand the holding of A.R. Moyer beyond its specific facts. See Casa Clara Condo. Ass'n v. Charley Toppino and Sons, Inc., 620 So.2d 1244, 1248 at n. 9 (Fla.1993) ("We also limit A.R. Moyer, Inc. v. Graham, 285 So.2d 397 (Fla.1973), strictly to its facts."); Spancrete, Inc. v. Ronald E. Frazier & Assocs., PA., 630 So.2d 1197,
The Complaint alleges facts sufficient to establish TY LIN's control over Posen insofar as the pleading standard is concerned.
TY LIN disagrees and instead refers the Court to its contract with Lee County to refute the proposition that it had any control or supervision of Posen's work. It is appropriate to look at the terms of the contract, because, according to TY LIN, they "are `of record' through Plaintiff's incorporation by reference" in the Complaint. The Court agrees that the contract between TY LIN and Lee County is central to Posen's claim for negligence (as opposed to negligent misrepresentation) because the applicable theory of liability centers on the supervision and control it had over Posen on this particular project. See, e.g., Bamert v. Pulte Home Corp., 445 Fed.Appx. 256, 267-68 (11th Cir.2011) (holding that relationship forming contracts are uniquely central to a claim when the level of control is at issue). TY LIN argues that its agreement with Lee County "clearly demonstrate[s] that TY LIN had no authority or obligation to supervise POSEN." Dkt. 20, ¶ 40. The Court disagrees.
For example, as one measure of control over Posen the contract states that "[t]he successful Consultant [TY LIN] shall perform management engineering services required to ... [m]aintain [an] adequate level of surveillance of the construction contractors' activities." See Dkt. 20, Exhibit 1 at A1, § 2, ¶ 5. TY LIN also had the authority to review, maintain, and analyze all sampling and testing records to "ascertain acceptability of material and completed work items." See Dkt. 20, Exhibit 1 at A1, § 2, ¶ e.
TY LIN's ability to control Posen, as indicated by those provisions, must be juxtaposed with the mere advisory role TY LIN had in other regards. See Dkt. 20, Exhibit 1 at A1, § 2, ¶ c ("Review of contractor requests for time extension and/or Consultant [TY LIN] recommended alternatives shall be performed by the Consultant, as required.") (emphasis added); id.
TY LIN also moves to dismiss Counts VI and VII of the Intervenor Complaint. See Dkt. 62. The allegations contained in the Intervenor Complaint are substantially similar to the allegations of the Posen Complaint. For the reasons already stated, TY LIN's Motion to Dismiss Counts VI and VII is denied.
Defendants CPH Engineers, Inc. ("CPH") and Stephen R. Romano ("Romano") move to dismiss Counts VIII and IX, respectively, of the Posen Complaint. See Dkt. 19. Posen asserts two legal bases for a duty allegedly owed by CPH and Romano. First, according to Posen, engineers are liable in tort to general contractors even though there is an absence of privity when the injury is reasonably foreseeable. Dkt. 30, p. 8. Second, Posen is owed a duty of care pursuant to Florida Administrative Code §§ 61G15-19.001(4) and 61G15-19.001 (5). The Court is not persuaded by Posen's arguments and will dismiss Counts VIII and IX without prejudice. Posen should not take this as a directive that a claim could not exist, but rather that none exists currently as the Complaint is drafted.
CPH and Romano cite to Recreational Design & Constr., Inc. v. Wiss, Janney, Elstner Assocs., Inc., 820 F.Supp.2d 1293 (S.D.Fla.2011) for the proposition that Posen must establish a "close nexus" between itself and the defendants to establish a legal duty pursuant to Florida law. Posen disagrees that Recreational Design bars its claim and instead argues that it "is fully consistent" with its position. Dkt. 30, p. 4. According to Posen, there is a simple temporal distinction to determine whether there exists liability in these construction cases: engineers involved during the project owe a duty to the contractors but engineers that become involved after the completion of the project do not. Id. That distinction is ostensibly derived from the fact that both Recreational Design and E.C. Goldman, Inc. v. A/R/C Assoc., Inc., 543 So.2d 1268 (Fla. 5th DCA 1989), the cases cited for this proposition, involved situations in which consultants hired to perform ex post facto inspections of completed
The Court disagrees with Posen and instead reads Recreational Design as simply applying the natural progression of Florida court decisions on this point since A.R. Moyer. Posen's argument creates an artificial distinction derived from a common propositional fallacy often referred to as "denying the antecedent." The problem with denying the antecedent is that there is a logical disconnect between the antecedent and the consequent such that the predictive behavior of the consequent is not accurately linked to the nonoccurrence of the antecedent.
The Florida Supreme Court in A.R. Moyer specifically held that something more than being hired prior to completion of the job is required to provide the sufficient nexus:
285 So.2d at 402 (emphasis added). The common theme in each of the above mentioned factual scenarios is the presence of a supervisory role or element of control by the architect and engineer. The Court must be careful not to read out that important modifier in each factual scenario. The phrase "close nexus," as used in Recreational Design, is simply another way to state that supervising architects and engineers are liable for the foreseeable injuries to general contractors proximately caused by their negligent conduct even when there is an absence of contractual privity, whereas nonsupervising engineers and architects — irrespective of when they are hired — will not be. A.R. Moyer, 285 So.2d at 402. The Court does not believe the court in Recreational Design was making a temporal distinction, but rather acknowledging the point that a consultant hired after the job is completed cannot have a supervisory role.
There is no allegation that CPH or Romano exercised any control over Posen. Moreover, Posen's argument, even ignoring the absence of an allegation of control, is predicated on a now outdated pleading standard. Posen asserts that the Court should only dismiss its claims if the pleadings "show that the plaintiff has no claim whatsoever." Dkt. 30, p. 3. That is an iteration of Federal Rule of Civil Procedure 8(a) as it was formerly understood in the wake of Conley v. Gibson, 355 U.S. 41, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957). But nearly six years ago the United States
CPH's and Romano's Motion to Dismiss Counts VIII and IX of the Intervenor Complaint is granted. If Posen can allege facts to support a claim for negligence based on a theory of liability supported by Florida law, whether it be the supervising engineer theory espoused in A.R. Moyer or some other supportable theory, the Court will permit it to file an amended pleading. The amended pleading must be filed within fourteen (14) days of this order.
CPH and Romano also move to dismiss Counts VIII and IX, respectively, of the Intervenor Complaint by incorporation of its motion to dismiss the Posen Complaint. See Dkt. 66. The allegations contained in the Intervenor Complaint are substantially similar to the allegations of the Posen Complaint. For the reasons already stated, CPH's and Romano's motion to dismiss Counts VIII and IX of the Intervenor Complaint is granted, also with leave to amend.
Accordingly, it is
Fla. Stat., § 768.28(18). The cited passage "reflects [the legislature's] care nor to waive, by accident, its Eleventh Amendment immunity as part of the same legislation." Hufford v. Rodgers, 912 F.2d 1338, 1342 (11th Cir. 1990) (emphasis in original). This case, however, does not implicate the Eleventh Amendment.