JOHN E. STEELE, District Judge.
In this case plaintiff Redfish Key Villas Condominium Association, Inc. (Redfish or plaintiff) seeks a declaratory judgment and damages from Amerisure Insurance Company (Amerisure or defendant) based upon defective stucco work performed by a subcontractor of Amerisure's insured, Dooley Mack Constructors, Inc. (DooleyMack). The matter is now before the Court on the defendant's Motion for Summary Judgment (Doc. #66), which asserts that Amerisure is entitled to judgment because (1) DooleyMack did not notify Amerisure of Redfish's lawsuit as required by the insurance policy, and (2) the damages sought by Redfish involve solely the defective work of the stucco subcontractor, which are not covered by the insurance policy. Plaintiff filed a Response in Opposition (Doc. #78) asserting that material issues of disputed facts preclude summary judgment. The Court agrees with plaintiff, and therefore denies the motion for summary judgment.
Summary judgment is appropriate only when the Court is satisfied that "there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). "An issue of fact is `genuine' if the record taken as a whole could lead a rational trier of fact to find for the nonmoving party."
In ruling on a motion for summary judgment, the Court views all evidence and draws all reasonable inferences in favor of the non-moving party.
On or about June 24, 2005, DooleyMack entered into a construction contract with Redfish Key, LLC (the developer) for the construction of a four story condominium building with a covered parking area. (Doc. #89, p. 11.) This construction contract required DooleyMack to obtain general liability insurance, which included completed operations liability coverage. (
DooleyMack subcontracted with R. Simpson Plastering & Stucco, Inc. (Simpson Stucco) to perform the stucco and plaster work on Redfish Key Villas. (
Plaintiff asserts that in early 2010, its members
DooleyMack was unable to repair the defective stucco because of its dire financial condition. In and around January 2011, Redfish hired Spectrum Contracting, Inc. (Spectrum) to remediate the damage caused by the defective work of Simpson Stucco. (Doc. #62-1, p. 113.) The repairs were completed on or about July 21, 2012, for a total cost of $202,902.97, which was paid by Redfish.
On or about February 6, 2012, while repairs were still pending, Redfish filed a two-count Complaint against DooleyMack in Charlotte County Circuit Court seeking damages for the defective stucco work (the DooleyMack lawsuit). DooleyMack was served with process on February 13, 2012, and on February 16, 2012, counsel for DooleyMack filed a Notice of Appearance in the lawsuit. DooleyMack filed nothing further in the case. On April 9, 2012, a default was issued against DooleyMack. On August 17, 2012, after an evidentiary hearing on damages, the Charlotte County Circuit Court issued a default judgment in favor of Redfish and against Gulf Coast Project Services, Inc. (f/k/a DooleyMack) in the amount of $202,902.97. (Doc. #2-5, Ex. E.)
On November 2, 2012, Kyle Summer (Summer), claims supervisor of Amerisure, sent an e-mail to Redfish's counsel which identified Amerisure as an insurance carrier for DooleyMack. Summer stated he was attempting to determine the current status of the 558 Notice and any remediation or repairs that may have taken place. Plaintiff asserts that this was its first notice of any insurance policy by DooleyMack. (Doc. #2-6, Exh. F.) On the same day, Redfish's counsel responded by email requesting information as to how Amerisure planned on satisfying the judgment against DooleyMack. Amerisure asserts this was its first notice that the DooleyMack lawsuit had been filed.
On November 26, 2012, pursuant to Summer's request, Redfish sent Amerisure documents relating to the lawsuit. On February 8, 2013, Amerisure sent a letter to Redfish denying coverage for the default judgment under the Policy, asserting that it had been materially prejudiced by DooleyMack's failure to provide Amerisure notice of the lawsuit as required by the Policy. (Doc. #2-7, Exh. G.) No other basis for denial of coverage was asserted.
On March 13, 2013, Redfish filed a two-count Complaint (Doc. #2) against Amerisure in Charlotte County Circuit Court, seeking declaratory relief and alleging a breach of the Policy as a third-party beneficiary. On March 28, 2013, Amerisure removed this case to federal court on the basis of diversity jurisdiction. (Doc. #1.)
Amerisure asserts that it did not owe either DooleyMack or Redfish any duty under the insurance Policy because DooleyMack did not notify Amerisure of the DooleyMack lawsuit, as required by the Policy. This lack of notice, Amerisure asserts, breached the terms of the Policy and was prejudicial to its opportunity to eliminate or reduce the loss by participation in the defense of the suit. (Doc. #66, pp. 4, 6.)
While variously phrased under Florida law, it is clear that resolution of the notice issue is a multi-step process. First, the Court must determine if there is a contractual notice requirement and, if so, its scope. When an insurance contract contains a provision which requires notice to the insurer of a claim, an insured must give such notice.
Second, the Court must determine whether or not notice was timely given.
Third, if the notice has been determined to be untimely or absent, and thus prejudice to the insurer is presumed, the insured must overcome the presumption by proving that the insurer was not prejudiced.
It is clear that the Policy does contain a notice requirement for DooleyMack. Section IV of the Commercial General Liability Coverage Form (Doc. #2-2) portion of the Policy provides:
(Doc. #2-2, Exh. B, pp. 24-25.) "Suit" is a defined term which means "a civil proceeding in which damages because of . . . `property damage' . . . to which this insurance applies are alleged." (
A requirement of notice "as soon as practicable" requires "notice to be given with reasonable dispatch and within a reasonable time in view of all the facts and circumstances of each particular case."
The 558 Notice (Doc. #2-3, Exh. C) was sent to DooleyMack in February 2011, and forwarded to and received by Amerisure no later than April 20, 2011. (Doc. #2-3, Exh. C; Doc. #62-1, Summer Dep. 81:11-14; 97:3-10, Jan, 16, 2014.) Amerisure does not argue that there was a lack of notice for the "claim" set forth in the 558 Notice.
Amerisure does argue, however, that there was a lack of notice of the DooleyMack lawsuit. The DooleyMack lawsuit was filed on February 6, 2012, and the default judgment was entered on August 17, 2012. While there were conversations between Amerisure and DooleyMack in this time frame, there is no evidence that Amerisure was even verbally notified of the actual filing of the DooleyMack lawsuit. Indeed, there is no evidence that DooleyMack ever informed Amerisure of the actual lawsuit filed by Redfish. It was not until November 2, 2012, when Redfish sent an e-mail notifying Amerisure of the entry of a default judgment against DooleyMack in state court, that Amerisure was notified that a suit had been brought. There are no facts from which a reasonable trier of fact could determine that the complete lack of notice by DooleyMack satisfied the "as soon as practicable" requirement of the Policy.
Plaintiff suggests that because Amerisure had notice of the claim pursuant to the 558 Notice, which contained the threat of an imminent lawsuit, there was sufficient notice even if there was no specific notice of the actual lawsuit. The Court disagrees. The Policy requires notice of both a "claim" and notice of a "suit". Amerisure had a contractual right to notification of the filing of a suit, even after it had been notified of the claim.
Amerisure asserts that plaintiff cannot rebut the presumption of prejudice resulting from the failure to provide notice of the lawsuit against its insured. At his deposition, Mr. Summer suggested that the prejudice to Amerisure included the inability to conduct discovery, dispute liability and damages, participate in settlement discussions, and to file claims against others. (Summer Dep. 216:21-217:6.) Plaintiff disagrees, asserting that there is at least an issue of material disputed facts regarding whether Amerisure was prejudiced by the delay.
As noted earlier, "[a]n insurer is prejudiced by untimely notice when the underlying purpose of the notice requirement is frustrated by late notice."
Amerisure also argues that the defective work of Simpson Stucco is not covered by the Policy because the $202,902.97 in damages did not involve damage to "other property", only stucco remediation, and that Redfish failed to mitigate the damages. Plaintiff responds that whether the damage was due to underlying issues remains a question of fact.
Under Section V of the Policy, "Property damage" means "[p]hysical injury to tangible property, including all resulting loss of use of that property." (Doc. #2-2, p. 29.) Under Section I of the Policy, "property damage" does not include "[t]hat particular part of real property on which you or any contractors or subcontractors working directly or indirectly on your behalf are performing operations, if the "property damage" arises out of those operations", or if to "your work"
Mr. Summer testified with regard to having had discussions with Chuck Evans of DooleyMack regarding water intrusion coming in through the walls, and Joel C. Potter of Spectrum testified that they company tested for water leaks and the painting proposal came after the proposal to repair hairline cracks. (Doc. #62-1, p. 113; Doc. #65-1, p. 24.) Plaintiff has also presented sufficient facts to support coverage under the Policy. (Doc. #78, pp. 13-18.)
Accordingly, it is now
Defendant's Motion for Summary Judgment (Doc. #66) is
(Doc. #2-2, p. 30.)