Summary: ORDER CHARLENE EDWARDS HONEYWELL , District Judge . This cause comes before the Court upon the Report and Recommendation filed by Magistrate Judge Anthony E. Porcelli on August 14, 2018 (Doc. 40). In the Report and Recommendation, Magistrate Judge Porcelli recommends that Plaintiff Spivey Utility Construction Company's Amended Motion for Attorneys' Fees and Costs (Doc. 17) be DENIED. All parties were furnished copies of the Report and Recommendation and were afforded the opportunity to fil
Summary: ORDER CHARLENE EDWARDS HONEYWELL , District Judge . This cause comes before the Court upon the Report and Recommendation filed by Magistrate Judge Anthony E. Porcelli on August 14, 2018 (Doc. 40). In the Report and Recommendation, Magistrate Judge Porcelli recommends that Plaintiff Spivey Utility Construction Company's Amended Motion for Attorneys' Fees and Costs (Doc. 17) be DENIED. All parties were furnished copies of the Report and Recommendation and were afforded the opportunity to file..
More
ORDER
CHARLENE EDWARDS HONEYWELL, District Judge.
This cause comes before the Court upon the Report and Recommendation filed by Magistrate Judge Anthony E. Porcelli on August 14, 2018 (Doc. 40). In the Report and Recommendation, Magistrate Judge Porcelli recommends that Plaintiff Spivey Utility Construction Company's Amended Motion for Attorneys' Fees and Costs (Doc. 17) be DENIED. All parties were furnished copies of the Report and Recommendation and were afforded the opportunity to file objections pursuant to 28 U.S.C. § 636(b)(1). No such objections were filed.
Upon consideration of the Report and Recommendation, and upon this Court's independent examination of the file, it is determined that the Report and Recommendation should be adopted. Accordingly, it is now
ORDERED AND ADJUDGED:
(1) The Report and Recommendation of the Magistrate Judge (Doc. 40) is adopted, confirmed, and approved in all respects and is made a part of this Order for all purposes, including appellate review.
(2) Plaintiff Spivey Utility Construction Company's Amended Motion for Attorneys' Fees and Costs (Doc. 17) is DENIED.
(3) As all issues in this case, including the underlying dispute between the parties, have been resolved, the parties are directed to file a stipulation of dismissal of this case on or before September 18, 2018.
DONE AND ORDERED.