BETH BLOOM, District Judge.
On July 29, 2016, Prime Investors filed a Complaint for breach of contract against Rockwood in the Seventeenth Judicial Circuit Court in and for Broward County, Florida. See ECF No. [1-1], Exh. A. Prime Investors alleges that Rockwood breached a Subcontractor Base Agreement (the "Agreement") that the parties entered into on July 10, 2015, whereby Rockwood was to "supply and install finished carpentry, architectural woodwork, millwork and trim" for a project relating to property in Key Largo, Florida. Id. at ¶¶ 8, 10. On September 13, 2016, Rockwood filed an Answer, Affirmative Defenses and Counterclaim (the "Counterclaim"), wherein Rockwood asserts its own claim for breach of contract against Prime Investors, and also seeks to enforce a construction lien and recover on a quantum meruit claim against Counter-Defendant Key Largo Hospitality Land Trust, Steven B. Greenfield, Trustee — the owner of the subject property. ECF No. [1-1], Exh. B. On September 13, 2016, Rockwood propounded a single request for admission relating to Prime Investor's damages. See ECF No. [1] at ¶ 3. Prime Investors responded on October 21, 2016, admitting that the amount in controversy exceeds $75,000. ECF No. [1-1], Exh. C. Thereafter, on November 10, 2016, Rockwood removed this matter to this Court pursuant to this Court's diversity jurisdiction.
Pursuant to 28 U.S.C. § 1332(a), a district court is vested with subject matter jurisdiction when the parties are diverse and the amount in controversy "exceeds the sum or value of $75,000, exclusive of interest and costs." There is no dispute here that the amount in controversy exceeds the jurisdictional threshold; Prime Investors instead moves for remand on the basis that removal was not timely effectuated. The time limit for removal is set forth in 28 U.S.C. § 1446(b), which provides in relevant part:
The parties are in disagreement as to what triggered the 30-day period during which Rockwood had to remove the action. Prime Investors contends that the Complaint filed on July 29, 2016 triggered the 30-day removal period in that it sufficiently disclosed an amount in controversy in excess of $75,000. Alternatively, Prime Investors argues that the 30-day removal period was triggered, at the latest, by Rockwood's Counterclaim filed on September 13, 2016, wherein Rockwood alleges "damages for greater than the sum or value of $75,000 . . . ." ECF No. [1-1], Exh. B at 4, ¶ 1. In response, Rockwood argues that the Complaint is not clear as to the damages alleged by Prime Investors, and therefore directs the Court to Prime Investors' October 21, 2016 response to Rockwood's request for admission as the trigger for the 30-day removal period. The removal, effectuated on November 10, 2016, would be timely only if the October 21, 2016 date applies.
The Complaint, in its opening paragraph, states that "the amount in controversy exceeds $15,000" — the threshold amount required to invoke the state court's jurisdiction. ECF No. [1-1], Exh. A at ¶ 1. At paragraph 10, the Complaint alleges Rockwood's breach of the Agreement (attached to the Complaint) by Rockwood's failure, among other things, "to promptly correct defective work resulting in delays to the Overall Project Schedule (`OPS')" and "to timely deliver and install granite/solid surface countertops resulting in delays to the OPS." Id. at ¶¶ 10(a)-(b) (emphasis added). With respect to the alleged delays in Rockwood's work, the Complaint, at paragraph 12, references a liquidated damages provision contained in the parties' Agreement:
Id. at ¶ 12. The OPS referred to in paragraphs 10 and 12 of the Complaint is delineated in the attached Agreement and indicates that the work to be performed by Rockwood was to be completed by August 17, 2015, more than eleven months prior to Prime Investors' filing of the Complaint. See ECF No. [1-1] at 68.
Notwithstanding the above, Rockwood argues in conclusory fashion that the Complaint's "vague reference to a liquidated damage claim" was insufficient to trigger the 30-day removal period. ECF No. [22] at 3. Importantly, however, Rockwood does not dispute that its work was to be completed by August 17, 2015 pursuant to the OPS outlined in the Agreement, or that the "substantial delays" alleged in paragraph 12 of the Complaint included more than 75 days following August 17, 2015 — assertions raised in Prime Investors' Motion to Remand.
As the holding in George was predicated on the lack of a relationship between the amounts stated and the causes of action asserted in the complaint, the Court finds it inapposite. Here, unlike in George, the damages sought by Prime Investors are "clearly identified and [] linked" to the breach of contract claim asserted against Rockwood. Id. Specifically, the Complaint alleges that Prime Investors is entitled to liquidated damages as a result of Rockwood's "substantial delays" with respect to the OPS. ECF No. [1-1], Exh. A at ¶ 12. Furthermore, the Complaint identifies those delays as well as a specific term under the Agreement regarding the calculation of the resulting damages. See id. at ¶¶ 10(a)-(b), 12.
Regarding the actual amount of damages, while the Court "will not speculate as to the amount of damages and cannot expect the Defendant to have done so[] where the pleading itself states only that the amount in controversy exceeds $15,000[,]" Lamberton v. Go Fit, LLC, 918 F.Supp.2d 1283, 1285 (S.D. Fla. 2013) (emphasis added), the initial pleading in this case clearly states much more than that. The Complaint alleges specific "delays to the OPS" as a result of Rockwood's work, incorporates the parties' Agreement — which, as mentioned, indicates that Rockwood was to complete its work by August 17, 2015 — and references the Agreement's liquidated damage provision under which Prime Investors is entitled to "$1,000.00 for each and every day Rockwood is late in completing the Work". The Complaint does not invite speculation as to damages in this context given that it was filed well after 75 days had passed since the August 17, 2015 deadline. ECF No. [1-1] at 14-68; ECF No. [1-1], Exh. A at ¶¶ 10(a)-(b), 12; see also ECF No. [1-1], Exh. A at ¶¶ 11, 13 (alleging that Rockwood refused to correct the defective work and that Prime Investors "continues to suffer damages") (emphasis added); cf. Lamberton, 918 F. Supp. 2d at 1285 (finding that the complaint's allegations that the plaintiff suffered serious permanent physical injuries — including near complete blindness in one eye and partial vision loss in the other eye — were insufficient without more to establish the jurisdictional minimum). Thus, the Court finds that it is apparent on the face of the Complaint (and the Agreement incorporated therein) that the amount in controversy exceeds the jurisdictional requirement.
Accordingly, the 30-day removal period began upon service of the Complaint — not upon Rockwood's Counterclaim filed on September 13, 2016 or Prime Investors' October 21, 2016 response to Rockwood's request for admission. Rockwood's notice of removal filed on November 10, 2016 was therefore untimely.
For the foregoing reasons, it is