Coomer, Judge.
This case comes to us for a third time on appeal.
"Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. A trial court's grant of summary judgment is reviewed de novo on appeal, construing the evidence in the light most favorable to the nonmovant." Bruce v. Georgia-Pacific, LLC, 326 Ga.App. 595, 595, 757 S.E.2d 192 (2014) (citations and punctuation omitted).
The relevant facts and procedural history of this case are set forth in this Court's prior opinions as well as the order giving rise to this appeal:
Southern States II, 338 Ga. App. XXVIII at pg. 1-6 (citations and footnote omitted).
After the case was remanded to the trial court following Southern's first appeal, Southern States I, Southern filed a fourth amended complaint which included for the first time, a claim for breach of contract based on the one-year express warranty and for breach of contract per se. In a July 2015 order, the trial court granted Appellees' motion for summary judgment finding, on the issue of fraud and equitable estoppel, that fraud did not toll the statute of repose and that Southern did not exercise due diligence to discover any alleged fraud by Appellees because it never conducted annual testing of the cathodic protection system as recommended by the post-inspection report. The trial court determined that because an essential element of fraud was absent, Appellees were not estopped from successfully asserting a statute of repose defense under OCGA § 9-3-51 (a). The July 2015 order gave rise to Southern's second appeal in this case. In Southern States II, this Court affirmed the trial court's judgment granting Appellees' motion for summary judgment without remand for further adjudication. See Southern States II, 338 Ga. App. XXVIII at pg. 6-18.
Southern then petitioned the Georgia Supreme Court for a writ of certiorari, which was denied. See Southern States Chemical, Inc. v. Tampa Tank & Welding, Inc., S17C0109, 2017 Ga. LEXIS 276 (April 17, 2017) (unpublished). However, prior to the entry of a final disposition order by the trial court, Southern filed a fifth amended complaint, wherein it raised claims for breach of contract under an express warranty, breach of contract per se, and attorney fees and litigation costs. Tampa Tank and CCI each filed dispositive motions, which the trial court granted in its December 2017 final order. In the final order, the trial court found that the allegations in Southern's fifth amended complaint related to Southern's breach of contract claims against Appellees "fall within the ambit of OCGA § 9-3-51 (a) under which [Appellees] have already successfully asserted a statute of repose defense." The trial court further held that Southern's claims for breach of contract are also barred under the six-year statute of limitation applicable to actions upon written simple contracts because Southern's contract claims were brought approximately ten years after substantial completion of the project. With that, the trial court concluded that Southern's ancillary
It is undisputed that in the initial letter proposal between Tampa Tank and Southern, Tampa Tank made the following express one-year warranty provision: "All material and workmanship are guaranteed for a period of twelve (12) months from the date of completion of this work." However, Southern contends that in addition to the express 12 month warranty with Tampa Tank, Southern was an intended third-party beneficiary of CCI's contract with Tampa Tank for the cathodic protection system and that certain promises were made in favor of Southern in CCI's post installation compliance report. Southern contends that the calculations of the estimated life expectancy of the cathodic protection system in the post installation report CCI prepared and sent to Tampa Tank are akin to an express warranty by CCI that the system should last 43 or 45 years. We disagree.
Pretermitting whether the calculations of the estimated life expectancy of the cathodic protection system is an express warranty, "[i]n order for [Southern] to have standing to enforce a contract ... it must clearly appear from the contract that it was intended for [its] benefit. The mere fact that [Southern] would benefit from performance of the agreement is not alone sufficient." Donnalley v. Sterling, 274 Ga.App. 683, 685 (1), 618 S.E.2d 639 (2005) (citations and punctuation omitted). "Although the third-party beneficiary need not be specifically named in the contract, the contracting parties' intention to benefit the third party must be shown on the face of the contract." Brown v. All-Tech Investment Group, Inc., 265 Ga.App. 889, 897 (2) (a) (i), 595 S.E.2d 517 (2003) (citation omitted). "A third-party beneficiary contract is one in which the promisor engages to the promisee to render some performance to a third person." Northen v. Tobin, 262 Ga.App. 339, 344 (2) (b), 585 S.E.2d 681 (2003) (footnote omitted).
On September 25, 2000, Tampa Tank signed a purchase order confirming a January 12, 2000 letter in which CCI agreed to provide Tampa Tank "design documents, installation plans, materials, and final testing with a compliance report" for a cathodic protection system. Tampa Tank agreed to pay $13,690 to CCI for the costs associated with the services CCI provided. Neither the January 12, 2000 letter nor the September 25, 2000 purchase order include any promises to or from Southern regarding CCI's services. Southern was not a signatory on the September 25 purchase order and was not invoiced by CCI for payment related to CCI's services. While the letter and invoices provide that CCI would conduct post installation testing and provide a report to Tampa Tank, nothing in the record suggests that the report was incorporated as part of Southern's bargain with Tampa Tank or that Tampa Tank was required under its contract with Southern to provide Southern with a copy of CCI's post installation compliance report.
At oral argument before this Court, we asked the parties to supplement their briefs and answer the question whether there was any consideration given by Southern for the alleged 43 or 45-year warranty Southern contends was made as part of the post installation compliance report prepared by CCI for Tampa Tank in 2002. In its supplemental brief, Southern argued that it paid consideration for the warranties of the post-installation report when it paid Tampa Tank's itemized cost of $13,690 for the installation of the cathodic protection system, noting that $1,200 of that amount was "for system testing and the preparation of a final written report." However, Southern cites no Georgia case law to support its position that payments made by a contractor to a subcontractor for services can be co-opted by a third-party beneficiary as consideration. See
(a) As an initial matter, in its amended brief on appeal, Southern argues that the application of the statute of repose to its fifth amended complaint would be unconstitutional because under the theory of freedom to contract, contractual obligations that extend beyond the period of repose should effectively waive the protections of the statute of repose and to rule otherwise would impair the fundamental liberty of landowners to protect themselves by contract. This argument is unavailing. As our Supreme Court noted in its order transferring Southern's appeal to this Court, the Impairment Clause of the Georgia Constitution
(b) Southern contends the trial court erred in applying the statute of repose to Southern's contract and express warranty claims. In support of its argument, Southern contends our Supreme Court's ruling in Turner, 238 Ga. at 518, 233 S.E.2d 773 is controlling, and that under Turner, the renovation of the pre-existing storage tank was not an improvement to realty and therefore not subject to the statute of repose. Southern argues in the alternative that the statute of repose is not applicable here because Southern's complaint does not allege deficient construction but instead alleges the breach of an express promise. We disagree.
OCGA § 9-3-51 (a) provides in relevant part that
In Turner, the City of Adel contracted with Marable-Pirkle to convert the City's electrical distribution system to a higher voltage system. 238 Ga. at 518, 233 S.E.2d 773. "This required the removal of every transformer in the system and replacement of each transformer with a transformer of greater capacity. This conversion also required the replacement of lightning arrestors, fuse cutouts, and other hardware on the poles with similar equipment of greater capacity." Id. at 518, 233 S.E.2d 773. Eleven years after the project was completed, appellant was injured when a roto-tiller that he was operating came into contact with the wire running from one of the City's utility poles. Id. at 518, 233 S.E.2d 773. The Supreme Court concluded that OCGA § 9-3-51 (a) was not applicable in that case because "the mere changing or replacement of such equipment on a pole already erected is not an improvement to realty pursuant to this statute." Id. at 519, 233 S.E.2d 773.
Although the holding in Turner has not been disapproved, we disagree with Southern's contention that Turner's holding is controlling
Mullis, 250 Ga. at 94 (4), 296 S.E.2d 579 (citations omitted). The Court held that the electrical system "clearly qualifies as an improvement to real property," noting the project's permanence, as shown by its "complex system of buildings and electrical components," and that the electrical system is essential to the purpose of the realty. Id.
Applying the Mullis factors to the renovation of the storage tank at issue in the present case, the conversion of the storage tank was a significant undertaking and not a simple repair or addition of component parts. Permanent modifications were made to not only the tank itself but additional components were added to the original design in order for the tank to meet its new intended use as a storage tank for sulfuric acid. The retooling of the tank was integral to the proper functioning of Southern's storage system and it materially enhanced the value of the realty. See Broadfoot v. Aaron Rents, Inc., 195 Ga.App. 297, 300 (1), 393 S.E.2d 39 (1990), aff'd in part, rev'd in part, 260 Ga. 836, 401 S.E.2d 257 (1991) (Under the Mullis standards, statute of repose applied where work done was intended to prolong the life of the brick veneer, to improve the performance of the wall, and to change the original design); Toole v. Georgia-Pacific, LLC, No. A10A2179, 2011 WL 7938847, at *5 (5) (Ga. Ct. App. Jan. 19, 2011) (applying Mullis factors to determine the installation of new insulation and removal of old insulation qualified as an improvement to realty). For these reasons, Appellees' work in converting the storage tank was an improvement to real property within the meaning of OCGA § 9-3-51 (a) and the trial court did not err in granting summary judgment on that issue.
(c) Southern next argues the statute of repose did not apply because its claims do not sound in negligence or construction deficiency, but instead go to a breach of an express promise to renovate the storage tank. We disagree.
Principal Lien Svcs., LLC v. Kimex Boat Rock 1183, LLC, 349 Ga.App. 511, 514-515 (1), 826 S.E.2d 365 (2019) (citations and punctuation omitted).
The applicable statute of repose in this case provides that "[n]o action to recover damages ... [f]or any deficiency in the ... design, ... or construction of an improvement to real property ... shall be brought against any person performing or furnishing... construction of such an improvement more than eight years after substantial completion of such an improvement." OCGA § 9-3-51 (a). In its fifth amended complaint, Southern contends Appellees breached their
This Court's review of the unambiguous language of the OCGA § 9-3-51 (a) finds that the statute makes no distinction among claims sounding in negligence and those sounding in contract. Whether in tort or in contract, the statute broadly precludes any action to recover damages brought outside the eight year period of repose. It is well settled that "a statute of ultimate repose frames the time period in which a right may accrue, if at all. Therefore, if an injury occurs outside this time period, the injury is not actionable[.]" Rosenberg v. Falling Water, Inc., 289 Ga. 57, 59, 709 S.E.2d 227 (2011) (citation omitted). It is undisputed that the storage tank was substantially completed by January 2002 and Southern did not initiate this action until January 2012. Consequently, Southern's breach of contract claims against Appellees arising out of the alleged deficiency in Appellees' planning, design, or construction of the storage tank renovation are barred under OCGA § 9-3-51 (a).
4. Southern next argues the trial court erred in ruling as a matter of law that it failed to exercise due diligence in discovering Appellees' alleged fraud. Southern contends the trial court incorporated by reference its "flawed" reasoning from its July 2015 order into its final order. However, this Court in Southern States II affirmed the trial court's July 2015 judgment and found no evidence of actual fraud or intent to conceal by Appellees such as would preclude them from asserting the defense of the statute of repose. 338 Ga. App. XXVIII at pg. 17. See also Brown v. Piggly Wiggly Southern, Inc., 228 Ga.App. 629, 629 (1), 493 S.E.2d 196 (1997) ("The law of the case rule has formally been abolished except as it applies to rulings by one of the appellate courts; they are binding in all subsequent proceedings." (citation and punctuation omitted)).
5. In light of this Court's holding in Division 3 that the statute of repose bars Southern's claims against Appellees, we need not address Southern's remaining enumeration.
Judgment affirmed.
Markle, J., and Hodges, J., concur.