ROBERT J. FARIS, Bankrupty Judge.
This adversary proceeding arises out of a construction contract between Plaintiff Thomas C. Pearson, as owner, and Defendant Canaan Construction, Ltd. ("Canaan Construction"). Defendant Max Bradford Suiter ("Suiter") is the owner of Canaan Construction. Defendants Canaan Builders, LLC ("Canaan Builders"), 1122 Makepono Street, LLC ("1122 Makepono"), and Raymond T. Suiter ("R.T. Suiter") are affiliated with Suiter. Suiter and R.T. Suiter are brothers.
There has been extensive litigation activity in this case. Pearson's third amended complaint
The parties have filed twenty-four dispositive motions. As is explained in more detail below, some of the motions address core proceedings in which the bankruptcy court can enter final judgment, and others relate to noncore proceedings where the bankruptcy court can only provide recommendations for the district court's de novo review. Adding to the complexity, the core and noncore proceedings share common factual questions. Therefore, this recommendation will be unusually lengthy.
Suiter is the president, sole officer, and principal responsible managing employee of Canaan Construction.
Pearson entered into a contract dated September 17, 2012, with Canaan Construction to remodel and reconstruct of Pearson's home for $1,200,000.
After construction began, disputes arose between the parties. Pearson and Canaan Construction accused each other of breaching the contract. I discuss these disputes in more detail below. Pearson ceased making payments and Canaan Construction stopped work.
On May 27, 2014, Pearson received a letter from Suiter explaining that Canaan Construction was in "some serious financial difficulties," that his brother R.T. Suiter and father Raymond C. Suiter had started Canaan Builders, a new construction company for which Suiter was going to work, and that Canaan Builders wanted to complete Pearson's project-for an additional $682,883.
On January 22, 2015, Suiter filed a chapter 7 bankruptcy petition. This is his second trip to the bankruptcy court; he filed a chapter 7 petition in 2003 and received a discharge.
Pearson claims that Canaan Construction breached the construction contract and is liable to him for the cost of completion and other damages. Pearson also claims that the defendants committed fraud, unfair and deceptive trade acts and practices, and other wrongs. Suiter argues that, to the contrary, Pearson breached the contract and Canaan Construction is entitled to recover the unpaid contract price plus change orders and other damages from Pearson.
There is no dispute that the court has personal and subject matter jurisdiction and venue is proper in this district.
In a "core proceeding," the bankruptcy court can enter final judgment, subject to ordinary appellate review.
In addition, all of Pearson's claims against Suiter are encompassed in the proof of claim that Pearson filed in Suiter's bankruptcy case, and are covered by Suiter's objection to that claim. This dispute about the allowability of Pearson's claims in Suiter's bankruptcy case is a core proceeding.
The remaining claims in the third amended complaint, and all of the claims in Canaan Construction's counterclaim and third party complaint, are not core proceedings. Because the defendants have not consented to the entry of final judgment by the bankruptcy court, the bankruptcy court may not enter final judgment on those claims, but the bankruptcy court may provide proposed findings and a recommended judgment for the district court's de novo review.
The overlap between the core and noncore proceedings further complicates matters. For example, each of the nondischargeability claims against Suiter under section 523 of the Bankruptcy Code, and Pearson's standing to object to Suiter's discharge under section 727, are based on the assertion that Suiter owes a debt to Pearson. All of those claims have their genesis in the construction contract between Pearson and Canaan Construction. Because Canaan Construction is not a debtor in bankruptcy, and Pearson's claims against Canaan Construction are not based on bankruptcy law, Pearson's claims against Canaan Construction are not core proceedings. In other words, before the bankruptcy court can decide the core proceedings between Pearson and Suiter, the district court must decide the noncore proceedings between Pearson and Canaan Construction.
Therefore, any determination in this decision in favor of Pearson on the section 523 and 727 claims is subject to a determination in favor of Pearson on the related noncore claims that Canaan Construction (and therefore Suiter) owes money to Pearson.
In an attempt to make this disposition complete and comprehensible, I will set forth my reasoning on the core proceedings in which I can enter final judgment, as well as the noncore proceedings where I can only recommend that the district court enter a final judgment.
Pearson argues that he is entitled to prevail on his objections to discharge under section 727 even though his claims against Suiter are disputed. Pearson's claims, even though they are disputed, give him standing to maintain this action. But the bankruptcy court should not deny Suiter's discharge unless and until the district court determines that Suiter owes money to Pearson. It would be anomalous to deny Suiter a discharge in bankruptcy, only to determine later that the party who objected to the discharge had no valid claims against him.
The court may dismiss a complaint for "failure to state a claim upon which relief can be granted."
A party may move for summary judgment, identifying each claim or defense, or the part of each claim or defense, on which summary judgment is sought.
Section 502 of the Bankruptcy Code governs the allowance of claims in bankruptcy. Unless a specific bankruptcy defense applies (and none are applicable here), a claim is disallowed only to the extent that the claim is unenforceable under applicable nonbankruptcy law.
A properly filed proof of claim is prima facie valid. An objector bears the initial burden of producing evidence that would negate at least one of the elements of the claim. If the objector meets that burden, then the burden shifts back to the claimant to prove the claim by a preponderance of the evidence. The claimant always bears the burden of persuasion.
Suiter, Canaan Construction, and Canaan Builders filed separate motions to dismiss Pearson's second amended complaint.
Suiter argued that Pearson has no claims against him because Suiter's company, Canaan Construction, not Suiter personally, contracted with Pearson. I recommend that the district court reject this argument. The second amended complaint alleges that Suiter made misrepresentations and personally committed a variety of other allegedly wrongful acts. Under Hawaii law, when an officer, director, or shareholder of a corporation actively or passively participates in wrongful conduct, he or she is "not shielded by the corporation and will be personally liable."
Pearson also argues that Canaan Construction committed numerous unfair and deceptive trade acts, in violation of Haw. Rev. Stat. § 480-2. Hawaii law imposes personal liability on Suiter for such acts.
Thus, the fact that Pearson entered into a contract with Canaan Construction, and not with Suiter personally, does not insulate Suiter from liability from his own tortious or wrongful conduct.
Canaan Construction argued that the court should dismiss the claims against it based on abstention, in favor of a mechanics' lien proceeding brought by Canaan Construction against Pearson in state court. Pearson pointed out that the mechanics' lien case was dismissed before Pearson filed his reply memorandum and that, still later, Canaan Construction filed a new breach of contract action in state court.
28 U.S.C. § 1334(c)(1) provides for discretionary abstention:
According to the Ninth Circuit, a court should consider twelve factors in determining whether discretionary abstention is appropriate:
The court must weigh each of these factors against the others. A court can apply discretionary abstention even if fewer than all of the factors weigh in favor of abstention, and vice versa.
Under the Tucson Estates analysis, the facts of this case weigh against the exercise of discretionary abstention under 28 U.S.C. § 1334(c)(1). All of the claims in this adversary proceeding are closely related to each other. The federal courts have primary, if not exclusive, jurisdiction over some of the most important claims: the claims against Suiter under sections 523 and 727.
The defendants argue that Pearson cannot assert claims to avoid and recover fraudulent transfers because those claims belong exclusively to the trustee. I recommend that the district court agree with this argument and dismiss those claims without leave to amend. Section 548 and similar provisions of the Bankruptcy Code permit "the trustee" to avoid certain transfers. A creditor may not seek avoidance (unless perhaps the trustee agrees to permit the creditor to do so and and the bankruptcy court approves such an agreement).
The defendants argued that Pearson cannot assert "alter ego" claims against the entity defendants because those claims belong to the bankruptcy estate. I recommend that the district court agree. The Bankruptcy Appellate Panel for this circuit has so held.
Suiter argues that the second amended complaint does not adequately allege a claim under section 727(a)(3). That section provides that the bankruptcy court may not grant a discharge if "the debtor has concealed, destroyed, mutilated, falsified, or failed to keep papers, from which the debtor's financial condition or business transactions might be ascertained, unless such act or failure to act was justified under all of the circumstances of the case."
To carry its initial burden,
The statute does not require absolute completeness of the debtor's records but it does require the debtor to keep and preserve records that will allow his creditors to ascertain his financial condition and business transactions.
The second amended complaint alleged that Suiter failed to keep proper records relating to Pearson's project. The failure to keep adequate records concerning a single project, however, may not be sufficiently material to justify denial of the discharge.
The second amended complaint also alleged that the U.S. Department of Labor sued Suiter and one of the entities for failure to keep adequate records, and that the suit was resolved by a consent judgment. The second amended complaint did not describe what records were at issue or allege that the records in that case were ones "from which the debtor's financial condition or business transactions might be ascertained" or that the failure to keep records was not justified within the meaning of section 727(a)(3).
Therefore, the section 727(a)(3) claim should be dismissed with leave to amend.
Suiter argued that the second amended complaint did not adequately allege a claim under section 523(a)(4). That section provides that a chapter 7 discharge does not discharge a debt for "fraud or defalcation while acting in a fiduciary capacity, embezzlement, or larceny. . . ."
The second amended complaint alleged that Suiter owed Pearson fiduciary duties of loyalty and the like, but it did not adequately allege that Suiter acted in a fiduciary capacity within the narrow meaning of section 523(a)(4).
To prove embezzlement, the plaintiff must prove "`(1) property rightfully in the possession of a nonowner; (2) nonowner's appropriation of the property to a use other than which [it] was entrusted; and (3) circumstances indicating fraud.'"
The second amended complaint alleged that Suiter obtained payments from Pearson but did not pay certain bills related to Pearson's project. In order to state a claim for embezzlement under section 523(a)(4), the complaint would have to allege that Pearson continued to own the money after he paid it to Canaan Construction and that Pearson entrusted the money to Canaan Construction expressly to pay expenses for the project and not for any other purpose. These allegations were missing.
Therefore, the section 523(a)(4) claim should be dismissed with leave to amend.
Suiter argued that the second amended complaint did not adequately allege a claim under section 523(a)(2)(B).
A chapter 7 discharge does not discharge an individual from any debt for money to the extent that the debtor obtained it by "false pretenses, a false representation, or actual fraud, other than a statement respecting the debtor's or an insider's financial condition."
If the statement in question is not about the "financial condition" of the debtor or an insider, the plaintiff must prove five elements by a preponderance of the evidence:
A creditor acts in "justifiable reliance" on a debtor's misrepresentation if he did not have notice of the debtor's fraud.
If the statement is about "financial condition," then section 523(a)(2)(B) applies, and the creditor must prove that (1) the statement was in writing; (2) the statement was "materially false," (3) the statement concerned "the debtor's or an insider's financial condition," (4) the creditor "reasonably relied" on the statement, and (5) the debtor "made or published" the statement with "intent to deceive."
The phrase "a statement respecting the debtor's . . . financial condition" has a narrow meaning. Those statements "`are those that purport to present a picture of the debtor's overall financial health.'"
Exceptions to discharge must be strictly construed in favor of the debtor in order to effectuate the Bankruptcy Code's goal of giving debtors a fresh start.
The second amended complaint did not allege that Suiter's misrepresentations about his financial condition, as that phrase is used in section 523(a)(2)(B), were made in writing. Therefore, the section 523(a)(2)(B) claim should be dismissed with leave to amend.
In response to my order on the motions to dismiss the second amended complaint,
Suiter moved to dismiss eight counts of the third amended complaint.
Suiter sought dismissal of various claims for unfair and deceptive trade practices under Haw. Rev. Stat. § 480-2 ("UDAP"). That statute provides that "unfair or deceptive acts or practices in the conduct of any trade or commerce are unlawful." As to counts 116, 117, 119, and 122, he argued that he had no legal duty to disclose the facts that he allegedly omitted or to do the things that he allegedly failed to do. As to count 120, based on alleged unilateral changes of certain project specifications, he argued that the alleged violations amounted to a breach of contract at best and not fraud or a UDAP violation. He also argued that count 123, for various unspecified UDAP violations, was defective because it did not allege any particular act or omission and was only a formulaic recital of the elements of the claim. Pearson responded that the allegations plausibly suggested UDAP violations and fraud claims.
I recommend that the district court deny this portion of the motion, with two exceptions.
The question of whether a particular act or practice is a UDAP violation is a question of fact. Section 480-2 is written broadly in order to provide plaintiffs with a flexible tool to prosecute their claims.
A "`practice is unfair when it offends established public policy and when the practice is immoral, unethical, oppressive, unscrupulous or substantially injurious to consumers.'"
An act is deceptive if it is "`(1) a representation, omission, or practice that (2) is likely to mislead consumers acting reasonably under the circumstances where (3) the representation, omission, or practice is material.'"
Whether an act or practice is unfair is a question of fact.
Except for count 123, the allegations of the third amended complaint are plausible and more than sufficient to give the defendants notice of the claims against them. If the trier of fact believes those allegations, the trier of fact might decide that they add up to UDAP violations. Count 123 should be dismissed, however, because that count is a catchall and does not state any particular facts that might give rise to UDAP liability.
I also recommend that the district court dismiss the portion of count 122 that relates to "weekend workers." A reasonable trier of fact could not find that simply hiring part-time workers, or workers who have other primary jobs, is an unfair or deceptive act or practice.
Suiter argued that count 118, for nondischargeability under section 523(a)(2)(A), should be dismissed. That count alleges that Suiter misrepresented that he had the financial ability to complete Pearson's project and failed to disclose that Canaan Construction was insolvent, subject to numerous liens in substantial amounts, and did not intend to perform under the construction contract. Suiter argued that these are "statement[s] respecting the debtor's or an insider's financial condition" which are covered by section 523(a)(2)(B) and are only actionable if in writing.
I discuss the applicable legal standard in section IV.A.7 above.
The allegation about Canaan Construction's insolvency and financial ability to perform the Pearson contract relate to Canaan Construction's "overall financial health" and are therefore statements about "an insider's financial condition."
Suiter argued that count 129, for denial of discharge under section 727(a)(3), should be dismissed because the records that he allegedly did not maintain were actually not missing or were not material. This count alleged that Suiter discarded Canaan Construction's bookkeeping computer in 2014, that Suiter failed to keep records of his purchase of Canaan Construction from his father in 2006 for $2.5 million, and that the U.S. Department of Labor found that Canaan Construction and Suiter failed to keep adequate employment-related records. In response, Suiter claimed that he backed up the data on the discarded computer and that the other records were not material.
I discuss the applicable legal standard in section IV.A.5 above.
I denied this aspect of the motion. The allegations of the questioned count plausibly allege the claim asserted. The real issues are whether the computer backup exists and whether any missing records are material. These are questions of fact that should not be decided on a motion under rule 12.
Canaan Builders, 1122 Makepono, and R.T. Suiter moved to dismiss the third amended complaint against them in its entirety.
Canaan Builders, 1122 Makepono, and R.T. Suiter first argued that Pearson had no dealings with them, so they could be liable to Pearson only if Suiter is liable to Pearson, and Suiter is not liable. For the reasons explained in section IV.A.1 above, I recommend that the district court not dismiss the complaint on this ground but leave for subsequent determination the question whether Suiter owes money to Pearson.
The moving defendants sought dismissal of the "alter ego" claims (counts 125 and 126). As I explain in section IV.A.4 above, only Suiter's bankruptcy trustee, and not Pearson, is entitled to assert these claims. Therefore, I recommend that the district court dismiss these claims without leave to amend.
The moving defendants sought dismissal of the "civil conspiracy" claims.
The third amended complaint alleges that 1122 Makepono and R.T. Suiter conspired in the fraud when they refused to grant Pearson access to 1122 Makepono's warehouse, a portion of which Canaan Construction was using. Pearson wanted to enter the warehouse to inspect certain cabinets which Canaan Construction claimed it was building for Pearson at that location.
Finally, the moving defendants sought dismissal of the "aiding and abetting" claims.
I recommend that the district court deny the motion as to the civil conspiracy and aiding and abetting claims. The third amended complaint plausibly alleges enough facts to state those claims.
Canaan Construction filed a counterclaim against Pearson
Canaan Construction also filed a third party complaint against Mrs. Pearson
The Pearsons filed motions to dismiss the counterclaim and third party complaint in their entirety on various grounds.
First, the Pearsons argue that Canaan Construction should be judicially estopped from asserting any claims because Suiter represented to the bankruptcy court that Canaan Construction had no assets.
Judicial estoppel is an equitable doctrine invoked by a court at its discretion to "protect the integrity of the judicial process by prohibiting parties from deliberately changing positions according to the exigencies of the moment."
According to Pearson, Canaan Construction should be judicially estopped from pursuing its counterclaim. This argument suffers from multiple fatal flaws.
First, Canaan Construction made no representations to this court. Suiter, not Canaan Construction, is the debtor in the main case, and only Suiter made representations about his assets. The Pearsons offer no authority for the proposition that, for purposes of judicial estoppel, a statement made by the owner of a company is attributed to the company.
Second, Suiter was required to disclose to this court the value of his assets, which include his shares of stock in Canaan Construction. He stated that his stock in the company was worthless. This is not the same as stating that the company has no assets; rather, it means that the value of the company's assets minus its liabilities is less than or equal to zero. In other words, Suiter's representation to this court that his stock in Canaan Construction was worthless is not a representation that Canaan Construction has no claims against Pearson.
Third, one premise of the judicial estoppel doctrine is that the debtor has gotten a benefit-usually in the form of a discharge-based on the representation about the debtor's assets. In this case, however, Suiter has not yet gotten his discharge (because Pearson has objected under section 727), and therefore has not benefitted from his representations about his assets.
Therefore, I recommend that the district court deny the motion as to the judicial estoppel theory.
The Pearsons also argued that the court should dismiss count 1 of the counterclaim and third-party complaint, for breach of contract, and count 5, for breach of the implied covenant of good faith and fair dealing, because the district court should hold that the contract is void.
The Pearsons are correct. In section IV.D, I explain why the contract violates section 480-2. Under the plain language of Haw. Rev. Stat. § 480-12,
The Pearsons also argued that the court should dismiss count 2, for quantum meruit or unjust enrichment, and count 3, for promissory estoppel or detrimental reliance. They point out that, under section 480-13, a contract that is void under chapter 480 is not enforceable "at law or in equity [emphasis added]." The Hawaii Intermediate Court of Appeals has held, however, in Hiraga v. Baldonado,
The Pearsons also sought dismissal of count 4, which alleged tortious interference with contract and business relations. The Pearsons claimed that this count could not stand because the alleged interference occurred in November 2014, six months after Canaan Construction admittedly shut down its own business, and because there is no allegation that the Pearsons had any knowledge of the business with which they allegedly interfered. Canaan Construction responded that, although it ceased operations, it is still an active company and that the Pearsons knew of Canaan Construction's ongoing business relationship with Ferguson Enterprises.
Tortious interference with a contract requires:
To prevail on a claim for tortious interference with prospective business advantage, Canaan Construction must establish:
The Pearsons argue that the construction contract is void. This is correct (as I recommend in section IV.D) but irrelevant. Party A is not free to interfere with Party B's contract or business dealings with Party C, even if Party A and Party B have no valid contract.
The allegations of count 4 are not ideal but they plausibly allege claims. Therefore, I recommend that the district court deny dismissal of count 4.
Later, the Pearsons filed a motion for partial summary judgment on the same count.
Canaan Construction will bear the burden of proof at trial on its counterclaims, and it has had more than adequate time to conduct discovery.
The six elements of tortious interference with contract are set out in section IV.C.1.(c).
Canaan Construction has failed to prove the first element. It offers no evidence that it had a contract with any of the suppliers whom the Pearsons contacted. Canaan Construction presumably bought materials from the suppliers from time to time, but that does not amount to an ongoing contract.
Canaan Construction has also failed to prove the second element. Canaan Construction has shown that the Pearsons knew it bought materials from the suppliers, but has not shown that the Pearsons knew that Canaan Construction had a contract with any of them.
If Canaan Construction had proven the first two elements (and it has not), there would be a genuine dispute of fact concerning the Pearsons' intentions. There is no direct evidence of their mental state, but summary judgment should rarely be granted on a question of intent, and the trier of fact might conceivably draw an inference about the Pearsons' intentions from their conduct.
Similarly, if Canaan Construction had proven the first two elements (and it has not), there would be a genuine dispute of fact concerning justification. The Hawaii courts have adopted a rather indefinite definition of justification in this context.
Canaan Construction has failed to establish the fifth element. Because Canaan Construction has not offered any evidence that it had a contract with any of the suppliers, it has also not offered evidence that any such contract was breached.
Canaan Construction has failed to prove the sixth element. There is no evidence that the Pearsons' conduct damaged Canaan Contruction. "It is of the essence in an action for wrongful interference with contractual relationships that the plaintiff suffer damages as a consequence of the defendant's conduct, and these damages cannot be speculative or conjectural losses."
Because Canaan Construction has failed to offer any admissible evidence on some of the elements of the claim for tortious interference with contract, the district court should enter partial summary judgment in favor of the Pearsons on that claim.
I discuss the five elements of a claim for tortious interference with prospective business advantage in section IV.C.1.(c).
Canaan Construction has failed to create a genuine dispute of fact concerning the first element. It is clear that Canaan Construction had business relationships with the suppliers, but once Canaan Construction's business failed (for reasons unrelated to the Pearsons' contact with the suppliers), there was no "reasonable probability" that the relationships would continue.
Canaan Construction has established the second element. The Pearsons knew that Canaan Construction did business with the suppliers. In fact, the Pearsons spoke to those suppliers precisely because they thought that Canaan Construction might have ordered materials for their job from them.
As in the case of the claim for interference with contract, there is a genuine dispute of fact concerning the Pearson's intentions.
Causation presents a closer question. According to Suiter, the Pearsons' comments affected Canaan Construction's relations with the suppliers, but the relationship would have been severed anyway when Canaan Construction closed its doors. Because Canaan Construction has not proven other elements of this claim, however, it is not necessary to consider this element further.
Finally, as in the case of the interference with contract claim, Canaan Construction offers no admissible evidence of non-speculative damages.
Because Canaan Construction has failed to offer any admissible evidence to prove some of the elements of its claim for tortious interference with prospective business advantage, the district court should enter partial summary judgment on that claim in favor of the Pearsons.
Pearson filed a motion for partial summary judgment on counts 3, 4, and 5 of the third amended complaint.
Count 3 alleges that Canaan Construction and Suiter failed to disclose Pearson's bonding rights and Canaan Construction's lien rights and include a provision in the contract explaining the bonding and lien rights, contrary to Haw. Rev. Stat. § 444-25.5.
Count 4 alleges that Canaan Construction and Suiter failed to identify subcontractors to be used or the approximate percentage of work to be subcontracted as required by Haw. Admin. R. § 16-77-79(a)(3)
Count 5 alleges that Canaan Construction and Suiter failed to provide the Contractor Repair Act notice as required by Haw. Rev. Stat. §§ 672E-11(b)
In his opposition,
Suiter also cited provisions of the construction contract. Section A.11.5.1 of the contract sets forth the Owner's (Pearson's) right to require the Design-Builder (Canaan Construction) to furnish bonds.
Suiter declared that Canaan Construction provided Pearson with weekly or semi-monthly Field Reports, each of which listed any subcontractors currently involved in the project in the top right corner.
In his declaration, Suiter made a conclusory statement that he, on behalf of Canaan Construction, "provided the disclosures required under [Haw. Rev. Stat.] § 444-25.5."
Specifically, although section A.11.5.1 of the construction contract gives Pearson the right to demand bonding, it does not "explain" Pearson's bonding rights or the lien rights of Canaan Construction and its subcontractors and suppliers, disclose the approximate cost of a bond, or provide that Pearson had waived his rights to the bonding and lien rights disclosures.
Similarly, there is no written disclosure of the approximate percentage of work to be subcontracted. (Pearson argued that Canaan Construction and Suiter were required to disclose the identity of any subcontractors, but neither the statute nor the regulation requires that disclosure.) Canaan Construction and Suiter cite section A.9.10.2 of the Contract, but that section does not disclose the percentage of work to be subcontracted.
Finally, Suiter offers no evidence that he or Canaan Construction provided the Contractor Repair Act notice as required by sections 672E-11 and 444-25.5(b)(2). Section A.12.2 of the Contract does not contain all of the required information.
Therefore, I recommend that the district court enter a partial summary judgment determining that Suiter and Canaan Construction failed to provide the necessary written disclosures and notices, and that therefore these defendants violated section 480-2.
This violation has important implications. First, the construction contract is void.
Pearson filed a motion for partial summary judgment on counts 2 and 3 of the counterclaim. In those counts, Canaan Construction sought recovery on quantum meruit and other equitable grounds. Pearson's motion sought to limit Canaan Construction's maximum possible claim.
Section 1.3 of the contract provides that it could only be modified by a change order or other writing.
The parties signed eight numbered change orders and one document called a proposal which was a change order in substance.
Disputes arose among the parties. Pearson disputed the payment applications presented by Canaan Construction and, in late 2013, Canaan Construction stopped work on the project.
Hawaii law requires construction contractors to give specific disclosures in writing to homeowners. I have recommended (in section IV.D above) that the district court grant partial summary judgment holding that Canaan Construction did not give Pearson all of the required written disclosures and that, as a result, the construction contract is void.
Under Hiraga v. Baldonado, the voidness of the contract does not deprive Canaan Construction of the right to recover from Pearson in quantum meruit.
This formula produces a sensible result: if a construction contract is void because the contractor did not comply with the law, the contractor can never recover more than the contractor could have recovered if the contract were valid. If this were not the rule, a contractor who broke the law could earn more than one who did not.
The Hiraga formula requires the court to calculate how much Canaan Construction could have recovered from Pearson if the contract were valid. The Pearsons argue that Canaan Construction is not entitled to recover the amounts set forth in Change Order 9 under the contract, and that therefore Canaan Construction's maximum recovery on a quantum meruit theory must not include those charges.
I recommend that the district court enter a partial summary judgment determining that the amounts reflected in Change Order 9 may not be included in the Hiraga cap on Canaan Construction's possible equitable recovery.
The Pearsons argue that Change Order 9 is invalid in its entirety because Canaan Construction did not give written notice before commencing the additional work and did not timely seek an adjustment of the contract price, in accordance with the contract. Canaan Construction says that the Pearsons authorized all of the work reflected in Change Order 9, but does not deny that Canaan Construction failed to follow the process spelled out in the contract.
At first blush, it seems odd to hold Canaan Construction to the requirements of a void contract. But one must remember that the contract is void because Canaan Construction did not follow Hawaii law. It would be anomalous and unfair to deprive Pearson of the contract's protections because of Canaan Construction's misconduct. Further, the Hiraga formula requires the court to determine how much would have been owed under the contract. One cannot determine that amount without also determining whether the contractor complied with the procedural requirements of the contract.
Because Canaan Construction does not deny that it failed to follow the contractual process for change orders and adjustments, Change Order 9 is not enforceable against Pearson, and the amounts claimed in Change Order 9 may not be added to Canaan Construction's maximum quantum meruit recovery.
Canaan Construction argues that the Pearsons are bound by Change Order 9. Pearson never signed Change Order 9. Canaan Construction argues, however, that a construction consultant retained by Pearson sent an email to Suiter in which the consultant agreed to Change Order 9,
First, the Pearsons point out that, under the contract, Pearson was the "Designated Representative" of the owner, and the consultant never became a "Designated Representative."
Second, the Pearsons point out that, under Hawaii law, a construction contract must be in writing and signed by the owner.
Third, the Pearsons argue that the consultant's email is a settlement communication that is inadmissible under Fed. R. Evid. 408.
But Canaan Construction's argument rests on a partial, cherry picked, out of context quotation from the consultant's email. Read in its entirety, it is clear that the consultant was discussing a possible global resolution of the dispute between Pearson and Canaan Construction. It is not reasonable to read the email as accepting Change Order 9 in the absence of a mutually acceptable global resolution (which never came to pass). Regardless of whether the consultant had actual or apparent authority to bind Pearson to Change Order 9, it is clear beyond any genuine dispute that the consultant did not intend to bind Pearson to Change Order 9 in the absence of a complete settlement. Therefore, summary judgment on those points should be granted.
Pearson also objects to most of the specific items claimed in Change Order 9. If the district court accepts my recommendation and enters a partial summary judgment determining that Change Order 9 must not be included in the cap on Canaan Construction's possible equitable claims, then Pearson's specific objections would be irrelevant. But, if the district court rejects that recommendation, I recommend that the district court enter a partial summary judgment concerning some of those subsidiary issues.
The Pearsons argue that Suiter represented that Canaan Construction would not charge for much of the work described in Change Order 9 (the pool equipment pad, the extension of stairs, and the sweet filters). Canaan Construction does not respond to this argument. Even assuming that Change Order 9 is enforceable against Pearson at all, the Pearsons are entitled to partial summary judgment on this point.
The Pearsons claim that Canaan Construction agreed to provide the plumbing fixtures for a flat amount of $25,000 plus $4,774.10 documented in Change Order 1, and that the claim in Change Order 9 for an additional $19,489.88 for the plumbing fixtures is unauthorized. Suiter repeatedly confirmed that Canaan Construction would charge $25,000 for the plumbing fixture package (plus the additional amount agreed to in Change Order 1) regardless of its cost.
This statement completely ignores Suiter's repeated statements that Canaan Construction would provide the plumbing package for $25,000 plus the Change Order 1 amount, even though the actual cost was higher. Even if Change Order 9 is enforceable against Pearson, the Pearsons are entitled to summary judgment on this point.
The Pearsons argue that Canaan Construction never completed many of the items described in Change Order 9. Canaan Construction concedes that this argument is partly correct; it says that "Change Order #9 includes work completed on the Pearson residence as well as work not yet finished, but was in progress . . . ."
Assuming that Canaan Construction is entitled to recover for any of the work covered by Change Order 9, there is a genuine dispute of material fact concerning the amount (if any) that Canaan Construction would be entitled to recover under the contract for the work that was incomplete but "in progress" at the date of termination. (To the extent Canaan Construction is not entitled to recover for such work under the contract, its maximum quantum meruit recovery must also be reduced.)
The Pearsons contend that, when Pearson agreed to drop his objections and pay the amounts requested in Pay App 12, Canaan Construction agreed to waive some or all of the claims covered by Change Order 9. But the email exchange which the Pearsons cite is cryptic at best.
Pearson contends that Canaan Construction is not entitled to charge for repairs to a retaining wall because it had given Pearson a warranty of the "structural integrity" of the same wall.
Pursuant to a proposal dated November 18, 2012, and covered by Change Order 1, Canaan Construction installed micropiles to address possible movement of a retaining wall. Canaan Construction provided a "warranty [of] the structural integrity of the CMU repaired wall as long as the Pearsons, Tom, Julia, and Alicia own the home."
During October 2013, water began to leak through the retaining wall. Canaan Construction determined that "some of the waterproof barrier that was applied by Canaan Construction LTD on this Main Retaining Wall last year was delaminating. . . . [T]he waterproofing on the street side of the Main Retaining wall has failed since it was applied when the wall was built. The Hydrostatic pressure is too much for the inside membrane to hold."
There is a genuine dispute of material fact concerning the meaning of the term "structural integrity" in the warranty. One could read the term narrowly as a promise that the wall would not collapse; the record does not establish that the wall would have fallen down if the additional sealing were not done. One could also read the term more broadly and include watertightness as an aspect of "structural integrity;" this reading would be particularly plausible if it were shown that water leaks could have undermined the foundation of the wall. But I can not exclude either of these interpretations on this record. Summary judgment on this point should be denied.
Pearson filed a motion for partial summary judgment on counts 6, 13, 20, 27, 34, 41, 48, 55, 60, 67, 74, 81, 88, 95, 102, 109, 116, 130, 137, 144, 151, 158, 165, and 168 of the third amended complaint.
(1) failing to disclose to Pearson, when Canaan Construction entered into a construction contract with Pearson, that Canaan Construction was subject to numerous unpaid tax liens;
(2) using a letterhead during the design phase of the project that used a name other than that of Canaan Construction;
(3) offering to complete the job for $1.2 million, while knowing that the job would actually cost much more;
(4) submitting false payment applications; and
(5) billing and receiving payment for labor and supplies that Canaan Construction never provided.
Count 168 of the third amended complaint alleges that Canaan Construction, Suiter, Canaan Builders, and R.T. Suiter also violated section 480-2 by:
(6) submitting an offer to complete the job, after Canaan Construction had closed its doors, for an additional $682,883.
The defendants deny most of Pearson's factual predicates.
(1) Canaan Construction had made arrangements to satisfy the lien claims such that they would not prevent Canaan Construction from completing the job, and in any event construction contractors do not owe a duty to disclose liens to their clients;
(2) Suiter used obsolete letterhead due to inadvertence and with no intention to deceive, and because the construction contract contained the correct name, Pearson was not misled;
(3) Canaan Construction did not underbid the job; the increases in cost were due to Pearson's delays and demands for upgrades and changes;
(4) and (5) Pearson knew and agreed that the payment applications did not accurately reflect the actual state of completion of the job, and that Canaan Construction was "billing ahead" to cover the cost of extras demanded by Pearson; and
(6) the offer to complete the work was made by Canaan Builders, a separate company controlled by R.T. Suiter, not by Suiter or Canaan Construction, was made at the request of a representative of Pearson, and was not wrongful.
I recommend that the district court deny this motion because there are many genuine disputes concerning the factual question of whether the defendants' conduct was "unfair" or "deceptive." I find much of Suiter's testimony implausible, but the court may not weigh conflicting evidence on a motion for summary judgment unless one side's evidence is so weak that the court would not even present it to a jury, and that exception does not apply here.
Pearson filed a motion for partial summary judgment on counts 127 and 128 of the third amended complaint.
Under section 727(a)(2)(A), the bankruptcy court may not grant a discharge if the debtor transferred "property of the debtor" within one year before he filed for bankruptcy with the intent to hinder, delay, or defraud creditors.
Section 727(a)(2)(A) can apply when a debtor deposits paychecks into a bank account in his wife's name, and over which he has no control, in order to "diminish the amount of money creditors would be able to obtain from a judgment against him."
Suiter testified that when he received a paycheck from Canaan Construction and, after that company ceased doing business in June 2014, for work as a handyman, he would either cash the check or sign it over to his wife so she could deposit it in her checking account.
Suiter and his attorney both have submitted declarations stating that, during meetings with the IRS in an attempt to resolve Suiter's tax liabilities, they told the IRS agents that Suiter did not have a personal bank account and that "I was depositing funds into an account owned solely by my wife."
Suiter does not deny that, when he deposited his paychecks into his wife's account, he transferred "property of the debtor," and that these transfers occurred within one year before his bankruptcy filing. Suiter also does not attempt to contradict or explain away his testimony at the meeting of creditors that he did so in order to avoid a possible garnishment by the IRS. He says, however, that he and his attorney told the IRS about this practice. This testimony does not negate his intent to hinder the IRS. In the first place, Suiter does not say when he told the IRS that he was depositing his paychecks in his wife's account, so the practice could have been going on for some time before he made the disclosure. Further, despite disclosure, the fact that the money was in his wife's account would have made it more difficult for the IRS to garnish that account. It is much easier to garnish an account in the name of the debtor than it is to garnish an account in someone else's name, even if that account may hold funds belonging to the debtor. In other words, even if Suiter told the IRS about the deposits, his practice of stashing his money in his wife's account still hindered the IRS.
Pearson is therefore entitled to partial summary judgment on this issue.
Section 727(a)(4)(A) provides that the court may not grant a discharge if the debtor "knowingly and fraudulently in connection with the [bankruptcy] case . . . made a false oath or account. . . ."
Providing false information, or failing to provide required information, in the debtor's schedules or statement of financial affairs can be a false oath within the meaning of section 727(a)(4)(A).
Although the text of section 727(a)(4)(A) does not mention a materiality requirement, judicial interpretations have imposed one. It is settled, however, that "[m]ateriality is broadly defined."
In general, "[a] false statement is material if it bears a relationship to the debtor's business transactions or estate, or concerns the discovery of assets, business dealings, or the existence and disposition of the debtor's property."
The test of materiality is not limited to the dollar value of the undisclosed items. Therefore, "[a] false statement or omission may be material even if it does not cause direct financial prejudice to creditors."
A debtor "knowingly" makes a false oath "if he or she acts deliberately and consciously," rather than carelessly or recklessly.
In order to establish that the debtor made false oaths "fraudulently," the objector must show that the debtor "made them with the intention and purpose of deceiving the creditors. . . ."
I now must apply these definitions to each of the statements which Pearson identifies.
First, Pearson claims that Suiter made three different statements about the date on which Canaan Construction ceased operations. In his statement of financial affairs, Suiter swore that the "ending date" of Canaan Construction was "5-2014."
Second, Pearson points out that, in his schedule I, Suiter swore that he was self-employed on the date of his bankruptcy filing (in January 2015) and had been self-employed for two months. Pearson claims that, in truth, Suiter was employed by Canaan Builders at that time. At his meeting of creditors, Suiter testified that he worked as an independent contractor for Canaan Builders beginning in November 2014 and did not become an employee of that company until March 2015. Pearson argues that this cannot be true because Suiter became the "Principal Responsible Managing Employee" of Canaan Builders on July 23, 2014.
Third, Pearson argues that Suiter stated in schedule I that his wife's income was only $350 per month but said in his meeting of creditors that she makes about $1,000 per month. Suiter claims that he misspoke during the meeting of creditors, that her income had fallen, and that the figure listed in schedule I was correct.
Fourth, Pearson claims that Suiter failed to disclose rental income in his statement of affairs. According to Suiter's unrebutted declaration, however, the properties which generated the income did not belong to Suiter, but rather to his wife's trust.
Fifth, Pearson points out that Suiter failed to disclose in his schedules and statement of affairs that he had been depositing his checks into his wife's bank account. Pearson claims that Suiter should have disclosed this in response to question 7 of the statement of financial affairs, which requires debtors to disclose gifts to family members of more than $200. Suiter responds to this only indirectly, saying that the funds in his wife's account were used for "the payment of joint household expenses and debts for which I am personally liable."
Sixth, Pearson points out that, in his 2003 bankruptcy case, Suiter indicated that he had a pension account with a value of $8,200, but no pension plan was listed in his 2015 bankruptcy filing. Suiter testifies in his declaration that he cashed out his pension plan in the twelve year period between the two bankruptcy cases. Pearson offers no evidence to the contrary. Thus, Pearson has offered no evidence that Suiter made a false statement in this respect and partial summary judgment on this point must be denied.
Seventh, Pearson argues that Suiter failed to disclose the assets of Canaan Construction. The schedules required Suiter to identify and value all assets he owns, including his ownership of separate legal entities, but did not ask him to list or value the assets of those separate legal entities. In this case, Suiter disclosed his ownership of Canaan Construction and claimed that his ownership interest in the company was worthless. There is no evidence that these statements were false. Thus, partial summary judgment must be denied.
Finally, Pearson argues that Suiter made a false statement when he did not provide any information in response to question 10.b of the statement of financial affairs, which requires the debtor to "[L]ist all property transferred by the debtor within ten years immediately preceding the commencement of this case to a self-settled trust or similar device of which the debtor is a beneficiary."
Pearson filed a motion for summary judgment as to count 129 of the third amended complaint.
Pearson states that between 2012 and 2014, Canaan Construction had its accounting done in house by a bookkeeper. The accounting included billings for jobs and payments made to subcontractors and suppliers. Pearson alleges that after Canaan Construction shut down in May 2014, Suiter simply threw away the bookkeeper's computer.
The third amended complaint alleges that Suiter purchased Canaan Construction from his father in 2006 for $2,500,000 but the agreement was never formalized. Suiter admitted that he stopped making payments in 2007. He was unable to state how much he paid or how much he still owed.
The complaint further alleges that, despite repeated requests, neither Canaan Construction nor Suiter have produced Canaan Construction's general checking account ledger, bank account statement and deposit slips, records of labor expenses, contracts evidencing any other projects that were in progress, records of payments received, loans, advances made to third parties, or communications between the defendants regarding the Pearson project.
Suiter opposed Pearson's motion and filed a countermotion.
Suiter claimed that, although he no longer had the computer, the records were backed up onto a server and would be produced once a protective order is in place. Suiter said that he did not hide the fact that he bought Canaan Construction, and the transaction occurred too long ago to have a bearing on the bankruptcy case.
I discuss the legal standard applicable to section 727(a)(3) in section IV.B.1.(c) above.
I denied this motion. Suiter represented that the records on the computer were backed up to a server; if that proves true, the disposal of the computer could be unimportant. Pearson has not shown that the records concerning Suiter's purchase of Canaan Construction from his father meet the statutory standard; the purchase transaction and the last payment occurred many years before the bankruptcy filing. The absence of records of such an old transaction does not make it "impossible" to ascertain Suiter's financial condition. Considering the limited discovery that had been conducted when the motion was heard, there was not enough information in the record to permit me to ascertain what records were truly missing and the significance, if any, of those records. (Pearson later filed another motion for partial summary on these counts, which I discuss in the following section.)
Counts 128 and 129 of the third amended complaint contend that the court must deny Suiter's discharge because he allegedly concealed, destroyed, or failed to keep records from which his financial condition could have been ascertained, within the meaning of section 727(a)(3), and uttered false oaths in the bankruptcy case satisfying section 727(a)(4)(A). Pearson filed a motion for summary judgment on those counts.
In this motion, Pearson relied on two missing sets of documents to substantiate his section 727(a)(3) claim. I discuss the applicable legal standard in section IV.B.1.(c) above.
The first is Canaan Construction's unfiled tax returns for 2012-14. Suiter acknowledged that his now-defunct company, Canaan Construction, did not file tax returns for 2012-2014.
The second set of documents on which Pearson relied is Canaan Construction's checking account statements. Suiter acknowledged that his counsel did not initially produce to Pearson copies of Canaan Construction's checking account statements.
As I discuss in section IV.G.2 above, section 727(a)(4)(A) relates to false oaths in a bankruptcy case. The false oaths on which this motion relied are Suiter's failure to disclose an interest in the property of Mrs. Suiter's trust and the transfer of Suiter's interest in certain property to the trust.
On February 11, 2008, Suiter's wife, Mary Suiter, created a trust to facilitate the estate plan of Suiter and herself. Shortly thereafter, Suiter and Mrs. Suiter transferred two pieces of real property, including their residence, to the trust. Neither party has provided a copy of the trust agreement, apparently because the copy which Suiter produced to Pearson is nearly illegible. In response to requests for admissions, Suiter admitted that (1) Mrs. Suiter is the settlor, initial trustee, and primary lifetime beneficiary of the trust; (2) he is the successor trustee of the trust, the sole beneficiary of the marital trust after his wife passes, and the beneficiary (along with his children) of the family trust; (3) the trustee has discretion to use the net income and principal of the trust in the best interests of Suiter and Mrs. Suiter; and (4) the trust gives Suiter the right, during Mrs. Suiter's lifetime, to occupy and use the residence.
Suiter did not list the trust's real estate on his schedule A or statement of financial affairs based on his attorneys' advice. Suiter's counsel says that he decided that Suiter did not need to disclose the real property on schedule A because counsel "generally only list[s] property on a debtor's Schedules if the debtor's name is actually on title to said property."
Suiter says that he disclosed the circumstances to, and relied on the advice of, his counsel when he completed his schedules.
Finally, Pearson argues that Suiter made a false statement when he did not provide any information in response to question 10.b of the statement of financial affairs, which requires the debtor to "list all property transferred by the debtor within
Pearson filed a motion for partial summary judgment on Count 21. That count alleges that Suiter committed fraud when he, on behalf of Canaan Construction, charged Pearson for certain work on windows that was never completed, and that his liability is not dischargeable under section 523(a)(2).
The contract specifications required Canaan to order and install "top of the line Fleetwood window and door systems."
The contract provided that Canaan Construction would submit monthly applications for payment ("Pay Apps").
Each Pay App included a statement signed by Suiter on behalf of Canaan Construction that "the undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the work covered by this Application for Payment has been completed in accordance with the Contract Documents. . . ."
Suiter, on behalf of Canaan Construction, delivered to Pearson several Pay Apps representing that portions of the window work had been completed.
Pearson paid the amounts requested in Pay App 4, 9, 11, and 12.
Each Pay App represented that the total scheduled value of the windows order and installation was $135,500.00.
Suiter, on behalf of Canaan Construction, also provided to Pearson numerous "field reports," which falsely implied that the windows were "completed and stored to date."
The representations in the Pay Apps and field reports were false. The windows were never installed at the project or delivered to the project site. It is not clear that Suiter had any intention to "initiate the order now" when he represented such in his January 25, 2013 email. Suiter never made the deposit for the windows as he represented on January 25, 2013.
Suiter admits that, "The Pay Apps did not accurately reflect the work progress as of the date of each Pay App due to the numerous delays to the project by the Pearsons and not making timely approvals and repeated requests for free work and numerous upgrades to the project."
Suiter also says that the Pearsons were aware that the Pay Apps were not accurate and that "the Pay Apps would bill in advance for work not yet then completed."
But in early October 2013, Pearson confirmed his knowledge that the Pay Apps did not accurately reflect the progress of the work. On October 7, 2013, Pearson e-mailed Suiter to express concerns over numerous discrepancies between the represented progress in Pay App 12 and the actual work completed.
I discuss section 523(a)(2) in section IV.B.1(b) above.
Suiter admits that the Pay Apps falsely represented the extent to which the window work was completed, and that he knew those statements were false. Pearson is entitled to partial summary judgment on those points.
Suiter also testifies that the Pearsons knew that the Pay Apps were false in this respect "through a combination of emails, oral discussions, and course of dealing (i.e. payments). . . ."
In addition, Pearson's own communications show that, at least by October 2013, he suspected that the Pay Apps were false. He could not have justifiably relied on the Pay Apps when he paid Pay App 12.
Summary judgment on the issue of damages must also be denied. If the court determines that Pearson breached the contract and owes money to Canaan Construction, the court might determine that Suiter's misrepresentations did not cause any net injury to Pearson.
I will grant Pearson's motion for partial summary judgment in part, determine that the statements in the Pay Apps about the progress of the window work were false and that Suiter knew they were false, and deny the motion in all other respects.
Pearson filed a motion for partial summary judgment on count 35, which alleges that Suiter committed common law fraud when he, on behalf of Canaan Construction, charged Pearson for cabinet work that was never done.
The contract specifications required Canaan to fabricate and install a "complete cabinet package."
Section A.3.15.1 of the contract provides that Canaan Construction "shall provide [Pearson] access to the Work in preparation and progress wherever located."
Suiter, on behalf of Canaan Construction, delivered to Pearson several Pay Apps representing that portions of the cabinet work had been completed.
Pearson paid the amounts requested in Pay App 5, 7, 10, 11, and 13.
Each Pay App represented that the total scheduled value of the complete cabinet package was $90,000. Thus, Pay App 13 represented that Canaan Construction had completed slightly more than 90% of the work on the cabinet package.
This representation was false. The cabinets were never installed at the project or delivered to Pearson. It is not clear that any cabinets were built; Pearson repeatedly sought permission to inspect the cabinets 1122 Makepono's warehouse (where Canaan Construction had its shop), but Suiter consistently refused. Suiter says he cannot recall these conversations and that Pearson could not have entered the warehouse due to OSHA and safety regulations.
As is noted above, Suiter admits that, "The Pay Apps did not accurately reflect the work progress as of the date of each Pay App due to the numerous delays to the project by the Pearsons and not making timely approvals and repeated requests for free work and numerous upgrades to the project."
Suiter also says that the Pearsons were aware that the Pay Apps were not accurate and that "the Pay Apps would bill in advance for work not yet then completed."
The analysis of count 35 as the same as count 21, discussed in the preceding section.
I will grant Pearson's motion for partial summary judgment in part, determine that the statements in the Pay Apps about the progress of the cabinet work were false and that Suiter knew they were false, and deny the motion in all other respects.
Pearson filed a motion for partial summary judgment on count 33 of the third amended complaint. This count alleges that Canaan Construction and Suiter fraudulently billed and collected for a photovoltaic ("PV") system that Canaan Construction did not install in Pearson's construction project, and that Suiter's liability is nondischargeable under section 523(a)(2)(A).
It is undisputed that:
(1) Canaan Construction and Pearson entered into Change Order 2, pursuant to which Canaan Construction agreed to provide a PV system for $58,950;
(2) Pearson paid a 50% deposit of $29,475;
(3) Canaan Construction and Suiter presented payment applications to Pearson that represented that $45,075 of the PV work was done and Pearson paid the amount demanded; and
(4) Other than steel mounting brackets on the roof to hold the PV panels and conduit routed to the roof, Canaan Construction did not complete any part of the PV system or make any PV equipment available to Pearson.
The following facts are disputed:
(1) Canaan Construction and Suiter claim that Pearson agreed and understood that the pay applications did not reflect the actual progress of the job because Canaan Construction was "billing ahead" on account of extra work requested by Pearson. Pearson denies that there was any such agreement.
(2) Canaan Construction and Suiter claim that Canaan Construction had begun work on design and permitting of the PV system and had installed the steel roof brackets to hold the PV panels.
(3) Pearson argues that the roof mounting brackets were defective, that Canaan Construction had cracked some of the roof tiles, and that he had to pay $7,068 for corrective work.
I will grant Pearson's motion for partial summary judgment in part, to the same extent and for the same reasons discussed in section IV.J and K above regarding the cabinet and window claims.
Pearson filed a motion for partial summary judgment on counts 47, 54, and 59 of the third amended complaint. Those counts allege that Canaan Construction and Suiter fraudulently billed and collected for T&G, gypboard, and finished carpentry work on Pearson's construction project, that Canaan Construction did not actually perform for which Pearson paid, and that Suiter's liability is not dischargeable under section 523(a)(2)(A).
It is undisputed that:
(1) Canaan Construction and Pearson entered into a construction contract that provided that Pearson would pay for the work based on pay applications reflecting the value of the work completed and stored to date.
(2) Canaan Construction and Suiter presented payment applications to Pearson that represented that $42,650 of the finished carpentry work, $36,265 of the T&G work, and $14,001 of the gypboard work had been completed;
(3) Pearson paid the amount demanded; and
(4) Canaan Construction did not complete all of the finished carpentry, T&G, or gypboard work.
The following facts are disputed:
(1) Canaan Construction and Suiter claim that Pearson agreed and understood that the pay applications did not reflect the actual progress of the job because Canaan Construction was "billing ahead" on account of extra work requested by Pearson. Pearson denies that there was any such agreement.
(2) The extent of completion of the finished carpentry, T&G, and gypboard work is disputed.
I will grant Pearson's motion for partial summary judgment in part, to the same extent and for the same reasons discussed in section IV.J and K above respecting the cabinet and window claims.
Pearson filed a motion for partial summary judgment on counts 12 and 19 of the third amended complaint. Those counts allege that Canaan Construction and Suiter fraudulently billed and collected for stone building materials that Canaan Construction did not even purchase, let alone install in Pearson's construction project, and that Suiter's liability is nondischargeable under section 523(a)(2)(A).
The construction contract valued the total work on stone floors, stone counters, and the pool deck at $172,800.
Canaan Construction and Suiter do not deny that several pay applications they presented to Pearson stated that $123,304.62 of the stone work had been completed, and that Pearson paid that amount.
Pearson claims that Canaan Construction did not install any stone on the job site before Canaan Construction stopped work. Canaan Construction and Suiter do not deny this assertion.
Suiter claims that Canaan Construction paid a supplier $39,965 as a deposit against the purchase price for the stone and to compensate the supplier for storing the stone until needed.
Suiter claims (and Pearson denies) that Pearson knew that the pay applications were false, and that Canaan Construction was "billing ahead" for extra work requested by Pearson.
I will grant Pearson's motion for partial summary judgment in part, to the same extent and for the same reasons discussed in sections IV.J and K above with respect to the cabinet and window claims.
1. Pearson's claims in the second amended complaint to avoid transfers and for alter ego recovery should be dismissed with prejudice and without leave to amend. See section IV.A.3 and 4 above. Those counts are core proceedings against Suiter and noncore proceedings against the other defendants. In the interest of simplicity, I will recommend this disposition, subject to the district court's de novo review.
2. Count 123 and the portion of count 122 relating to "weekend workers" should be dismissed with prejudice and without leave to amend. See section IV.B.1(a) above. Like the claims described in paragraph 1 above, those counts are hybrid core/noncore proceedings. Therefore, I will recommend this disposition, subject to the district court's de novo review.
3. The portion of count 123 that alleges that Suiter's alleged failures to disclose that Canaan Construction was insolvent and financially unable to perform the contract result in nondischargeable liability should be dismissed with prejudice and without leave to amend. See section IV.A.7 and IV.B.1(b) above. This is a core proceeding which is subject to district court review under the usual appellate standard.
4. I recommend that the district court dismiss counts 1 and 5 of Canaan Construction's counterclaim and third party complaint, with prejudice and without leave to amend. See sections IV.C.1 above. This is a noncore proceeding.
5. I recommend that the district court enter partial summary judgment in favor of the Pearsons on counts 4 of Canaan Construction's counterclaim and third party complaint, with prejudice and without leave to amend. See section IV.C.2 above. This is a noncore proceeding.
6. I recommend that the district court grant partial summary judgment in favor of Pearson on counts 3, 4, and 5 of the third amended complaint as set forth in section IV.D above. This is a hybrid core/noncore proceeding.
7. I recommend that the district court grant partial summary judgment in favor of Pearson on counts 2 and 3 of the counterclaim and determine that the amounts claimed in proposed Change Order 9 may not be included in Canaan Construction's maximum quantum meruit recovery under Hiraga v. Baldonado. See section IV.E above. If the district court does not accept this recommendation in full, I recommend that the district court limit Canaan Construction's recovery as set forth in section IV.E.3 above. This is a noncore proceeding.
8. If the district court determines that Suiter owes money to Pearson, Suiter's discharge in bankruptcy should be denied under section 727(a)(2)(A). See section IV.G.1 above. This is a core proceeding. This decision makes it unnecessary to consider whether Suiter's discharge must be denied under other provisions of section 727(a) or whether Pearson's claims are dischargeable under section 523. If the district court reverses my decision under section 727(a)(2)(A), my decisions regarding the claims under section 523 and the other provisions of section 727 are set forth above.
9. I recommend that the district court deny all other motions to dismiss and for partial summary judgment.
Claims for unjust enrichment derive from principles of equity. Sung v. Hamilton, 710 F.Supp.2d 1036, 1064 (D. Haw. 2010). To recover on an unjust enrichment claim, a plaintiff must prove: (1) the defendant received a benefit without adequate legal basis; and (2) unjustly retained the benefit at the expense of the plaintiff. Balboa v. Hawaii Care & Cleaning, Inc., 105 F.Supp.3d 1165, 1174 (D. Haw. 2015). In reviewing unjust enrichment claims, courts must be guided by the "underlying conception of restitution, the prevention of injustice." Id.
In order to establish a claim of promissory estoppel, "(1) There must be a promise; (2) The promisor must, at the time he or she made the promise, foresee that the promisee would rely upon the promise (foreseeability); (3) The promisee does in fact rely upon the promisor's promise; and (4) Enforcement of the promise is necessary to avoid injustice." Gonsalves v. Nissan Motor Corp., 100 Haw. 149, 164, 58 P.3d 1196, 1211 (2002).