ALAN C. KAY, Senior District Judge.
Invoking the Court's diversity jurisdiction, Petitioner Metzler Contracting Co. LLC ("Metzler") has moved under Hawai'i state law for the Court to confirm an arbitration award and has filed a memorandum in support of its motion ("Mot. Mem."). (ECF Nos. 1-2.) The arbitration concerned a home on the Island of Hawai'i that Metzler contracted to build for Respondents Elle Stephens and Paul Stephens.
The Stephenses have filed a memorandum in opposition to Metzler's motion. (ECF No. 18.) They have also filed a petition under federal law for the court to vacate the arbitration award ("Cross-Pet.") and a memorandum in support of that petition ("Cross-Pet. Mem.").
The claims submitted for arbitration include so-called "audit claims," including claims by the Stephenses that Metzler overbilled for the project by approximately 70 percent, or about $7 million, that approximately $2.3 million in costs billed were not reimbursable, and that the Stephenses suffered losses of more than $2.5 million due to delay, (Mot. Mem. Ex. L. ("Final Award") at 5-10); "defect claims" by the Stephenses, including claims involving the residence's doors, stone flooring, roofing system, landscape, plumbing, integrated control system, and fifty-one miscellaneous issues, (id. at 11-36.); and an "affirmative claim" by Metzler for approximately $450,000, the remaining amount billed but not yet paid at the time of the arbitration. (Id. at 10-11.)
The arbitrator awarded $800,103.40 to the Stephenses on their claims and $645,921.76 to Metzler on its claims. (Final Award at 36-37.) The arbitrator also allocated 75 percent of the fees, expenses, and compensation of the American Arbitration Association and the arbitrator to the Stephenses, resulting in an additional award to Metzler of $106,672.62.
Although they agree that the standard for evaluating whether to confirm or vacate the arbitration award is the same either way, the parties disagree about whether state or federal law governs that evaluation.
The contract says that "judgment may be entered upon [a final arbitration award] in accordance with applicable law in any court having jurisdiction thereof." (Gen. Conditions § 4.6.6.) The contract contains "no express limitation stating that the Arbitration may only be confirmed under" either state or federal law; in that situation, a court in this district has previously applied state law to the confirmation of an arbitration award. Valrose Maui, Inc. v. Maclyn Morris, Inc., 105 F.Supp.2d 1118, 1122 & nn. 5-6 (D.Haw.2000).
Since the decision in Valrose Maui, however, the Ninth Circuit has developed a "strong default presumption that the FAA, not state law, supplies the rules for arbitration," and has held that the presumption only can be overcome by "clear intent to incorporate state law rules for arbitration." Johnson v. Gruma Corp., 614 F.3d 1062, 1066-67 (9th Cir.2010) (ellipsis and internal quotation marks omitted) (quoting Fid. Fed. Bank, FSB v. Durga Ma Corp., 386 F.3d 1306, 1311 (9th Cir.2004); Sovak v. Chugai Pharm. Co., 280 F.3d 1266, 1269 (9th Cir.2002)). This presumption applies to the confirmation and vacation of arbitration awards as well as the arbitration itself. See Fid. Fed. Bank, 386 F.3d at 1308, 1311 (deciding consolidated appeals from the confirmation of an arbitration award and the denial of a motion to vacate that award and stating that "federal law governs" the "issues we address on appeal"); see also Johnson, 614 F.3d at 1067 ("[W]here the FAA's rules control arbitration proceedings, a reviewing court must also apply the FAA standard for vacatur.") (citing Fid. Fed. Bank, 386 F.3d at 1312). The Court will therefore depart from the analysis in Valrose Maui and will instead consider whether the contract evinces a clear intent to apply Hawai'i's arbitration rules.
As stated above, the contract does not specify which law governs the confirmation and vacation of arbitration awards. (Gen. Conditions § 4.6.6.) The contract also specifies that "arbitration ... shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect." (Gen. Conditions § 4.6.2.) Those rules similarly do not evince a clear intent to choose state over federal arbitration rules. See American Arbitration Association, Construction Industry Arbitration Rules R-49(c) (Jul. 2003), http://adr.org/sp.asp?id=26397 ("Parties to these rules shall be deemed to have consented that judgment upon the arbitration award may be entered in any federal or state court having
Although federal law governs the arbitration, including its confirmation or vacation, the contract itself is governed by Hawai'i state contract law. (Gen. Conditions § 13.1 ("The Contract shall be governed by the law of the place where the Project is located.").) The Court, following the Ninth Circuit cases cited above, interprets the contract as "electing federal procedural rules for arbitration and state substantive law." Fid. Fed. Bank, 386 F.3d at 1312 (citing Sovak, 280 F.3d at 1270); see also Johnson, 614 F.3d at 1066-67 (describing Fidelity Federal Bank and Sovak).
A Court must confirm an arbitration award if the award has not been vacated, corrected, or modified. See 9 U.S.C. § 9. There are few permissible bases for vacating an arbitration award under federal law, and the Stephenses focus on only one: that the "arbitrator[] exceeded [his] powers." 9 U.S.C. § 10(a)(4).
To obtain vacation on this basis, the Stephenses "must clear a high hurdle." Stolt-Nielsen S.A. v. AnimalFeeds Int'l Corp., ___ U.S. ___, 130 S.Ct. 1758, 1767,
The Stephenses claimed in the arbitration that they should not have to pay the full amount billed, which was more than $17 million, because cost increases beyond approximately $10.4 million had not been accompanied by the formal change-order procedures required by the contract. (Cross-Pet. ¶¶ 26, 45; Supp. Conditions § 7.1.3.1.) They therefore requested that the arbitrator force Metzler to "disgorge $5,879,759 in inappropriately collected sums in excess of the adjusted Contract Sum." (Metzler's Opp'n Ex. B ("Stephenses' Post-Hr'g Br.") at 246.) The arbitrator rejected this claim after determining that there was "doubt and ambiguity as to the meaning of the language embodying the[] contractual bargain," that "the parties through their course of conduct and dealing abandoned the formal change order procedure," and that "[t]hrough their course of conduct and dealing, the parties and their agents collectively treated the Project as a cost-plus-a-fee contract, rather than as a project with a guaranteed maximum price." (Final Award at 4, 7-8.) The Stephenses now argue that the arbitrator exceeded his powers by relying on the parties' course of conduct and dealing to determine that the formal change-order procedure had been abandoned. (Cross-Pet. Mem. at 17-24; Stephenses' Reply at 4-12.)
There are several reasons why the Stephenses' argument is not a basis for the Court to vacate the arbitration award. First, the Stephenses voluntarily submitted their argument concerning these issues to the arbitrator, and cannot now claim that the arbitrator had no authority to decide them. Second, the clause on which the Stephenses rely does not concern arbitrability. Finally, the arbitrator's interpretation of the contract neither exceeded his powers nor was implausible and is therefore beyond the Court's authority to vacate.
The Stephenses' argument that the arbitrator lacked the authority to decide an issue that the Stephenses extensively put before him is analogous to the losing side's argument in Tristar Pictures:
160 F.3d at 540.
The Stephenses, apparently dissatisfied with the arbitrator's evaluation of the arguments they presented in the arbitration hearing, now attempt to have the arbitration award vacated on the grounds that the arbitrator never should have evaluated their arguments in the first place. But the Stephenses asked the arbitrator to decide these issues at the arbitration hearing, and so cannot challenge their arbitrability now. See Nghiem v. NEC Elec, Inc., 25 F.3d 1437, 1440 (9th Cir.1994) ("Nghiem initiated the arbitration, attended the hearings with representation, presented evidence, and submitted a closing brief of fifty pages.... Once a claimant submits to the authority of the arbitrator and pursues arbitration, he cannot suddenly change his mind and assert lack of authority.").
The Stephenses devoted fifty pages to the so-called "Audit Claims" in their post-hearing brief to the arbitrator, including their theory that the amount billed over the "contractually authorized Contract Sum of $10,397,462.55" was uncollectable because of the lack of compliance with the change-order procedures. (Stephenses' Post-Hr'g Br. at 205-06 ("[W]hat must therefore be found is that [Metzler] was fully aware of the obligations to prepare change orders, that it failed to meet this obligation and that no enforceable waiver or modification of that obligation was undertaken to relieve [Metzler] of that obligation."); id. at 231-32 ("[Metzler] failed to meet its burden of proving that Mrs. Stephens intentionally waived and/or modified any contract provisions and in fact admitted that she never directed Keith Wallis not to prepare change orders.").)
The Stephenses cite several cases involving motions to compel or stay arbitration. See, e.g., HIM Portland, LLC v. DeVito Builders, Inc., 317 F.3d 41, 42 (1st Cir.2003); Farkar Co. v. R.A. Hanson DISC, Ltd., 583 F.2d 68, 69 (2d Cir.1978); Brookfield-N. Riverside Water Comm'n v. Abbott Contractors, Inc., 250 Ill.App.3d 588, 190 Ill.Dec. 284, 621 N.E.2d 153, 159 (1993). The difference in procedural posture distinguishes those cases from this one. As Tristar Pictures states, a party must challenge arbitrability in a judicial proceeding instead of, not after, voluntarily submitting the case to the arbitrator.
The arbitrator did not exceed his powers by determining whether the Stephenses were responsible for the amount billed over $10.4 million. The Stephenses specifically asked him to decide that issue. (Stephenses' Post-Hr'g Br. at 205-06, 231-32.) The Court therefore cannot vacate the arbitration award on this basis. See Nghiem, 25 F.3d at 1440.
Even if the Stephenses could challenge the arbitrability of the dispute about the amount billed over $10.4 million after presenting their case to the arbitrator, such a
The contract defines a "Claim" as "a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract." (Gen. Conditions § 4.3.1.) The contract further specifies that "[a]ny Claim arising out of or related to the Contract, except Claims relating to aesthetic effect and except those waived as provided for in [specified sections], shall, after decision by the Architect or 30 days after submission of the Claim to the Architect, be subject to arbitration." (Id. § 4.6.1.)
Taken together, these broad provisions include only narrow and defined limits to the subject matter of arbitrable claims arising out of the contract.
The Stephenses claimed that Metzler had overbilled them by increasing the cost of the home without following the formal change-order procedures and Metzler claimed that the Stephenses had failed to pay the full cost of the home. These claims fall within the arbitration clause's scope because they are claims for payment of money that do not involve "aesthetic effect" or any of the explicitly waived types of claims. (Gen. Conditions §§ 4.3.1, 4.6.1.)
The Stephenses nonetheless argue that the arbitrator exceeded its powers when it decided these claims. The Stephenses rely heavily on Western Employers Insurance, and particularly its statement that forcing a party to "arbitrate according to terms for which it did not bargain" exceeds an arbitrator's powers. 958 F.2d at 259. In that case, the parties agreement "require[d] arbitrators to accompany any award with a statement of their findings of fact and conclusions of law." Id. Other cases that the Stephenses rely on also involve arbitration clauses that expressly involve the arbitrability of certain types of claims. For example, in Polimaster Ltd. v. RAE Systems, Inc., 623 F.3d 832 (9th Cir.2010), the arbitration agreement specified that arbitration would take place at the defendant's site, meaning, as the Ninth Circuit determined, that
The contract provision at issue here does not contain express limitations on arbitrability. With certain exceptions that the parties do not argue are applicable, the contract specifies as follows:
(Supp. Conditions § 7.1.3.1.) This clause does not refer to arbitration, arbitrability, or the arbitrator, and is part of Article 7 of the contract, which governs "Changes in the Work," rather than Article 4, which governs "Administration of the Contract," including "Claims and Disputes," "Resolution of Claims and Disputes," "Mediation," and "Arbitration." (Gen. Conditions at 18-24, 26-28.) The Court concludes that § 7.1.3.1 does not limit the arbitrator's jurisdiction. Rather, the section could serve as the basis for an arbitrator to deny claims based on the parties' course of conduct—and as previously discussed, the Stephenses argued to the arbitrator that the section should do just that. See supra Part IV.A.1.
Absent any clear indication that the provision applies to arbitrability, rather than the parties' relations with each other, and particularly given the "federal policy favoring arbitration," the claims that the arbitrator evaluated were arbitrable. Moses H. Cone Mem'l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983) ("[A]ny doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration. . . .").
Because the claims were arbitrable, the Court can only vacate the arbitration award if the arbitrator's decision was not a "plausible interpretation of the agreement." Tristar Pictures, 160 F.3d at 541. The decision was plausible, both because the contract terms plausibly gave rise to ambiguity that entitled the arbitrator to look to extrinsic evidence to determine the meaning of those terms and because, regardless of whether there was ambiguity in the contract, the arbitrator was entitled to consider the parties' conduct to determine whether contract provisions, including among other provisions both the change-order provisions and the anti-waiver provisions, had been waived.
Under Hawai'i law, "extrinsic evidence . . . [may] be considered by the court to determine the true intent of the parties if there is any doubt or controversy as to the meaning of the language embodying their bargain." Hokama v. Relinc Corp., 57 Haw. 470, 559 P.2d 279, 283 (1977). Ambiguity can exist within a contract even if no particular words or phrases
The Stephenses acknowledge that extrinsic evidence may be considered to interpret an ambiguous document, but argue that this is only the case "if the ambiguity arises from the document itself." (Cross-Pet. Mem. at 22 n.11.) As a matter of Hawai'i law, the Stephenses are correct; a "court should look no further than the four corners of the document to determine whether an ambiguity exists." Found. Int'l, Inc. v. E.T. Ige Constr., Inc., 102 Haw. 487, 78 P.3d 23, 33 (2003). The arbitrator's statement that "doubt and ambiguity as to the meaning of the language" arose from "a course of conduct and dealing that varied significantly from procedures contemplated by the Contract Documents," (Final Award at 4), appears to have been erroneous.
Yet that error does not mean that the arbitration award may be vacated, for two reasons. First, mere legal error is not a basis for vacation. See, e.g., Stolt-Nielsen S.A., 130 S.Ct. at 1767. Second, the arbitrator's discussion of the audit claims shows that he found ambiguity within the terms of the contract, despite his statement that the ambiguity arose from the parties' conduct. (Final Award at 5-8.)
There are several contract provisions that, when read together, could plausibly give rise to ambiguity. First, the contract specifies that "[t]he Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the Contract" and that the "Contract Sum is the Cost of Work as defined in Article 7 plus the Contractor's Fee." (Agreement § 5.1.1.) The same article of the contract provides space for a "guaranteed maximum price," but the parties filled in that space with the term "N/A." (Id. § 5.2.) The parties dispute what "N/A" means; Metzler says that it means "not applicable" whereas the Stephenses say that it means "not available." (Final Award at 6.)
Based on these provisions, the arbitrator could plausibly determine that the Stephenses were required to pay Metzler for the cost of the work as defined in the contract, whatever it was, plus a fee, without reference to any maximum price or change-order procedure. This is not an inherently implausible arrangement; the American Institute of Architects offers a form contract for it. See A-Series: Owner/Contractor Agreements, http://www.aia.org/contractdocs/AIAS076742. This is the interpretation of the contract that Metzler advocated, and the arbitrator ultimately adopted it. (Final Award at 8.)
The contract also provides, however, that Metzler was to prepare a "Preliminary Budget, including an itemized Schedule of Values," based on its "best estimate of the Contract Sum," before it began construction. (First Add. § 6.5.) Metzler did so, and the preliminary budget was $10,301,541. (Cross-Pet. Mem. Ex. A-5.) The same section of the contract further provides that as the "Schedule of Values is refined . . . a Change Order shall be issued to adjust the Contract Sum. . . ." (First Add. § 6.5.) These provisions, as the Stephenses argued to the arbitrator, could represent a different type of contract: a
Faced with these competing interpretations of the contract terms, each plausibly inconsistent with the other,
Based on his assessment of that evidence, the arbitrator determined that the Stephenses' theory was not credible. (Final Award at 8.) That conclusion too was plausible, based on the arbitrator's determinations that the parties never negotiated a guaranteed maximum price; that Elle Stephens "agreed to have the pay requests sent directly to her for review and approval"; that she "requested myriad changes after the Preliminary Budget was issued"; that she "chose not to take advantage of the cost protection features in the Contract Documents" after a stage "[e]arly on in the Project [when] four Change Orders were issued"; that Metzler "periodically submitted updated budgets to Mrs. Stephens reflecting th[e] increased costs" due to her requested changes; that the most recent update to the budget, submitted on August 31, 2004, "showed projected costs at $17,285,032 and costs to date of more than $14 million"; and that the "increasing costs on the Project . . . were paid without objection through June 2005." (Final Award at 6-8.)
In sum, neither the arbitrator's decision to consider extrinsic evidence to interpret the contract terms nor his subsequent interpretation of those terms was implausible, so neither is a ground for the Court to vacate the arbitration award.
Even if the contract was unambiguous, and meant what the Stephenses argue it meant, the arbitrator did not exceed
Given the parties' conduct, the arbitrator's determination that certain of the contract's procedures had been abandoned was plausible and rooted in established principles of contract law. For example, in Stewart v. Spalding, 23 Haw. 502 (1916), a "clause in the specifications provided that `no extra compensation shall be due the contractor for the performance of any work or furnishing of any material, except in accordance with written agreement or by written order of the architect with the approval of the owner.'" Id. at 511. The Supreme Court of the Territory of Hawai'i noted "evidence that in several instances the owner himself had ordered changes to be made for which extra compensation might be claimed," and determined that "if the parties did not live up to the requirement of the specifications neither could set it up to defeat the just claims of the other." Id.; cf. also Wall v. Focke, 21 Haw. 399, 404-05 (1913) (noting that the "law ordinarily presumes or implies a contract whenever this is necessary to account for other relations found to have existed between the parties," such as when there is "evidence that defendant requested plaintiff to render the services or assented to receiving their benefit under circumstances negativing any presumption that they would be gratuitous").
The proposition that parties may waive formal change-order provisions, particularly, appears in numerous cases from around the nation.
The parties (or at least the Stephenses) apparently intended to draft the contract to preclude course-of-conduct claims, but that intent does not render the architect's interpretation implausible. "It is a well-established rule of law that parties to a written contract may modify, waive, or make new terms notwithstanding terms in the contract designed to hamper such freedom." Davis v. Payne & Day, Inc., 10 Utah.2d 53, 348 P.2d 337, 339 (1960).
Farkar Co., which the Court distinguished above on the basis of its procedural posture, see supra Part IV.A.1, is also distinguishable because of the absence of waiver. See Farkar Co., 583 F.2d at 72 (modifying an order compelling arbitration to exclude a category of claims that the contract specified could not give rise to liability, where there was no determination that the limitation of liability had been waived). Similarly, the arbitrator in this case granted summary judgment to the respective defendants of the claims for defamation per se and injurious falsehood because the parties had expressly waived claims for consequential damages in the contract. (Mot. Mem. Ex. G (citing Gen. Conditions § 4.3.10).) Unlike the provisions in the contract that the arbitrator determined were waived, and particularly § 7.1.3.1, there was no determination that the limitation of liability in § 4.3.10 had been waived.
The contract specifies that "Claims . . . shall be referred initially to the Architect
The Stephenses argue that Metzler's failure to refer certain claims to the architect before those claims were submitted to the arbitrator precluded the arbitrator from addressing those claims, such that the arbitrator exceeded his authority by addressing them. The Court rejects the Stephenses' argument, both because the claims were voluntarily submitted to the arbitrator and because the arguments fail on their merits.
The Stephenses particularly focus, in this portion of their argument, on the arbitrator's consideration of their $1.15 million claim for the replacement of 172 custom-made wenge doors. (Cross-Pet. Mem. at 24-31.) Of the residence's 185 wenge doors, 124 were exterior doors, and the architect rejected these because "the orientation of the laminated core material in the doors differed from the orientation of the cores depicted in approved Shop Drawings." (Final Award at 11.) The door manufacturer replaced thirteen of the exterior doors, and the Stephenses sought replacement of the remaining exterior doors along with the interior doors, which the architect had not rejected. (Id.)
Just as the Court determined above, see supra Part IV.A.1, the Stephenses' argument that the claims concerning doors were outside the arbitrator's authority to decide fails because the Stephenses voluntarily presented those claims to the arbitrator, including their arguments concerning the requirement of submitting claims to the architect, both as a condition precedent to arbitration and as a necessary step to be taken to preserve a claim "within 21 days after occurrence of the event giving rise to such Claim." (Stephenses' Post-Hr'g Br. at 11-13, 33-36; Gen. Conditions § 4.3.2.) In total, the Stephenses devoted twenty-seven pages to the claims involving doors in their brief to the arbitrator. (Stephenses' Post-Hr'g Br. at 25-51.) The Stephenses made no attempt to challenge the arbitrability of these claims in a judicial proceeding instead of voluntarily presenting them to the arbitrator. Rather, they offered the same proposition in the introduction to their post-hearing brief that the Court relies on below to evaluate the merits of their argument:
(Id. at 11 (citations and internal quotation marks omitted).) The arbitrator did not exceed his powers by evaluating the claims that the Stephenses submitted to him. See Nghiem v. NEC Elec., Inc., 25 F.3d at 1440.
Even if the Stephenses had raised their argument concerning submission of claims to the architect in a judicial proceeding instead of voluntarily submitting those claims to the arbitrator, the argument would have failed. Whether the contract's preconditions for arbitration had been met was a question for the arbitrator to decide. See Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 84, 123 S.Ct. 588, 154 L.Ed.2d 491 (2002) (citing John Wiley & Sons, Inc. v. Livingston, 376 U.S. 543, 557, 84 S.Ct. 909, 11 L.Ed.2d 898 (1964), for the proposition that "an arbitrator should decide whether the first two steps of a grievance procedure were completed, where these steps are prerequisites to arbitration").
The Court cannot revisit the arbitrator's factual determinations that "[i]t was evident from the parties' course of conduct and dealing that they effectively removed the Architect from the Contract administration process" and that "multiple Contract provisions related to change orders, payment, and submission of claims to the Architect for initial decision were ignored by both [sides]." (Final Award at 5.) Given those determinations, the arbitrator's conclusion that both parties "effectively waived whatever rights they might otherwise have had . . . to challenge one another's claims on the grounds that those claims were not timely submitted to the Architect for initial decision as a condition precedent to arbitration of those claims" was plausible.
Having evaluated the Stephenses' petition to vacate the arbitration award, the Court turns to Metzler's motion to confirm it. The award must be confirmed if it has not been modified, corrected, or vacated. See 9 U.S.C. § 9. The Stephenses have not demonstrated that the award should be vacated, and have not argued that the award has been or should be modified or corrected, so the Court is bound to confirm the award and will do so.
Metzler also asks that the Court expressly find that Metzler has satisfied all amounts owing under the arbitration award. Based on the exhibits to Metzler's motion, which include a copy of a check for the amount owed and a receipt for its delivery to one of the Stephenses' attorneys, the Court so finds. (Mot. Mem. Exs. N-O.)
The Court denies, however, Metzler's request for attorneys' fees under section 658A-25 of the Hawaii Revised Statutes. As the Court noted above,
For the foregoing reasons, the Court: (1) GRANTS in part and DENIES in part Petitioner and Cross-Respondent Metzler Contracting Co. LLC's Motion to Confirm Arbitration Award; and (2) DENIES Respondents and Cross-Petitioners Elle Stephens and Paul Stephens's Petition to Vacate Arbitration Award.
IT IS SO ORDERED.
In evaluating the phrase "question of arbitrability," the Supreme Court has acknowledged that "[l]inguistically speaking, one might call any potentially dispositive gateway question a `question of arbitrability,' for its answer will determine whether the underlying controversy will proceed to arbitration on the merits." Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 83, 123 S.Ct. 588, 154 L.Ed.2d 491 (2002). But the Court went on to say that "the phrase `question of arbitrability' has a far more limited scope," and concerns questions such as "whether the parties are bound by a given arbitration clause" or "whether an arbitration clause in a concededly binding contract applies to a particular type of controversy." Id. at 84, 123 S.Ct. 588. Under Howsam, whether an arbitration award should be confirmed is not necessarily a question of arbitrability.
The Court's determination that federal law governs whether the award should be confirmed or vacated is based on the parties' lack of a clear intent to have their dispute governed by state arbitration rules, not the presence vel non of questions of arbitrability. Even assuming for the sake of argument that the Stephenses present questions of arbitrability in their petition to vacate, those questions would not compel the application of federal law to Metzler's separate motion to confirm. Otherwise, a party could, by artful pleading, overcome even a clear contractual intent to have state law rules for arbitration apply. Cf. Johnson, 614 F.3d at 1066-67 (applying state arbitration rules where the contract evinced a clear intent to have those rules apply).
The Court notes that it found several of the citations in this footnote in a construction-law treatise. See Philip L. Bruner & Patrick J. O'Connor, Jr., 1-2 Bruner and O'Connor on Construction Law §§ 4:40, 5:109 (2010). That there is at least one treatise with sections covering waiver of formal change-order provisions, even in the presence of "anti-waiver" clauses (as the treatise terms them), suggests that the arbitrator's conclusion concerning this contract's allowance for waiver was plausible.