ROBERT M. DOW, JR., District Judge.
Before the Court is Defendant Henry Bros. Construction Management Services, LLC's motion to dismiss Count II of Plaintiff Hartford Fire Insurance Company's complaint [37]. For the following reasons, Defendant's motion [37] is granted.
The instant dispute arises out of a construction project at the Glenbrook South High School in Glenview, Illinois. The school project is owned by the Northfield Township High School District # 225 (the "District"). Defendant Henry Bros. Construction Management Services, LLC ("HBC") performed construction management services on the project pursuant to a contract with the District. See Ex. A to Cmplt. (hereinafter the contract or the "CM Contract"). The only parties to the contract were the District and HBC.
Among other things, the CM Contract established certain of HBC's duties and obligations during the project. ¶ 12. One of the duties that the contract imposed on HBC was to develop and implement procedures for reviewing and processing payment applications submitted by the various contractors and subcontractors. ¶ 14. In connection with this responsibility, HBC had an "affirmative obligation to investigate the work performed by the contractors on the Project and make certifications to [the District] that the contractor requesting payment is entitled to payment in the amount certified under the contract documents." ¶ 15. Certifying payment meant that HBC was certifying to the District that (1) the work in question had progressed to the point indicated in the payment request; (2) the quality of work was acceptable and in accordance with the contract documents; and (3) the contractor requesting payment was entitled to payment under the applicable contract documents. ¶ 16. The contract also required HBC to gather lien waivers and sworn statements listing subcontractors and materialmen before issuing payment certificates.
Grace Electrical Construction Corporation ("Grace") is a contractor that performed electrical work on the project under HBC's supervision. Grace, too, contracted directly with the District. See Ex. B to Cmplt. (the "Grace Contract"). The only parties to the Grace Contract were the District and Grace. Illinois law required Grace to provide a performance and payment surety bond to secure its performance of the Grace Contract and its payment of certain subcontractors, laborers, and materialmen. On May 29, 2007, Plaintiff Hartford Fire Insurance Company ("Hartford") issued a bond on behalf of Grace for the project. See Ex. C to Cmplt. In exchange for the bond, Hartford required Grace to execute a general indemnity agreement.
During the course of performance of the Grace Contract, Grace submitted three payment applications to HBC. Hartford alleges that HBC certified work included in these payment applications which Grace either did not perform, performed defectively, and/or performed in an untimely manner. ¶ 39. In reliance on HBC's certification of the payment applications, the District paid Grace a total of $731,880. ¶ 40. On or about December 4, 2007, due to a financial hardship, Grace ceased work on the project and sent the District a letter terminating its rights under the Grace Contract. Grace had not achieved substantial completion of the Grace Contract at that time. Further, Grace had failed to pay numerous of its project vendors and had failed to provide the required lien waivers pursuant to the contract. ¶¶ 45-46.
Following Grace's default, the District asserted a claim against the performance bond. In order to discharge is obligations under the bond, Hartford agreed to take over and complete Grace's performance of the Grace Contract. ¶¶ 50-51. Hartford paid $447,662.21 to numerous vendors of Grace that furnished labor and material to the project but never received payment from Grace. Hartford also ultimately paid $742,480.29 in costs to remedy the work of Grace to complete the project. In total, Hartford alleges that it has incurred a net loss of $833,104.21. ¶ 80. Hartford alleges that after it "paid the claimants and completed the [Grace] Contract as required by the Bonds, by operation of law, [Hartford] subrogated to the rights of Grace's project vendors, Grace and [the District]." ¶ 69. Hartford further alleges that "[b]ecause of [HBC's] mismanagement and other deficiencies, the project vendors and [the District] are entitled to assert a cause of action against [HBC] for breach of contract and negligent misrepresentation." ¶ 70. Hartford now "brings the instant action as subrogee against [HBC]."
Count I alleges that HBC breached the CM Contract by, inter alia, failing to properly investigate, supervise, and administer Grace's work on the project. ¶¶ 72-80. In particular, Hartford alleges that the District overpaid Grace in reliance on HBC's certifications. Count II is a claim for negligent misrepresentation relating to HBC's approvals of Grace's payment applications. Hartford alleges that "[w]hile performing its professional construction administration services, HBC negligently supplied incomplete, inaccurate, misleading, and false information to SD225 concerning Grace's performance of the Prime Contract." Hartford claims that it suffered losses as a result of the unavailability of sufficient contract funds to "correct, repair or complete Grace's work." Hartford makes no claim for personal injury or damage to other property.
A motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) tests the sufficiency of the complaint, not the merits of the case. See Gibson v. City of Chicago, 910 F.2d 1510, 1520 (7th Cir.1990). To survive a 12(b)(6) motion to dismiss, the complaint first must comply with Rule 8(a) by providing "a short and plain statement of the claim showing that the pleader is entitled to relief" (Fed.R.Civ.P. 8(a)(2)), such that the defendant is given "fair notice of the way the * * * claim is and the grounds upon which it rests." Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007) (quoting Conley v. Gibson, 355 U.S. 41, 47, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)). Second, the factual allegations in the complaint must be sufficient to raise the possibility of relief above the "speculative level," assuming that all of the allegations in the complaint are true. E.E.O.C. v. Concentra Health Servs., Inc., 496 F.3d 773, 776 (7th Cir.2007) (quoting Twombly, 550 U.S. at 555, 127 S.Ct. 1955). "[O]nce a claim has been stated adequately, it may be supported by showing any set of facts consistent with the allegations in the complaint." Twombly, 550 U.S. at 563, 127 S.Ct. 1955. The Court accepts as true all of the well-pleaded facts alleged by the plaintiff and all reasonable inferences that can be drawn therefrom. See Barnes v. Briley, 420 F.3d 673, 677 (7th Cir.2005).
In order to state a claim for negligent misrepresentation under Illinois law, a party must allege (1) a false statement of material fact; (2) carelessness or negligence in ascertaining the truth of the statement by the party making it; (3) an intention to induce the other party to act; (4) action by the other party in reliance on the truth of the statement; (5) damage to the other party resulting from such reliance; and (6) a duty on the party making the statement to communicate accurate information. See Tricontinental Industries, Ltd. v. PricewaterhouseCoopers, LLP, 475 F.3d 824, 833-34 (7th Cir.2007). The tort of negligent misrepresentation essentially has the same elements as fraudulent misrepresentation, except that the defendant's mental state is different.
Suits for purely economic damages based on negligent misrepresentations generally are barred in Illinois under the so-called Moorman doctrine. See Moorman Manufacturing Co. v. National Tank Co., 91 Ill.2d 69, 61 Ill.Dec. 746, 435 N.E.2d 443 (1982).
Hartford's complaint explicitly alleges that HBC, acting in its capacity as construction manager, was in the business of providing information for the guidance of others. In its response brief, Hartford maintains that this allegation demonstrates that it has sufficiently pled a negligent misrepresentation claim. This point warrants only brief discussion. Hartford's allegation that HBC, acting in its capacity as construction manager, "was in the business of providing information for the use and benefit of SD225 and other entities" cannot alone stave off dismissal of the negligent misrepresentation claim. While the Court must accept all well-pleaded allegations of the complaint as true, "it need not accept as true legal conclusions or opinions that are couched as factual allegations * * * * The claim that a party is in the business of providing information for the guidance of others states a legal conclusion and must be supported by well-pleaded factual allegations." Union Oil v. John Brown E&C, 1994 WL 535108, at *4 (N.D.Ill. Sept. 30, 1994).
Hartford points to several misrepresentations found in its complaint, including misrepresentations by HBC on issues such as the amount due to Grace, the existence of defective and non-conforming work, and the status of construction. But the negligent misrepresentation exception to the Moorman doctrine requires more than mere misrepresentation. "It requires that the misrepresenter be `in the business of supplying information for the guidance of others in their business transaction.'" MW Mfrs., Inc. v. Friedman Corp., 1998 WL 417501, at *4-6 (N.D.Ill. July 21, 1998). The Illinois Appellate Court has observed that it may be useful to "envision a continuum [of enterprises] with pure information providers at one
In between the pure information and the tangible product ends of the spectrum are the "difficult cases" which can go either way, such as those involving life insurance companies, banks and financial service providers, and financing inspectors. Tolan, 308 Ill.App.3d at 28, 241 Ill.Dec. 427, 719 N.E.2d 288 (collecting cases). This "in between" category consists of businesses that supply tangible goods (or non-informational goods or services) as well as information. Id. (citing Rankow v. First Chicago Corp., 870 F.2d 356, 364 (7th Cir. 1989)). "The critical question for businesses in this category is whether the information is an important part of the product offered. These businesses will be deemed to be in the business of supplying information if the information furnished along with the non-informational good or services is central to the business transactions." Id. (quoting Gen. Elec. Capital, 797 F.Supp. at 1443).
"The Illinois Supreme Court's test for determining whether a defendant `is in the business of supplying information for the guidance of others in their business transactions' is whether the end product of the relationship between plaintiff is a tangible object (i.e., a product) which could be readily described in a contract or whether it is intangible." MW Mfrs., Inc., 1998 WL 417501 at *4 (citing Fireman's Fund Insurance Co. v. SEC Donohue, Inc., 176 Ill.2d 160, 223 Ill.Dec. 424, 679 N.E.2d 1197, 1201 (1997)). In short, if the intended end result of the relationship is for the defendant to create a product — a tangible thing — then the defendant will not fit into the "business of supplying information" negligent misrepresentation exception. For instance, an architect, who "supplies information" in the form of blueprints, is still not in the "business of supplying information" because the intended end result is not mere information but a tangible object: a building. See 2314 Lincoln Park West Condominium Assoc. v. Mann, Gin, Ebel & Frazier, 136 Ill.2d 302, 313, 144 Ill.Dec. 227, 555 N.E.2d 346, 351 (1990). Similarly, an engineer might "supply information" in the form of plans and drawings, but the engineer is not in the "business of supplying information" because the intended end result is a tangible object — for example, a water supply system. See Fireman's Fund Ins., 223 Ill.Dec. 424, 679 N.E.2d at 1201-02. The information "supplied" in these cases is merely incidental to the end result of a tangible object. Id. Contrast these examples with two traditional examples of defendants in the "business of supplying
Congregation of the Passion, Holy Cross Province v. Touche Ross & Co., 159 Ill.2d 137, 201 Ill.Dec. 71, 636 N.E.2d 503, 515 (1994); see also Tribune Co. v. Geraghty & Miller, Inc., 1997 WL 438836, at *3 (N.D.Ill. Jul. 25, 1997) (applying tangible object test to environmental assessment service defendant; finding that ultimate result of relationship between plaintiff and defendant was to produce an intangible result, i.e., the analysis in the environmental assessment report).
In this case, the terms of the contract between HBC and the District set out the project's ultimate goal: "Additions, Remodeling, Life Safety and Infrastructure Work at Glenbrook South High School." HBC was the construction manager for the school project and was retained, through a written contract, to perform certain services during the remodeling of the school. Those services included supervising contractors and subcontractors, which in turn included, pursuant to the terms of the CM Contract, inspecting Grace's work and drafting certifications or reports of deficiencies. The actual language of the CM Contract between the parties sheds further light on HBC's role in the construction of the Project:
These sections indicate that HBC's services were an integral part of the construction, the end product being the completed additions and renovations of the school. HBC was hired to supervise the subcontractors to the Project and, incidental to that task, was to provide certification (or "information") to the District that the subcontractors (including Grace) were performing work in an acceptable manner. The end product in this case was not the information provided to the District; rather,
This conclusion is highlighted by additional terms in the contract, which provide that it was the Owner's (the District's) responsibility to verify the contractor's applications for payment:
Thus, while HBC was supplying information incidental to the building process, these provisions demonstrate that the District was involved at the "pure information end" of the continuum — in other words, it was the District's job to enlist additional parties (as necessary) — the lawyers, accountants, or insurance agents — to weigh in on the "pure information" side of the continuum. To the extent that the District sought information from Defendant, that information was incidental to the District's end result — the remodeling of the school. None of the advice or information sought or given in this case relates to anything other than the desired end result of completing the school. HBC's duty to the District clearly arose out of its contract with the District and any damages must flow from that. Because Defendant was not in the "business of supplying information," as that term is defined in the Illinois case law, Plaintiff's negligent misrepresentation claim fails.
For the reasons stated above, Defendant's motion to dismiss Count II of Plaintiff's complaint [37] is granted. This case remains set for a status hearing on July 12, 2012, at 9:00 a.m.